2. process department.pdf
TRANSCRIPT
-
8/16/2019 2. Process department.pdf
1/45
Page 46 of 462
S T P - 0 1 1 / 1 3
2.0 PROCESS DEPARTMENT
2.1
Block Diagram
The flow diagrams of a plant, showing the material and energy streams,
are the most useful documents to visualize the process in its globality
and understand the sequence of the unit operations foreseen in that
plant.
In the block diagram, a complex plant is divided in a sequence of
modules (block), each one representing a unit, a sub-unit or a group of
equipment performing a certain operation or function. The several
blocks are connected by arrows, which represent the main flow ofmaterials.
Normally the feedstocks are entering at the left side of the sheet, and
the succession of the blocks is from left to right. The final products are
normally obtained at the right side of the diagram.
Each block contains a name describing its function, and the lines
between blocks are also identified by the description of the stream and,
eventually, by its flow rate.
In Fig. 01 a typical refinery block diagram is shown. In this diagram
each block refers to a refinery unit, and the streams connecting the
blocks represent the petroleum cuts and the final products.
-
8/16/2019 2. Process department.pdf
2/45
Page 47 of 462
S T P - 0 1 1 / 1 3
F i g .
0 1
-
8/16/2019 2. Process department.pdf
3/45
Page 48 of 462
S T P - 0 1 1 / 1 3
2.2
Process Plant Definition
HOLD-UP TIMES
Level Emergency Span (1) [min]Service Level Normal Span [min] HL - LL
HHL-HL LL-LLL
Feed to Unit 10 2 2
Feed to fractionator 5 2 2
Feed to furnace 5 2 2
Product to storage 2 1 1
Reflux to column (2) 5 1 1
Compressor K.O. Drum (3) 5 2 2
Fuel Gas K.O. Drum 5 (4) 2 2
Steam Flash Drum 5 (4) 1 2
Steam Boiler 2 (5) - -
Hot Oil expansion tank (6) - -
Sour Water Stripper Surge Drum 60
Crude Oil / Gas separator 5 (7) 1 1
Crude Oil / Gas separator
(API 12 J)
Oil gravity < 0.85
0.85 < Oil gravity < 0.934
0.934 < Oil gravity < 1
1
1 – 2
2 – 4
1
1
1
Flare K.O. Drum 10 - 30 (8)
Note:
1. applicable only if HHl or LLL independent alarms /shutdown are foreseen;
2.
for reflux drum consider the gold-up times for both the reflux and the product streams;
3. if no liquid is entering the K.O. Drum, assume a liquid mass flow rate equal to 5% of gas flow
rate;
4. volume shall be at least equal to the volume of 15 m of inlet pipe;
5. volume shall be not greater than 1/3 of Boiler volume;
6. volume (calculated between ambient temp. and max operat. temp.) shall be not greater than 1/2of total volume;
7.
HL not higher than 60 % of diameter;
8. based on maximum liquid discharge to flare system.
-
8/16/2019 2. Process department.pdf
4/45
Page 49 of 462
S T P - 0 1 1 / 1 3
2.2.1
Process Simulation
The first activity to be performed by the process engineer is the
definition of all the unit operations, with the correct sequence, required
to obtain the desired products, starting from a given feedstock.
Normally this activity needs equilibrium calculation of multicomponent
mixtures, which can be more easily performed by a process simulator.
These dedicated softwares enable the users to characterize the
feedstock, selecting the chemical components (or pseudo-components)
or defining a crude assay. Then it is possible to select the appropriate
thermodynamic property package to be applied for flash calculations,
and finally the user will select the unit operations to be performed
sequentially along the plant.
The unit operations taken into account to simulate the plant are all
those which may vary a process parameter (pressure, temperature, flow
rate, composition) of a stream. Typical unit operations are:
L/V separation, corresponding to an equilibrium calculation at T
& P of the stream; in the plant this is performed by a vessel
separator;
heating / cooling of a stream, to obtain an increase / decrease of
its temperature, in conjunction with a pressure decrease; thisoperation can be performed by a heat exchanger, with or without
change of phase;
compression / pumping of a gaseous / liquid stream, to impose
an increase of its pressure; this operation implies also an
increase in temperature;
flow through valve, causing an adiabatic (isoenthalpic)
depressurization;
distillation, to calculate the separation obtained through a
distillation column; this is the most difficult process calculation,
due to the complexity of simultaneous energy and material
balance among the components, stage by stage.
-
8/16/2019 2. Process department.pdf
5/45
Page 50 of 462
S T P - 0 1 1 / 1 3
The way to proceed to carry out the process simulation is the following:
a preliminary scheme with all necessary unit operations isprepared, characterizing all the input streams (feedstock);
process variables have to be adjusted in order to obtain the
optimum operating conditions, necessary to get the desired
product;
if applicable, a sensitivity analysis shall be conducted, by varying
some process variable in order to optimize the equipment sizing;
this shall be done for the distillation column: the required
product separation may be obtained with a low number of trays
and a greater reboiler duty, or alternatively with a greater number
of trays and a reduced reboiler duty; after the preliminary process simulation has been completed,
the corresponding Process Flow Diagram (PFD - see paragraph
2.2) shall be prepared; always during the preparation of the PFD
some modifications to the scheme are necessary: for instance the
temperature at the exit of a cooler shall be increased because the
cooling water temperature has been assumed lower than actual
one, or an operating pressure at one vessel should be increased
because the contribution of some control valves has been
underestimated, etc.
after the modifications of the PFD, the process simulation shall be
finalized incorporating all necessary changes of processparameters.
-
8/16/2019 2. Process department.pdf
6/45
Page 51 of 462
S T P - 0 1 1 / 1 3
A printout of a process simulation scheme is shown in Fig. 02.
Fig. 02
-
8/16/2019 2. Process department.pdf
7/45
Page 52 of 462
S T P - 0 1 1 / 1 3
2.3 Process Flow Diagram
The Process Flow Diagram (PFD) is always used by the process engineerin the design work and in process study.
The PFD represents the heart of the process design, because in this
diagram it is possible to see:
the correct sequence of unit operations (pumps, heat exchangers,
L/V separators, distillation columns, etc.) needed to get the plant
performance;
the routing of the main process streams, with their flow rates;
all the operating conditions (pressure & temperature); all process controls foreseen in the plant;
eventual information regarding energy streams (power of
machinery, duties of furnaces and heat exchangers, etc.);
the stream numbers, from which it is possible to find a complete
stream characterization in the document "Heat and Material
Balance" (see paragraph 2.4);
It is quite obvious that the finalization of the PFD is obtained only after
the optimization of the process scheme, with all relevant process
calculations (flash, distillations, heating/cooling, phase change, etc.).
Each modification to material balance, operating conditions and
equipment change (addition or deleting) has to be reflected into PFD.
Some simple rules are used when preparing PFD:
all equipment (having an item) shall be represented in the PFD.
This means that all items are shown on PFD;
all engines (compressors and pumps) and eventual tanks shall be
drawn in the lower side of the sheet, over an hypothetic grade line
placed at one quarter of the sheet height from the lower edge;vessels, column and heaters will be drawn in the superior side,
leaving the middle space free for exchangers and connecting lines;
column condensers and reboilers will be drawn beside their
pertinence equipment; air condensers will be represented on the
horizontal trace of the overhead line, while the water condensers
will be placed upon or below the receiver;
-
8/16/2019 2. Process department.pdf
8/45
Page 53 of 462
S T P - 0 1 1 / 1 3
spare equipment do not need to be represented separately from
the main equipment: for istance the pumps P-1 A/S (A is the
main and S is the spare pump) will be represented as a single
pump, but showing the item P-1 A/S;
the incoming streams shall be located preferably on the left side
of the sheet, while the outgoing streams should leave the sheet
from the right side;
lines connecting the equipment shall be vertical or horizontal;
oblique lines are not allowed; in case of intersection of two lines,
the less important one will be interrupted. The order of
importance is:
-
main process line- secondary process line
- utility line
- instrument line
In case of intersection of two lines of equal importance, the vertical one
will be interrupted.
starting from the second issue of the diagram, every modificationmade on the previous revision shall be evidenced by a revision
cloud around the modified elements; this will help the reader to
identify the modifications made, without analyze the whole
drawing.
A typical PFD is shown in Fig. 03.
-
8/16/2019 2. Process department.pdf
9/45
Page 54 of 462
S T P - 0 1 1 / 1 3
Fig. 03
-
8/16/2019 2. Process department.pdf
10/45
Page 55 of 462
S T P - 0 1 1 / 1 3
2.4 Heat and Material Balance
After the finalization of the PFD and the process simulation, it isnecessary to prepare the "Heat and Material Balance", containing a
detailed characterization of each stream.
This document is mainly constituted by a table, where for each stream
the following physical properties and characteristics are shown:
stream label (as shown on PFD)
temperature & pressure
flow rates, volumetric and mass
vapour fraction
molecular weight
physical properties (density, specific heat, thermal conductivity,
viscosity, surface tension)
stream enthalpy
stream composition
These data are used to fill the data sheets of equipment and to make all
subsequent process calculations. These information are available from
the printout of the process simulation, if it has been done, or shall becalculated, case by case, if the particular system does not require a
simulation.
In Fig. 04 an extract of a typical material balance is shown.
-
8/16/2019 2. Process department.pdf
11/45
Page 56 of 462
S T P - 0 1 1 / 1 3
Fig. 04
-
8/16/2019 2. Process department.pdf
12/45
Page 57 of 462
S T P - 0 1 1 / 1 3
2.5 Data Validation
It is important to check and validate the quality and the correctness ofthe documents described in this chapter, i.e. PFD, Process Simulation,
Heat and Material Balance, because any mistake done at this first stage
of the project may have tremendous impact on plant performance. Any
change in operating conditions will cause changes in flow rates of the
relevant streams, and a re-sizing of the connected equipment could be
needed. If the changes happen at a late stage of the project, when all
equipment have been already supplied, the economic consequences will
be significant.
2.6 Piping and Instrumentation Diagram
2.6.1
General
The Piping & Instrumentation Diagrams (P&ID) have the scope to show
all equipment, all pipe elements and all the instrumentation existing in
a plant. P&ID is a schematic drawing, but the sequences in which all
the plant elements are installed must be faithfully represented;
2.6.2
Graphic Representation in P&ID
While preparing a P&ID it is necessary to consider that during the
subsequent engineering phases additional elements may be required.
For this reason in the first draft of the drawing it is opportune to leave
sufficient free space in the drawing area.
The graphic representation shall follow these general principles:
a. Equipment distribution in the drawing area should be uniform in
order to avoid areas with excessive concentration of drawing
elements. If the drawing is particularly empty, it is not advisable
to spread drawing elements over all available drawing area,especially if it leads to separate elements which functionally
operate close one to the other. The placement of the objects on
the drawing shall be as much as possible rational and
“aesthetically pleasant”, to facilitate the reading and the
interpretation of the drawing.The way of the lines shall be chosen
in order to reduce the number of curves and intersections with
other lines.
-
8/16/2019 2. Process department.pdf
13/45
Page 58 of 462
S T P - 0 1 1 / 1 3
b.
Equipment dimensions shall be selected to maintain, as much as
possible, the real proportionality scale: a pump should be smaller
than a tank and bigger than an instrument symbol.
c.
Main drains, sample connections, all the manoeuvring valves,
insulated / jacketed / steam traced lines, slop lines, start-up
lines, drainage systems, etc., shall always be indicated.
d.
All the machines (compressors and pumps) and eventual tanks
shall be drawn in the bottom side of the drawing area,
horizontally aligned on a hypothetic ground line placed more or
less at a quarter of the drawing height. Vessels, columns and
heaters will be drawn in the upper side, leaving the middle space
available for the interconnecting lines and exchangers. It is
obvious that the condensers and the reboilers will be represented
beside their pertinence equipment.e.
The air condensers will be represented on the horizontal run of
the overhead line while the water condensers will be placed on the
vertical run upon or below the receiver, depending on their
effective installation.
f.
Minimum elevation above grade shall always be indicated for each
vessel. The elevation shall refer to the bottom tangent line for
vertical equipment and to the bottom line for horizontal
equipment. Moreover if some elevation difference between
equipment and/or piping runs is mandatory to guarantee a
correct plant operation, it shall be clearly shown on P&ID.
g.
Whenever a complex equipment requires the representation of
many components / instruments (for instance a furnace with
several coils, skin thermocouples, fuel to burners, snuffing steam
and soot blowers), it would be opportune to use multiple sheets to
represent all details required. In this case on the first diagram
where the relevant equipment is drawn, it must be written the
number of drawings where these details are shown.
h. If the diagram is made of several sheets, all the pipes going to
consecutive P&ID, or coming from the previous P&ID, shall be
extended at left or right side of drawing, and the height shall be
correspondent to the height of the same line on linked P&ID; sothat two sequential drawings can be overlapped and all the lines
pass from one to the other.
-
8/16/2019 2. Process department.pdf
14/45
Page 59 of 462
S T P - 0 1 1 / 1 3
i.
If any pipe is not connected to any equipment in one or more
sheet, it shall be represented only in the drawing where the
equipment is shown. This means that it is not necessary to draw
a line sequentially along all sheets, if this is not specificallyrequired to represent some elements (fitting or instrument) on
these sheets. Pipes incoming and outgoing from the sheet shall
show the fluid indication, the destination (From\To), the origin /
destination drawing number, on the panel in which they are
connected.
j. In the pipes incoming (feed) and outgoing (products) from the
plant, the battery limits shall be clearly represented, with the
eventual block valves and/or spectacle blind. Limits relevant to
the scope of supply (for packages, parts of plant, equipment, etc.)
shall be clearly represented, with indication of each responsible
for the supply (for instance: Client, package’s vendor, EPC
contractor, etc.) at the transition point. Supply limit shall be
shown also for instrument (for instance between a local
transmitter, by package vendor, and DCS controller, by
Contractor).
k. Generally the equipment item shall be placed under the machines
and storage tanks, while for vessels, heaters, columns etc., it
shall be placed upon.
The equipment service shall be indicated under its item.
Two different solutions could be actuated for the graphic location of
the equipment item and service:
In the drawing area, next to the equipment the item only shall be
indicated, and in the lowest/highest side of the sheet, vertically
aligned with the equipment, it is represented the item, the service
and any other information relevant to that equipment; these
information shall be located in the bottom side if referring to
machines (pumps and compressors), in the upper side for all
other equipment.
Item and service of equipment are indicated next to the same
equipment in the drawing area.
Solution 1 is normally the preferred one.
The equipment items normally used in P&ID are listed in paragraph
2.6.3.
-
8/16/2019 2. Process department.pdf
15/45
Page 60 of 462
S T P - 0 1 1 / 1 3
l.
The connection lines of the equipment shall be horizontal or
vertical while the oblique lines, unless particular exceptions, shallbe avoided.
m.
In case of interception of two lines, vertical line is interrupted if
both lines have the same importance, otherwise the less
important line will be interrupted. The line importance level is:
- Main process lines
- Secondary process lines
- Utility lines
- Instrument lines
n.
Starting from the second issue, any modification of the elements
of the drawing shall be identified by revision clouds, with a
revision index.
o.
Line numbers or pipe diameters shall be written:
- in horizontal position upon the line, if it is horizontal;
- in vertical position (bottom-up) on the left of the line ifit is vertical.
If next to the line there is no space for writing its number, this shall be
placed in close proximity to it. An arrow shall be used to connect the
line number / diameter to the interested line.
The list of the equipment represented in the P&ID shall be indicated
over the template. This list shall be readable with the drawing folded in
A4.
-
8/16/2019 2. Process department.pdf
16/45
Page 61 of 462
S T P - 0 1 1 / 1 3
2.6.3
Item of Equipment
All equipment is identified with an "item". Equipment item is assigned
by the process manager as soon as it is inserted into the process
scheme. It may also be necessary, in order to meet the Client needs, to
rename the equipment previously “itemized” with other items names.
Equipment item will be assigned according to the following criteria
(unless some modifications requested by the Client).
The item is structured as:
TTT-UUNN (X/…/Z) to include the following information: TTT: equipment typology
UU: plant/unit of the equipment
NN: progressive number (within typology and unit)
X/…/Z: functional class – if required (parallel, main or spare)
The equipment typology is identified by means of 3 letters maximum in
accordance with the following Table 1:
-
8/16/2019 2. Process department.pdf
17/45
Page 62 of 462
S T P - 0 1 1 / 1 3
Table 1
Equipment TypeItem Equipment Type
A Basins – Pits
B Fans – Blowers
BC Battery Charger
C Columns
CB Power Factor Improvement Groups
CF Centrifuges
CT Cooling towers
D (as second letter) Diesel Engine
DE Diesel Emergency Generators
DH Deaerators
DR Dryers
DS Desuperheaters
E Heat exchangers
EA Air CoolersEG Electric Generators
F Filters
FL Flares
GE (as 2nd and 3rd letter) Machinery Gas Engines
H Fired Heaters - Furnaces
I Equipment for Solid Handling (belts, lifting equipment, etc.)
J Ejectors
K Compressors
LA Loading Arms
LP Local Panels
M (as 2nd letter) Machinery Electric Motor
MCC Motor Control Center
MX Mixers (both agitator and static mixers)
P Pumps
PC Low Voltage PanelsR Reactors
SG Boilers
SL Silos
SC Steam trap
SWG Medium Voltage Panel
T (as 2nd letter) Machinery Turbine
TG Gas Turbine
TR Transformers
TK Tanks
TS Steam Turbine (generator)
U Various no process Equipment (balances, bridge cranes, etc.)
UPS Uninterrupted Power Supply
V Vessels
W "Package" Unit
X Miscellaneous
Z Special Equipment
-
8/16/2019 2. Process department.pdf
18/45
Page 63 of 462
S T P - 0 1 1 / 1 3
The equipment of the same typology shall be numbered with 4 digits,
where the first and the second will represent the unit and the other two
the progressive number.
For instance a Pumps of Unit 02 will be numbered as: P-0201, P-0202,
P-0203, etc.
When the same service is provided by two or more equipment, the
functional class indicates if the equipment are working in parallel or if
the other one is spare.
The working equipment shall be identified with alphabetic letters
starting from A. The spare equipment will be identified with the letter S.
For instance the item P-0203 A/B/S identifies the 3rd pump of the unit
02, and it indicates that 3 pumps are installed (A, B, S), where two (A,
B) are working in parallel, and one (S) is kept as spare.When an equipment belongs to a "package" or to a complex equipment,
such as a compressor or a gas turbine, its item shall be written after the
main equipment item.
For instance the item W-1202-P-01 S identifies the pump P-01 S
(therefore spare) related to the package W-1202.
2.6.4
Fluid Identification
Each fluid moving along the Plant is identified by a code, made of
maximum 3 alphabetic characters. Fluid can be categorized as process
fluid or utility fluid.
When a project starts, the Fluid List is prepared by the Process
Department, in order to allow the selection of suitable Piping Classes.
The process fluids can be generically identified with a “P” letter.
Different code can be adopted if it is required by the Client.
The utility fluids codes will be in accordance with the Table 2, unless
otherwise requested by Client.
-
8/16/2019 2. Process department.pdf
19/45
Page 64 of 462
S T P - 0 1 1 / 1 3
Table 2
Codes for Utility FluidsItem Fluid
WATER
HW Hot Water
CHW Chilled Water
CW (S) Cooling Water (Supply)
CW (R) Cooling Water (Return)
BW Boiler Feed Water
HBW High Pressure Boiler Feed Water
LBW Low Pressure Boiler Feed Water
SW Sea Water
DM Demineralised Water
PW Process Water
DW Drinking Water
RW Raw Water
FW Fire WaterSTEAM & CONDENSATE
HHS Very High Pressure Steam
HS High Pressure Steam
MS Medium Pressure Steam
IS Intermediate Pressure Steam
LS Low Pressure Steam
LLS Very Low Pressure Steam
HPC High Pressure Condensate
MPC Medium Pressure Condensate
LPC Low Pressure Condensate
SC Suspect Condensate
COMPRESSED GASES
PA Plant Air
IA Instrument Air
NI Nitrogen
IG Innert Gas
HNI High Pressure Nitrogen
OX Oxygen
FUELS
FG Fuel Gas
NG Natural Gas
FO Fuel Oil
CHEMICAL
CA Caustic Solution
CAS Spent Caustic
NH Ammonia
SA Sulphuric Acid
HO Hot Oil
FLARE & BLOWDOWNBD Blow Down
ABD Acid Blow Down
AF Acid Flare
HF Hydrocarbon Flare
SEWERS
CSR Chemical Sewer
OSR Oily Sewer
SSR Sanitary Sewer
WSR Water Sewer
CD Closed Drain
-
8/16/2019 2. Process department.pdf
20/45
Page 65 of 462
S T P - 0 1 1 / 1 3
2.6.5 Line Classification
Each line shall be classified to permit the procurement of the adequate
instrument and piping bulk material.
Each line shall have its own number. A unique line number can be
assigned to contiguous runs of piping having the same piping class, the
same operating temperature and the same design conditions.
In order to assign a specific piping class to a line, it is necessary to
select, within the piping classes having the material and the corrosion
allowance specified for the specific fluid, the one with the flange rating
suitable to the design conditions of that line.
Material and corrosion allowance to be applied for a certain fluid are
normally defined in the “Material Selection Diagram”, document
prepared by the process team before the development of the P&IDs.
If the change of the piping class (and line number) is operated between
two contiguous lines, it is necessary to show the exact point of the
change. In this case a class transition segment (spec-break) with the
indication of the two contiguous line numbers shall be inserted. If the
change of the line number is due to the necessity to change the material
of the line (i.e. the piping class), at the transition point it shall be shown
the change in piping class instead of the change of line number.
The lines numbering shall be carried out in accordance with the Client
Standards. In absence of specific requirements by the Client the here
below described APS standards shall be used. The line number is a text cell which contains the following character
groups:
DDDD-FFF- NNNNN-CCCC-L
DDDD: nominal pipe size, in inches or, whenever required by the
Client, in millimetres; maximum of 4 digits;
FFF: fluid code; maximum of 3 digits;
NNNNN: line number, eventually combined with the unit number;5 digits maximum;
CCCC: piping class; 4 digits maximum
L: insulation code; 2 digits maximum;
Example: 12"-LS-25523-AB01-H
-
8/16/2019 2. Process department.pdf
21/45
Page 66 of 462
S T P - 0 1 1 / 1 3
Line number shall be made of the unit number followed by a
progressive number of 3 digits (from 001 to 999).
Process lines shall use progressive numbers from 001 to 499 (withineach unit). The numbers from 500 to 999 shall be used for the utility
lines.
As soon as the project starts it shall be decided the units numeration
and the numbers range to be used for each utility in the Plant (for
example: LS from 501 to 550, MS from 551 to 600, CW from 601 to 650,
etc.).
Table 3Insulation Codes
ItemInsulation
AAnti Sweetening Insulation
NNot Insulation and Not Painting
VPainting
CCold Insulation
HHeat Conservation
P Personnel Protection
SSteam Tracing
EElectrical Tracing
UUnderground Line
XAcoustical Insulation
W Jacketing
Note:
1 - Those codes may be incremented to meet specific project needs. Whenever the lines need morethan one insulation type (for example for heat conservation and acoustical insulation) it will bepossible to use the double code.
-
8/16/2019 2. Process department.pdf
22/45
Page 67 of 462
S T P - 0 1 1 / 1 3
2.7 Process Calculation
In a previous paragraph has been described the process simulation, to
be performed during the development of the Process Flow Diagrams,
which finalize the flows of the streams within the plant and the
operating variable. After that, before the preparation of the process data
sheets of equipment and instrumentation, the process engineer is called
to calculate, from a process point of view, most of the plant
components. It is important to note that the complete design of a plant
component (like a vessel for instance), requires the contribution of
several engineering specialties: the process engineer, who identifies
some basic data, the mechanical engineer, who calculate the
mechanical details and identifies the exact materials to be used for eachpart of the equipment, the piping engineer who identifies the orientation
of nozzles, etc.. In the next paragraphs it is described the main
calculation to be carried out by the process engineer, necessary for the
subsequent preparation of the process data sheets.
2.7.1 Line Sizing
This calculation is required to identify the diameter of each pipe of the
plant. The calculation is based on the following input data:
type of fluid (liquid, vapour, mixed phase)
flow rate
fluid characteristics (density, viscosity, etc.)
expected pipe length
available pressure drop
At the beginning of the project, when the routing and the components of
the pipes has not yet finalized, the pipe length is simply estimated on
the basis of the distance of the connected equipment.
-
8/16/2019 2. Process department.pdf
23/45
Page 68 of 462
S T P - 0 1 1 / 1 3
Using dedicated software, or graphs collection, it is possible to obtain,
for each line, the following two characteristic parameters:
fluid velocity
specific pressure drop
On the basis of extensive experience, the correct size of the pipe is
chosen in order to keep these two parameters within a range of
acceptable value.
In the following tables 4-1 A-C are indicated the acceptable range for
velocity and specific pressure drop, which could be used for pipe size
selection.
-
8/16/2019 2. Process department.pdf
24/45
Page 69 of 462
S T P - 0 1 1 / 1 3
Table 4-1 A
Liquid Service
Service Pressure Drop
[bar/km]
Velocity
[m/s]
1. Pump suction:
- C1,C2, C3 at boiling point 0.4 – 0.7 0.5 max
- liquid at boiling point 0.6 – 0.9
- subcooled by 25 °C 2.3 – 3.5
1.0 max (Ø ≤ 18")
1.5 max (Ø > 18")
2. Pump discharge 3.0 – 5.0 3.0 max
3. Natural circulation (reboiler inlet) 0.2 – 0.4 - - -
4. Column side extraction
- Ø ≤ 8" 0.7 max
- 8" < Ø ≤ 16" 0.9 max
- 16" < Ø 1.1 max
5. Inlet to L/L separator 1.0 max
6. Cooling Water
- branches to users 2.3 – 3.5 2.5 max
- interconnecting headers 0.6 – 1.0 2.5 max
7. Utility Water 3.0 – 4.5 1.5 – 3.0
8. Boiler Feed Water
- P ≤ 50 bar 3.0 – 4.5 1.5 – 3.0
- P > 50 bar 7.0 – 9.0
9. Steam condensate 0.3 – 0.6 1.0 max
10. Sea water 2.0 – 2.5
11. Hot Oil 1.0 min
12. Gravity Lines 0.2 – 0.5 1.0 max
13. Drain Lines 1.0 max (Ø ≤ 2")
Table 4-1 B
-
8/16/2019 2. Process department.pdf
25/45
Page 70 of 462
S T P - 0 1 1 / 1 3
Gas Service
ServicePressure Drop
[bar/km]
Velocity
[m/s]
1. Process Gas
- general 18 – 24
- with CO2 > 1 % vol. 15 max
2. Compressors suction / discharge
- centrifugal max allowed:
{- 2.2608X3 + 9.2286X2
– 21.332X + 28.931}
with X=Log10 (Density)
expressed as kg/m3
- reciprocating max allowed:
{- 2.186X3 + 7.6539X2 –
12.444X + 15.618}
with X=Log10 (Density)
expressed as kg/m3
3. Vacuum 4 % Abs. Press. max
4. Steam to users
P ≤ 10 bar 0.5 – 2.0 30 max
10 < P ≤ 30 bar 1.0 – 2.5 45 max
30 bar < P 1.0 – 2.5 50 max
5. Steam to headers
P ≤ 10 bar 0.1 – 0.2 30 max
10 < P ≤ 30 bar 0.2 – 1.0 45 max
30 bar < P 0.2 – 1.0 50 max
6. Column overhead 0.2 – 0.6
7. Plant Air 30 max
8. Instrument Air 30 max
9. Fuel Gas 40 max
10. Flare header 0.7 Mach max
11. Safety Valve discharge 0.5 Mach max
ρv2 < 60'000 kg/ms2
-
8/16/2019 2. Process department.pdf
26/45
Page 71 of 462
S T P - 0 1 1 / 1 3
Table 4-1 C
Mixed Phase
ServicePressure Drop
[bar/km]
Velocity
[m/s]
1. Preliminary Sizing 5'000
-
8/16/2019 2. Process department.pdf
27/45
Page 72 of 462
S T P - 0 1 1 / 1 3
2.7.2 Vessel Calculation
2.7.2.1
Liquid / Gas Separator
These vessels shall be sized in order to keep vapor velocity sufficiently
low and facilitate the separation of the two phases.
Whenever suspended droplets of liquid must be removed from the vapor
to the maximum extent (e.g. process compressor suction separators),
mist eliminators shall be installed.
The L/V inlet nozzle shall be always equipped with internal distributor
promoting the separation of the phases.
Vessels with vapor flow only, such as compressor KO drum, shall bedesigned as for liquid-vapor separators, assuming that the
characteristics of liquid are those of the liquid in equilibrium with the
vapors.
The recommended hold – up times shall be in accordance with the Table
here enclosed.
The installation of a high liquid level alarm shall be foreseen (and the
corresponding hold-up shall be considered) on the following services:
compressor suction separators
unit surge drum
The installation of a low liquid level alarm shall be foreseen (and the
corresponding hold-up shall be considered) on the following services:
critical pump suction vessels
L/V separator feeding liquid to a downstream vessel by pressure
difference.
The min. liquid level in L/V separators (horizontal or vertical) shall be at
least 250 mm.In horizontal L/V separators, the vapor space, or space above the
maximum liquid level, shall not be less than 20% of diameter.
-
8/16/2019 2. Process department.pdf
28/45
Page 73 of 462
S T P - 0 1 1 / 1 3
For vertical separators, the following geometric constraints shall be
satisfied:
the height between the bottom of inlet nozzle and the max liquid
level shall be not less than 300 mm or inlet nozzle diameter,
whichever is greater;
the height between the top of inlet nozzle and the top tangent line
of the vessel (without demister) shall be not less than 50 % of
vessel diameter, with a minimum of 500 mm and a maximum of
900 mm;
the height between the top of inlet nozzle and the bottom of the
demister shall be not less than 250 mm plus the 25 % of vessel
diameter, with a minimum of 500 mm; the height between the top of the demister and the top tangent
line of the separator shall be not less than 250 mm plus the 7.5
% of vessel diameter, with a minimum of 450 mm;
Vessel height or length should be within the range of 2-4 times vessel
diameter.
The maximum allowable vapor velocity may be calculated following
several methods, here below described.
Critical velocity method
The “critical velocity” of the vapor phase is defined as follows:
VC = 0.048 * [(ρL/ρV) - 1]0.5
where:
VC = critical velocity, m/sec.
ρL = liquid density at cond., kg/m3
ρV = vapor density at cond., kg/m3
The area used for calculating critical velocity is the one available for
vapor flowing: in a horizontal vessel is the cross sectional area above
the max liquid level, and in a vertical vessel the total cross sectional
area.
-
8/16/2019 2. Process department.pdf
29/45
Page 74 of 462
S T P - 0 1 1 / 1 3
The L/V separators shall be sized for a maximum allowable vapor
velocity as specified on Table 4-2 A.
Table 4-2 A
Max Allowable Vapor Velocity (% of Critical Velocity)
Service without Demister with Demister
Vertical Horiz. Vertical Horiz.
Separator (P < 35 Bar g) 125 220 220 220
Separator (P ≥ 35 Bar g) 100 165 165 165
Compressor K.O. Drum
(P < 35 Bar g)
100 - - - 175 - - -
Compressor K.O. Drum
(P ≥ 35 Bar g)
80 - - - 133 - - -
Steam Flash Drum 125 - - - 220 - - -
Vacuum Service
(P < 0.17 Bar A)
- - - - - - 110 110
Vacuum Service
(0.17 ≤ P < 1.013 Bar A)
- - - - - - 180 180
Flare K.O. Drum - - - 275 - - - - - -
API RP 521 Practice
Following this practice, for a liquid drop of a fixed diameter dispersed in
the gaseous stream it is possible to calculate the dropout velocity and
subsequently the time required to travel vertically down to the liquid
level. If the residence time of the gas phase inside the separator is
greater than the descent time of the liquid particle, the particles of such
particular diameter will be separated.
The minimum diameter of particles to be separated are defined in Table
4-2 B as function of the service.
-
8/16/2019 2. Process department.pdf
30/45
Page 75 of 462
S T P - 0 1 1 / 1 3
Table 4-2 B
Diameter of Liquid Drop to be Separated
Service Diameter [μm]
Flare K.O. Drum 300 - 600
API 12 J Specification
Following this practice, specifically relevant to gas / oil separators, theL/V separation is considered adequate if the actual gas velocity is not
greater than the maximum allowable superficial velocity VA:
VA = K * [(ρL/ρV) - 1]0.5
where ρL and ρV have the same meaning as in the critical velocity
expression, and K is a constant depending upon design and operating
conditions, which should be not greater than:
0.5 * (L/10) 0.56 where L is the separator length, in feet.
2.7.2.2 Liquid – Liquid Separators
These vessels shall be sized in such a way that the settling time for each
liquid phase from the other is less than its residence in the vessel itself.
Settling velocity for the dispersed droplets is calculated using Stokes,
Newton’s or an intermediate law, according to field of application. The
dimensions to be assumed for the droplets are defined in Table 4-2 C
Table 4-2 C
Diameter of Dispersed Droplets
Light phase density (@ 15 °C) Heavy phase Drop Diameter [mm]
850 kg/m3 or lower Water or caustic solution 0.12
over 850 kg/m3 Water or caustic solution 0.08
-
8/16/2019 2. Process department.pdf
31/45
Page 76 of 462
S T P - 0 1 1 / 1 3
A maximum settling velocity of 250 mm/minute shall be assumed for
light hydrocarbons.
It should also be verified that the hold-up time necessary for any phasefor settling satisfies process hold-up requirements.
In Fig.05 is shown a typical calculation sheet for an horizontal V/L/L
separator.
-
8/16/2019 2. Process department.pdf
32/45
Page 77 of 462
S T P - 0 1 1 / 1 3
Fig. 05
-
8/16/2019 2. Process department.pdf
33/45
Page 78 of 462
S T P - 0 1 1 / 1 3
2.7.2.3
K.O. Drum on Reciprocating Compressor
The analogic study of reciprocating compressor circuit will be extended
up to the suction KO drum, when the minimum volume of the drum
itself is calculated as follows:
V = (10*C*A)/(2π*n/60)
where:
V = vessel volume [m3 ]
C = gas sonic velocity [m/sec]
A = cross section of piping between KO drum and compressor [m2 ]n = Compressor rpm. Assume 300 during design phase and verify after
compressor definition.
2.7.3
Pump Calculation
Overdesign
Pump design flow rates shall include a minimum of 5% margin on max.
operating flow rate for pump with rated power higher than 150 kW and
10% for pump with lower rated power.
For reflux and pumparound pumps, design flow rate shall include a
margin of 20% on max. operating flow rate.
Pump differential head indicated in the specification sheet shall be
calculated at design flow-rate.
NPSH Calculation
Suction line losses shall be calculated at design flow rate of the pump.
Pressure drop through the suction strainer shall be taken into account.
Pressure drop across the strainer will be assumed equal to 0.5 m of
liquid column.
For subcooled liquids, the source pressure shall be the minimum
normal operating pressure and the vapor pressure shall be at specified
pumping temperature.
-
8/16/2019 2. Process department.pdf
34/45
Page 79 of 462
S T P - 0 1 1 / 1 3
Static suction head shall be measured from the minim liquid level to the
centreline of a horizontal centrifugal or rotary pump, or the suction
nozzle of a vertical centrifugal pump or reciprocating pump.
Static suction head for pumps connected to storage tanks shall be
calculated at the lowest specified liquid level in the tank a which design
pump flow rate is required.
If vortex breaker is required, the pressure drop through it shall be
considered.
For horizontal centrifugal pumps, the elevation of the pump centreline
shall normally be 0.6 m minimum above grade, unless the actual
elevation is know.
Available NPSH values not higher than 7 m shall be shown on pump
specifications, even if actually available. Maximum value of NPSH = 7shall be shown on pump specification in case of a higher value will be
calculated.
In Fig. 06 is shown a typical calculation sheet for pumps.
-
8/16/2019 2. Process department.pdf
35/45
Page 80 of 462
S T P - 0 1 1 / 1 3
Fig. 06
-
8/16/2019 2. Process department.pdf
36/45
Page 81 of 462
S T P - 0 1 1 / 1 3
2.7.4 Column and Tray Calculation
Column diameter will be calculated using an over design of 10% of
normal flow rates.
In general, valve or sieve trays shall be used, together with rain deck
trays (or equivalent) and packing (unless otherwise required).
Sieve trays may be used in fouling service.
Valve tray columns will be specified with the following max. flooding
factors:
77% for Vacuum Tower
82% for other services
70% for column diameter under 900 mm
Tray hydraulic calculations and hence column diameter confirmation
shall be performed by the tray vendor. The following sizing criteria shall
be recommended to tray vendors.
Required tray flexibility shall be 50 – 110% unless otherwise specified.
The following values are minimum recommended for tray spacing of
valve tray towers:
-
8/16/2019 2. Process department.pdf
37/45
Page 82 of 462
S T P - 0 1 1 / 1 3
Table 4-4 A
Tray Spacing
Fouling Service Tower
Diameter (ID)
Clean Service
1 pass 2 or more passes
[mm] [mm] [mm] [mm]
ID ≤ 1500 300 450 - - -
1500 < ID ≤2300 300 525 450
2300 < ID ≤3100 375 600 525
3100 < ID ≤6000 450 675 600
6000 < ID 525 750 675
Note:
1) If a manhole is present, minimum tray spacing shall be 600 mm or 150 mm morethan manhole diameter, whichever is greater;
Indicative pressure drop values per tray are listed below according to
operating pressure:
Table 4-4 B
Tray Pressure Drop
Column Pressure
[Bar abs]
Pressure Drop
[Bar] / tray
0.05 0.004
1.013 (ATM) 0.005 – 0.008
30 0.01
Vapor load for a column with high liquid load can be increased using
multi-pass trays.
Being more expensive, however, this option is only justified by an
effective saving in total column costs (by utilising smaller column
diameters).
-
8/16/2019 2. Process department.pdf
38/45
Page 83 of 462
S T P - 0 1 1 / 1 3
Downcomer clearance, vertical distance between the tray and the
downcomer bottom, is generally not less than 25mm, 40 mm for dirty
liquid.
Downcomer clearance velocity should be lower than 0.3 m/sec.
Weir height value is usually 50 mm, with a total lenght not lower than
60% of column diameter.
Weir loading, to avoid blowing, should be 0.01 lt/min cm.
Downcomer back-up shall not be higher than 50% of tray spacing plus
weir height.
A lower value (40%) should be used for services with high or moderate
foaming tendencies, or with a tray spacing
-
8/16/2019 2. Process department.pdf
39/45
Page 84 of 462
S T P - 0 1 1 / 1 3
Fig. 07
-
8/16/2019 2. Process department.pdf
40/45
Page 85 of 462
S T P - 0 1 1 / 1 3
2.8 Process Data Sheets
The process data sheets are formats (one type for each class ofequipment) with fixed cells relevant to representative parameters for
that class of equipment, to be filled in by the process engineer.
Once the process data sheet has been compiled, it can be passed to the
engineering section for further design development.
The process parameters which need to be specified on all data sheets
are typically:
operating conditions (pressure and temperature)
design conditions (pressure and temperature) construction material (for istance "carbon steel" or "stainless
steel") and corrosion allowance
connection nozzles size and rating
For pumps, compressors, filters, etc., in general for all the equipment
which are sized taking into account the flow rate and quality of the fluid
handled in the equipment, it will be necessary to specify:
nature of the fluid
flow rate
physical properties of the fluid (at operating conditions)
presence of corrosive / toxic materials
In addition to these data, each class of equipment is identified by
additional peculiar parameters, as shown below.
-
8/16/2019 2. Process department.pdf
41/45
Page 86 of 462
S T P - 0 1 1 / 1 3
Vessel / Column Data Sheets
diameter
height / length
liquid level (high, low) inside the equipment
elevation of some particular nozzle
need for insulation
Pump Data Sheet
differential height
NPSH available
Compressor Data Sheet
differential pressure
gas composition / molecular weight
gas Cp/Cv
Filter Data Sheets
degree of filtration required
efficiency of filtration
Heat Exchanger Data Sheets
Duty exchanged
Physical properties of both cold / hot fluids
Vaporization / condensation enthalpy curve (in case of change of
phase)
The following Fig. 08 - 10 show some typical process data sheet for
vessel, pump and heat exchanger.
-
8/16/2019 2. Process department.pdf
42/45
Page 87 of 462
S T P - 0 1 1 / 1 3
-
8/16/2019 2. Process department.pdf
43/45
Page 88 of 462
S T P - 0 1 1 / 1 3
-
8/16/2019 2. Process department.pdf
44/45
Page 89 of 462
S T P - 0 1 1 / 1 3
-
8/16/2019 2. Process department.pdf
45/45
Page 90 of 462
1 1 / 1 3