2. process department.pdf

Upload: ragh

Post on 06-Jul-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 2. Process department.pdf

    1/45

     

    Page 46 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    2.0  PROCESS DEPARTMENT

    2.1 

    Block Diagram

     The flow diagrams of a plant, showing the material and energy streams,

    are the most useful documents to visualize the process in its globality

    and understand the sequence of the unit operations foreseen in that

    plant.

    In the block diagram, a complex plant is divided in a sequence of

    modules (block), each one representing a unit, a sub-unit or a group of

    equipment performing a certain operation or function. The several

    blocks are connected by arrows, which represent the main flow ofmaterials.

    Normally the feedstocks are entering at the left side of the sheet, and

    the succession of the blocks is from left to right. The final products are

    normally obtained at the right side of the diagram.

    Each block contains a name describing its function, and the lines

    between blocks are also identified by the description of the stream and,

    eventually, by its flow rate.

    In Fig. 01 a typical refinery block diagram is shown. In this diagram

    each block refers to a refinery unit, and the streams connecting the

    blocks represent the petroleum cuts and the final products.

  • 8/16/2019 2. Process department.pdf

    2/45

     

    Page 47 of 462 

       S   T   P  -   0   1   1   /   1   3

     

       F   i  g .

       0   1

  • 8/16/2019 2. Process department.pdf

    3/45

     

    Page 48 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.2 

    Process Plant Definition

    HOLD-UP TIMES

    Level Emergency Span (1) [min]Service Level Normal Span [min] HL - LL

    HHL-HL LL-LLL

    Feed to Unit 10 2 2

    Feed to fractionator 5 2 2

    Feed to furnace 5 2 2

    Product to storage 2 1 1

    Reflux to column (2) 5 1 1

    Compressor K.O. Drum (3) 5 2 2

    Fuel Gas K.O. Drum 5 (4) 2 2

    Steam Flash Drum 5 (4) 1 2

    Steam Boiler 2 (5) - -

    Hot Oil expansion tank (6) - -

    Sour Water Stripper Surge Drum 60

    Crude Oil / Gas separator 5 (7) 1 1

    Crude Oil / Gas separator

    (API 12 J)

    Oil gravity < 0.85

    0.85 < Oil gravity < 0.934

    0.934 < Oil gravity < 1

    1

    1 – 2

    2 – 4

    1

    1

    1

    Flare K.O. Drum 10 - 30 (8)

    Note:

    1.  applicable only if HHl or LLL independent alarms /shutdown are foreseen;

    2. 

    for reflux drum consider the gold-up times for both the reflux and the product streams;

    3.  if no liquid is entering the K.O. Drum, assume a liquid mass flow rate equal to 5% of gas flow

    rate;

    4.  volume shall be at least equal to the volume of 15 m of inlet pipe;

    5.  volume shall be not greater than 1/3 of Boiler volume;

    6.  volume (calculated between ambient temp. and max operat. temp.) shall be not greater than 1/2of total volume;

    7. 

    HL not higher than 60 % of diameter;

    8.  based on maximum liquid discharge to flare system.

  • 8/16/2019 2. Process department.pdf

    4/45

     

    Page 49 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    2.2.1 

    Process Simulation

     The first activity to be performed by the process engineer is the

    definition of all the unit operations, with the correct sequence, required

    to obtain the desired products, starting from a given feedstock.

    Normally this activity needs equilibrium calculation of multicomponent

    mixtures, which can be more easily performed by a process simulator.

     These dedicated softwares enable the users to characterize the

    feedstock, selecting the chemical components (or pseudo-components)

    or defining a crude assay. Then it is possible to select the appropriate

    thermodynamic property package to be applied for flash calculations,

    and finally the user will select the unit operations to be performed

    sequentially along the plant.

     The unit operations taken into account to simulate the plant are all

    those which may vary a process parameter (pressure, temperature, flow

    rate, composition) of a stream. Typical unit operations are:

      L/V separation, corresponding to an equilibrium calculation at T

    & P of the stream; in the plant this is performed by a vessel

    separator;

      heating / cooling of a stream, to obtain an increase / decrease of

    its temperature, in conjunction with a pressure decrease; thisoperation can be performed by a heat exchanger, with or without

    change of phase;

      compression / pumping of a gaseous / liquid stream, to impose

    an increase of its pressure; this operation implies also an

    increase in temperature;

      flow through valve, causing an adiabatic (isoenthalpic)

    depressurization;

      distillation, to calculate the separation obtained through a

    distillation column; this is the most difficult process calculation,

    due to the complexity of simultaneous energy and material

    balance among the components, stage by stage.

  • 8/16/2019 2. Process department.pdf

    5/45

     

    Page 50 of 462 

       S   T   P  -   0   1   1   /   1   3

     The way to proceed to carry out the process simulation is the following:

     

    a preliminary scheme with all necessary unit operations isprepared, characterizing all the input streams (feedstock);

      process variables have to be adjusted in order to obtain the

    optimum operating conditions, necessary to get the desired

    product;

      if applicable, a sensitivity analysis shall be conducted, by varying

    some process variable in order to optimize the equipment sizing;

    this shall be done for the distillation column: the required

    product separation may be obtained with a low number of trays

    and a greater reboiler duty, or alternatively with a greater number

    of trays and a reduced reboiler duty;  after the preliminary process simulation has been completed,

    the corresponding Process Flow Diagram (PFD - see paragraph

    2.2) shall be prepared; always during the preparation of the PFD

    some modifications to the scheme are necessary: for instance the

    temperature at the exit of a cooler shall be increased because the

    cooling water temperature has been assumed lower than actual

    one, or an operating pressure at one vessel should be increased

    because the contribution of some control valves has been

    underestimated, etc.

      after the modifications of the PFD, the process simulation shall be

    finalized incorporating all necessary changes of processparameters.

  • 8/16/2019 2. Process department.pdf

    6/45

     

    Page 51 of 462 

       S   T   P  -   0   1   1   /   1   3

    A printout of a process simulation scheme is shown in Fig. 02.

    Fig. 02

  • 8/16/2019 2. Process department.pdf

    7/45

     

    Page 52 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.3  Process Flow Diagram

     The Process Flow Diagram (PFD) is always used by the process engineerin the design work and in process study.

     The PFD represents the heart of the process design, because in this

    diagram it is possible to see:

      the correct sequence of unit operations (pumps, heat exchangers,

    L/V separators, distillation columns, etc.) needed to get the plant

    performance;

      the routing of the main process streams, with their flow rates;

     

    all the operating conditions (pressure & temperature);  all process controls foreseen in the plant;

      eventual information regarding energy streams (power of

    machinery, duties of furnaces and heat exchangers, etc.);

      the stream numbers, from which it is possible to find a complete

    stream characterization in the document "Heat and Material

    Balance" (see paragraph 2.4);

    It is quite obvious that the finalization of the PFD is obtained only after

    the optimization of the process scheme, with all relevant process

    calculations (flash, distillations, heating/cooling, phase change, etc.).

    Each modification to material balance, operating conditions and

    equipment change (addition or deleting) has to be reflected into PFD.

    Some simple rules are used when preparing PFD:

      all equipment (having an item) shall be represented in the PFD.

     This means that all items are shown on PFD;

      all engines (compressors and pumps) and eventual tanks shall be

    drawn in the lower side of the sheet, over an hypothetic grade line

    placed at one quarter of the sheet height from the lower edge;vessels, column and heaters will be drawn in the superior side,

    leaving the middle space free for exchangers and connecting lines;

    column condensers and reboilers will be drawn beside their

    pertinence equipment; air condensers will be represented on the

    horizontal trace of the overhead line, while the water condensers

    will be placed upon or below the receiver;

  • 8/16/2019 2. Process department.pdf

    8/45

     

    Page 53 of 462 

       S   T   P  -   0   1   1   /   1   3

      spare equipment do not need to be represented separately from

    the main equipment: for istance the pumps P-1 A/S (A is the

    main and S is the spare pump) will be represented as a single

    pump, but showing the item P-1 A/S;

      the incoming streams shall be located preferably on the left side

    of the sheet, while the outgoing streams should leave the sheet

    from the right side;

      lines connecting the equipment shall be vertical or horizontal;

    oblique lines are not allowed; in case of intersection of two lines,

    the less important one will be interrupted. The order of

    importance is:

    main process line- secondary process line

    - utility line

    - instrument line

    In case of intersection of two lines of equal importance, the vertical one

    will be interrupted.

     

    starting from the second issue of the diagram, every modificationmade on the previous revision shall be evidenced by a revision

    cloud around the modified elements; this will help the reader to

    identify the modifications made, without analyze the whole

    drawing.

    A typical PFD is shown in Fig. 03.

  • 8/16/2019 2. Process department.pdf

    9/45

     

    Page 54 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Fig. 03

  • 8/16/2019 2. Process department.pdf

    10/45

     

    Page 55 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.4  Heat and Material Balance

    After the finalization of the PFD and the process simulation, it isnecessary to prepare the "Heat and Material Balance", containing a

    detailed characterization of each stream.

     This document is mainly constituted by a table, where for each stream

    the following physical properties and characteristics are shown:

      stream label (as shown on PFD)

      temperature & pressure

      flow rates, volumetric and mass

     

    vapour fraction

      molecular weight

      physical properties (density, specific heat, thermal conductivity,

    viscosity, surface tension)

      stream enthalpy

      stream composition

     These data are used to fill the data sheets of equipment and to make all

    subsequent process calculations. These information are available from

    the printout of the process simulation, if it has been done, or shall becalculated, case by case, if the particular system does not require a

    simulation.

    In Fig. 04 an extract of a typical material balance is shown.

  • 8/16/2019 2. Process department.pdf

    11/45

     

    Page 56 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Fig. 04

  • 8/16/2019 2. Process department.pdf

    12/45

     

    Page 57 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.5  Data Validation

    It is important to check and validate the quality and the correctness ofthe documents described in this chapter, i.e. PFD, Process Simulation,

    Heat and Material Balance, because any mistake done at this first stage

    of the project may have tremendous impact on plant performance. Any

    change in operating conditions will cause changes in flow rates of the

    relevant streams, and a re-sizing of the connected equipment could be

    needed. If the changes happen at a late stage of the project, when all

    equipment have been already supplied, the economic consequences will

    be significant.

    2.6  Piping and Instrumentation Diagram

    2.6.1 

    General

     The Piping & Instrumentation Diagrams (P&ID) have the scope to show

    all equipment, all pipe elements and all the instrumentation existing in

    a plant. P&ID is a schematic drawing, but the sequences in which all

    the plant elements are installed must be faithfully represented;

    2.6.2 

    Graphic Representation in P&ID

    While preparing a P&ID it is necessary to consider that during the

    subsequent engineering phases additional elements may be required.

    For this reason in the first draft of the drawing it is opportune to leave

    sufficient free space in the drawing area.

     The graphic representation shall follow these general principles:

    a.  Equipment distribution in the drawing area should be uniform in

    order to avoid areas with excessive concentration of drawing

    elements. If the drawing is particularly empty, it is not advisable

    to spread drawing elements over all available drawing area,especially if it leads to separate elements which functionally

    operate close one to the other. The placement of the objects on

    the drawing shall be as much as possible rational and

    “aesthetically pleasant”, to facilitate the reading and the

    interpretation of the drawing.The way of the lines shall be chosen

    in order to reduce the number of curves and intersections with

    other lines.

  • 8/16/2019 2. Process department.pdf

    13/45

     

    Page 58 of 462 

       S   T   P  -   0   1   1   /   1   3

    b. 

    Equipment dimensions shall be selected to maintain, as much as

    possible, the real proportionality scale: a pump should be smaller

    than a tank and bigger than an instrument symbol.

    c. 

    Main drains, sample connections, all the manoeuvring valves,

    insulated / jacketed / steam traced lines, slop lines, start-up

    lines, drainage systems, etc., shall always be indicated.

    d. 

    All the machines (compressors and pumps) and eventual tanks

    shall be drawn in the bottom side of the drawing area,

    horizontally aligned on a hypothetic ground line placed more or

    less at a quarter of the drawing height. Vessels, columns and

    heaters will be drawn in the upper side, leaving the middle space

    available for the interconnecting lines and exchangers. It is

    obvious that the condensers and the reboilers will be represented

    beside their pertinence equipment.e.

     

     The air condensers will be represented on the horizontal run of

    the overhead line while the water condensers will be placed on the

    vertical run upon or below the receiver, depending on their

    effective installation.

    f. 

    Minimum elevation above grade shall always be indicated for each

    vessel. The elevation shall refer to the bottom tangent line for

    vertical equipment and to the bottom line for horizontal

    equipment. Moreover if some elevation difference between

    equipment and/or piping runs is mandatory to guarantee a

    correct plant operation, it shall be clearly shown on P&ID.

    g. 

    Whenever a complex equipment requires the representation of

    many components / instruments (for instance a furnace with

    several coils, skin thermocouples, fuel to burners, snuffing steam

    and soot blowers), it would be opportune to use multiple sheets to

    represent all details required. In this case on the first diagram

    where the relevant equipment is drawn, it must be written the

    number of drawings where these details are shown.

    h.  If the diagram is made of several sheets, all the pipes going to

    consecutive P&ID, or coming from the previous P&ID, shall be

    extended at left or right side of drawing, and the height shall be

    correspondent to the height of the same line on linked P&ID; sothat two sequential drawings can be overlapped and all the lines

    pass from one to the other.

  • 8/16/2019 2. Process department.pdf

    14/45

     

    Page 59 of 462 

       S   T   P  -   0   1   1   /   1   3

    i. 

    If any pipe is not connected to any equipment in one or more

    sheet, it shall be represented only in the drawing where the

    equipment is shown. This means that it is not necessary to draw

    a line sequentially along all sheets, if this is not specificallyrequired to represent some elements (fitting or instrument) on

    these sheets. Pipes incoming and outgoing from the sheet shall

    show the fluid indication, the destination (From\To), the origin /

    destination drawing number, on the panel in which they are

    connected.

     j.  In the pipes incoming (feed) and outgoing (products) from the

    plant, the battery limits shall be clearly represented, with the

    eventual block valves and/or spectacle blind. Limits relevant to

    the scope of supply (for packages, parts of plant, equipment, etc.)

    shall be clearly represented, with indication of each responsible

    for the supply (for instance: Client, package’s vendor, EPC

    contractor, etc.) at the transition point. Supply limit shall be

    shown also for instrument (for instance between a local

    transmitter, by package vendor, and DCS controller, by

    Contractor).

    k.  Generally the equipment item shall be placed under the machines

    and storage tanks, while for vessels, heaters, columns etc., it

    shall be placed upon.

     The equipment service shall be indicated under its item.

     Two different solutions could be actuated for the graphic location of

    the equipment item and service:

      In the drawing area, next to the equipment the item only shall be

    indicated, and in the lowest/highest side of the sheet, vertically

    aligned with the equipment, it is represented the item, the service

    and any other information relevant to that equipment; these

    information shall be located in the bottom side if referring to

    machines (pumps and compressors), in the upper side for all

    other equipment.

      Item and service of equipment are indicated next to the same

    equipment in the drawing area.

    Solution 1 is normally the preferred one.

     The equipment items normally used in P&ID are listed in paragraph

    2.6.3.

  • 8/16/2019 2. Process department.pdf

    15/45

     

    Page 60 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    l. 

     The connection lines of the equipment shall be horizontal or

    vertical while the oblique lines, unless particular exceptions, shallbe avoided.

    m. 

    In case of interception of two lines, vertical line is interrupted if

    both lines have the same importance, otherwise the less

    important line will be interrupted. The line importance level is:

    -  Main process lines

    -  Secondary process lines

    -  Utility lines

    - Instrument lines

    n. 

    Starting from the second issue, any modification of the elements

    of the drawing shall be identified by revision clouds, with a

    revision index.

    o. 

    Line numbers or pipe diameters shall be written:

    -  in horizontal position upon the line, if it is horizontal;

    - in vertical position (bottom-up) on the left of the line ifit is vertical.

    If next to the line there is no space for writing its number, this shall be

    placed in close proximity to it. An arrow shall be used to connect the

    line number / diameter to the interested line.

     The list of the equipment represented in the P&ID shall be indicated

    over the template. This list shall be readable with the drawing folded in

    A4.

  • 8/16/2019 2. Process department.pdf

    16/45

     

    Page 61 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    2.6.3 

    Item of Equipment

    All equipment is identified with an "item". Equipment item is assigned

    by the process manager as soon as it is inserted into the process

    scheme. It may also be necessary, in order to meet the Client needs, to

    rename the equipment previously “itemized” with other items names.

    Equipment item will be assigned according to the following criteria

    (unless some modifications requested by the Client).

     The item is structured as:

     TTT-UUNN (X/…/Z) to include the following information: TTT: equipment typology

    UU: plant/unit of the equipment

    NN: progressive number (within typology and unit)

    X/…/Z: functional class – if required (parallel, main or spare)

     The equipment typology is identified by means of 3 letters maximum in

    accordance with the following Table 1:

  • 8/16/2019 2. Process department.pdf

    17/45

     

    Page 62 of 462 

       S   T   P  -   0   1   1   /   1   3

     

     Table 1

    Equipment TypeItem Equipment Type

    A Basins – Pits

    B Fans – Blowers

    BC Battery Charger

    C Columns

    CB Power Factor Improvement Groups

    CF Centrifuges

    CT Cooling towers

    D (as second letter) Diesel Engine

    DE Diesel Emergency Generators

    DH Deaerators

    DR Dryers

    DS Desuperheaters

    E Heat exchangers

    EA Air CoolersEG Electric Generators

    F Filters

    FL Flares

    GE (as 2nd and 3rd letter) Machinery Gas Engines

    H Fired Heaters - Furnaces

    I Equipment for Solid Handling (belts, lifting equipment, etc.)

     J Ejectors

    K Compressors

    LA Loading Arms

    LP Local Panels

    M (as 2nd letter) Machinery Electric Motor

    MCC Motor Control Center

    MX Mixers (both agitator and static mixers)

    P Pumps

    PC Low Voltage PanelsR Reactors

    SG Boilers

    SL Silos

    SC Steam trap

    SWG Medium Voltage Panel

     T (as 2nd letter) Machinery Turbine

     TG Gas Turbine

     TR Transformers

     TK Tanks

     TS Steam Turbine (generator)

    U Various no process Equipment (balances, bridge cranes, etc.)

    UPS Uninterrupted Power Supply

    V Vessels

    W "Package" Unit

    X Miscellaneous

    Z Special Equipment

  • 8/16/2019 2. Process department.pdf

    18/45

     

    Page 63 of 462 

       S   T   P  -   0   1   1   /   1   3

     The equipment of the same typology shall be numbered with 4 digits,

    where the first and the second will represent the unit and the other two

    the progressive number.

    For instance a Pumps of Unit 02 will be numbered as: P-0201, P-0202,

    P-0203, etc.

    When the same service is provided by two or more equipment, the

    functional class indicates if the equipment are working in parallel or if

    the other one is spare.

     The working equipment shall be identified with alphabetic letters

    starting from A. The spare equipment will be identified with the letter S.

    For instance the item P-0203 A/B/S identifies the 3rd pump of the unit

    02, and it indicates that 3 pumps are installed (A, B, S), where two (A,

    B) are working in parallel, and one (S) is kept as spare.When an equipment belongs to a "package" or to a complex equipment,

    such as a compressor or a gas turbine, its item shall be written after the

    main equipment item.

    For instance the item W-1202-P-01 S identifies the pump P-01 S

    (therefore spare) related to the package W-1202.

    2.6.4 

    Fluid Identification

    Each fluid moving along the Plant is identified by a code, made of

    maximum 3 alphabetic characters. Fluid can be categorized as process

    fluid or utility fluid.

    When a project starts, the Fluid List is prepared by the Process

    Department, in order to allow the selection of suitable Piping Classes.

     The process fluids can be generically identified with a “P” letter.

    Different code can be adopted if it is required by the Client.

     The utility fluids codes will be in accordance with the Table 2, unless

    otherwise requested by Client.

  • 8/16/2019 2. Process department.pdf

    19/45

     

    Page 64 of 462 

       S   T   P  -   0   1   1   /   1   3

     

     Table 2

    Codes for Utility FluidsItem Fluid

    WATER

    HW Hot Water

    CHW Chilled Water

    CW (S) Cooling Water (Supply)

    CW (R) Cooling Water (Return)

    BW Boiler Feed Water

    HBW High Pressure Boiler Feed Water

    LBW Low Pressure Boiler Feed Water

    SW Sea Water

    DM Demineralised Water

    PW Process Water

    DW Drinking Water

    RW Raw Water

    FW Fire WaterSTEAM & CONDENSATE

    HHS Very High Pressure Steam

    HS High Pressure Steam

    MS Medium Pressure Steam

    IS Intermediate Pressure Steam

    LS Low Pressure Steam

    LLS Very Low Pressure Steam

    HPC High Pressure Condensate

    MPC Medium Pressure Condensate

    LPC Low Pressure Condensate

    SC Suspect Condensate

    COMPRESSED GASES

    PA Plant Air

    IA Instrument Air

    NI Nitrogen

    IG Innert Gas

    HNI High Pressure Nitrogen

    OX Oxygen

    FUELS

    FG Fuel Gas

    NG Natural Gas

    FO Fuel Oil

    CHEMICAL

    CA Caustic Solution

    CAS Spent Caustic

    NH Ammonia

    SA Sulphuric Acid

    HO Hot Oil

    FLARE & BLOWDOWNBD Blow Down

    ABD Acid Blow Down

    AF Acid Flare

    HF Hydrocarbon Flare

    SEWERS

    CSR Chemical Sewer

    OSR Oily Sewer

    SSR Sanitary Sewer

    WSR Water Sewer

    CD Closed Drain

  • 8/16/2019 2. Process department.pdf

    20/45

     

    Page 65 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.6.5  Line Classification

    Each line shall be classified to permit the procurement of the adequate

    instrument and piping bulk material.

    Each line shall have its own number. A unique line number can be

    assigned to contiguous runs of piping having the same piping class, the

    same operating temperature and the same design conditions.

    In order to assign a specific piping class to a line, it is necessary to

    select, within the piping classes having the material and the corrosion

    allowance specified for the specific fluid, the one with the flange rating

    suitable to the design conditions of that line.

    Material and corrosion allowance to be applied for a certain fluid are

    normally defined in the “Material Selection Diagram”, document

    prepared by the process team before the development of the P&IDs.

    If the change of the piping class (and line number) is operated between

    two contiguous lines, it is necessary to show the exact point of the

    change. In this case a class transition segment (spec-break) with the

    indication of the two contiguous line numbers shall be inserted. If the

    change of the line number is due to the necessity to change the material

    of the line (i.e. the piping class), at the transition point it shall be shown

    the change in piping class instead of the change of line number.

     The lines numbering shall be carried out in accordance with the Client

    Standards. In absence of specific requirements by the Client the here

    below described APS standards shall be used. The line number is a text cell which contains the following character

    groups:

    DDDD-FFF- NNNNN-CCCC-L

      DDDD: nominal pipe size, in inches or, whenever required by the

    Client, in millimetres; maximum of 4 digits;

      FFF: fluid code; maximum of 3 digits;

     

    NNNNN: line number, eventually combined with the unit number;5 digits maximum;

      CCCC: piping class; 4 digits maximum

      L: insulation code; 2 digits maximum;

    Example: 12"-LS-25523-AB01-H

  • 8/16/2019 2. Process department.pdf

    21/45

     

    Page 66 of 462 

       S   T   P  -   0   1   1   /   1   3

    Line number shall be made of the unit number followed by a

    progressive number of 3 digits (from 001 to 999).

    Process lines shall use progressive numbers from 001 to 499 (withineach unit). The numbers from 500 to 999 shall be used for the utility

    lines.

    As soon as the project starts it shall be decided the units numeration

    and the numbers range to be used for each utility in the Plant (for

    example: LS from 501 to 550, MS from 551 to 600, CW from 601 to 650,

    etc.).

     Table 3Insulation Codes

    ItemInsulation

    AAnti Sweetening Insulation

    NNot Insulation and Not Painting

    VPainting

    CCold Insulation

    HHeat Conservation

    P Personnel Protection

    SSteam Tracing

    EElectrical Tracing

    UUnderground Line

    XAcoustical Insulation

    W Jacketing

    Note:

    1 - Those codes may be incremented to meet specific project needs. Whenever the lines need morethan one insulation type (for example for heat conservation and acoustical insulation) it will bepossible to use the double code.

  • 8/16/2019 2. Process department.pdf

    22/45

     

    Page 67 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    2.7  Process Calculation

    In a previous paragraph has been described the process simulation, to

    be performed during the development of the Process Flow Diagrams,

    which finalize the flows of the streams within the plant and the

    operating variable. After that, before the preparation of the process data

    sheets of equipment and instrumentation, the process engineer is called

    to calculate, from a process point of view, most of the plant

    components. It is important to note that the complete design of a plant

    component (like a vessel for instance), requires the contribution of

    several engineering specialties: the process engineer, who identifies

    some basic data, the mechanical engineer, who calculate the

    mechanical details and identifies the exact materials to be used for eachpart of the equipment, the piping engineer who identifies the orientation

    of nozzles, etc.. In the next paragraphs it is described the main

    calculation to be carried out by the process engineer, necessary for the

    subsequent preparation of the process data sheets.

    2.7.1  Line Sizing

     This calculation is required to identify the diameter of each pipe of the

    plant. The calculation is based on the following input data:

      type of fluid (liquid, vapour, mixed phase)

      flow rate

      fluid characteristics (density, viscosity, etc.)

      expected pipe length

      available pressure drop

    At the beginning of the project, when the routing and the components of

    the pipes has not yet finalized, the pipe length is simply estimated on

    the basis of the distance of the connected equipment.

  • 8/16/2019 2. Process department.pdf

    23/45

     

    Page 68 of 462 

       S   T   P  -   0   1   1   /   1   3

    Using dedicated software, or graphs collection, it is possible to obtain,

    for each line, the following two characteristic parameters:

      fluid velocity

      specific pressure drop

    On the basis of extensive experience, the correct size of the pipe is

    chosen in order to keep these two parameters within a range of

    acceptable value.

    In the following tables 4-1 A-C are indicated the acceptable range for

    velocity and specific pressure drop, which could be used for pipe size

    selection.

  • 8/16/2019 2. Process department.pdf

    24/45

     

    Page 69 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Table 4-1 A

    Liquid Service 

    Service Pressure Drop

    [bar/km]

    Velocity

    [m/s]

    1. Pump suction:

    - C1,C2, C3 at boiling point 0.4 – 0.7 0.5 max

    - liquid at boiling point 0.6 – 0.9

    - subcooled by 25 °C 2.3 – 3.5

    1.0 max (Ø ≤ 18")

    1.5 max (Ø > 18")

    2. Pump discharge 3.0 – 5.0 3.0 max

    3. Natural circulation (reboiler inlet) 0.2 – 0.4 - - -

    4. Column side extraction

    - Ø ≤ 8" 0.7 max

    - 8" < Ø ≤ 16" 0.9 max

    - 16" < Ø 1.1 max

    5. Inlet to L/L separator 1.0 max

    6. Cooling Water

    - branches to users 2.3 – 3.5 2.5 max

    - interconnecting headers 0.6 – 1.0 2.5 max

    7. Utility Water 3.0 – 4.5 1.5 – 3.0

    8. Boiler Feed Water

    - P ≤ 50 bar 3.0 – 4.5 1.5 – 3.0

    - P > 50 bar 7.0 – 9.0

    9. Steam condensate 0.3 – 0.6 1.0 max

    10. Sea water 2.0 – 2.5

    11. Hot Oil 1.0 min

    12. Gravity Lines 0.2 – 0.5 1.0 max

    13. Drain Lines 1.0 max (Ø ≤ 2")

    Table 4-1 B

  • 8/16/2019 2. Process department.pdf

    25/45

     

    Page 70 of 462 

       S   T   P  -   0   1   1   /   1   3

     Gas Service 

    ServicePressure Drop

    [bar/km]

    Velocity

    [m/s]

    1. Process Gas

    - general 18 – 24

    - with CO2 > 1 % vol. 15 max

    2. Compressors suction / discharge

    - centrifugal max allowed:

    {- 2.2608X3 + 9.2286X2 

     – 21.332X + 28.931}

    with X=Log10 (Density)

    expressed as kg/m3

     

    - reciprocating max allowed:

    {- 2.186X3 + 7.6539X2 –

    12.444X + 15.618}

    with X=Log10 (Density)

    expressed as kg/m3 

    3. Vacuum 4 % Abs. Press. max

    4. Steam to users

    P ≤ 10 bar 0.5 – 2.0 30 max

    10 < P ≤ 30 bar 1.0 – 2.5 45 max

    30 bar < P 1.0 – 2.5 50 max

    5. Steam to headers

    P ≤ 10 bar 0.1 – 0.2 30 max

    10 < P ≤ 30 bar 0.2 – 1.0 45 max

    30 bar < P 0.2 – 1.0 50 max

    6. Column overhead 0.2 – 0.6

    7. Plant Air 30 max

    8. Instrument Air 30 max

    9. Fuel Gas 40 max

    10. Flare header 0.7 Mach max

    11. Safety Valve discharge 0.5 Mach max

    ρv2 < 60'000 kg/ms2 

  • 8/16/2019 2. Process department.pdf

    26/45

     

    Page 71 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Table 4-1 C

    Mixed Phase 

    ServicePressure Drop

    [bar/km]

    Velocity

    [m/s]

    1. Preliminary Sizing 5'000

  • 8/16/2019 2. Process department.pdf

    27/45

     

    Page 72 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    2.7.2  Vessel Calculation

    2.7.2.1 

    Liquid / Gas Separator

     These vessels shall be sized in order to keep vapor velocity sufficiently

    low and facilitate the separation of the two phases.

    Whenever suspended droplets of liquid must be removed from the vapor

    to the maximum extent (e.g. process compressor suction separators),

    mist eliminators shall be installed.

     The L/V inlet nozzle shall be always equipped with internal distributor

    promoting the separation of the phases.

    Vessels with vapor flow only, such as compressor KO drum, shall bedesigned as for liquid-vapor separators, assuming that the

    characteristics of liquid are those of the liquid in equilibrium with the

    vapors.

     The recommended hold – up times shall be in accordance with the Table

    here enclosed.

     The installation of a high liquid level alarm shall be foreseen (and the

    corresponding hold-up shall be considered) on the following services:

      compressor suction separators

      unit surge drum

     The installation of a low liquid level alarm shall be foreseen (and the

    corresponding hold-up shall be considered) on the following services:

      critical pump suction vessels

      L/V separator feeding liquid to a downstream vessel by pressure

    difference.

     The min. liquid level in L/V separators (horizontal or vertical) shall be at

    least 250 mm.In horizontal L/V separators, the vapor space, or space above the

    maximum liquid level, shall not be less than 20% of diameter.

  • 8/16/2019 2. Process department.pdf

    28/45

     

    Page 73 of 462 

       S   T   P  -   0   1   1   /   1   3

    For vertical separators, the following geometric constraints shall be

    satisfied:

      the height between the bottom of inlet nozzle and the max liquid

    level shall be not less than 300 mm or inlet nozzle diameter,

    whichever is greater;

      the height between the top of inlet nozzle and the top tangent line

    of the vessel (without demister) shall be not less than 50 % of

    vessel diameter, with a minimum of 500 mm and a maximum of

    900 mm;

      the height between the top of inlet nozzle and the bottom of the

    demister shall be not less than 250 mm plus the 25 % of vessel

    diameter, with a minimum of 500 mm;  the height between the top of the demister and the top tangent

    line of the separator shall be not less than 250 mm plus the 7.5

    % of vessel diameter, with a minimum of 450 mm;

    Vessel height or length should be within the range of 2-4 times vessel

    diameter.

     The maximum allowable vapor velocity may be calculated following

    several methods, here below described.

    Critical velocity method

     The “critical velocity” of the vapor phase is defined as follows:

    VC = 0.048 * [(ρL/ρV) - 1]0.5

    where:

    VC = critical velocity, m/sec.

    ρL = liquid density at cond., kg/m3

    ρV = vapor density at cond., kg/m3

     The area used for calculating critical velocity is the one available for

    vapor flowing: in a horizontal vessel is the cross sectional area above

    the max liquid level, and in a vertical vessel the total cross sectional

    area.

  • 8/16/2019 2. Process department.pdf

    29/45

     

    Page 74 of 462 

       S   T   P  -   0   1   1   /   1   3

     

     The L/V separators shall be sized for a maximum allowable vapor

    velocity as specified on Table 4-2 A.

     Table 4-2 A

    Max Allowable Vapor Velocity (% of Critical Velocity)

    Service without Demister with Demister

    Vertical Horiz. Vertical Horiz.

    Separator (P < 35 Bar g) 125 220 220 220

    Separator (P ≥ 35 Bar g) 100 165 165 165

    Compressor K.O. Drum

    (P < 35 Bar g)

    100 - - - 175 - - -

    Compressor K.O. Drum

    (P ≥ 35 Bar g)

    80 - - - 133 - - -

    Steam Flash Drum 125 - - - 220 - - -

    Vacuum Service

    (P < 0.17 Bar A)

    - - - - - - 110 110

    Vacuum Service

    (0.17 ≤ P < 1.013 Bar A)

    - - - - - - 180 180

    Flare K.O. Drum - - - 275 - - - - - -

    API RP 521 Practice

    Following this practice, for a liquid drop of a fixed diameter dispersed in

    the gaseous stream it is possible to calculate the dropout velocity and

    subsequently the time required to travel vertically down to the liquid

    level. If the residence time of the gas phase inside the separator is

    greater than the descent time of the liquid particle, the particles of such

    particular diameter will be separated.

     The minimum diameter of particles to be separated are defined in Table

    4-2 B as function of the service.

  • 8/16/2019 2. Process department.pdf

    30/45

     

    Page 75 of 462 

       S   T   P  -   0   1   1   /   1   3

     

     Table 4-2 B

    Diameter of Liquid Drop to be Separated

    Service Diameter [μm]

    Flare K.O. Drum 300 - 600

    API 12 J Specification

    Following this practice, specifically relevant to gas / oil separators, theL/V separation is considered adequate if the actual gas velocity is not

    greater than the maximum allowable superficial velocity VA:

    VA = K * [(ρL/ρV) - 1]0.5

    where ρL and ρV have the same meaning as in the critical velocity

    expression, and K is a constant depending upon design and operating

    conditions, which should be not greater than:

    0.5 * (L/10) 0.56 where L is the separator length, in feet.

    2.7.2.2 Liquid – Liquid Separators

     These vessels shall be sized in such a way that the settling time for each

    liquid phase from the other is less than its residence in the vessel itself.

    Settling velocity for the dispersed droplets is calculated using Stokes,

    Newton’s or an intermediate law, according to field of application. The

    dimensions to be assumed for the droplets are defined in Table 4-2 C

     Table 4-2 C

    Diameter of Dispersed Droplets

    Light phase density (@ 15 °C) Heavy phase Drop Diameter [mm]

    850 kg/m3 or lower Water or caustic solution 0.12

    over 850 kg/m3 Water or caustic solution 0.08

  • 8/16/2019 2. Process department.pdf

    31/45

     

    Page 76 of 462 

       S   T   P  -   0   1   1   /   1   3

    A maximum settling velocity of 250 mm/minute shall be assumed for

    light hydrocarbons.

    It should also be verified that the hold-up time necessary for any phasefor settling satisfies process hold-up requirements.

    In Fig.05 is shown a typical calculation sheet for an horizontal V/L/L

    separator.

  • 8/16/2019 2. Process department.pdf

    32/45

     

    Page 77 of 462 

       S   T   P  -   0   1   1   /   1   3  

    Fig. 05

  • 8/16/2019 2. Process department.pdf

    33/45

     

    Page 78 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.7.2.3 

    K.O. Drum on Reciprocating Compressor

     The analogic study of reciprocating compressor circuit will be extended

    up to the suction KO drum, when the minimum volume of the drum

    itself is calculated as follows:

    V = (10*C*A)/(2π*n/60)

    where:

    V = vessel volume [m3 ]

    C = gas sonic velocity [m/sec]

    A = cross section of piping between KO drum and compressor [m2 ]n = Compressor rpm. Assume 300 during design phase and verify after

    compressor definition.

    2.7.3 

    Pump Calculation

    Overdesign

    Pump design flow rates shall include a minimum of 5% margin on max.

    operating flow rate for pump with rated power higher than 150 kW and

    10% for pump with lower rated power.

    For reflux and pumparound pumps, design flow rate shall include a

    margin of 20% on max. operating flow rate.

    Pump differential head indicated in the specification sheet shall be

    calculated at design flow-rate.

    NPSH Calculation

    Suction line losses shall be calculated at design flow rate of the pump.

    Pressure drop through the suction strainer shall be taken into account.

    Pressure drop across the strainer will be assumed equal to 0.5 m of

    liquid column.

    For subcooled liquids, the source pressure shall be the minimum

    normal operating pressure and the vapor pressure shall be at specified

    pumping temperature.

  • 8/16/2019 2. Process department.pdf

    34/45

     

    Page 79 of 462 

       S   T   P  -   0   1   1   /   1   3

    Static suction head shall be measured from the minim liquid level to the

    centreline of a horizontal centrifugal or rotary pump, or the suction

    nozzle of a vertical centrifugal pump or reciprocating pump.

    Static suction head for pumps connected to storage tanks shall be

    calculated at the lowest specified liquid level in the tank a which design

    pump flow rate is required.

    If vortex breaker is required, the pressure drop through it shall be

    considered.

    For horizontal centrifugal pumps, the elevation of the pump centreline

    shall normally be 0.6 m minimum above grade, unless the actual

    elevation is know.

    Available NPSH values not higher than 7 m shall be shown on pump

    specifications, even if actually available. Maximum value of NPSH = 7shall be shown on pump specification in case of a higher value will be

    calculated.

    In Fig. 06 is shown a typical calculation sheet for pumps.

  • 8/16/2019 2. Process department.pdf

    35/45

     

    Page 80 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Fig. 06

  • 8/16/2019 2. Process department.pdf

    36/45

     

    Page 81 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.7.4  Column and Tray Calculation

    Column diameter will be calculated using an over design of 10% of

    normal flow rates.

    In general, valve or sieve trays shall be used, together with rain deck

    trays (or equivalent) and packing (unless otherwise required).

    Sieve trays may be used in fouling service.

    Valve tray columns will be specified with the following max. flooding

    factors:

      77% for Vacuum Tower

      82% for other services

      70% for column diameter under 900 mm

     Tray hydraulic calculations and hence column diameter confirmation

    shall be performed by the tray vendor. The following sizing criteria shall

    be recommended to tray vendors.

    Required tray flexibility shall be 50 – 110% unless otherwise specified.

     The following values are minimum recommended for tray spacing of

    valve tray towers:

  • 8/16/2019 2. Process department.pdf

    37/45

     

    Page 82 of 462 

       S   T   P  -   0   1   1   /   1   3

     

     Table 4-4 A

     Tray Spacing

    Fouling Service Tower

    Diameter (ID)

    Clean Service

    1 pass 2 or more passes

    [mm] [mm] [mm] [mm]

    ID ≤ 1500 300 450 - - -

    1500 < ID ≤2300 300 525 450

    2300 < ID ≤3100 375 600 525

    3100 < ID ≤6000 450 675 600

    6000 < ID 525 750 675

    Note:

    1) If a manhole is present, minimum tray spacing shall be 600 mm or 150 mm morethan manhole diameter, whichever is greater;

    Indicative pressure drop values per tray are listed below according to

    operating pressure:

     Table 4-4 B

     Tray Pressure Drop

    Column Pressure

    [Bar abs]

    Pressure Drop

    [Bar] / tray

    0.05 0.004

    1.013 (ATM) 0.005 – 0.008

    30 0.01

    Vapor load for a column with high liquid load can be increased using

    multi-pass trays.

    Being more expensive, however, this option is only justified by an

    effective saving in total column costs (by utilising smaller column

    diameters).

  • 8/16/2019 2. Process department.pdf

    38/45

     

    Page 83 of 462 

       S   T   P  -   0   1   1   /   1   3

    Downcomer clearance, vertical distance between the tray and the

    downcomer bottom, is generally not less than 25mm, 40 mm for dirty

    liquid.

    Downcomer clearance velocity should be lower than 0.3 m/sec.

    Weir height value is usually 50 mm, with a total lenght not lower than

    60% of column diameter.

    Weir loading, to avoid blowing, should be  0.01 lt/min cm.

    Downcomer back-up shall not be higher than 50% of tray spacing plus

    weir height.

    A lower value (40%) should be used for services with high or moderate

    foaming tendencies, or with a tray spacing

  • 8/16/2019 2. Process department.pdf

    39/45

     

    Page 84 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Fig. 07

  • 8/16/2019 2. Process department.pdf

    40/45

     

    Page 85 of 462 

       S   T   P  -   0   1   1   /   1   3

    2.8  Process Data Sheets

     The process data sheets are formats (one type for each class ofequipment) with fixed cells relevant to representative parameters for

    that class of equipment, to be filled in by the process engineer.

    Once the process data sheet has been compiled, it can be passed to the

    engineering section for further design development.

     The process parameters which need to be specified on all data sheets

    are typically:

      operating conditions (pressure and temperature)

     

    design conditions (pressure and temperature)  construction material (for istance "carbon steel" or "stainless

    steel") and corrosion allowance

      connection nozzles size and rating

    For pumps, compressors, filters, etc., in general for all the equipment

    which are sized taking into account the flow rate and quality of the fluid

    handled in the equipment, it will be necessary to specify:

     

    nature of the fluid

      flow rate

      physical properties of the fluid (at operating conditions)

      presence of corrosive / toxic materials

    In addition to these data, each class of equipment is identified by

    additional peculiar parameters, as shown below.

  • 8/16/2019 2. Process department.pdf

    41/45

     

    Page 86 of 462 

       S   T   P  -   0   1   1   /   1   3

    Vessel / Column Data Sheets

     

    diameter

      height / length

      liquid level (high, low) inside the equipment

      elevation of some particular nozzle

      need for insulation

    Pump Data Sheet

      differential height

      NPSH available

    Compressor Data Sheet

      differential pressure

      gas composition / molecular weight

      gas Cp/Cv

    Filter Data Sheets

      degree of filtration required

      efficiency of filtration

    Heat Exchanger Data Sheets

      Duty exchanged

      Physical properties of both cold / hot fluids

      Vaporization / condensation enthalpy curve (in case of change of

    phase)

     The following Fig. 08 - 10 show some typical process data sheet for

    vessel, pump and heat exchanger.

  • 8/16/2019 2. Process department.pdf

    42/45

     

    Page 87 of 462 

       S   T   P  -   0   1   1   /   1   3

     

  • 8/16/2019 2. Process department.pdf

    43/45

     

    Page 88 of 462 

       S   T   P  -   0   1   1   /   1   3

     

  • 8/16/2019 2. Process department.pdf

    44/45

     

    Page 89 of 462 

       S   T   P  -   0   1   1   /   1   3

     

  • 8/16/2019 2. Process department.pdf

    45/45

     

    Page 90 of 462 

    1   1   /   1   3