2004 - 2010 capital planning
DESCRIPTION
2004 - 2010 CAPITAL PLANNING. Information Sessions February 2003. CAPITAL PLANNING ADVISORY BOARD (CPAB). KRS Chapter 7A 1990 General Assembly 15 members - 5 appointed by each branch Comprehensive statewide capital improvements plan. TIMETABLE. April 15* - Agency plans due to CPAB - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/1.jpg)
2004 - 2010 CAPITAL PLANNING
Information SessionsFebruary 2003
![Page 2: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/2.jpg)
2
CAPITAL PLANNING ADVISORY BOARD (CPAB)
KRS Chapter 7A
1990 General Assembly
15 members - 5 appointed by each branch
Comprehensive statewide capital improvements plan
![Page 3: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/3.jpg)
3
April 15*April 15* - Agency plans due to CPAB
July July - CPAB hearing on plans
October 1October 1 - Plan amendments due to CPAB
November 1*November 1* - CPAB statewide plan due to branch heads
TIMETABLE
* Statutory
![Page 4: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/4.jpg)
4
STATEWIDE PLANS
Project recommendations
– General Fund cash or bonds
– other fund sources
Policy recommendations
– proposed legislation
– other
Cabinet / agency projects (prioritized)
![Page 5: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/5.jpg)
5
STATEWIDE PLANSInputs
Cabinet / agency plans
Testimony / presentations to CPAB
CIO and CPE recommendations (info technology, postsec educ)
CPAB member information / issues
Other
![Page 6: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/6.jpg)
6
CHANGES FROM 2002-2008
Major– Web-based capital planning system– Project evaluation / scoring system
Other– Reorganization of plan contents– Facilities management information– Six year horizon for equipment and IT
![Page 7: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/7.jpg)
7
SUBMISSION LEVELSingle “Agency” Plan
Independent agencies
Boards & commissions
Universities & KCTCS
Judicial Branch & Legislative Branch
Most cabinets
Selected other agencies
![Page 8: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/8.jpg)
8
SUBMISSION LEVELMulti-Agency Cabinet Plan
Education, Arts & Humanities Justice Public Protection & Regulation Tourism Development
– Cabinet & Agency Priorities– Cabinet Plan Overview
![Page 9: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/9.jpg)
9
AGENCY PLANS
Background
– Understand agency
– Context to review needs & proposals
Plan
– Capital-related needs
– How agency proposes to address
Ancillary Records
![Page 10: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/10.jpg)
10
BACKGROUND
Agency Mission and Programs
Agency Facilities Management
Capital-Related Reports
Agency Physical Plant
Status of Recently Completed / Ongoing Projects
![Page 11: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/11.jpg)
11
BACKGROUNDAgency Mission and Programs
(Form SYP-B1)
Content– Statutory basis– Major programs and functions– Service delivery (facilities, technology)
Other– One page maximum– Base on size & complexity of agency
![Page 12: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/12.jpg)
12
BACKGROUNDAgency Facilities Management
(Form SYP-B2) Content
– Organizational unit and location– Responsibilities– Personnel– Contracts / outsourcing
Other– One page maximum– Base on size & complexity of agency
![Page 13: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/13.jpg)
13
BACKGROUNDCapital-Related Reports
(Form SYP-B3)
Criteria– Completed since last plan (4/2001)– Currently underway– Planned in 2002-04
Examples– Campus or facility master plans– Feasibility studies
![Page 14: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/14.jpg)
14
BACKGROUNDForm SYP-B3 (continued)
Title Purpose Who Prepared the Report Completion Date Approval Status of Providing Copy to CPAB Related Projects
![Page 15: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/15.jpg)
15
BACKGROUNDAgency Physical Plant
State-owned property administered by the agency (Form SYP-B4a)
Other state-owned property occupied by the agency (Form SYP-B4b)
Non-state-owned property occupied / leased by the agency (Form SYP-B4c)
Non-state-owned space leased by another agency, occupied by the agency (Form SYP-B4d)
![Page 16: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/16.jpg)
16
BACKGROUNDAgency Physical Plant (continued)
Non-state-owned facilities located on state-owned land administered by the agency (Form SYP-B4e) - new
State-owned aircraft (Form SYP-B4f) - new
![Page 17: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/17.jpg)
17
BACKGROUNDStatus of Recently Completed/Ongoing Projects
(Form SYP-B5) Criteria
– Not completed as of 3/31/01
– Unbudgeted - reported to CPBOC
– Initiated under FY 2002/03 spending plan Data
– Authorizations & descriptions
– Budget (initial, current)
– Status, completion date
– Current description
![Page 18: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/18.jpg)
18
PLAN
Overview
Proposed Projects
Space Needs
Space Reductions
![Page 19: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/19.jpg)
19
PLANOverview
(Form SYP-P1)
Narrative (Form SYP-P1)
– Capital related needs & issues - how agency plans to address them
– Current priorities - process & factors
– Changes from 2002-2008 plan
– Actions affecting approach to needs
![Page 20: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/20.jpg)
20
PLANOverview
Summary Reports
– Financial Summary for Proposed Projects (Form SYP-P1a)
– (Listing of) Proposed Projects Involving the General Fund or Road Fund (Form SYP-P1b)
– (Listing of) Proposed Projects NOT Involving the General Fund or Road Fund (Form SYP-P1c)
![Page 21: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/21.jpg)
21
PLANProposed Projects (Form SYP-P2)
Capital construction - $400,000 or more
Equipment - $100,000 or more*
IT system - $400,000 or more*
State-administered grant / loan programs
Court facilities - Annual use allowance of $200,000 or more
*all three bienniaunless postsecondary scientific or research
![Page 22: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/22.jpg)
22
NEW DefinitionInformation Technology System
$400,000 threshold requiring submission now includes one or more of the following:
– Hardware
– Software
– Professional services
– Digital data products
![Page 23: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/23.jpg)
23
PLANProposed Projects (Form SYP-P2)
Project Title Biennium Agency Priority / Cabinet Priority / AB Priority Category Location Item Number Additional Funding? Brief Description / Justification
![Page 24: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/24.jpg)
24
PLANForm SYP-P2 (continued)
Project Budget
– Fund Sources & Cost Elements Impact on Agency Operating Budget
– Figures & Narrative Specific (based on category) Additional Description / Justification Previous Plans Previous Budget Requests Previous Budget Authorizations
![Page 25: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/25.jpg)
25
PROPOSED PROJECTS (Budget - Fund Sources)
General Fund (cash or bonds) Restricted Funds Federal Funds Road Fund Agency Bonds Other (private funds - cash) Other (long-term financing) - must explain Other (local bonds, court projects only)
![Page 26: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/26.jpg)
26
PLANSpace Needs (Form SYP-P3)
other than projects submitted on Form SYP-P2
Location Type of Need Why Needed Type of Space Square Footage Biennium Impact on Existing Space
![Page 27: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/27.jpg)
27
PLANSpace Reductions (Form SYP-P4)
Location Square Footage Type of Space Why the space is to be eliminated Biennium
![Page 28: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/28.jpg)
28
ANCILLARY RECORDS
Minor Projects ($50,000 - $400,000 each)– Facility Name– Type of Space– Description– Biennium– Cost Estimate– Included in Another Project (Form SYP-P2)
Agency Bond Priorities Off-Budget Funds Projects in Plans of Multiple Agencies
![Page 29: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/29.jpg)
29
PROJECT EVALUATION /SCORING SYSTEM
Critical Life Safety or Legal Liability Protecting Investment in Plant Safety Concerns, Security Issues, and Other
Government Mandates Cabinet / Agency Priority User / Non-State Financing Use Relationship to Prior Authorized Projects Savings or Efficiencies Other Factors
![Page 30: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/30.jpg)
30
2004-2010CAPITAL PLANNING SYSTEM
Web-based All sections of the plan Validations Electronic only, no hard copies
![Page 31: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/31.jpg)
31
PREPARING THE AGENCY PLAN
Obtain access to CP System
Respond to Checklist
Complete Forms
Assign Priorities
View/Print Forms
Run Validations
Submit
![Page 32: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/32.jpg)
32
USER ACCESS TO THE CP SYSTEM
AgencyContact
AgencyUser
CabinetContact
Enter/Edit Checklist Enter Data View/Print Reports Run Validations Set Agency Priorities Set Cabinet Priorities Submit Plan
![Page 33: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/33.jpg)
33
Version 0 - pre-populated data (read only)
Version 1 - April 15 submission
Version 2 - July 2003 CPAB meeting
Version 3 - as of October 1, 2003
each version will become read-onlyas of the designated cut-off date
2004-2010PLAN VERSIONS
![Page 34: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/34.jpg)
34
CPAB OFFICE CPAB Staff
– Pat Ingram, Committee Staff Administrator
– Mary Lynn Collins
– Nancy Osborne
– Dawn Groves
Room 34, Capitol Annex
[email protected] http://www.lrc.state.ky.us/statcomm/CPAB/homepage.htm
![Page 35: 2004 - 2010 CAPITAL PLANNING](https://reader035.vdocuments.us/reader035/viewer/2022062408/5681411f550346895dacf224/html5/thumbnails/35.jpg)
2004 - 2010 CAPITAL PLANNING
Information SessionsFebruary 2003