5. piping department.pdf

Upload: ragh

Post on 06-Jul-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 5. Piping department.pdf

    1/74

     

    Page 187 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.0 

    PIPING DEPARTMENT

    5.1 

    Foreword

     The scope of the Piping Department is to design interconnecting

    pipelines between different equipment to carry out fluids from the

    source to the delivery point by means of pumps, gravity etc. and to

    recycle fluids through closed circuit by following industrial codes &

    standards which meet the following criteria for good engineering:

      Its material has to be defined from a point of view of the quality,

    in order to convey the fluid, in safety conditions for all the years

    of the plant duration.

      Its route has to be carried out in the more rational and economic

    way, as much as possible, and, in addition, it has to satisfy stress

    analysis requirements.

       The supporting modalities and arrangement have to be properly

    designed and verified.

      If any, suitable coating has to be provided in order to limit the

    losses of heat and gaining of heat.  If any, pipes have to be equipped with a proper heating fluid, in

    order to assure the minimal temperature of the process fluid

    located inside the pipe.

       The easy access to the working areas has to be assured.

       The lay-out of new piping has to be properly studied in order to

    facilitate the connection with the existing ones.

  • 8/16/2019 5. Piping department.pdf

    2/74

     

    Page 188 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.2  Definitions

    5.2.1 

    Definition of Piping and Piping Components

    We define Piping the whole of the components which allow the fluid to

    be properly contained, conveyed, deviated, intercepted.

    We define Piping Component the element which allows one of the

    mentioned operations:

    Namely

     

     To fluid flow, it shall be necessary to connect the pipe to theequipment by means of flanges.

       To convey the fluid, a pipe will be used.

       To deviate the fluid, fittings will be used.

       To intercept the fluid, valve will be used.

    So, we have introduced those elements which in the technical literature

    are called “the four families” that constitute the piping, namely:

      Pipes.

      Fittings.

      Flanges.

      Valves.

    A per cent distribution of the various components (in weight) could be:

      Pipes, properly said 56%

      Valves 21%

      Fittings (curve, T pieces etc.) 13%

      Flanges 9%

      Others (springs, shoes, etc.) 1%

  • 8/16/2019 5. Piping department.pdf

    3/74

     

    Page 189 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.2.2  Metallurgic Definition of a Steel Component

    A steel component, from the metallurgic point of view, can be in carbonsteel, alloy steel, austenitic stainless steel or special, depending on it

    constitution:

      Iron and carbon steel (apart from impurities);

      Iron, carbon steel and a metal more pure than iron;

      Iron, carbon steel, chrome in a percentage not lower than 18%,

    nickel in percentage not lower than 8%;

      Iron, carbon steel and higher percentages of a metal more pure

    than iron.

    5.2.3  Product Definition

    If this definition is sufficient from a theoretical point of view, it is not

    enough for what concerning the technical ones due to the reason here

    below listed.

    For Engineering Company, purchasing always for a third Client at its

    own responsibility, the problem relevant to the purchasing definition ofany piping component is quite difficult. Let’s try to understand together

    which are the problems to be solved in order to purchase without

    inconveniences the simplest component: the pipe.

    It shall provide the Purchasing Department with a technical description

    of the component to be purchased. This description shall be suitable

    and clear in order to assure a perfect understanding and explanation

    about the items to be furnished avoiding further or different kind of

    furniture.

    In the request of purchasing of any component and therefore also for

    the pipe it shall be foreseen a non dimensional and a dimensional

    classification. The dimensional classification in the case of pipe isformed from the diameter and the thickness or schedule.

  • 8/16/2019 5. Piping department.pdf

    4/74

     

    Page 190 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.2.4  Schedule

    In terms of schedule, it has to be remembered that it is just an

    indicative number that Anglo-Saxon Norms locates in correspondence of

    some thicknesses. It can be also said that on equal terms of number

    (including the schedule) the thicknesses are variable to the changes of

    diameter even though suitable to support, from a mechanical point of

    view, the same conditions of pressure and temperature.

    5.2.5 

    Nominal Diameter

    Nominal pipe size (NPS) is a dimensionless designator of pipe size. It

    indicates standard pipe size when followed by the specific size

    designator number without an inch symbol. For example, NPS 2

    indicates a pipe whose outside diameter is 2.375 in. The NPS 12 and

    smaller pipe has outside diameter greater than the size designator (say,

    2,4,6….) However, the outside diameter of NPS 14 and larger pipe is the

    same as the size designator in inches. For example, NPS 14 pipe has an

    outside diameter equal to 14 in. The inside diameter will depend upon

    the pipe wall thickness specified by the schedule number. Refer to

    ASME B36.10M or ASME B36.19M. Refer to App. E2 or E2M.

    It is well-know that the values concerning the diameter and its

    thickness are not perfectly realised from constructor. In other words, it

    must be accepted that pipe cannot be wholly cylindrical and thickness

    absolutely constant. It is clear that these variations, are agreed in a

    paragraph relevant to those tolerances. Subsequently these tolerances

    engrave also to the weight that it will be always different from the

    theoretical one.

  • 8/16/2019 5. Piping department.pdf

    5/74

     

    Page 191 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.2.6  Non Dimensional Characteristics

    From a non dimensional point of view, in the purchasing order, it has to

    specify the following characteristics:

      Chemical Composition

      Mechanical Characteristics

      Mechanical and chemical Testing

      Hydraulic Testing

      Non destructive Testing

      Acceptance or rejection criteria

      Bars lengths

       Transport

    From what was said earlier, we may conclude that knowledge and the

    best definition of all relevant prescriptions, done each time during

    purchasing be the purchasing order become burdensome, also because

    being forced in the negotiation with various manufacturers, the risk of a

    long exhausting dealing, in order to comply to all these prescriptions, is

    very high.

    So as to avoid this kind of situation, the remedy is complete the

    purchasing description with an applied codes and specification where

    all the necessary prescription are listed in a very analytical way. This

    norm is acquainted and accepted by the manufacturer which is officially

    in turn to punch the pipes with the mark related to the same norm.

    Reference codes generally applied by engineering companies for pipes

    are:

    API (American Petroleum Institute)

    ASTM (American Society for Testing and Materials)As regards the dimensional part, reference codes are those referred to

    ASME (American Society of Mechanical Engineers). Therefore, in the

    piping field, it must exist a group of persons specialised in the

    materials, apt to furnish to the purchasing department, which has the

    commercial aspect, a purchase order, completely defined from a

    technical point of view. These persons constitute the Piping Materials

    Office.

  • 8/16/2019 5. Piping department.pdf

    6/74

     

    Page 192 of 462 

       S   T   P  -   0   1   1   /   1   3

     They receive necessary information from Process Department.

    Precisely, Process Department, furnish, for each plant, a list completed

    with all fluids (process and service fluids) to the maximum pressure and

    temperature conditions, selecting the steel defined from a metallurgicpoint of view for each fluid

    5.3 

    References

     The following shows the documents and their content, which refer to

    the piping design.

    5.3.1 

    Piping and Instrumentation Diagrams (P&ID)

     The P&ID is a basic document for the piping design of a plant, this

    relates to:

      Schematic and functional indications for all of the equipment;

      All of the process and service lines which connect to the

    equipment or otherwise pertaining to the plant. Each line will

    have a diameter, fluid content, line number, belong to a pipingclass, possible tracing and/or jacketing;

      Valve type and position;

      Instrumentation.

    5.3.2  Line List

     The line list is a list of all the lines foreseen for the plant and describes

    each line based on the following:

      Project

      Unit

      Line number

      Revision

      Connection reference (to/from)

  • 8/16/2019 5. Piping department.pdf

    7/74

     

    Page 193 of 462 

       S   T   P  -   0   1   1   /   1   3

      Number of P&ID it belongs to

      Operating and design temperature

     

    Operating and design pressure

      Piping class

      Material

      Rating

      Flange finishing

      Fluid and service abbreviation

      Phase

      Corrosion allowance

     

    Coating (painting/insulation)

       Test Pressure

      Material and insulation thickness

    5.3.3  Piping Classes

    Each class describes in detail the dimensional characteristics and the

    quality of material for each and every element belonging to the piping

    class.

     These information are developed in order to create one of the most

    important documents for the piping design; this document is called

    Mechanical Piping Classification.

    Classifications are therefore a classes collection and each one can be

    defined as a list of all the pipe components defined from a purchasing

    point of view in order to convey one or more fluids at certain pressure

    and temperature settings through the year in safety conditions. This

    collection has the purpose to assembly in a sole document all the non

    dimensional definitions of components and to permit to the designer to

    rapidly find necessary data.

  • 8/16/2019 5. Piping department.pdf

    8/74

     

    Page 194 of 462 

       S   T   P  -   0   1   1   /   1   3

     5.3.4  Project Documentation

     The following shows the characteristics and content of each documentproduced for the piping design.

    5.3.4.1 Plot plan

    One or both types of Plot plan are produced in accordance with the

    characteristics of the plant.

      General plot plan

     

    Detailed plot plan

     The arrangement of units areas, storage areas, buildings, and facilities

    for loading/unloading to be provided within the plant, shall be decided

    on the base of the following factors:

      Soil characteristic.

      Main road or rail access ways.

      Location of pipelines to and from plant.

      Direction of prevailing wind.

     

    Local law and regulation which may affect the location of units

    and storage facilities.

      Natural elevation for location of upstream/downstream units and

    equipment (such as feed and product storage tanks, waste water

    plant, oil/water separator, etc…)

    5.3.4.2 

    General Plot Plan

    It is usually designed in A0 format on an appropriate scale, based onthe extension of the plant. The plot plan will show:

      Battery limits with relevant coordinates;

      All of the main roads;

       The process units;

       The service production units;

       The storage tank parks with their relevant containment basins;

  • 8/16/2019 5. Piping department.pdf

    9/74

     

    Page 195 of 462 

       S   T   P  -   0   1   1   /   1   3

      Areas for product loading and unloading;

      Main pipe-racks and sleeper ways;

     

    Buildings and structures;

      Orientation towards geographical north and the direction of

    prevailing winds.

    5.3.4.3 

    Detailed Plot Plan

    Normally designed in A0/A1 format, on a scale of 1:100 or 1:200.

    It represents a unit or a zone of the plant.

     This plot plan will show:

      Battery limits of the unit or zone;

      Main roads with their relevant coordinates;

      All of the equipment on the ground or at elevation with their

    “items” and their position, with the reference axis;

      All of the structures and their positions based on their aligning

    reference axis, the position of the ladders and the development of

    platform, possible monorails and/or overhead cranes;

     

    All of the pipe-racks mounted on the ground with their positionrelevant to the reference axis and alignments;

      All of the sleeper ways with the position of the sleeper relevant to

    the reference axis;

      All of the buildings and their position relevant to the reference

    axis and the dimension of the external obstruction;

      Dismounting areas and areas for maintenance necessary for the

    equipment;

       The table for the elevation of the equipment. The table will show

    the elevation of all the equipment, based on the tangent line for

    the vertical equipment, and the axis for the horizontal equipmentor the support plan for the equipment that have a related axis. In

    particular cases, where it is necessary further detail of particular

    portions of the plant, elevation designs will be produced.

  • 8/16/2019 5. Piping department.pdf

    10/74

     

    Page 196 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.3.4.4 

    Key Plan

    A small-scale plan of a plant or a group of subdivided plan of differentareas of the plant, which indicates the placement of the principal items

    and piping layout of the master scheme.

    5.3.4.5 

    Piping Layout

     The piping layout represents an area of the plant, identified on the Key

    plan.

    It is normally designed in A0/A1 format, and on a scale of 1:33 1/3 or

    1:50 the process and/or service production areas, on a scale of 1:50 or

    1:100 for the storage areas.Each area, if necessary, will be designed on various levels in order to

    clearly show the following:

      All the elements shown on the detailed plot plan (equipment,

    structures, etc.);

      All the foundation parts that come out of the ground;

      All the channels;

      All the ladders and platforms on the equipment;

     

    All the essential obstructions that create obstacles for piping or

    for accessibility (instruments panels, fire prevention equipment,

    etc.)

      All the pipes and pipe components (valves, flanges, reductions,

    etc.).

      All the instruments on the lines and equipment.

    5.3.4.6 Sections, Elevations and Details

     The sections and elevations of the piping layout will be carried out only

    in particular cases and only when isometric sketches are not foreseen.

    Particular detail on a scale of 1:50 or 1:33 may be necessary for piping

    layout on a scale of 1:100 for storage areas.

  • 8/16/2019 5. Piping department.pdf

    11/74

     

    Page 197 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.3.4.7 Isometric Sketches

    Isometric Sketches will be made for all the lines with a diameter of 2”and greater, unless otherwise indicated on the scope of work, shown on

    the appropriate A3 format; the drawing will not be made on a scale and

    will always be done on a single line tract. These will show:

       The route of the line with the position of all its components.

    (Valves, flanges, elbows, etc.).

       The symbol with references for typical installations. (Vents,

    drains, etc.).

     

     The flow direction.   The line number.

       The line piping class.

       The piping size and its components.

      References to the equipment that connects the pipe.

      All of the necessary dimensions for the construction of the line.

       The orientation details of the pressure taps for the orifice flanges.

       The orientation details for the flange holes if they are different

    from the standard.

      Eventual construction details, for special pieces to be made on

    site, with piping material.

      Item and number of all lines or equipment instruments.

      For lines of 1 ½ “and less, if required, the isometric sketches will

    be approximate for the route and for the dimensions, and must be

    verified on the site by the mechanical construction department

    before erection, and will not indicate pipes support.

    For lines 2” and greater, the isometric sketches will further show:

       The exact elevation in a way to permit the prefabrication, other

    than the mounting, of the lines.

       The symbol with the item of the standard and special auxiliary

    support for the contract.

      Indication of the field welding to carry out with the mounting, if

    required by the scope of work.

  • 8/16/2019 5. Piping department.pdf

    12/74

     

    Page 198 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.3.4.8 

    As Built Drawings

    At the end of the plant construction, the drawings, which will be

    updated “as built”, will be the plot plans and the underground pipinglayout.

    5.3.4.9 Material Take Off

    For each pipe and/or isometric sketch a material list will be made with

    the following content:

    a.  Reference to the sketch

      Line number

       The zone or area where it is

      Sheet number

      Date

      Piping class

    b. 

    Description of the elements

      Code

      Destination (see destination code table)

      Component type

      Material type

      Diameter and/or diameters

      Schedule and/or thickness

      Rating

     

    Quantity  Weight of every single element

      Prefabrication and erection weight

       Total weight

  • 8/16/2019 5. Piping department.pdf

    13/74

     

    Page 199 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.3.4.10 Piping Material Summary

    Depending on specific demands, a piping material list will be

    summarized by:

      Code;

      Area /Zone /Unit;

      Destination.

    5.3.4.11 

    Isometric List

     The isometric list is a list of all isometric sketches of the plant. For eachone of these sketches, the following will be described in detail:

      Line number;

      Date and revision of issue;

      Piping class.

    5.3.4.12 

    Auxiliary Piping Supports

     The auxiliary piping supports will be defined in accordance with thestandard.

    a.  Auxiliary supports for 2″ lines and greater.

    b.  Auxiliary supports for 1 ½” lines and lower.

    5.3.4.13 Auxiliary Piping Support List

    Supports for 2″  lines and greater will be prepared based on a

    compilation of different types:

      Standard supports

      Non-standard supports

     The standard supports will be identified by an alphanumerical code

    which will indicate the type and size.

  • 8/16/2019 5. Piping department.pdf

    14/74

     

    Page 200 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.3.4.14 

    List of Material for Auxiliary Piping Support

     The document, where all of the materials necessary for the construction

    of special and standard supports are listed, will show in detail:

       Type of material (HEA, Plate ecc.) and size;

      Quantity;

       Total weight of the type of material;

       Total weight of supports.

    5.3.4.15 

    Verification of the Piping Stresses

    A flexibility analysis for the lines of the plant will be carried out in

    accordance with the Stress Analysis specification.

  • 8/16/2019 5. Piping department.pdf

    15/74

     

    Page 201 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.4  Definitions

    5.4.1 

    General Criteria

     To reach a correct planimetric solution, all of the elements of the plant

    must be positioned in order to assure that all of the plant requirements

    in the following paragraphs are followed.

    5.4.1.1 Security

     This refers to all personnel present in the plan, the environment, hazard

    equipments and all ancillaries within the plant. These requirements will

    be followed from the point of view of the planimetric solutions, using the

    following preventive measures:

    a. 

    Foresee adequate space between the hazardous components and

    other components inside and outside the plant with the purpose of

    eliminating or reducing the possibility of risk that they may cause

    harmful effect in case of an accident and/or the entity of the

    damage.

    b. 

     The positioning of dangerous components in order to eliminate or

    limit the effects of their proper functioning both inside and outside

    of the plant;c.

     

     The reserving space and access to allow the installation and

    operation of fixed and mobile safety equipment, safety scape for

    personnel in case of an accident;

    d.  Protection such as: dikes, protection walls, height differences,

    corridors and slopes to reduce or eliminate hazard in case of an

    accident

    In lack of different standards or contractual limitations, table 4.1.1A

    provides a guide for the minimum distances to keep between

    components to satisfy the safety requirements (these distances are

    referred to the outer surface of the related subject). The regulations inthat table come from the standards of NFPA (National Fire Protection

    Association) in which it can be referred to for further details.

    For projects requiring a security analysis, the pertinence of the

    planimetric solution must be verified case by case respecting the risks

    identified by the analysis.

  • 8/16/2019 5. Piping department.pdf

    16/74

     

    Page 202 of 462 

       S   T   P  -   0   1   1   /   1   3

    Table 4.1.1A –Minimum Distance Between Components

    Note :

     The distances are measured in meters-  Where it is not specified, the distance will be calculated on the

    basis of necessity for accessibility, operability and maintenance.

    (1) Ex.: Water pumps, air compressors, etc.

    (2) Ex.: Valves and/or activation systems for shut down systems,

    water sprayers, etc.

  • 8/16/2019 5. Piping department.pdf

    17/74

     

    Page 203 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.4.1.2 

    Functionality

     This expression stands for the functional performance and productive

    capacity of the plant designed. For the best output of the plant, fromthe planimetric point of view, all equipment, plant’s units and

    obstructions shall be arranged in such way which shall follow limitation

    of PFD, P&ID and equipment data sheet properly.

    In particular:

      Minimum and maximum lengths of connections and differences

    in elevation. Particular attention should be paid to determine the

    elevation of different plants, parameters and structure that have

    been foreseen for the plant, which causes an elevated cost impact

    on the total plant value for the earth work and structural work;

      Flexibility for start-up and for the total or partial plant

    functioning;

      Positioning of components in a manner which assume proper

    execution of all connections (piping and relevant accessories,

    etc.).

    5.4.1.3 Operability

    For a good engineering practice and planimetric solution, control

    system of all components of the plant shall be located in a suitable

    position in order to provide easy access for handling and inspection

    during normal operating condition.

     To achieve this objective it may be required to foresee accessories like

    fixed or mobile platform and relevant stairways.

    Moreover it is recommended to integrate all distributed control and

    handling components or system of similar characteristics up to its

    possible extent.

     The standard spaces related to accessibility and operability may differ

    considerably from project to project based on the typical environmental

    conditions and operating personnel requirements to run the plant

    efficiency.

  • 8/16/2019 5. Piping department.pdf

    18/74

     

    Page 204 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.4.1.4 Maintenance

     The maintenance requirements are satisfied, from the planimetric point

    of view, through the predisposition of:

      Roads and routes, wide enough and spacious to enable easy

    access and use for mobile equipment for maintenance of the

    plant;

      Open spaces, around components that need maintenance,

    sufficient for: operation of maintenance vehicles, dismounting and

    substitution of parts which may need it (such as: motors for

    machines, heat exchanger bundles);  Eventual fixed equipment such as: davits, monorails, hoists,

    according to the scope of work.

    5.4.1.5 

    Constructability

     This requirement is fulfilled from the planimetric point of view assuming

    that:

    a. 

    Spaces and access for transporting components of the plant andconstruction equipment is sufficient within the site;

    b.  Sufficient space for any necessary temporary installation for

    construction.

    Observation should be paid for the positioning of big size, heavy and

    long lead items in order to avoid any delay in sequential and

    compulsory erection schedule due to the constriction or blockage of

    passages.

    Moreover attention must be given to the positioning of heavy items;

    which are subjected to be lifted up during erection and usually providedwith two lifting vehicles (one for lifting and another for holding).

    For best practice position the component close to the erection area

    provided with sufficient spaces for easy access to the area and align

    horizontally adjacent to the foundation if two components are

    positioned in the same area, it is necessary to optimize the area and

    leave space for lifting and, in some cases, for their assemblage during

    erection.

  • 8/16/2019 5. Piping department.pdf

    19/74

     

    Page 205 of 462 

       S   T   P  -   0   1   1   /   1   3

     5.4.2  Pipe–Rack, Pipe-Way and Building Positioning

     This section provides instructions regarding the positioning of singlecomponents of the Plant, particularly regarding problems related to

    installation, accessibility and working maintenance.

    5.4.2.1 Pipe – Racks

    Pipe–Racks, in general, are the piping support and cables, above ground

    structures, connecting various process and utility users within the

    plant.

    In order to work, it is necessary that the lines do not obstruct paths forpersonnel and machines in order to assure safety and accessibility for

    other components.

     These are normally placed on longitudinal wheel-tracks in the area

    representing the limits of the plant’s Units with the purpose of

    optimizing the aboveground route and with a symmetrical distribution

    for the various users.

    Pipe–Racks may be developed on different levels where the elevation

    varies according to the material used for construction (ex. for concrete

    pipe racks in cement, a large beam obstruction must be considered) and

    the eventual presence of intermediate levels, for pipes of a large

    diameter (this provides necessary space between the various levels).

    As a guide, for steel pipe racks, the height of the support levels is

    established as follows:

    4.6 m 6.2 m 7.8 m Main pipe-rack

    3.8 m 5.4 m 7.0 m For branches

    In order to stabilize the size of the pipe-racks, it must be taken into

    consideration that, apart from the need to support all pipelines and

    cable trays it is necessary to provide 20% of space for the future lines.

    When support is also required for air coolers, the width of the pipe-

    racks must be the same size as the equipment.

  • 8/16/2019 5. Piping department.pdf

    20/74

     

    Page 206 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.4.2.2 

    Walkways

    In general, pipe ways are corridors where pipe runs above the ground

    along the corridor and supported by sleepers, connects different off-siteareas, process and utility areas of the plant.

    For pipe ways elevations are exempted from any limitation unless

    otherwise indicated.

     These are normally positioned along the connecting roads in order to

    have easy access for maintenance and operation.

    5.4.2.3 

    Control Rooms

     The control rooms are concrete structures composed of offices,

    computers, laboratories and other services, where plant operation for

    process, utilities are followed and eventually other parts of the complex

    are subjected to a continuous surveillance of the plant.

     The size of the control rooms and their relevant locations are defined by

    the Instrumentation and Civil sections.

     The control rooms must be in areas that are not subject to accidental

    consequences.

    Such as:

      Explosions

       Toxic clouds

       The spread of fires

    Where not obtainable, Explosion Test of Construction shall be carried

    out according to the pressurization conditions, etc.

    Particular attention must be given to the vulnerability of exits and

    emergency escape routes.

     The control rooms must be located, in a central area in relation with the

    users connections and orientations, as long as this does not jeopardize

    operators’ interventions, with a cable entrance/exit side facing towards

    it; this is to permit an optimal path for the cables and uniformity of

    intervention time for the various plant Units.

  • 8/16/2019 5. Piping department.pdf

    21/74

     

    Page 207 of 462 

       S   T   P  -   0   1   1   /   1   3

    Control room must be positioned in proximity to the roads and there

    must be zones reserved for operations and parking; this is in order to

    permit access (both during normal operation and for maintenance

    interventions), a quick intervention in case of emergency and a rapidevacuation.

    5.4.2.4 

    Electrical Substations

     The substations and the electrical substations are structures or

    buildings containing feeding equipment, transformers, distributors and

    control system of electrical power necessary for the Plant’s operation.

    In general, this includes:

    a.  A High Voltage substation or entrance station located where

    electrical power feed lines arrive from outside;

    b. 

    A main station, fed from the lines coming from the high voltage

    substation and, if any, fed from internal self generators.

    c. 

    Some secondary distribution stations, the number of which varies

    according to its complexity, by the number and the users

    dislocation.

     The dimensions of the substations and electrical substations will be

    defined by the Electrical and Civil departments; the location and

    orientation will be agreed on, by the Electrical department.

    5.4.2.5 

    High Voltage Substations Or Entrance Cabin

     These are generally located in proximity to the High Voltage Switch

    Gear. High voltage switchgear is any switchgear used to connect or

    disconnect a part of high-voltage power system. These switchgears are

    essential elements for the protection and safe operation, without

    interruption, of a high voltage power system. These substations must be

    provided with roads and with sufficient area for vehicles movement and

    parking; this is in order to permit access during normal operation for

    maintenance interventions, quick interventions in case of emergency

    and rapid evacuations.

    In any case, the location of the main electrical substation must be

    chosen in a manner to avoid overhead power transmission lines, across

    the plant (therefore it is preferable to locate in a decentralized location,

    in order to prevent from any accidental consequences; e.g. explosions,

    lightning, etc.).

  • 8/16/2019 5. Piping department.pdf

    22/74

     

    Page 208 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.4.2.6 

    Electrical Power Distribution Stations

    According to the international codes and standards, the powerdistribution substations should be located in safe areas where formal

    risk analysis, conducted properly and methodically to ensure that

    potential accidental risk is either eliminated, or else reduced to a level

    as low as reasonably practicable.

    Such as:

      Explosions

       Toxic clouds

     

     The spread of fires

    Where not obtainable, Explosion Test of Construction shall be carried

    out according to the pressurization conditions, etc.

    Particular attention must be given to the reliability of exits and escape

    routes.

    5.4.3 

    Equipment Positioning

    5.4.3.1 Heaters, Boilers, Relevant Accessories and Stacks

     The heaters and relevant accessories are generally grouped in

    appropriate areas situated within the battery limits of the pertaining

    plant’s Unit and must be distinct from the other equipment.

     These areas are chosen on the basis of the prevailing wind directions so

    that an eventual gas fuel leak from the plant, will not reach the open

    flames of the burners.

    Within the distance among the various heaters, there must be adequate

    space for operation and maintenance. The minimum distance between the heater edge and the equipment is

    shown in table 4.1.1.A.

    Within this limit, there may be some equipment that are strictly

    connected to the heater, reforming plant reactors, high pressure

    exchangers and decoking vessels.

  • 8/16/2019 5. Piping department.pdf

    23/74

     

    Page 209 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.4.3.2 Columns and Reactors

     The minimum distance among the columns, reactors and other

    equipment is shown in table 4.1.1.A.

    When fixed equipment of lifting are installed on the columns and/or

    reactors (ex. davits), there must be free space at the bottom of the

    equipment in question, the size of the space is given by the range for

    the means of lifting plus a margin of about 1 m. These above

    requirements permit the transfer, operations and accessibility around

    the parts movable (catalyst, internals, valves, etc.). it is mandatory to

    foresee an area on the reactors plot plan for the substitution or

    replacement of spare parts, for catalyst loading and unloading operation

    in order to facilitate any movement required by the operating personnel(ex. need for a particular kind of pavement, eventual bases, etc.).

    5.4.3.3 

    Heat Exchangers

     The heat exchangers are installed in groups and, when possible,

    providing sufficient space for operators.

    In case of exchangers installed on the ground, it has to find the

    possibility to install in overlay position.

    However, this is normally limited to maximum two elements, except for

    the double pipe exchangers or exchangers with a shell diameter lessthan 12” (305 mm).

    In case of heat exchangers installed on the structures or the

    exchanger’s axis is at an elevation higher than 3.6 m, it will be required

    availability of lifting equipment (e.g. monorail) capable of removing and

    dismantling shell head, heavy tube bundles and distributors belts on

    the shell-side.

     The exchanger distributor belt shall be aligned with the shell side

    nozzles and also with the concrete saddles, which facilitate marking of

    civil works during engineering survey.

     The exchangers must be positioned with the distributors facingoutwards the plant.

     The plot plan must indicate at least two saddles; one fixed and another

    sliding saddle. Horizontal saddle and free to move in the longitudinal

    direction, due to thermal and pressure differentials, at the other saddle.

    Around the exchanger, the following minimum distances must be

    respected:

  • 8/16/2019 5. Piping department.pdf

    24/74

     

    Page 210 of 462 

       S   T   P  -   0   1   1   /   1   3

      0.7 m between each exchanger (this number refers to the

    maximum overall dimension, for example between the largest

    flange of the distributors);

      If there are intermediate groups for regulation or maneuver

    valves, a passage equal to 0.9 m must be kept;

      If there are no other constrains (to access to other components)

    each group of 4 exchangers must be positioned 1.5 m apart from

    each other in order to provide sufficient space for maneuvers and

    movement of the operating personnel.

    5.4.3.4 

    Vessels

     The distance among vessels and other equipment is shown in table4.1.1.A.

     The small vessels with vertical axes, containing chemical additives,

    must be gathered on the plot plan in a single zone in order to centralize

    the operation for their filling.

    5.4.3.5 Centrifugal and Alternatives Compressors

     The compressors must be positioned, if possible, in only one area (the

    compressors may be grouped into one or more of the plant’s Units),

    both to facilitate the engineering and the maintenance work: thisgrouping of more compressors with relevant motors permit the use of

    only one building and only one monorail, if the closing area is required.

    If not otherwise specified, the compressors are generally installed

    outside.

    If it is necessary to install compressors in a closed building, this will be

    done keeping in mind the problem of ventilation which may be solved by

    leaving the walls open up to 2.5 m greater than the service platform and

    providing appropriate vents on the roof; in any case, we have to

    consider the relevant density of the gas, air or steam that may be

    released into the atmosphere during normal operation and at anyextreme hazardous conditions as foreseen.

    Further problems may arise from the classification of dangerous areas,

    with possible requirements for pressurization of the building.

  • 8/16/2019 5. Piping department.pdf

    25/74

     

    Page 211 of 462 

       S   T   P  -   0   1   1   /   1   3

    During the positioning of the reciprocating compressors on the plot

    plan, spaces must be provided for:

      Draw off of pistons (the draw off will be generally indicated on the

    machines design);

      Possible pulsation dampers;

      Possible intermediary coolers, etc;

      Possible local panel

    In the design of the compressor room on the plot plan, the following

    must be kept in mind:

    a.  Sufficient space around the machine (about 1.5 m) greater than

    what is already planned for the draw off of pistons;

    b. 

    Sufficient space to permit the foundation construction in reinforced

    concrete spaced in order to avoid transmitting vibrations;

    c. 

    Utilize the respective spaces, under the work platform, to position

    possible pulsation dampers, intermediary coolers;

    d.  Sufficient space to position the steam turbine, when foreseen, with

    the relevant condenser (under the service platform). This spacemust be, around the turbine and the relevant operating equipment

    (1.5 m minimum).

    e.  Align the pillars of the building in a way that they don’t interfere

    with the machine’s foundations, this is to facilitate the ground

    support of the service platform which must be independently

    supported by the machines foundations which so that, should not

    transmit inevitable machine vibrations;

    f. 

    Provide an access available for means of transportation and

    loading / unloading bay within the room;

    g.  Do not position any of the equipment or piping bundle, above the

    compressors (except for the sealing oil tanks);

    h.   The K.O. drums must be located outside the compressor rooms.

  • 8/16/2019 5. Piping department.pdf

    26/74

     

    Page 212 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.4.3.6 Pumps

     The horizontal pumps will normally be positioned under the pipe-rackwith the hydraulic part facing outwards. If the pumps are placed in

    double rows, there must be a free space (minimum 3 m) between the

    two rows for the vehicle movement.

    When positioning the pumps on the plot plan, it is necessary to:

    a. 

    Align the discharge nozzles with respect to the pipe-rack pillars (as

    shown in fig. “Aligning and Pump Basement”);

    b.  Provide sufficient space (min 3m) behind the motors, or turbines,

    to permit cables routing, access, transit for the personnel, with therelevant equipment, both for normal operating phases and for

    maintenance interventions;

    c.  Hydraulic side of the pumps shall be oriented toward the direction

    where fluids flow into the plant for pumps suction;

    d. 

    Provide sufficient space between each pump in order to permit easy

    transit for operative personnel and plant maintenance. That space

    will be normally fixed to about 0.8 / 1 m minimum clear span.

    e.  Install a fixed monorail for the movement and substitution of spare

    part or any other parts when it is not possible to have easy access

    to equipment with mobile lifting transport.

    In addition to what has been previously described, when positioning the

    pumps it is necessary to comply with all the following safety

    precautions (including what is shown in table 4.1.1A).

    a. 

     The light hydrocarbon treating pumps with P > 3.5 MPa (relevant)

    must not be positioned under the air coolers, but they may bepositioned under the pipe-rack;

    b.   The hydrocarbon treating pumps with T ≥ T+ (flash point) must not

    be positioned under the air coolers and must also not be positioned

    under the pipe-rack. Furthermore, they must have a distance at

    least 4 ÷ 5 m from the flammable product treating pumps with T <

     T+ (point of flammability);

  • 8/16/2019 5. Piping department.pdf

    27/74

     

    Page 213 of 462 

       S   T   P  -   0   1   1   /   1   3

    c. 

     The pumps handling flammable products with T < T+ (point of

    flammability) may be positioned both under the air coolers and the

    pipe rack;

    d. 

    Pumps handling hydrocarbon must be at a distance, as much as

    possible, 4 ÷ 5 m from the equipment containing flammable

    liquids, or combustibles. If this is impossible, it is necessary to

    take precautions by providing adequate fire protection and an

    adequate fire proofing systems;

    e.   The pumps must not be installed within dikes or storage tank

    enclosure walls.

  • 8/16/2019 5. Piping department.pdf

    28/74

     

    Page 214 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.4.3.7 

    Air Coolers

    Apart from particular requirements, the air coolers will generally be

    installed above the pipe-racks, preferably in a central position relevant

    to the connecting equipment, avoiding too close to equipment and/or

    structures which may interfere.

     To permit sufficient air passage and an efficient thermal exchange, the

    following requirement must be considered:

    a.  Keep sufficient space between the motor service platform and the

    upper pipe-rack floor. These requirements are normally met by

    leaving a minimal distance of 1.6 m from the highest point of theobstacle, for example from the outside row of the pipe with the

    largest diameter on the pipe-rack floor (including eventual

    insulation);

    b.  In case of Air Coolers located within 9m each other, the outlet port

    will be at the same elevation (this is to avoid the recirculation of

    hot air);

    c.  No equipment may be placed over the air coolers.

    When planning the plot plan for all of the components of the plant’sunit, it is necessary to consider that the air coolers need access road

    and space for the maneuvering of cranes.

     The relevant sizing will be set according to the following demands:

      Installation of air coolers during construction;

      Substitution of ventilators (motors, propellers, exhaust fans);

      Substitution of air cooler parts and/or connected piping;

      Substitution of tube bundles.

  • 8/16/2019 5. Piping department.pdf

    29/74

     

    Page 215 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.4.3.8 

    Hydrocarbon Storage Tanks (Atmospheric)

     These tanks may be, according to their construction, fixed roof and/or

    floating roof.

     The fixed roof tanks are used for light hydrocarbons as petrol, crude oil,

    naphtha.

     To position a storage tank in the tank farm, following criteria have to be

    considered:

    a.   The tank farm area for the crude oil storage must be located at the

    highest point within the plant area and possibly where it does not

    exist any booster pump in order to facilitate loading pump suction.

    b. 

     The tank farm area of semi-refined products has to be located tothe unit of the plant aimed for loading.

    c.   The tank farm area for “finished products” is generally located near

    the former (semi-finished products) and possibly towards the

    shipment facilities.

     The minimum distance between the tanks, the conformation and the

    location of the containment dams and the sizes and capacity of the

    relevant dikes will be defined on the basis of the codes of the country

    where the Plant will be carried out.In lack of precise data, it is possible to assume:

    a.   The volume of the dike must be equal to that of the tank (more

    than 10 cm of border on each side). If the dike contains more than

    one tank, the volume must be equal to the tank with the maximum

    capacity plus the submersed volume by the other tanks;

    b.   The height of the dike above ground level must not exceed 4 m;

    c. 

     The height of the tank must not exceed 12 m of the dike wallsunless otherwise indicated by local codes;

  • 8/16/2019 5. Piping department.pdf

    30/74

     

    Page 216 of 462 

       S   T   P  -   0   1   1   /   1   3

    d. 

     The size of the dike will be defined fulfilling the condition that any

    straight line passing through the area of the tank’s roof (or the

    upper edge, if the it’s a floating roof) and forming a 45° angle with

    the vertical point falling within the perimeter inside of the dikeitself.

     The dikes are generally formed up with soil covered by a layer of

    concrete (this choice is rather preferable than concrete walls).

    A passage way 1 m wide must be provided on the crest of the dikes and

    shall have stairways outside the dike at a distance not more than 8 m.

    5.4.3.9 Pumping Stations (“Off-Site” Areas)

    During designing a plot plan, the altitude profile has to be considered tolimit the pumping station work; in addition in the design of the plot

    plan, it is important to take into consideration the following

    requirements:

    a. 

     The elevation of the pump’s suction nozzles must be arranged in a

    way to avoid the creation of pocket on the lines. These pockets

    negatively influence the performance of the pump and can block

    the total emptying of the connected tanks.

    b. 

     The pumping stations must be positioned near the roads and musthave areas for operation and parking; this is to permit access (both

    during normal operation and for maintenance), a rapid intervention

    in case of emergency;

    c.   The layout of the connected piping must be optimized (to/from

    pipe-way and to/from tanks).

    5.4.3.10 

    Light Hydrocarbon Storage Tanks (Balls and Large Cylinders)

     The storage tanks for light hydrocarbons can be spherical containers

    (spheres) and/or horizontal cylindrical containers; they are used for

    stocking liquefied petroleum gas (LPG) and semi-cooled products

    (“Cigar” shape, type).

    From the safety point of view, a proper solution to be adopted, in order

    to avoid possible overheating with the possibility of explosion, could be

    the one to use buried horizontal containers.

  • 8/16/2019 5. Piping department.pdf

    31/74

     

    Page 217 of 462 

       S   T   P  -   0   1   1   /   1   3

     This solution is particularly recommended:

     

    For storages near built-up areas;  For high capacity storages;

      For small storages (ex. intermediate products) adjacent to the

    process Unit;

    5.4.3.11  Flares

     The distance of the flares from the process unit and from the

    hydrocarbon storage tanks depends on the height on the heat generated

    from the flame, in order to avoid to damage the equipment and

     jeopardize the safety of personnel.

     This distance will be defined, after a careful safety analysis, during the

    execution of the Project.

     The zones near the flares where there may be the presence of personnel

    must be treated in accordance with API RP 521.

    5.4.4 

    Free Spaces for Maintenance

    a. 

    Access roads and inside of the plant’s limits:

    1. 

    width of the principal access road 6.0m

    2. width of the road within the Unit 4.0m

    3. footh path width 1.0m

    4. internal curve 6.0m

    b.  Headroom for the passage of large maintenance

    vehicles at the principal access points of the plant,

    measured from the roadway and the lowest point

    of the pipe or structures elements:

    6.1m

    c.  Headroom for the passage of railways, measured

    by the summit of the rail and the lowest point

    of the pipe; isolated or not structures

    elements (to verify with local codes:) 6.5m

    d.  Minimum distance from rail axis to any obstacle

    (to verify with local codes): 2.6m

  • 8/16/2019 5. Piping department.pdf

    32/74

     

    Page 218 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    e.  Minimum height for the passage of maintenance

    cranes in areas of the plant: 4.3m

    f. 

    Headroom for maintenance access for

    the pumps 3.2m

    g. 

    Access space for pump maintenance , measured

    by the end of the pump/motor to the external

    edge of the structure and/or piping:

    3.0m

    h.  Minimum distance between the road edge footh

    path and equipment and/or piping

    1.5m

    i. 

    Minimum passage for personnel access among

    equipment,structures and/or piping:

    0.75m

     j.  Minimum overhead passage under piping 2.1m

    or structures

    k. 

    Minimum walkway width for walkways

    connecting to the platforms or sleeper-ways 0.80m

    5.4.4.1 Horizontal Heat Exchangers Installed on Structures

    a.  Fixed tube bundle exchangers:

    Minimum space between structure limits

    and the external distributor edges: 0.75m

    b. 

    Removable bundle exchangers:

    Minimum free space between the structurelimits and the external edge for the fixed shell: 0.75m

  • 8/16/2019 5. Piping department.pdf

    33/74

     

    Page 219 of 462 

       S   T   P  -   0   1   1   /   1   3

    c. 

    “Double tube” or “fin-tube” heat exchangers:

    Minimum free space between structure limits

    and shell cover: 1.5m

    Minimum free space between the structure

    limits and piping connections: 0.75m

    d. 

    For all types of exchangers, the minimum

    distance between the lower nozzle flanges

    and the structure will be: 0.2m

    5.4.4.2 

    Air Coolers Mounted on Elevated Structures or Pipe-Racks

    a.  Free access from piping and/or equipment,

    for the mounting of piping bundles by a crane 4.0m

    b. 

    Free vertical space between the electrical motors

    of fans and service walkways 1.8m

    5.5 

    Piping Installation

     This Section will provide the criteria regarding the installation of piping

    connected to the various equipment of the Plant, with particular detail

    regarding problems related to positioning, work accessibility,

    maintenance and proper function.

    5.5.1  Pipe-Racks

    Normally, when more floors are necessary, the pipes are positioned as

    follows:  Service piping: upper floor

      Process piping: lower floor

    A typical distribution of the piping on the pipe-rack, on the basis of

    services and size, is shown in the figure 1.

  • 8/16/2019 5. Piping department.pdf

    34/74

     

    Page 220 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.5.1.1 Pipe Spacing

     The piping installed on pipe-racks will have sufficient space betweeneach other.

     This space is necessary in order to carry out the operations following

    the installations, those being: flanges clamping, welded joints, painting,

    insulation, etc.

     The pipe spacing (L) between two pipes, no jacketed, must at least

    respect the distance resulting from the following formula:

    .min252

    )(   ++

    =  Dt  DF 

    mm L

     where:

    DF (mm) = external diameter of the piping flange with DN or greater

    rating

    Dt (mm) = external diameter of the piping with a smaller DN

     Table 5.2.1A shows the pipe spacing (L) normally respected between

    non-jacketed piping with a flange rating of 150# ÷ 900#.

  • 8/16/2019 5. Piping department.pdf

    35/74

     

    Page 221 of 462 

       S   T   P  -   0   1   1   /   1   3

    Table 5.2.1.A – Pipe Spacing Between Non-Insulated Piping

    (mm)  

    Note: for diameters or ratings not covered by the present table, apply the

    formula already indicated.

    If one or both of the pipes are jacketed and are steam traced, the pipe

    spacing must be increased by the insulation thickness.

  • 8/16/2019 5. Piping department.pdf

    36/74

     

    Page 222 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.5.1.2 Branches

    As general rule, the piping branches from the header are positioned:

      Underside, for lines conveying liquids. This allows the self-

    drainage, avoiding the likely risks caused by product stagnancy in

    the pipelines (corrosion, water hammer, etc.)

      On the top part for lines conveying air, gas or steam. This allows

    to prevent the possibility of circulation of the relevant

    condensates that may cause erosions, not considered, in the

    choice of the appropriate material concerning the above

    mentioned fluid.

     The branches from the cooling water header, with lines of DN ≤ 1- 1/2",

    are to be placed on the top part in order to avoid occlusions due to

    slush.

     The connection of outlet piping to the blow-down header are to be

    placed on the top part and must be made at 90° for lines of DN ≤  1-

    1/2", or with an inclination of 45° toward the flow, for lines with DN ≥ 

    2". This configuration is necessary for the following reasons:

     

    Because of the low pressure within the line, the head loss mustbe reduced as much as possible.

       The stress on the joints must be reduced as much as possible.

    5.5.1.3 

    Positioning

     The lines of DN >12"must be placed within the piping bundle and as

    close as possible to the column of the Pipe Rack structure in order to

    reduce the stress coming from the beams (see figure 1).

    Steam and condensate headers, that generally need loops, must beplaced so that the loop mainly develops within the pipe-rack (see figure

    1).

    Piping facing downwards (for control valves, hose station, etc.) must be

    placed toward the pipe-rack pillar in order to facilitate the supporting.

     They must face outside the pipe rack reserving a free area of 500 mm of

    clear light between the pipe surface and the edge of the pillar.

  • 8/16/2019 5. Piping department.pdf

    37/74

     

    Page 223 of 462 

       S   T   P  -   0   1   1   /   1   3

    A span of about 31 m under the pipe rack must be free of pipes,

    machines and equipment in order to allow the passage for service

    vehicles.

    5.5.1.4 

    Elevations

     The bottom pipe elevation of the insulated lines must consider the

    shoes height that are normally as follows:

      100mm with insulation ≤  80mm

      150mm with insulation 85 ÷130mm

     The blow down manifolds must have a minimum slope towards the

    relevant separators equal to 2 per mil, so avoiding pocket.

  • 8/16/2019 5. Piping department.pdf

    38/74

     

    Page 224 of 462 

       S   T   P  -   0   1   1   /   1   3

     Fig. 01 – Typical Section of Pipe-Rack

  • 8/16/2019 5. Piping department.pdf

    39/74

     

    Page 225 of 462 

       S   T   P  -   0   1   1   /   1   3

     5.5.2  Pipe- Way

     The piping installation criteria on the pipe-way are the same describedfor the pipe-rack with the exception of all process and service pipelines,

    which will be installed at the same elevation; the minimum suggested

    DN will be 1-1/2″ .

    On the pipe-way, for pipelines with DN>30″ (750), the pipe spacing will

    be estimated considering the possibility of access among the pipes

    (about 300 mm of clear light).

    5.5.2.1 

    Elevations

    Piping must be installed at a bottom elevation equal to 400 mm. Such

    elevation is valid for all of the process and service lines, regardless of

    diameter. An exception to this rule regards the pipelines conveying

    steam of which elevation is fixed in accordance with the following table.

    Bottom of Pipe Minimum Elevation for Lines Conveying Steam

    DN Line ≤ 10″  12" ÷ 20" > 20

    Elevation (mm) 400 600 650

     The above mentioned minimum elevations are required in order to allow

    the installation, where necessary, in the low part of condensate of

    drainage groups by means of steam traps, the above mentioned groups

    must be arranged to allow, with a minimum distance from the ground,

    the operations in the relevant maintenance.

  • 8/16/2019 5. Piping department.pdf

    40/74

     

    Page 226 of 462 

       S   T   P  -   0   1   1   /   1   3

     5.5.3  Installations on Pressure Equipment

    5.5.3.1 Piping on Columns or Vessels

     The piping installed on columns will be grouped in a free section, facing

    the pipe-rack so avoiding, where it is possible, to cross the service

    platforms.

     The pipelines that descend on the columns will be placed away from the

    equipment, in order to allow proper supports.

    All the spillage lines of fractionating columns have to come down from

    the nozzles, downward 3 m, at least, before changing direction.

    5.5.3.2 

    Piping on Exchangers

     The lines connected to the distributors nozzles shall be supported in

    order to allow the disassembly of the spool. The pipelines connected to

    the exchangers shall be designed and supported in order to facilitate

    the removal of the tubes bundle, introducing, where necessary, coupling

    flange for disassembly.

     Typical installation of piping on exchangers is shown in the figure 3.

  • 8/16/2019 5. Piping department.pdf

    41/74

     

    Page 227 of 462 

       S   T   P  -   0   1   1   /   1   3

     Fig. 02 – Typical of Piping Installation on Columns

  • 8/16/2019 5. Piping department.pdf

    42/74

     

    Page 228 of 462 

       S   T   P  -   0   1   1   /   1   3

     Fig. 03 – Typical of Piping Installation on Exchangers

  • 8/16/2019 5. Piping department.pdf

    43/74

     

    Page 229 of 462 

       S   T   P  -   0   1   1   /   1   3

     5.5.4  Piping Installations on Pumps, Compressors and Steam Turbines

    5.5.4.1 Pumps

     The pumps suction lines shall possibly be shorter in line according to

    the requirements of the thermal expansion of the suction line. In any

    case, pockets shall not be formed.

    On centrifugal pumps, in case that the suction nozzle would be smaller

    than the line, it will be used a reduction “eccentric type” placed with the

    plane part upward. For the lines that are involved in transport of high

    density fluids (slurry) or fluids, for which, pocket are expressly

    forbidden, the eccentric reduction will be placed with the plane part

    downward.

    Concerning double suction pumps “side-side type”, a length of straight

    pipe, equal to five times the diameter of the line, between the pump

    nozzle and the first elbow if placed on the horizontal plane, shall be

    foreseen. When the elbow is placed on the vertical plane, the straight

    length could be omitted.

    Typical of lines installation on double suction pumps

  • 8/16/2019 5. Piping department.pdf

    44/74

     

    Page 230 of 462 

       S   T   P  -   0   1   1   /   1   3

    For the pipelines that are connected to threaded part of machines

    (service line, seal lines, vent or drain lines) a flanged connection

    between the machine and the block valve of the line, shall be foreseen.

    When the connection of a temporary strainer is needed, this will be

    installed as near as possible to the machine, between suction nozzles

    and the first block valve. The route of the line and the supports, shall

    allow the disassembly of the filter.

    5.5.4.2 Compressors

    In order to reduce vibrations, suction and discharge pipes reciprocating

    compressors shall be positioned on the ground and hook up on it, as

    near as possible to the machine, according to the thermal expansion

    requirements.

    In the case of lines involved in chemical washing, appropriate

    connections or tube pipes to the machine, will be provided. The relevant

    supports will be provided for the line filled with water or temporary

    supports will be provided.

    5.5.5  Storage Atmospheric Tanks

    As far as the installation of these tanks is concerned, an adjustable

    connection has to be provided.

     The suction pipes from a tank, have to be installed to the minimum

    allowed elevation in order to avoid the forming of pockets on the line

    that could interfere with the operation of the pump and prevent the

    entire emptying of the connected tank.

     The firewater, used to convey water mixture and foaming-agent liquid,

    have to be installed within the basin and on the ground to reduce as

    much as possible the damage of the pipelines in case of accident.

     The pipelines jointed to the distribution manifold nozzles of products

    from/to tank, have to be gathered as much as possible in a manifold.

     The relevant valves have to be positioned on the addle of the service

    platform. The distance between centers among pipelines of manifold has

    to allow the access for the assemblage and for the maintenance of the

    relevant valves.

  • 8/16/2019 5. Piping department.pdf

    45/74

     

    Page 231 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.5.6  High Pressure Storage Vessels

    For security reasons, only the pipelines directly connected to the

    relevant high pressure storage vessels, could be installed in the storagearea.

     The above mentioned pipelines have to be suitably supported

    considering the requirements of expansion/contraction and vibrations.

    Normally the connection to the vessel is carried out providing a single

    line placed at the bottom of the vessel.

     This single line has to be used for all the operations: filling, emptying

    and drainage.

    When, for specific operating conditions, the Process requires a returning

    vapor line, this will be connected at the edge of the vessel. The distribution pipes of the product from/to the vessels have to be

    grouped, in a manifold that, for security, has to be placed outside on

    the partition wall.

     To reduce at minimum the possibility of dripping, the threaded

    connections must not be used inside the pipelines and the quantity of

    the flanged connections has to be reduced to the minimum.

    Concerning inlet and outlet piping, a drainage has to be provided. This

    has to be placed after the first block valve in the length outward from

    the manifold; the relevant discharged inflammable vapors shall be taken

    out to a safety place.For the conditions of assembling execution, see the typical examples

    shown in pictures 4, 5, 6 and 7.

  • 8/16/2019 5. Piping department.pdf

    46/74

     

    Page 232 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Fig.04.- Typical Arrangement of Vessel Piping Layout

  • 8/16/2019 5. Piping department.pdf

    47/74

     

    Page 233 of 462 

       S   T   P  -   0   1   1   /   1   3

    Fig. 05 – Typical Model of Piping Assembling

  • 8/16/2019 5. Piping department.pdf

    48/74

     

    Page 234 of 462 

       S   T   P  -   0   1   1   /   1   3

     Fig. 06 – Details of Piping Assembling

  • 8/16/2019 5. Piping department.pdf

    49/74

     

    Page 235 of 462 

       S   T   P  -   0   1   1   /   1   3

    Fig. 07 – Typical Models of Fire Fighting Assembling

  • 8/16/2019 5. Piping department.pdf

    50/74

     

    Page 236 of 462 

       S   T   P  -   0   1   1   /   1   3

     5.5.7  Valves and Instruments

    All of the valves which require operating intervention must bepositioned in a way so that the hand wheel is accessible from the

    ground or from a platform. If it is positioned higher than 2.1m (hand

    wheel axle) from the operating level, they will be operated by means of a

    chain (this does not apply for valves which are 1 ½” or less). If the

    valves are positioned under the operation levels, the hand wheel

    extension will be brought to 1.2m over the operation levels. All valves up

    to 1 ½” are considered accessible, for operation made from vertical fixed

    ladders.

    For the block valves positioned at the header branches, operation

    devices are not foreseen.

     The control valves must be accessible from the ground or from

    platforms. When they are mounted on platforms, the control valves will

    be positioned on the inner side of the handrail.

     The safety valves must be accessible from the ground or from platforms.

    When mounted on platforms, safety valves will be positioned on the

    inner side of the handrail.

     The valve for pressure instruments must be accessible from the ground,

    from platforms or from fixed vertical ladders. If positioned at a height

    higher than 3.6m from the ground, they will be accessible by portable

    vertical ladders.

     The temperature instruments will be accessible from the ground,

    platforms or fixed vertical ladders. If positioned at a height higher than

    3.6m from the ground, they will be accessible by portable vertical

    ladders.

     The valve for flow instrument will be accessible from the ground,

    platforms or fixed vertical ladders. If positioned at a height higher than

    3.6 from the ground, they will be accessible by portable vertical ladders.

    If positioned on a pipe-rack, no fixed installation for accessibility will be

    foreseen.

     The glass level gauges will be accessible from the ground, platforms or

    fixed vertical ladders.

     The displacement or differential level gauges will be accessible from the

    ground or a platform. If positioned with a bottom edge at a height

    higher than 3 m from the ground, they will be accessible by a fixed

    vertical ladder.

  • 8/16/2019 5. Piping department.pdf

    51/74

     

    Page 237 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.5.8  Installation of Piping Parts and Accessories

    5.5.8.1 

    General

     The piping will be arranged in a way which permits the removal of

    pieces of equipment or parts of it which may require maintenance

    operation (pipe bundle of the exchangers, pumps, etc.) without

    removing the block valves or all pipe connected to the equipment itself.

     The hot piping will be arranged or insulated so that the heat radiation

    conditions within 40°C of the neighboring equipment do not damage the

    surrounding equipment.

     The piping will be gathered into groups whenever possible. These

    groups will have different elevations in order to permit deviations,change of route and perpendicular intersections of the pipes without

    interference among them.

     The piping will be designed so that liquid and gas pockets are avoided.

    When this is not possible, there will be a vent for the gas pockets and a

    drain for the liquid pockets.

    Dead legs on the piping will be avoided for pipes which transport

    caustic products, acids, liquids which may solidify or gas which may

    form a corrosive condensate.

     There will be no process piping inside the control room. No steam or

    condensate piping will be inside the electrical substation.

    5.5.8.2 Installation of Gate Valves and Globe Valves

    At the inlet and at the outlet of safety valves, the valve stem will be

    always oriented horizontally.

    On pipes containing dangerous liquids, the valve stem will never be

    installed below the horizontal level.

    On cryogenic service pipes, the valve stem will be oriented vertically or

    at 45° from vertical.

    Chain for valve handling shall not obstruct passage areas. The chain

    will extend to 900 mm above the operation platform

    All Car Seal Open (CSO)/ Lever Operated (LO) gate valves will be

    installed with horizontal stem, in order to avoid that, in case of failure,

    the wedge should fall due to the force of gravity, and obstruct the fluid

    flow.

  • 8/16/2019 5. Piping department.pdf

    52/74

     

    Page 238 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.5.8.3 

    Check Valves Installation

    Clapet check valve will be preferably installed horizontally. Vertical

    installation will be in the case of upwards flow.

    If a check valve is installed in such a way that when it closes liquid

    accumulates in the pipes, a drain is required upstream from the valve.

    5.5.8.4 

    Plug Valves and Ball Valves Installation

    On the plug valves, and ball valves chain operation, with or without

    extension, will be allowed only in exceptional cases.

     The position indicator of gear-operated plug and ball valves shall bevisible from operational floor.

    5.5.8.5 Butterfly Valves Installation

    In the butterfly valves installation, it is necessary to verify that, during

    the operation, the butterfly valve does not interfere with element inside

    pipes (thermo-well pips, line reduction, internal coating).

    If butterfly valve is not “Threaded connection type”, additional couple of

    flanges will be installed when, downstream line, it has to be removedduring maintenance operations.

  • 8/16/2019 5. Piping department.pdf

    53/74

     

    Page 239 of 462 

       S   T   P  -   0   1   1   /   1   3

    Fig. 08 – Valves With Stems in Vertical Position

  • 8/16/2019 5. Piping department.pdf

    54/74

     

    Page 240 of 462 

       S   T   P  -   0   1   1   /   1   3

     Fig. 09 – Valves With Stems in Horizontal Position

  • 8/16/2019 5. Piping department.pdf

    55/74

     

    Page 241 of 462 

       S   T   P  -   0   1   1   /   1   3

     Fig. 10 – Typical Example of Battery Limit Installation (placed on theground)

  • 8/16/2019 5. Piping department.pdf

    56/74

     

    Page 242 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    Fig. 11 – Typical Example of Battery Limit Installation (Placed on Pipe-

    Rack)

  • 8/16/2019 5. Piping department.pdf

    57/74

     

    Page 243 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.5.8.6 Vents and Drains

    Piping will be designed in order to avoid gas and liquid accumulation.

    Otherwise:

      On all liquid accumulation, drain valves will be installed.

      On all gas accumulation, valved vents will be installed.

    Vent diameter: 3/4″ 

    Drain diameter:

     

    3/4" for 3/4" to 8″ 

      1” for 10" or larger lines.

    An exception is made for lines containing heavy products, where the

    diameter will be 1” minimum .

    For vents and drains installed on high pressure lines or hydrogen lines,

    the first connection nipple to main line will be SCH. 160 min.

    Drains installed on hydrogen and LPG lines will be designed with a

    double valve.

    5.5.9  Control Valves

    For control valve installation, sufficient clearance for actuator

    accessibility and/or removal will be provided.

       The plug will always be removable from the bottom of the valve

    and the minimum clearance shall be agreed with the Instrument

    Section.

       The actuator’s diaphragm will be accessible from the top of the

    valve and a 300mm clearance will be provided.

  • 8/16/2019 5. Piping department.pdf

    58/74

     

    Page 244 of 462 

       S   T   P  -   0   1   1   /   1   3

    Control valves will be positioned preferably with the stem in a vertical

    position. In special cases, the stem may be orientated up to 45°from the

    vertical axis. The stem may never be orientated horizontally or

    downwards.

    In the control sets, a valved drain will be provided between the first

    block valve and control valve.

    5.5.10 

    Safety Valves

    Installation criteria

     

     The safety valves will be installed in accessible areas in order toensure operability and disassembling.

      Safety valves will preferably be installed vertically.

       The installation of these valves in a dead stretches of pipe (e.g. at

    the end of horizontal pipes where normally there is no fluid flow),

    have to be avoided.

      Valves discharging into the atmosphere will be located at the

    highest point of the line on which they operate. Valves

    discharging into a closed system will be located at a minimum

    distances from the header to which they are connected.

    Inlet line

       The safety valve inlet line will be vertical and as short as possible;

    fittings used will be kept to a minimum to minimize the pressure

    drop.

      In order to reduce mechanical stress on safety valve and on

    relevant inlet lines, it will be necessary to take into consideration

    the reaction forces caused by valve opening, especially in the case

    of discharge into the atmosphere.

     

    A proper analysis of such forces and relevant effect on valve and

    connected piping will be made applying the calculation criteria for

    such forces as per ANSI B31.1 and per API 520.

      Gate valves will be installed with horizontal stem in order to avoid

    any failure, falling of wedge due to the gravity, and to obstruct the

    fluid flow.

  • 8/16/2019 5. Piping department.pdf

    59/74

     

    Page 245 of 462 

       S   T   P  -   0   1   1   /   1   3

      In case of joint assembly of a main safety valve and its spare,

    block valve on the inlet and outlet lines will be installed creating a

    system which does not allow the block valve to be closed on the

    main safety valve without first opening the block valve on thespare safety valve, or vice versa. This system can be obtained by

    mechanical interlock or using valves with padlocks.

      For safety valves that operate at a temperature below zero degrees

    Celsius and that discharge into the atmosphere, it is necessary to

    avoid the formation of ice and condensation in the valve plug, due

    to air humidity. For this purpose the safety valve will be installed

    with the last part of the inlet line not insulated. In this case, the

    not insulated part will be long enough to prevent reaching dew

    point in the valve; otherwise the safety valve must be heated

    (using steam or other proper means).

    Outlet line – Discharge into the atmosphere

      When a valve discharge into the atmosphere the outlet line shall

    be directed upwards for gas discharge, and downwards for liquid

    discharge.

      For dangerous fluids, if a safe location discharge is expressly

    required on the P&ID, the outlet pipe will be raised 3 m above any

    walkway situated within 15m.

     

    For those fluids for which a safe discharge location is notrequired, the outlet pipe will be oriented towards an area where

    the passage of persons is not foreseen

      Outlet pipe of safety valves discharging into the atmosphere will

    have a 10mm diameter hole in the bottom to drain condensate or

    rain water, if any. In case of dangerous fluids, the said hole will

    be connected by piping to a safe area or to the sewer.

    Outlet line – Discharge into a closed system

     

    Safety valves discharging into a closed system will be installed atthe higher level than flare header, so that safety valve outlet line

    is always sloping towards the header; the intake will be on the top

    header, oriented at 45° in the flow direction. Horizontal intakes

    will be allowed when the safety valve discharge pipe diameter is at

    least one diameter smaller than of the header one.

  • 8/16/2019 5. Piping department.pdf

    60/74

     

    Page 246 of 462 

       S   T   P  -   0   1   1   /   1   3

      If the safety valve has to be installed lower than header, a ¾”

    valved drain line should be provided, at the minimum distance

    from safety valve outlet flange, discharging, after checking of

    process, into a recovery pot where liquid, after vaporization, shallbe connected to blow down header.

      For the assembly of block valves on safety valve outlet lines, the

    same rules will be observed as for the assembly of inlet line valve.

      Special care will be taken in the safety valve outlet lines

    arrangement, in order to minimize changes of direction.

      Support for the above line will be designed in order to minimize

    stress on the valve, taking into account that the line will have to

    maintain its position with the safety valve.

    5.5.11 Piping Characteristics

    5.5.11.1 

    Line Diameters

    Pipes and fittings with diameters of 1 ¼ ", 2 ½" , 3 ½ ",4 ½ " and 5” will

    not be normally used. Where such diameters are required for

    connections to equipment, the pipe length will be reduced to a

    minimum.

    5.5.11.2 

    Flanges and Unions

     The use of flanges on pipes will be minimized and anyway limited to:

      Connecting lines to equipment;

      Connecting flanged elements installed on-line (valves, etc.);

      On pipes which have to be removed for particular service and

    maintenance.

    Unions will not be used on flammable or toxic products lines. In any

    case, the use of union will be limited to utility lines, 1 ½” or smaller

    diameter and when the line rating is not larger than 600#.

    Flat-faced flanges (FF) will be used for cast iron valves and/or

    equipment nozzle joints.

  • 8/16/2019 5. Piping department.pdf

    61/74

     

    Page 247 of 462 

       S   T   P  -   0   1   1   /   1   3

    5.5.11.3 

    Bends

    Changes of direction will be made by means of elbows (forged, cast or

    mitred) or bent pipe.

    Elbows will be long radius type (R=1.5D) if not otherwise specified.

    Miter bends will be made with 3,4 or 5 elements.

    For changes direction, bent pipe can be used with a bending radius

    longer than 1.5 times the pipe diameter, in particular, this solution will

    be adopted for slurry lines, pneumatic transport lines, pigged lines,

    utility lines with 11/2” or smaller diameter, (e.g., steam tracing, utility

    lines of equipment, etc.).

    5.5.11.4 

    Diameter Reductions

     To reduce piping diameter, reducers or reducer nipples, weldedolet and

    similar will be used; reduction flanges will be used only in exceptional

    cases.

    5.5.11.5 

    Branches

    Branches will generally be at 90° and will be made with “T” pieces, pipe

    to pipe branch connection with or without reinforcing plates orweldolets.

    Pipe to pipe branch connections (with or without reinforcing plates),

    with an angle smaller than 90°, will be used only for flow

    requirements(slurry lines, safety valve discharge on flare headers, etc.)

    Reinforcing plates will be defined as per ANSI B31.3 standard.

    5.5.12 

    Steam Distribution Network

    Where possible, the steam header will be positioned at one end of thepipe-racks and sleepers, for the installation of thermal expansion loop,

    if any.

    Steam headers will be blind flanged, (never with cap), in order to allow

    the cleaning. When block valves are provided on header branches, they

    will be installed on the upper horizontal length of pipe to allow the line

    to drain on both sides.

    On the lowest points on the end of steam header, pots will be provided

    with steam traps.

  • 8/16/2019 5. Piping department.pdf

    62/74

     

    Page 248 of 462 

       S   T   P  -   0   1   1   /   1   3

     

    5.5.13 

    Utility Stations

    Service hose stations for water, air, steam and nitrogen supplies (last

    one only where expressly required by the design specification) will be

    located in the following areas:

    Process and utilities production areas

    At ground floor; hose stations will be arranged to reach all equipment or

    pipes concerned, by means of 15 m hose length.

    On structures; hose stations will be arranged to serve all the floor. Thewater hose station shall be limited to the first floor.

    On fractionate columns; hose stations will be provided on all manholes

    platforms and on the highest platform, with the exception of water.

    For vertical structures and vessels, in general, utilities stations will be

    installed on all floors.

    Off-site area for storage and loading

    Hose station will be provided in pumps room, in tank trucks and/or

    railway loading area and in waste treatments area

    5.5.14 

    Instrument Air Distribution

     The instrument air distribution network will be completely separated

    from the service air network; use will be only for plant instrumentation.

    For each utility branch from the header, a block valve will be provided,installed at a minimum distance from the header.

     Threaded piping instrument air distribution network shall be provided

    with assembly joint by unions on 11/2” or smaller lines, and flanges on

    2” or larger lines, to be installed about every 12m length of straight pipe

    and every two changes of direction.

  • 8/16/2019 5. Piping department.pdf

    63/74

     

    Page 249 of 462 

       S   T   P  -   0   1   1   /   1   3

    APPENDIXNotices on ferrous materials, used in the

    Industrial Plants

    I.  Carbon Steels

     The carbon steels are considered the alloys of iron and carbon usually

    containing about from 0.02 to 1.2 % C and with the percentage of Mn

    from 0.25 to 1% and further quantity of other e