2020 midyear update 2020 - home | city of denton...and pedestrian safety on mckinney street from...

8
CONSTRUCTION GUIDE CITY OF DENTON 2020 RECENTLY COMPLETED MAJOR INFRASTRUCTURE PROJECTS TOTAL MORE THAN $76 MILLION IN TRANSPORTATION IMPROVEMENTS 2020 2020 MIDYEAR UPDATE While COVID-19 temporarily shut down various businesses and limited operations within the City, the pandemic also provided a small measure of good news when it came to vital transportation projects: it helped moved them forward. As streets and highways cleared out in accordance with social distancing and telecommuting orders, City crews and contractors adjusted to the new normal and were able to maintain or accelerate major construction project timelines without having to trigger major disruptions and traffic backups. Major City Transportation Projects Recently Completed Most major City transportation projects are bond-funded Capital Improvement Projects (CIPs). These voter-approved projects reflect the priorities and vision of the City from residents. Over the past several months, the City has completed one CIP and three phases of active CIPs, totaling more than $76 million in transportation improvements throughout the city of Denton. MAGNOLIA DRAINAGE Hinkle (University to W. Windsor) & Windsor (Hinkle to N. Elm) New underground utilities, roadway, and roundabout at Hinkle Drive and Mimosa Drive. $8,198,340. Funding Source: 2012 and 2014 Bond Programs. 100% COMPLETE MCKINNEY STREET PHASE 1 (South Fork to Grissom Road) New underground utilities and four-lane divided roadway with a continous turn lane to improve mobility and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs. 100% COMPLETE BONNIE BRAE PHASE 4A (Bonnie Brae Street at Scripture Street) Redesign of the road grade and alignment for a new roundabout at the intersection of Scripture Street and Bonnie Brae Street. $6,600,000. Funding Source: 2012 and 2014 Bond Programs. MAYHILL ROAD PHASE 1 (US 380 to north of Quail Creek Road) New four-lane, divided roadway to handle continued growth and serve as an alternate route to Loop 288/ Mayhill. $59,154,411. Funding Source: 2012 and 2014 Bond Programs. 100% COMPLETE 100% COMPLETE

Upload: others

Post on 04-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

CONSTRUCTION GUIDECITY OF DENTON

2020

RECENTLY COMPLETED MAJOR INFRASTRUCTURE PROJECTS TOTAL MORE THAN $76 MILLION IN TRANSPORTATION IMPROVEMENTS

20202020 MIDYEAR UPDATE

While COVID-19 temporarily shut down various businesses and limited operations within the City, the pandemic also provided a small measure of good news when it came to vital transportation projects: it helped moved them forward. As streets and highways cleared out in accordance with social distancing and telecommuting orders, City crews and contractors adjusted to the new normal and were able to maintain or accelerate major construction project timelines without having to trigger major disruptions and traffic backups. Major City Transportation Projects Recently Completed Most major City transportation projects are bond-funded Capital Improvement Projects (CIPs). These voter-approved projects reflect the priorities and vision of the City from residents. Over the past several months, the City has completed one CIP and three phases of active CIPs, totaling more than $76 million in transportation improvements throughout the city of Denton.

MAGNOLIA DRAINAGE Hinkle (University to W. Windsor) & Windsor (Hinkle to N. Elm)

New underground utilities, roadway, and roundabout at Hinkle Drive and Mimosa Drive. $8,198,340.Funding Source: 2012 and 2014 Bond Programs.

100%COMPLETE

MCKINNEY STREET PHASE 1 (South Fork to Grissom Road)

New underground utilities and four-lane divided roadway with a continous turn lane to improve mobility and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs.

100%COMPLETE

BONNIE BRAE PHASE 4A (Bonnie Brae Street at Scripture Street)

Redesign of the road grade and alignment for a new roundabout at the intersection of Scripture Street and Bonnie Brae Street. $6,600,000.Funding Source: 2012 and 2014 Bond Programs.

MAYHILL ROAD PHASE 1(US 380 to north of Quail Creek Road) New four-lane, divided roadway to handle continued growth and serve as an alternate route to Loop 288/Mayhill. $59,154,411.Funding Source: 2012 and 2014 Bond Programs.

100%COMPLETE

100%COMPLETE

Page 2: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

2

BOND PROGRAMS UPDATE

Through the past four voter-approved bond programs (2005, 2012, 2014, and 2019), Denton residents have committed to investing $381.8 million to fund large infrastructure projects. Transparency is of utmost importance to our community and a core value of our City government. A 2012, 2014, and 2019 Bond project status dashboard is available at www.cityofdenton.com/bonds. The dashboard showcases the progress, budgets, and timelines for the bond programs.

2012 BOND PROGRAM | $20,400,000 | 98% COMPLETEProposition 1: Street Reconstruction and Public Art

More than 98% percent complete, the 2012 Bond Program authorized construction and improvements of 208 local road segments. As of Sept. 1, 2020, 147 road segments have been completed. 31 road segments are in construction, and the remaining 30 road segments are under design. All road segments remain on schedule and are expected to be complete by June 2022.

MARCH 2019 | 94%

DECEMBER 2019 | 98%

FEBRUARY 2018 | 69%

2014 BOND PROGRAM | $98,155,000 | 92% COMPLETEProposition 1: Street ImprovementsProposition 2: Public Safety FacilitiesProposition 3: Stormwater Drainage & Flood ControlProposition 4: Park System Improvements

More than 92% percent complete, the 2014 Bond Program includes major roadway sections; reconstruction of Fire Stations 2, 3, and 4; numerous drainage improvements; and various Parks & Recreation projects. Major milestones in this program include the completion of several park system improvements, substantial completion of Fire Station 3, and the Magnolia Drive Drainage CIP.

JANUARY 2017 | 9%

FEBRUARY 2018 | 23%

DECEMBER 2019 | 77%

DECEMBER 2020 | 95% (PROJECTED)

JUNE 2022 | 100% (PROJECTED)

2019 BOND PROGRAM | $220,900,000 | 1% COMPLETEProposition 1: Street ImprovementsProposition 2: Police FacilitiesProposition 3: Land For Parks

Recently launched, the 2019 Bond Program includes public securities for street improvements, public safety facilities for the Police Department, and the purchase of land for parks. Issuance of Propositions 1 and 3 of this program began in Fiscal Year 2019-20. Construction is scheduled to begin in November 2020 for the Police Substation and renovations for the Police Headquarters and Police Indoor Firing Range.

DECEMBER 2021 | 13% (PROJECTED)

DECEMBER 2022 | 53% (PROJECTED)

DECEMBER 2023 | 72% (PROJECTED)

DECEMBER 2024 | 83% (PROJECTED)

DECEMBER 2020 | 99% (PROJECTED)

JUNE 2022 | 100% (PROJECTED)

DECEMBER 2020 | 1% (PROJECTED)

Page 3: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

MAJOR INFRASTRUCTURE PROJECTS

3

Bonnie Brae Street • Phase 1 (Roselawn to north of Vintage) is scheduled to be

complete in October 2020. Phase 2 (Vintage and the

intersection of Vintage at Bonnie Brae) is scheduled for

completion in March 2021. Phases 3-6 (Roselawn to US 77)

is currently in design

• Will accommodate mobility needs and relieve congestion

Mayhill Road• Phase 1 (US 380 to north of Quail Creek) was completed in

August 2020. Phase 2 (Colorado to north of Quail Creek) is

scheduled to begin in Q1 2021

• Will handle continued growth in the area, provide pedestrian

facilities, improve safety, and relieve congestion

Hickory Street• Phase 5 (Welch to Carroll) began August 2020 and is

scheduled to be complete by fall 2021

• Will improve pedestrian safety, install new street lighting,

address aging utilities, and reconstruct the street

Pecan Creek Tributary 4 (PEC-4) Drainage Improvement Project• Phases 1 (Elm from Hickory to Eagle) and Phase 2 (Locust

from Hickory to Eagle) are scheduled for completion in

February 2021. Phases 3 and 4 (between Prairie and Bernard)

are in the final stages of design

• Will reduce flooding and upgrade aging utilities

Hickory Creek Road West Project Phase 2• Active construction for this project (Hickory Creek from

Teasley to Riverpass) remains on schedule to be completed

by March 2021.

• Will improve mobility and safety in the area by expanding

the roadway to four lanes

Hickory Creek Road East Project• Construction start date (Hickory Creek from Teasley and

FM-2499) was delayed until August 2020 due to the

COVID-19 response

• Will improve mobility and safety in the area by expanding

the roadway to four lanes

Magnolia Drainage Project (Complete)• The final phase of construction on Hinkle (University to

W. Windsor) and Windsor (Hinkle to N. Elm) was completed

in August 2020.

• Will reduce flooding, upgrade aging utilities, resurface

the street, and install a roundabout at intersection of

Hinkle Drive and Mimosa Drive

North South Water Main Project• Phase 2 (Roselawn to I-35) remains on schedule to be

complete in September 2020. The start date for Phase 3

(I-35 to Scripture) was delayed due to the COVID-19

response, and is now under construction

• Will accommodate growth, increase capacity, and improve

water services

McKinney Street Project • Active construction for this project (Loop 288 to Southfork;

roundabout at Grissom) remains on schedule to be complete

by January 2022

• Will improve pedestrian safety, address aging utilities,

reconstruct the street, and improve lighting

1

2

3

4

6

7

8

9

5

2

1

89

3

7

5 6

4

I35

FM 1

56

UNIVERSITY

ELM

FM 2449

FM 7

20

FM 426

HWY

377

LOOP 288FM 1173

OAK

FM 2

931

BELL

WINDSOR SHER

MAN

TEASLEY

FM 4

24

LOCU

ST

BON

NIE

BRA

E

CARR

OLL

EAGLE

COU

NTR

Y C

LUB

FM 2

164

COLORADO

HOBSON

SCRIPTURE

ROSELAWN

MAS

CH

BRA

NCH

BERN

ARD

DALLAS

SWIS

HER

CORINTH

SHADY SHORES

WO

OD

ROW

NOTT

ING

HAM

PENN

SYLV

ANIA

LILL

IAN

B M

ILLE

R

SHAD

Y SH

OR

ES

I35

LOOP 288

I35

I35

UNIVERSITY

LOO

P 28

8

I35

I35

BELL

BONNIE BRAE

Legend

Major City ProjectsBonnie Brae Street

Hickory StreetHickory Creek Road EastHickory Creek Road West

Magnolia DrainageMayhill RoadMcKinney Street North South Water Main

Pecan Creek Tributary (PEC-4)

°N

4Miles

ED R

OBS

ON

BON

NIE

BRA

E

For multiple phase Major City Projects the map reflects all phases of the project.

For additional information on all current and upcoming

construction projects throughout the city of Denton,

including project timelines and an interactive map,

visit www.improvingdenton.com.

Page 4: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

PROJECT SCOPE STATUS*

2019 Street Bundle

Street reconstruction, water and sewer service improvements of the following roadways: Windsor (N. Locust to east of Old North); Scripture (Thomas to Jagoe); Thomas (Panhandle to Oak); Hercules (N. Locust to Sherman); Hercules Lane (Sherman to Meadow); Scripture (Thomas to Jagoe); Thomas (Panhandle to W. Oak);.

Active

2019 Street Intersection Improvements

Signal light and traffic improvements at University and Nottingham; Sherman and Loop 288; Hercules and Locust; McKinney and Loop 288; and McKinney and Woodrow.

Q4 2020

Allred Water Transmission MainInstall 14,000 linear feet of 24-inch and 30-inch water main along Old John Paine and Allred between the Southwest Pump Station and S. Bonnie Brae.

Complete

Morse StreetTransition from a 4-lane typical section at Loop 288 to a 3-lane configuration at Kimberly Drive. Maintain existing street width between Kimberly Drive and Mayhill Road.

Q3 2021

Downtown Drainage Systems Install drainage system along rail line from Sycamore to McKinney. Q4 2020

Elm & Locust Water/SewerReplace 5,900 feet of water and wastewater lines on Locust and Elm from Eagle to Hickory. Project combined with the active Pecan Creek Tributary 4 (PEC-4) project.

Active

I-35/Scripture Water Main Install 700 feet of 20-inch water main along I-35 near Scripture. Q1 2021

I-35/US 380 Water MainInstall 1,900 feet of 20-inch water main and 1000 feet of 16-inch water main along I-35 near US 380.

Q1 2021

City construction projects introduced in the last edition of the 2020 Construction Guide have progressed through their construction schedules, reached completion, or may have experienced a schedule delay due to unforeseen circumstances, such as the COVID-19 pandemic or weather delays. Pages 4 and 5 of this Guide will provide you with an update on these major projects and timelines for the remainder of the year. Whether the project is on a neighborhood street or major thoroughfare, you will know the project status and any updates to the project scope. For additional information about City of Denton projects, visit www.improvingdenton.com.

*Active - Project is in progress. | Complete - Project has been completed.

ADDITIONAL CITY PROJECTS SCHEDULED FOR 2020

4

Fire Station No. 3 – Construction on the new 16,000 square-foot facility is on track to be completed in October 2020. Following the opening of the new facility, demolition of the old station and new public parking will be complete by the end of 2020.

Fire Station No. 8 – The new 8,500 square-foot facility is expected to be complete in January 2021. Fire Station 8 will have two bays, house Engine and Medic 8, and provide residents and property owners, mainly in Southeast Denton, with faster services.

McKenna Park – McKenna Park is currently in the final stages of design with construction expected to begin in the first quarter of 2021. Planned improvements include additional walkways, landscaping, and a new playground.

MAJOR FACILITY PROJECTSTennis Center – The new Tennis Center Project will be completed in two phases. In Phase 1, the Pro Shop is currently under construction and expected to be complete in early 2021. The new Pro Shop will include new showers and restroom amenities, lounge area, office space, retail, meeting rooms, and storage. Phase 2, currently in the bidding process, will include multiple new tennis courts and improvements to the grounds.

City Park Improvements – Lake Forest and Milam Park improvements are completed and include a new pavilion and basketball court. Park amenity items are being finalized for the Vela Athletic Complex, including an entrance arch, a historical plaque, and sculpture. The South Lakes Park improvement project is expected to go out to bid this fall to include additional tennis courts and lighting. Future park land is being evaluated for anticipated acquisition.

Page 5: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

PROJECT STATUS PROJECT STATUS PROJECT STATUS

Amherst Drive (S, W, WW) (Fordham to Malone)

Q4 2020Orr Street (S, WW, W) (Elm to Locust)

Q1 2021Kendolph Drive (S, WW) (I-35 to Willowwood)

Complete

Atlas Drive (W, WW, S)(Redstone to Hercules)

Q1 2021Oak Tree Drive (D) (Mulkey to Paisley, Paisley to Audra)

Schedule Pending

Kerley Street (S, W, WW) (Duncan to Shady Oaks)

Complete

Avenue A (S)(Ave. A to Greenlee)

Schedule Pending

Panhandle Street (S)(Aileen to Malone)

Schedule Pending

Kings Row (S, W, WW)(Stuart to Sherman)

Complete

Avenue B (S, W) (Eagle to Underwood)

Q1 2021Precision Drive (W/WW)(Airport to 1500 feet north)

Q4 2020Laguna Street (S, WW)(Yellowstone to Sherman)

Complete

Avenue H (S) (Louise to Prairie)

Q1 2021Quail Ridge Drive (S, W)(Cooper Branch to La Paloma)

Q1 2021Londonderry Lane (S, W, WW)(Teasley to Hollyhill)

Complete

Bernard Street (S, W) (Hickory to Fannin)

Q1 2021

Roberts/Woodland/Brown (S, WW, W)Roberts (from Brown to Brown) and Woodland (Brown to Cherrywood)

ActiveManhattan Drive (S, W, WW)(Yellowstone to Sherman)

Complete

Choctaw Avenue (D)(Sequoia Park to Shawnee, University to Creek)

Schedule Pending

Sandy Creek Drive (S, WW)(Angelina Bend to Sandy Creek)

Q1 2021Paisley Street (S, W, WW)(Frame to Ruddell)

Complete

Fannin Street (S, W)(Welch to Bernard)

Q4 2020Wayne Street (S, W, WW)(Boyd to Mozingo)

Q1 2021Sagewood Street (S)(Meadow to Peartree)

Complete

Foxcroft Circle (S, WW, W,)(Emerson to Emerson)

ActiveWestgate Drive (S)(Fladger to Windsor)

Schedule Pending

Smith Street (D)(Dallas to Johnson)

Complete

Fulton Street (S, W, WW)(Congress to W. Oak)

Q1 2021Whitney Court (S)(Full extent)

Schedule Pending

Sheraton Road (S)(Imperial to Sun Valley)

Complete

Hillcrest Street (S,)(Panhandle to Scripture)

Q1 2021Bowling Green Street (S, W)(Georgetown to Auburn)

CompleteSierra Drive (S, W, WW)(Yellowstone to Sherman)

Complete

Johnson Street (S, W, D, WW) (Collins to Daugherty)

ActiveCastle Lane (S)(Full extent)

CompleteWoodbrook Street (S)(Southridge to Hollyhill)

Complete

Mistywood Lane/Royal Lane (S, W, WW, D)(Woodhaven to Jamestown, including Royal and Rockwood)

ActiveForrestridge Drive (S)(Hobson to Highview)

CompleteYellowstone Place (S, W, WW)(Kings Ct. to Monterey)

Complete

Northwood Terrace (S, W, WW)(North extent to Edgewood Place)

ActiveHighview Circle (S)(Full extent)

Complete

ONE PROJECT, MULTIPLE IMPROVEMENTSThe majority of City-planned construction includes routine maintenance projects, such as street reconstruction, sidewalk enhancements, curb and gutter replacements, and water main and sewer system upgrades. Various City departments are involved in these infrastructure projects to ensure that when the project is completed, we will not need to to return for additional construction work in the near future. Listed below are recent completions and the tentative timelines for the upcoming phase of active and scheduled road projects. For current projects, the statuses listed reflects the quarter of the calendar year that the upcoming phase is expected to have a completed design and schedule for construction. For more information, visit www.improvingdenton.com.

S - Streets Project | W - Water Project | WW - Wastewater Project | D - Drainage Project

Q1 - First Quarter | Q2 - Second Quarter | Q3 - Third Quarter | Q4 - Fourth Quarter

5

Quarters listed are based on a calendar year.

Page 6: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

TXDOT PROJECT UPDATES

6

TEASLEY LANE/FM 2181: The relocation of City utilities along FM 2181 has been completed. TxDOT’s crews are currently completing the drainage improvements and constructing the new lanes of the roadway. Multiple traffic shifts are to be expected from now until the completion of the project in November 2021. Visit www.drivetexas.org, for the latest traffic and detour information.

US 377: In July 2020, northbound and southbound traffic on US 377 shifted to the newly constructed roadway to allow crews to safely build the southbound lanes. The traffic shift will be in place until the lanes move into the final configuration in early 2021. Final utility relocations have been completed, including water and sewer lines between FM 1830 and the recently demolished railroad underpass. In August 2020, TxDOT extended its working hours for the US 377 project to accelerate the progress of the project. The project is expected to be complete by January 2021.

CONSTRUCTION SAFETY MEASURES IN RESPONSE TO COVID-19Most routine improvement projects—such as street microseals, sidewalk repairs, and underground utility maintenance—is completed by the City’s Public Works staff. These maintenance projects are typically funded through a department’s annual operating budget because the City anticipates them as costs associated with maintaining facilities and infrastructure.

To safeguard the health and safety of our community and field workers, City staff developed new safety protocols for field workers and support staff to perform their jobs safely. Based on guidance and best practices from local and federal agencies, below are some of the safety measures in place for the City’s Public Works staff to minimize the spread of COVID-19 in our community.

• Daily symptom screening and health checks;• Assigned Personal Protective Equipment (PPE); • City crews were directed to wear masks when

within 6 feet of each other on job sites;• Limited occupancy of vehicles to one person, if

possible. In the event that more than one employee is in a vehicle at a time, all employees in the vehicle must always wear face masks;

• Use of personal vehicles were temporarily permitted in the event that an employee preferred to maintain social distancing when traveling to job sites;

• All City vehicles are equipped with disinfection materials to be cleaned twice a day, at minimum;

• Office staff allowed to telecommute unless essential job duties were not able to be performed remotely; and

• Gloves must be worn when touching common surfaces.

FOR

T WO

RTH

TEA

SLE

Y LN

FORT WORTH D

R

ROSELAWN DR

N I-35E

S I-35E

JAM

ES

ST

WILLOWWOOD ST

BER

NAR

D S

T

PRIVATE DR

E HOBSON LN

WIS

TER

IA S

T

W HOBSON LN

PARVIN ST

MC

CO

RM

ICK

ST

ACME ST

ME

RC

ED

ES

RD

FAIR

FAX

RD

LONDONDERRY LN

WE

STW

OO

D D

R

JAC

QU

ELI

NE

DR

LESL

IE S

T

AZA

LEA

ST

LAUREL ST

SAM

BA

SS

BLV

D

JAS

MIN

E S

T

E MISSION ST

S I-35E NORTHBOUND SERVICE RD

CA

ME

LLIA

ST

HIGHVIEW CIR

KEN

DO

LPH

DR

S LO

CUST

ST

PRIV

ATE

MASSEY ST

MO

NTE

CIT

O R

DFA

IRFA

X T

RLRICH ST

HIGHVIEW CT

PRIVATE DR

TEA

SLE

Y LN

PRIVATE DR

PRIV

ATE

DR

LESL

IE S

T

PRIVATE DR

S I-35E

PRIVATE D

R

N I-35E

I35

TEA

SLE

Y

HOBSON

OLD HWY 77

SWIS

HER

MAYHILL

I35

I35

Page 7: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

GET INVOLVED: 2020 DENTON MOBILITY PLAN

Over the last several months, the City has been working on the 2020 Denton Mobility Plan, a multimodal mobility study and strategy to address citywide transportation, including vehicles, transit, bicycles, and pedestrians, for decades to come. The second round of public meetings have been rescheduled and will be held virtually to give residents an additional opportunity to review the final draft of the comprehensive transportation plan.

Visit www.cityofdenton.com/mobilityplan to sign up to participate in an upcoming virtual Mobility Plan public meeting and learn more about the 2020 Denton Mobility Plan.

7

Have a question about a project?We’re available to talk, answer questions, and get your feedback.

Use the listing below for frequently contacted departments. For a comprehensive listing, visit www.cityofdenton.com.

For questions regarding major City projects:CAPITAL PROJECTS | (940) 349-8910 For questions regarding water and sewer: WATER/WASTEWATER | (940) 349-8786

For questions regarding property access:UTILITIES DISPATCH | (940) 349-7000 For questions regarding utilities and account billing:UTILITIES CUSTOMER SERVICE | (940) 349-8700

CONTACT US

Keeping you informed on the progress of planned construction projects is a priority for the City of Denton. Below are some existing and new ways you can stay updated on construction projects happening throughout the community: (NEW) COMMUNICATION CHECKLISTS: The Major Infrastructure Projects listed on page 3 of this Guide now have communication checklists. The new checklists are an overview of the ways in which the City provides updates to residents during the various stages of the project and what future communication is planned. The checklist is updated as the project progresses as reflected by the date at the top of the page.

(NEW) EMAIL ALERTS: Sign up for project- specific email alerts for only the projects you are interested in at www.improvingdenton.com. Click the “Sign Up For Construction Project Email Updates” link to opt-in to receive the periodic updates.

ONLINE: Visit www.improvingdenton.com to check the status of a City-planned construction project at any time.

Visit www.improvingdenton.com to learn more.

2020 MOBILITY PLAN VIRTUAL PUBLIC MEETINGS

Wednesday, Sept. 9

Thursday, Sept. 10

Monday, Sept. 14

Thursday, Sept. 17

Thursday, Sept. 24

STAY INFORMED ABOUT CONSTRUCTION PROJECTS & UPDATES

Page 8: 2020 MIDYEAR UPDATE 2020 - Home | City of Denton...and pedestrian safety on McKinney Street from South Fork to Grissom Road, $3,000,000. Funding Source: 2012 and 2014 Bond Programs

STAY UPDATEDwww.improvingdenton.com

/cityofdenton

/cityofdenton

@cityofdentontx

A publication of the City of Denton • 08/20 • ADA/EOE/ADEA • TDD (800) 735-2989 • www.cityofdenton.com

/cityofdenton

Email Notifications

For additional information about these projects and more, visit www.improvingdenton.com.8

CONSTRUCTION GUIDECITY OF DENTON