2 wolf theiss

Upload: nathan-morales

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 2 Wolf Theiss

    1/33

    RES IN ROMANIA;RENEWABLE ENERGY LAWPROCEDURES & INCENTIVES

    Ciprian GlodeanuWolf Theiss

    Bucharest, 17 November 2011

  • 7/27/2019 2 Wolf Theiss

    2/33

    2

    TOC

    1. Romania RES WIND overview

    2. Up and running projects

    3. Mandatory quota of RES

    4. Support schemes

    5. Relevant legislation

    6. Promotion System for the Production of RES-Electricity

    7. Pricing for the trade of Green Certificates

    8. Price of energy

    9. Local Permitting

    10. Regulatory Framework

  • 7/27/2019 2 Wolf Theiss

    3/33

    3

    ROMNARE

    OREW

  • 7/27/2019 2 Wolf Theiss

    4/33

    4

    Romanian Energy System

  • 7/27/2019 2 Wolf Theiss

    5/335

    ROMANIA RES-WINDPotential for wind in Romania The WIND map of Romania

  • 7/27/2019 2 Wolf Theiss

    6/336

    ROMANIA TOP 20 WIND PROJECTSNo. Company Capacity (MW) Location County Investment

  • 7/27/2019 2 Wolf Theiss

    7/337

    UP AND RUNNING PROJECTS FANTANELE AND COGEALAC, CONSTANTA

    The largest project in Romania is Czech energy group CEZs wind farms in the villages of Fantanele and Cogealac inConstanta county, with turbines supplied by GE. The 1.1 billion Euro wind energy project, reportedly the largest on-shoreproject in Europe, aims to have a 600 MW total installed power capacity. In Fantanele, CEZ has raised around 120 turbinesand has an installed power of 300 MW. The firm will install around 19 more turbines for a further 47 MW in 2011.

    PESTERA AND CERNAVODA, CONSTANTAPortuguese renewable energy company EDP Renovaveis (EDPR) is using 76 Vestas wind generators, each with an installedcapacity of 3.0 MW, for this Dobrogean park. The project in Pestera [90 MW] and 69 MW of the Cernavoda project are nowconnected. The second half of Cernavoda [a further 69 MW] was due to be connected by June 2011. The company also has

    613 MW of power at different stages of development. EDPR aims to construct wind farms in Sarichioi (33MW) in Tulcea Countyand Vutcani (24 MW) in Vaslui County.

    AGIGHIOL AND SALBATICA, VALEA NUCARILOR, TULCEAItalian energy giant Enels renewable energy company Enel Green Power has opened a 34 MW wind farm in Agighiol and a 30MW farm in Salbatica, using 2 MW Gamesa wind turbines. The company hopes to install a further 40 MW by the end of 2011.Enel in 2009 bought local developer Blue Line, making the first step towards developing wind projects of a total installed powercapacity of 244 MW.

    SILISTEA 1, CONSTANTARomanian company Romconstruct Top has developed the wind park Silistea 1, Constanta county using GE turbines. Silistea 1has an installed capacity of 25 MW.

  • 7/27/2019 2 Wolf Theiss

    8/33

    8

    SUPPORT SCHEMES Feed-in tariff

    Green Certificate

  • 7/27/2019 2 Wolf Theiss

    9/33

  • 7/27/2019 2 Wolf Theiss

    10/33

    10

    Promotion System for the Production ofRES-Electricity

    for each 1MWh delivered in the electricity grid (biomass, biogas, gas of waste

    fermentation and geothermal energy), the producers of electricity through high

    efficiency cogeneration plants will supplementary benefit of one (1) GC

    for each 1MWh produced and delivered in the trial period the producers benefit

    from one (1) GC, regardless the type of electric plant which produces RES-E

    Projects must be completed by December 2016

  • 7/27/2019 2 Wolf Theiss

    11/33

    11

    Pricing for the trade of Green Certificates Trading period increased from 2008 through 2025

    Minimum trading value of EUR 27 per CG

    Maximum trading value of EUR 55 per CG

    Starting with 2011 trading value indexed with Euro zone inflation rate recorded inDecember of the previous year by the National Energy Regulatory Agency

    Failure to fulfill the annual quota obligations - an equivalent value of those GCs

    which were not purchased at a premium of EUR 110 for each un-purchased

    certificate

  • 7/27/2019 2 Wolf Theiss

    12/33

    12

    MANDATORY QUOTA

  • 7/27/2019 2 Wolf Theiss

    13/33

    13

    PRICE OF ENERGY October 2011: an average Peak price of EUR 65.46 / MW

    Off peak price of EUR 37.23 / MW

  • 7/27/2019 2 Wolf Theiss

    14/33

    14

    Source: opcom.ro

  • 7/27/2019 2 Wolf Theiss

    15/33

    15

  • 7/27/2019 2 Wolf Theiss

    16/33

    16

    LOCAL PERMITTING

    List of Permits (hand-out)

  • 7/27/2019 2 Wolf Theiss

    17/33

    17

    RGAO

    FRMWO

  • 7/27/2019 2 Wolf Theiss

    18/33

    18

    REGULATORY FRAMEWORK Outline of permitting procedures for RES-Electricity generating facilities

    Building permit (environmental authorization/approval)

    Access to the grid technical permit / Connection Agreement

    Setting up authorization (ANRE) Production License (ANRE)

    Registration with the Romanian Transmission and System operator

    Transelectrica (GCs)

  • 7/27/2019 2 Wolf Theiss

    19/33

    19

    REGULATORY FRAMEWORK

    Who issues the building permit?

    How long it takes to obtain the building permit?

    Which are the required documents?

    Are there any tax to be paid for obtaining the building permit?

  • 7/27/2019 2 Wolf Theiss

    20/33

    20

    REGULATORY FRAMEWORK Energy Law (13/2007)

    regulatory authority ANRE

    Setting up authorisation

    Production licence

  • 7/27/2019 2 Wolf Theiss

    21/33

    21

    REGULATORY FRAMEWORK License to generate RES-Electricity - outline

    ANRE authorizations for:

    construction/refurbishment of electricity and thermal power

    co-generation plants construction/refurbishment of electricity lines and transmission stations;

    and

    construction/refurbishment of electricity lines and supply stations with an

    installed power exceeding 110KV

  • 7/27/2019 2 Wolf Theiss

    22/33

    22

    REGULATORY FRAMEWORK License to generate RES-Electricity - outline

    Licenses are issued by ANRE to carry out the following:

    commercial exploitation of electric and thermal co-generated production

    capacity

    electricity transmission services electricity system services

    electricity distribution systems

    act as an electricity market operator; and

    electricity supply activity

  • 7/27/2019 2 Wolf Theiss

    23/33

    23

    REGULATORY FRAMEWORK Setting up authorisation procedure:

    the applicant files the standard application together with the relevant

    documentation

    within fifteen (15) days from the submission of documents, ANRE may

    require additional information

    the drafting of a report by ANRE either granting or rejecting theestablishment authorization and submitting this report to the regulatory

    committee of ANRE

    the regulatory committee of ANRE decides by a majority vote whether to

    grant or reject the establishment authorization; and

    communicating the committee's decision to the applicant within five (5)

    business days from such decision being issued

  • 7/27/2019 2 Wolf Theiss

    24/33

    24

    REGULATORY FRAMEWORK Additional documents required by ANRE:

    the organizational chart of the company

    files regarding the employees which evidence their professional skills;

    and

    organization and functioning regulation

    Validity:A maximum of twenty-five (25) years for commercial operation of

    electricity generating capacity and electricity distribution activities and

    a maximum of ten (10) years for electricity supply activity

    Charges on an annual basis:

    0.035% of the turnover generated by the owner for the previous year; or a minimum of approximate EUR 265, if the percentage applied to the

    turnover is lower than such minimum

  • 7/27/2019 2 Wolf Theiss

    25/33

    25

    REGULATORY FRAMEWORK Access to the electric grid for RES-E producers which benefit from GCs:

    Guaranteed access to the electric grid for RES-E producers which

    qualify and participate to the GC support scheme

    Order no. 42/2011 of ANRE provides the legal framework for the

    accreditation procedure

    Before entering the GCs market, all participants (i.e. producers of RES-

    Electricity and suppliers) must:

    register with the GCs market

    enter into a so-calledparticipation agreement

    with OPCOM; and

    register such participation agreement with the GCs Register

  • 7/27/2019 2 Wolf Theiss

    26/33

    26

    REGULATORY FRAMEWORK General trading terms for the Green Certificates:

    GCs on two different trading platforms:

    on the centralized green certificates market and

    on the green certificates bilateral contracts market

    regulated and supervised by OPCOM

    a GC, during its validity period, can be subject to successive

    transactions

    GCs value are determined, within the mandatory limits, by market

    mechanisms

    transfer of GCs from the account of the seller to the buyers account is

    performed by OPCOM only after payment confirmation.

  • 7/27/2019 2 Wolf Theiss

    27/33

    27

    REGULATORY FRAMEWORK Monitoring, reporting and enforcement of the Green Certificates system

    Order no. 44/2011 of ANRE

    monitoring is done by a special department of ANRE on the basis of the

    information provided by producers of RES-Electricity, suppliers, OPCOM

    and the TSO

    GCs may be traded only on the trading platforms

  • 7/27/2019 2 Wolf Theiss

    28/33

    28

    REGULATORY FRAMEWORK General issuing terms for Green Certificates

    - transport and system operator Transelectrica is issuing the GCs for the

    accredited RES-E producers

    - in order to obtain the GCs, the RES-E producers have to register with

    Transelectrica

    - Transelectrica issues each month, to the accredited RES-E producers,

    GCs for the electricity produced out of which it is decreased the energy

    used for own technological process

    - Transelectrica shall issue the GCs in four (4) days as of the moment all

    documentation has been provided by the RES-E producers

  • 7/27/2019 2 Wolf Theiss

    29/33

    29

    AMENDMENTS RECENTLYINTRODUCED Overcompensation 10% over the approved IRR, for each technology*

    * the indicators which ANRE is going to supervise in order to assess the possible overcompensation, extend

    usually over three (3) years.

  • 7/27/2019 2 Wolf Theiss

    30/33

    30

    AMENDMENTS RECENTLYINTRODUCED Guaranteed access RES-E producers which benefit from GCs after

    accreditation in compliance with Order 42/2011 of ANRE

    Incompatibility GCs and state aid funds reduction of the GCs number

    Decrease the number of GCs from three (3) to two (2) biomass, biogas,

    geothermal, biofluids

    Additional permits for projects exceeding 125 MW prior to accreditation

    request with ANRE, the investor must obtain approval of the GC supportscheme from the European Commission

  • 7/27/2019 2 Wolf Theiss

    31/33

    31

    Answers

    Questions

  • 7/27/2019 2 Wolf Theiss

    32/33

    32

    THANK YOU FOR YOUR ATTENTION!

    Ciprian Glodeanu

    Wolf Theiss si Asociatii SCA

    Attorneys-at-Law

    Bucharest Corporate Center

    58-60 Gheorghe Polizu Street, 13th Floor

    Bucharest, Romania

    Tel: +40 21 308 81 00

    E-mail: [email protected]

    www.wolftheiss.com

  • 7/27/2019 2 Wolf Theiss

    33/33

    33

    The contents of this presentation are provided for informational purposes only and

    are not intended to serve as legal advice and cannot substitute for legal advice or

    guidance in specific cases. Any specific questions that may arise on this topic

    should be reviewed with the assistance of legal counsel in order to ensure that any

    given concern is properly addressed in accordance with legal requirements.

    2011 Wolf Theiss si Asociatii

    All Rights Reserved