2.0 pem p36 contracts management dlp 22.08.14

Upload: sarth-shukla

Post on 02-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    1/16

    CONTRACT MANAGEMENT

    Defect Liability Period

    Prof. Ashish Goel

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    2/16

    Defect Liability Period (DLP)

    DLP:

    Meaning

    Obligations under this period

    Significance

    Contracts Management : Prof Ashish Goel,NICMAR

    2

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    3/16

    Defect Liability Period (DLP)

    Also called defect notification period.

    Starts immediately after taking over of thework.

    It is the period after taking over during whichthe contractor is responsible for correcting

    any defectin the said works.

    Contracts Management : Prof Ashish Goel,NICMAR

    3

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    4/16

    Defect Liability Period (DLP)

    What should be suitable period for defectliability ??

    One year is generally sufficient for civil engg.projects.

    In case of EPC jobs, a longer period may be requiredeg. HVAC plant.

    Employer may change the figure of 365 daysmentioned in FIDIC forms.

    Contracts Management : Prof Ashish Goel,NICMAR

    4

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    5/16

    Defect Liability Period (DLP)

    More involvement of client rather than the

    engineer... Why ???

    First hand use of completed works.

    More aware of any defects

    in the works.

    Employer need to make arrangement

    to identify any defects.

    Engineer may be used for this purpose if required.

    Contracts Management : Prof Ashish Goel,NICMAR

    5

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    6/16

    Contractors Obligation under DLP

    During the DLP the contractor is supposed to:

    Quickly address any defects or damages as notified by

    the client.

    Complete any pending works / rectifications as

    mentioned in the TOC before expiry of DLP.

    Defects due to clients mishandling & no/improper

    maintenance.

    Contracts Management : Prof Ashish Goel,NICMAR

    6

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    7/16

    Cost of Remedying Defects

    All the cost to this effect shall be borne by the

    contractor only if:

    Construction is based on contractor's design

    Problem in workmanship

    Problem in supplied material, P&M

    Contracts Management : Prof Ashish Goel,NICMAR

    7

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    8/16

    Cost of Remedying Defects

    Following are not covered under DLP :

    Normal Wear & tear.

    Defects due to clientsdesign.

    Defects due to clients mishandling & no/improper

    maintenance.

    Contracts Management : Prof Ashish Goel,NICMAR

    8

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    9/16

    Extension of DLP

    The employer may ask extension of DLP if:

    The plant or a part of same cannot be used for itsintended purpose due to the defects.

    Notice for extension for DLP is to be given byemployer at the earliest but before expiry of originalDLP.

    Generally contractors obligation shall not beapplicable two years after the DLP of plant & materialwould otherwise have expired.

    Contracts Management : Prof Ashish Goel,NICMAR

    9

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    10/16

    Failure to Remedy the Defects

    In case the contractor doesn't act even after receivingnotices from client, the employer may:

    Get the work done himself at the cost of contractor.

    In such case the contractor will be under obligation to thereasonablecost of remedying & not for the work as such.

    Accept the work with defect but reduce the contract pricein consultation with the engineer for reduction.

    Take extreme step of terminating full/part contract &recover total amount paid from contractor for such works(parts) + financing cost + dismantling cost + clearing thesite + returning plant & material to contractor.

    Contracts Management : Prof Ashish Goel,NICMAR

    10

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    11/16

    Removal of Defective work

    In case the defect is not readily rectified atsite, the contractor may remove such itemfrom site :

    The pre-requisite for such action ???.

    Employersconsent.

    Time for return

    Performance guarantee for the new/rectified part.

    This situation could result in increase of DLP.

    Contracts Management : Prof Ashish Goel,NICMAR

    11

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    12/16

    Right of Access

    During DLP (until performance certificate isissued), the contractor has the right of access tothe site but:

    Access will be reasonable as may be required to fulfil

    the obligation under contract.

    Have to be consistent with employers safetymeasures established at work place.

    In cases (specially design build/EPC contracts), thecontractor may need additional access during DLP toensure that plant is being operated as per their

    guideline. Contracts Management : Prof Ashish Goel,NICMAR 12

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    13/16

    Contractor to Search

    If required by the engineer, contractor shallsearch for cause of any defect, 2 possibilities:

    If the defect is such that it is to be remedied atthe cost of contractor ?.

    If not, then contractor may investigate theproblem & determine a suitable cost + profit forthe remedy in consultation with the engineer.

    Most common in case of employer design.

    In correct operation/maintenance by employers.

    The contractor should treat this as an extra claim &such provisions of the contract should govern.

    Contracts Management : Prof Ashish Goel,NICMAR

    13

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    14/16

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    15/16

    Un-fulfilled obligations

    Contractors obligation after issuance ofperformance certificate ??.

    Site clearance.

    Apply for final payment.

    Latent defects detected after issuance of

    certificate.

    Applicable only if the contract has specific provision to

    deal with such cases.

    Contracts Management : Prof Ashish Goel,NICMAR

    15

  • 8/10/2019 2.0 PEM P36 Contracts Management DLP 22.08.14

    16/16

    Clearance of Site

    After issuance of performance certificate thecontractor is supposed to remove following fromthe site:

    Any remaining equipment, material, rubbish &

    temporary works if any.If such items are not removed within 28 days after PC

    then the employer may

    Sell/ Dispose off such items

    Employer shall get any cost incurred in such process fromcontractor.

    If any balance amount left out after employers expenses,same to be handed over to employer.

    In case expenses exceed employer cost, contractor is

    supposed to pay the balance outstanding amount.Contracts Management : Prof Ashish Goel,NICMAR 16