2008-1-B-WSFWP-1

Water Supply Facilities Work Plan (WSFWP)

Adoption Hearing

May 19, 2009

2008-1-B-WSFWP-1Water Supply Facilities

Work Plan (WSFWP)

Adoption Hearing

May 19, 2009

Board of County CommissionersBoard of County Commissioners

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Presentation OutlinePresentation Outline

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Presentation OutlinePresentation Outline

Legislation passed in 2005 to improve coordination of water supply planning and land use planning

Strengthened the statutory linkage between WMD regional water supply plans and local government comprehensive plans

Orange County required to revise its comprehensive plan after approval of the regional water supply plans

Legislation passed in 2005 to improve coordination of water supply planning and land use planning

Strengthened the statutory linkage between WMD regional water supply plans and local government comprehensive plans

Orange County required to revise its comprehensive plan after approval of the regional water supply plans

OverviewOverview

Water Supply Plan requirements Project County water needs for a 10-year period Identify and prioritize water supply facilities,

primary sources and alternate sources of water needed to meet projected demand

Include capital improvements needed for the first 5 years, including revenue sources

Include a ten-year Capital Improvements Schedule

Water Supply Plan requirements Project County water needs for a 10-year period Identify and prioritize water supply facilities,

primary sources and alternate sources of water needed to meet projected demand

Include capital improvements needed for the first 5 years, including revenue sources

Include a ten-year Capital Improvements Schedule

OverviewOverview

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Presentation OutlinePresentation Outline

Issued by the Department of Community Affairs (DCA) on 08/29/08

Six objections

Staff coordinated with DCA, FDEP and WMDs (South Florida and St. Johns) to formulate response

Issued by the Department of Community Affairs (DCA) on 08/29/08

Six objections

Staff coordinated with DCA, FDEP and WMDs (South Florida and St. Johns) to formulate response

ORC Report and ResponseORC Report and Response

Objection 1: Map showing existing and proposed water sources, including wells and surface waters

Response: A new exhibit showing public water supply wells, proposed surface water intakes, water treatment facilities and service areas for Orange County Utilities (OCU) has been added as Work Plan Figure 4

Objection 1: Map showing existing and proposed water sources, including wells and surface waters

Response: A new exhibit showing public water supply wells, proposed surface water intakes, water treatment facilities and service areas for Orange County Utilities (OCU) has been added as Work Plan Figure 4

ORC Report and ResponseORC Report and Response

Objection 2: Water supply and facility concurrency

Response: Policies added requiring coordination during the permit review process to determine if adequate water supplies will be available to serve the development

Objection 2: Water supply and facility concurrency

Response: Policies added requiring coordination during the permit review process to determine if adequate water supplies will be available to serve the development

ORC Report and ResponseORC Report and Response

Objection 3: Capital Improvements Schedule

Response: OCU water/wastewater capital improvement projects and budgets were incorporated into the CIE amendment adopted in April 2009

Objection 3: Capital Improvements Schedule

Response: OCU water/wastewater capital improvement projects and budgets were incorporated into the CIE amendment adopted in April 2009

ORC Report and ResponseORC Report and Response

Objection 4: Incomplete data and analysis

Response: County is required to include information on all public and private water, wastewater and reuse water providers in the County

Objection 4: Incomplete data and analysis

Response: County is required to include information on all public and private water, wastewater and reuse water providers in the County

ORC Report and ResponseORC Report and Response

Objection 5: Water conservation and reuse practices

Response: Policies added detailing County reclaimed water reuse practices

Objection 5: Water conservation and reuse practices

Response: Policies added detailing County reclaimed water reuse practices

ORC Report and ResponseORC Report and Response

Objection 6: Implementation of potable water supply project

Response: Policies revised to add the Aquifer Storage and Recovery (ASR) Pilot Well Project

Objection 6: Implementation of potable water supply project

Response: Policies revised to add the Aquifer Storage and Recovery (ASR) Pilot Well Project

ORC Report and ResponseORC Report and Response

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Overview

Objections, Recommendations and Comments (ORC) Report and Response

Requested Action

Presentation OutlinePresentation Outline

Adoption of Amendment 2008-1-B-WSFWP-1, the Water Supply Facilities Work Plan (WSFWP),

including goal, objective and policy amendments to the Future Land Use, Potable Water / Wastewater / Reclaimed Water, Conservation, Aquifer Recharge,

Capital Improvements and Intergovernmental Coordination elements.

Adoption of ordinance

Adoption of Amendment 2008-1-B-WSFWP-1, the Water Supply Facilities Work Plan (WSFWP),

including goal, objective and policy amendments to the Future Land Use, Potable Water / Wastewater / Reclaimed Water, Conservation, Aquifer Recharge,

Capital Improvements and Intergovernmental Coordination elements.

Adoption of ordinance

Requested ActionRequested Action

2008-1-B-WSFWP-1

Water Supply Facilities Work Plan (WSFWP)

Adoption Hearing

May 19, 2009

2008-1-B-WSFWP-1Water Supply Facilities

Work Plan (WSFWP)

Adoption Hearing

May 19, 2009

Board of County CommissionersBoard of County Commissioners