5. piping department.pdf
TRANSCRIPT
-
8/16/2019 5. Piping department.pdf
1/74
Page 187 of 462
S T P - 0 1 1 / 1 3
5.0
PIPING DEPARTMENT
5.1
Foreword
The scope of the Piping Department is to design interconnecting
pipelines between different equipment to carry out fluids from the
source to the delivery point by means of pumps, gravity etc. and to
recycle fluids through closed circuit by following industrial codes &
standards which meet the following criteria for good engineering:
Its material has to be defined from a point of view of the quality,
in order to convey the fluid, in safety conditions for all the years
of the plant duration.
Its route has to be carried out in the more rational and economic
way, as much as possible, and, in addition, it has to satisfy stress
analysis requirements.
The supporting modalities and arrangement have to be properly
designed and verified.
If any, suitable coating has to be provided in order to limit the
losses of heat and gaining of heat. If any, pipes have to be equipped with a proper heating fluid, in
order to assure the minimal temperature of the process fluid
located inside the pipe.
The easy access to the working areas has to be assured.
The lay-out of new piping has to be properly studied in order to
facilitate the connection with the existing ones.
-
8/16/2019 5. Piping department.pdf
2/74
Page 188 of 462
S T P - 0 1 1 / 1 3
5.2 Definitions
5.2.1
Definition of Piping and Piping Components
We define Piping the whole of the components which allow the fluid to
be properly contained, conveyed, deviated, intercepted.
We define Piping Component the element which allows one of the
mentioned operations:
Namely
To fluid flow, it shall be necessary to connect the pipe to theequipment by means of flanges.
To convey the fluid, a pipe will be used.
To deviate the fluid, fittings will be used.
To intercept the fluid, valve will be used.
So, we have introduced those elements which in the technical literature
are called “the four families” that constitute the piping, namely:
Pipes.
Fittings.
Flanges.
Valves.
A per cent distribution of the various components (in weight) could be:
Pipes, properly said 56%
Valves 21%
Fittings (curve, T pieces etc.) 13%
Flanges 9%
Others (springs, shoes, etc.) 1%
-
8/16/2019 5. Piping department.pdf
3/74
Page 189 of 462
S T P - 0 1 1 / 1 3
5.2.2 Metallurgic Definition of a Steel Component
A steel component, from the metallurgic point of view, can be in carbonsteel, alloy steel, austenitic stainless steel or special, depending on it
constitution:
Iron and carbon steel (apart from impurities);
Iron, carbon steel and a metal more pure than iron;
Iron, carbon steel, chrome in a percentage not lower than 18%,
nickel in percentage not lower than 8%;
Iron, carbon steel and higher percentages of a metal more pure
than iron.
5.2.3 Product Definition
If this definition is sufficient from a theoretical point of view, it is not
enough for what concerning the technical ones due to the reason here
below listed.
For Engineering Company, purchasing always for a third Client at its
own responsibility, the problem relevant to the purchasing definition ofany piping component is quite difficult. Let’s try to understand together
which are the problems to be solved in order to purchase without
inconveniences the simplest component: the pipe.
It shall provide the Purchasing Department with a technical description
of the component to be purchased. This description shall be suitable
and clear in order to assure a perfect understanding and explanation
about the items to be furnished avoiding further or different kind of
furniture.
In the request of purchasing of any component and therefore also for
the pipe it shall be foreseen a non dimensional and a dimensional
classification. The dimensional classification in the case of pipe isformed from the diameter and the thickness or schedule.
-
8/16/2019 5. Piping department.pdf
4/74
Page 190 of 462
S T P - 0 1 1 / 1 3
5.2.4 Schedule
In terms of schedule, it has to be remembered that it is just an
indicative number that Anglo-Saxon Norms locates in correspondence of
some thicknesses. It can be also said that on equal terms of number
(including the schedule) the thicknesses are variable to the changes of
diameter even though suitable to support, from a mechanical point of
view, the same conditions of pressure and temperature.
5.2.5
Nominal Diameter
Nominal pipe size (NPS) is a dimensionless designator of pipe size. It
indicates standard pipe size when followed by the specific size
designator number without an inch symbol. For example, NPS 2
indicates a pipe whose outside diameter is 2.375 in. The NPS 12 and
smaller pipe has outside diameter greater than the size designator (say,
2,4,6….) However, the outside diameter of NPS 14 and larger pipe is the
same as the size designator in inches. For example, NPS 14 pipe has an
outside diameter equal to 14 in. The inside diameter will depend upon
the pipe wall thickness specified by the schedule number. Refer to
ASME B36.10M or ASME B36.19M. Refer to App. E2 or E2M.
It is well-know that the values concerning the diameter and its
thickness are not perfectly realised from constructor. In other words, it
must be accepted that pipe cannot be wholly cylindrical and thickness
absolutely constant. It is clear that these variations, are agreed in a
paragraph relevant to those tolerances. Subsequently these tolerances
engrave also to the weight that it will be always different from the
theoretical one.
-
8/16/2019 5. Piping department.pdf
5/74
Page 191 of 462
S T P - 0 1 1 / 1 3
5.2.6 Non Dimensional Characteristics
From a non dimensional point of view, in the purchasing order, it has to
specify the following characteristics:
Chemical Composition
Mechanical Characteristics
Mechanical and chemical Testing
Hydraulic Testing
Non destructive Testing
Acceptance or rejection criteria
Bars lengths
Transport
From what was said earlier, we may conclude that knowledge and the
best definition of all relevant prescriptions, done each time during
purchasing be the purchasing order become burdensome, also because
being forced in the negotiation with various manufacturers, the risk of a
long exhausting dealing, in order to comply to all these prescriptions, is
very high.
So as to avoid this kind of situation, the remedy is complete the
purchasing description with an applied codes and specification where
all the necessary prescription are listed in a very analytical way. This
norm is acquainted and accepted by the manufacturer which is officially
in turn to punch the pipes with the mark related to the same norm.
Reference codes generally applied by engineering companies for pipes
are:
-
API (American Petroleum Institute)
-
ASTM (American Society for Testing and Materials)As regards the dimensional part, reference codes are those referred to
ASME (American Society of Mechanical Engineers). Therefore, in the
piping field, it must exist a group of persons specialised in the
materials, apt to furnish to the purchasing department, which has the
commercial aspect, a purchase order, completely defined from a
technical point of view. These persons constitute the Piping Materials
Office.
-
8/16/2019 5. Piping department.pdf
6/74
Page 192 of 462
S T P - 0 1 1 / 1 3
They receive necessary information from Process Department.
Precisely, Process Department, furnish, for each plant, a list completed
with all fluids (process and service fluids) to the maximum pressure and
temperature conditions, selecting the steel defined from a metallurgicpoint of view for each fluid
5.3
References
The following shows the documents and their content, which refer to
the piping design.
5.3.1
Piping and Instrumentation Diagrams (P&ID)
The P&ID is a basic document for the piping design of a plant, this
relates to:
Schematic and functional indications for all of the equipment;
All of the process and service lines which connect to the
equipment or otherwise pertaining to the plant. Each line will
have a diameter, fluid content, line number, belong to a pipingclass, possible tracing and/or jacketing;
Valve type and position;
Instrumentation.
5.3.2 Line List
The line list is a list of all the lines foreseen for the plant and describes
each line based on the following:
Project
Unit
Line number
Revision
Connection reference (to/from)
-
8/16/2019 5. Piping department.pdf
7/74
Page 193 of 462
S T P - 0 1 1 / 1 3
Number of P&ID it belongs to
Operating and design temperature
Operating and design pressure
Piping class
Material
Rating
Flange finishing
Fluid and service abbreviation
Phase
Corrosion allowance
Coating (painting/insulation)
Test Pressure
Material and insulation thickness
5.3.3 Piping Classes
Each class describes in detail the dimensional characteristics and the
quality of material for each and every element belonging to the piping
class.
These information are developed in order to create one of the most
important documents for the piping design; this document is called
Mechanical Piping Classification.
Classifications are therefore a classes collection and each one can be
defined as a list of all the pipe components defined from a purchasing
point of view in order to convey one or more fluids at certain pressure
and temperature settings through the year in safety conditions. This
collection has the purpose to assembly in a sole document all the non
dimensional definitions of components and to permit to the designer to
rapidly find necessary data.
-
8/16/2019 5. Piping department.pdf
8/74
Page 194 of 462
S T P - 0 1 1 / 1 3
5.3.4 Project Documentation
The following shows the characteristics and content of each documentproduced for the piping design.
5.3.4.1 Plot plan
One or both types of Plot plan are produced in accordance with the
characteristics of the plant.
General plot plan
Detailed plot plan
The arrangement of units areas, storage areas, buildings, and facilities
for loading/unloading to be provided within the plant, shall be decided
on the base of the following factors:
Soil characteristic.
Main road or rail access ways.
Location of pipelines to and from plant.
Direction of prevailing wind.
Local law and regulation which may affect the location of units
and storage facilities.
Natural elevation for location of upstream/downstream units and
equipment (such as feed and product storage tanks, waste water
plant, oil/water separator, etc…)
5.3.4.2
General Plot Plan
It is usually designed in A0 format on an appropriate scale, based onthe extension of the plant. The plot plan will show:
Battery limits with relevant coordinates;
All of the main roads;
The process units;
The service production units;
The storage tank parks with their relevant containment basins;
-
8/16/2019 5. Piping department.pdf
9/74
Page 195 of 462
S T P - 0 1 1 / 1 3
Areas for product loading and unloading;
Main pipe-racks and sleeper ways;
Buildings and structures;
Orientation towards geographical north and the direction of
prevailing winds.
5.3.4.3
Detailed Plot Plan
Normally designed in A0/A1 format, on a scale of 1:100 or 1:200.
It represents a unit or a zone of the plant.
This plot plan will show:
Battery limits of the unit or zone;
Main roads with their relevant coordinates;
All of the equipment on the ground or at elevation with their
“items” and their position, with the reference axis;
All of the structures and their positions based on their aligning
reference axis, the position of the ladders and the development of
platform, possible monorails and/or overhead cranes;
All of the pipe-racks mounted on the ground with their positionrelevant to the reference axis and alignments;
All of the sleeper ways with the position of the sleeper relevant to
the reference axis;
All of the buildings and their position relevant to the reference
axis and the dimension of the external obstruction;
Dismounting areas and areas for maintenance necessary for the
equipment;
The table for the elevation of the equipment. The table will show
the elevation of all the equipment, based on the tangent line for
the vertical equipment, and the axis for the horizontal equipmentor the support plan for the equipment that have a related axis. In
particular cases, where it is necessary further detail of particular
portions of the plant, elevation designs will be produced.
-
8/16/2019 5. Piping department.pdf
10/74
Page 196 of 462
S T P - 0 1 1 / 1 3
5.3.4.4
Key Plan
A small-scale plan of a plant or a group of subdivided plan of differentareas of the plant, which indicates the placement of the principal items
and piping layout of the master scheme.
5.3.4.5
Piping Layout
The piping layout represents an area of the plant, identified on the Key
plan.
It is normally designed in A0/A1 format, and on a scale of 1:33 1/3 or
1:50 the process and/or service production areas, on a scale of 1:50 or
1:100 for the storage areas.Each area, if necessary, will be designed on various levels in order to
clearly show the following:
All the elements shown on the detailed plot plan (equipment,
structures, etc.);
All the foundation parts that come out of the ground;
All the channels;
All the ladders and platforms on the equipment;
All the essential obstructions that create obstacles for piping or
for accessibility (instruments panels, fire prevention equipment,
etc.)
All the pipes and pipe components (valves, flanges, reductions,
etc.).
All the instruments on the lines and equipment.
5.3.4.6 Sections, Elevations and Details
The sections and elevations of the piping layout will be carried out only
in particular cases and only when isometric sketches are not foreseen.
Particular detail on a scale of 1:50 or 1:33 may be necessary for piping
layout on a scale of 1:100 for storage areas.
-
8/16/2019 5. Piping department.pdf
11/74
Page 197 of 462
S T P - 0 1 1 / 1 3
5.3.4.7 Isometric Sketches
Isometric Sketches will be made for all the lines with a diameter of 2”and greater, unless otherwise indicated on the scope of work, shown on
the appropriate A3 format; the drawing will not be made on a scale and
will always be done on a single line tract. These will show:
The route of the line with the position of all its components.
(Valves, flanges, elbows, etc.).
The symbol with references for typical installations. (Vents,
drains, etc.).
The flow direction. The line number.
The line piping class.
The piping size and its components.
References to the equipment that connects the pipe.
All of the necessary dimensions for the construction of the line.
The orientation details of the pressure taps for the orifice flanges.
The orientation details for the flange holes if they are different
from the standard.
Eventual construction details, for special pieces to be made on
site, with piping material.
Item and number of all lines or equipment instruments.
For lines of 1 ½ “and less, if required, the isometric sketches will
be approximate for the route and for the dimensions, and must be
verified on the site by the mechanical construction department
before erection, and will not indicate pipes support.
For lines 2” and greater, the isometric sketches will further show:
The exact elevation in a way to permit the prefabrication, other
than the mounting, of the lines.
The symbol with the item of the standard and special auxiliary
support for the contract.
Indication of the field welding to carry out with the mounting, if
required by the scope of work.
-
8/16/2019 5. Piping department.pdf
12/74
Page 198 of 462
S T P - 0 1 1 / 1 3
5.3.4.8
As Built Drawings
At the end of the plant construction, the drawings, which will be
updated “as built”, will be the plot plans and the underground pipinglayout.
5.3.4.9 Material Take Off
For each pipe and/or isometric sketch a material list will be made with
the following content:
a. Reference to the sketch
Line number
The zone or area where it is
Sheet number
Date
Piping class
b.
Description of the elements
Code
Destination (see destination code table)
Component type
Material type
Diameter and/or diameters
Schedule and/or thickness
Rating
Quantity Weight of every single element
Prefabrication and erection weight
Total weight
-
8/16/2019 5. Piping department.pdf
13/74
Page 199 of 462
S T P - 0 1 1 / 1 3
5.3.4.10 Piping Material Summary
Depending on specific demands, a piping material list will be
summarized by:
Code;
Area /Zone /Unit;
Destination.
5.3.4.11
Isometric List
The isometric list is a list of all isometric sketches of the plant. For eachone of these sketches, the following will be described in detail:
Line number;
Date and revision of issue;
Piping class.
5.3.4.12
Auxiliary Piping Supports
The auxiliary piping supports will be defined in accordance with thestandard.
a. Auxiliary supports for 2″ lines and greater.
b. Auxiliary supports for 1 ½” lines and lower.
5.3.4.13 Auxiliary Piping Support List
Supports for 2″ lines and greater will be prepared based on a
compilation of different types:
Standard supports
Non-standard supports
The standard supports will be identified by an alphanumerical code
which will indicate the type and size.
-
8/16/2019 5. Piping department.pdf
14/74
Page 200 of 462
S T P - 0 1 1 / 1 3
5.3.4.14
List of Material for Auxiliary Piping Support
The document, where all of the materials necessary for the construction
of special and standard supports are listed, will show in detail:
Type of material (HEA, Plate ecc.) and size;
Quantity;
Total weight of the type of material;
Total weight of supports.
5.3.4.15
Verification of the Piping Stresses
A flexibility analysis for the lines of the plant will be carried out in
accordance with the Stress Analysis specification.
-
8/16/2019 5. Piping department.pdf
15/74
Page 201 of 462
S T P - 0 1 1 / 1 3
5.4 Definitions
5.4.1
General Criteria
To reach a correct planimetric solution, all of the elements of the plant
must be positioned in order to assure that all of the plant requirements
in the following paragraphs are followed.
5.4.1.1 Security
This refers to all personnel present in the plan, the environment, hazard
equipments and all ancillaries within the plant. These requirements will
be followed from the point of view of the planimetric solutions, using the
following preventive measures:
a.
Foresee adequate space between the hazardous components and
other components inside and outside the plant with the purpose of
eliminating or reducing the possibility of risk that they may cause
harmful effect in case of an accident and/or the entity of the
damage.
b.
The positioning of dangerous components in order to eliminate or
limit the effects of their proper functioning both inside and outside
of the plant;c.
The reserving space and access to allow the installation and
operation of fixed and mobile safety equipment, safety scape for
personnel in case of an accident;
d. Protection such as: dikes, protection walls, height differences,
corridors and slopes to reduce or eliminate hazard in case of an
accident
In lack of different standards or contractual limitations, table 4.1.1A
provides a guide for the minimum distances to keep between
components to satisfy the safety requirements (these distances are
referred to the outer surface of the related subject). The regulations inthat table come from the standards of NFPA (National Fire Protection
Association) in which it can be referred to for further details.
For projects requiring a security analysis, the pertinence of the
planimetric solution must be verified case by case respecting the risks
identified by the analysis.
-
8/16/2019 5. Piping department.pdf
16/74
Page 202 of 462
S T P - 0 1 1 / 1 3
Table 4.1.1A –Minimum Distance Between Components
Note :
-
The distances are measured in meters- Where it is not specified, the distance will be calculated on the
basis of necessity for accessibility, operability and maintenance.
(1) Ex.: Water pumps, air compressors, etc.
(2) Ex.: Valves and/or activation systems for shut down systems,
water sprayers, etc.
-
8/16/2019 5. Piping department.pdf
17/74
Page 203 of 462
S T P - 0 1 1 / 1 3
5.4.1.2
Functionality
This expression stands for the functional performance and productive
capacity of the plant designed. For the best output of the plant, fromthe planimetric point of view, all equipment, plant’s units and
obstructions shall be arranged in such way which shall follow limitation
of PFD, P&ID and equipment data sheet properly.
In particular:
Minimum and maximum lengths of connections and differences
in elevation. Particular attention should be paid to determine the
elevation of different plants, parameters and structure that have
been foreseen for the plant, which causes an elevated cost impact
on the total plant value for the earth work and structural work;
Flexibility for start-up and for the total or partial plant
functioning;
Positioning of components in a manner which assume proper
execution of all connections (piping and relevant accessories,
etc.).
5.4.1.3 Operability
For a good engineering practice and planimetric solution, control
system of all components of the plant shall be located in a suitable
position in order to provide easy access for handling and inspection
during normal operating condition.
To achieve this objective it may be required to foresee accessories like
fixed or mobile platform and relevant stairways.
Moreover it is recommended to integrate all distributed control and
handling components or system of similar characteristics up to its
possible extent.
The standard spaces related to accessibility and operability may differ
considerably from project to project based on the typical environmental
conditions and operating personnel requirements to run the plant
efficiency.
-
8/16/2019 5. Piping department.pdf
18/74
Page 204 of 462
S T P - 0 1 1 / 1 3
5.4.1.4 Maintenance
The maintenance requirements are satisfied, from the planimetric point
of view, through the predisposition of:
Roads and routes, wide enough and spacious to enable easy
access and use for mobile equipment for maintenance of the
plant;
Open spaces, around components that need maintenance,
sufficient for: operation of maintenance vehicles, dismounting and
substitution of parts which may need it (such as: motors for
machines, heat exchanger bundles); Eventual fixed equipment such as: davits, monorails, hoists,
according to the scope of work.
5.4.1.5
Constructability
This requirement is fulfilled from the planimetric point of view assuming
that:
a.
Spaces and access for transporting components of the plant andconstruction equipment is sufficient within the site;
b. Sufficient space for any necessary temporary installation for
construction.
Observation should be paid for the positioning of big size, heavy and
long lead items in order to avoid any delay in sequential and
compulsory erection schedule due to the constriction or blockage of
passages.
Moreover attention must be given to the positioning of heavy items;
which are subjected to be lifted up during erection and usually providedwith two lifting vehicles (one for lifting and another for holding).
For best practice position the component close to the erection area
provided with sufficient spaces for easy access to the area and align
horizontally adjacent to the foundation if two components are
positioned in the same area, it is necessary to optimize the area and
leave space for lifting and, in some cases, for their assemblage during
erection.
-
8/16/2019 5. Piping department.pdf
19/74
Page 205 of 462
S T P - 0 1 1 / 1 3
5.4.2 Pipe–Rack, Pipe-Way and Building Positioning
This section provides instructions regarding the positioning of singlecomponents of the Plant, particularly regarding problems related to
installation, accessibility and working maintenance.
5.4.2.1 Pipe – Racks
Pipe–Racks, in general, are the piping support and cables, above ground
structures, connecting various process and utility users within the
plant.
In order to work, it is necessary that the lines do not obstruct paths forpersonnel and machines in order to assure safety and accessibility for
other components.
These are normally placed on longitudinal wheel-tracks in the area
representing the limits of the plant’s Units with the purpose of
optimizing the aboveground route and with a symmetrical distribution
for the various users.
Pipe–Racks may be developed on different levels where the elevation
varies according to the material used for construction (ex. for concrete
pipe racks in cement, a large beam obstruction must be considered) and
the eventual presence of intermediate levels, for pipes of a large
diameter (this provides necessary space between the various levels).
As a guide, for steel pipe racks, the height of the support levels is
established as follows:
4.6 m 6.2 m 7.8 m Main pipe-rack
3.8 m 5.4 m 7.0 m For branches
In order to stabilize the size of the pipe-racks, it must be taken into
consideration that, apart from the need to support all pipelines and
cable trays it is necessary to provide 20% of space for the future lines.
When support is also required for air coolers, the width of the pipe-
racks must be the same size as the equipment.
-
8/16/2019 5. Piping department.pdf
20/74
Page 206 of 462
S T P - 0 1 1 / 1 3
5.4.2.2
Walkways
In general, pipe ways are corridors where pipe runs above the ground
along the corridor and supported by sleepers, connects different off-siteareas, process and utility areas of the plant.
For pipe ways elevations are exempted from any limitation unless
otherwise indicated.
These are normally positioned along the connecting roads in order to
have easy access for maintenance and operation.
5.4.2.3
Control Rooms
The control rooms are concrete structures composed of offices,
computers, laboratories and other services, where plant operation for
process, utilities are followed and eventually other parts of the complex
are subjected to a continuous surveillance of the plant.
The size of the control rooms and their relevant locations are defined by
the Instrumentation and Civil sections.
The control rooms must be in areas that are not subject to accidental
consequences.
Such as:
Explosions
Toxic clouds
The spread of fires
Where not obtainable, Explosion Test of Construction shall be carried
out according to the pressurization conditions, etc.
Particular attention must be given to the vulnerability of exits and
emergency escape routes.
The control rooms must be located, in a central area in relation with the
users connections and orientations, as long as this does not jeopardize
operators’ interventions, with a cable entrance/exit side facing towards
it; this is to permit an optimal path for the cables and uniformity of
intervention time for the various plant Units.
-
8/16/2019 5. Piping department.pdf
21/74
Page 207 of 462
S T P - 0 1 1 / 1 3
Control room must be positioned in proximity to the roads and there
must be zones reserved for operations and parking; this is in order to
permit access (both during normal operation and for maintenance
interventions), a quick intervention in case of emergency and a rapidevacuation.
5.4.2.4
Electrical Substations
The substations and the electrical substations are structures or
buildings containing feeding equipment, transformers, distributors and
control system of electrical power necessary for the Plant’s operation.
In general, this includes:
a. A High Voltage substation or entrance station located where
electrical power feed lines arrive from outside;
b.
A main station, fed from the lines coming from the high voltage
substation and, if any, fed from internal self generators.
c.
Some secondary distribution stations, the number of which varies
according to its complexity, by the number and the users
dislocation.
The dimensions of the substations and electrical substations will be
defined by the Electrical and Civil departments; the location and
orientation will be agreed on, by the Electrical department.
5.4.2.5
High Voltage Substations Or Entrance Cabin
These are generally located in proximity to the High Voltage Switch
Gear. High voltage switchgear is any switchgear used to connect or
disconnect a part of high-voltage power system. These switchgears are
essential elements for the protection and safe operation, without
interruption, of a high voltage power system. These substations must be
provided with roads and with sufficient area for vehicles movement and
parking; this is in order to permit access during normal operation for
maintenance interventions, quick interventions in case of emergency
and rapid evacuations.
In any case, the location of the main electrical substation must be
chosen in a manner to avoid overhead power transmission lines, across
the plant (therefore it is preferable to locate in a decentralized location,
in order to prevent from any accidental consequences; e.g. explosions,
lightning, etc.).
-
8/16/2019 5. Piping department.pdf
22/74
Page 208 of 462
S T P - 0 1 1 / 1 3
5.4.2.6
Electrical Power Distribution Stations
According to the international codes and standards, the powerdistribution substations should be located in safe areas where formal
risk analysis, conducted properly and methodically to ensure that
potential accidental risk is either eliminated, or else reduced to a level
as low as reasonably practicable.
Such as:
Explosions
Toxic clouds
The spread of fires
Where not obtainable, Explosion Test of Construction shall be carried
out according to the pressurization conditions, etc.
Particular attention must be given to the reliability of exits and escape
routes.
5.4.3
Equipment Positioning
5.4.3.1 Heaters, Boilers, Relevant Accessories and Stacks
The heaters and relevant accessories are generally grouped in
appropriate areas situated within the battery limits of the pertaining
plant’s Unit and must be distinct from the other equipment.
These areas are chosen on the basis of the prevailing wind directions so
that an eventual gas fuel leak from the plant, will not reach the open
flames of the burners.
Within the distance among the various heaters, there must be adequate
space for operation and maintenance. The minimum distance between the heater edge and the equipment is
shown in table 4.1.1.A.
Within this limit, there may be some equipment that are strictly
connected to the heater, reforming plant reactors, high pressure
exchangers and decoking vessels.
-
8/16/2019 5. Piping department.pdf
23/74
Page 209 of 462
S T P - 0 1 1 / 1 3
5.4.3.2 Columns and Reactors
The minimum distance among the columns, reactors and other
equipment is shown in table 4.1.1.A.
When fixed equipment of lifting are installed on the columns and/or
reactors (ex. davits), there must be free space at the bottom of the
equipment in question, the size of the space is given by the range for
the means of lifting plus a margin of about 1 m. These above
requirements permit the transfer, operations and accessibility around
the parts movable (catalyst, internals, valves, etc.). it is mandatory to
foresee an area on the reactors plot plan for the substitution or
replacement of spare parts, for catalyst loading and unloading operation
in order to facilitate any movement required by the operating personnel(ex. need for a particular kind of pavement, eventual bases, etc.).
5.4.3.3
Heat Exchangers
The heat exchangers are installed in groups and, when possible,
providing sufficient space for operators.
In case of exchangers installed on the ground, it has to find the
possibility to install in overlay position.
However, this is normally limited to maximum two elements, except for
the double pipe exchangers or exchangers with a shell diameter lessthan 12” (305 mm).
In case of heat exchangers installed on the structures or the
exchanger’s axis is at an elevation higher than 3.6 m, it will be required
availability of lifting equipment (e.g. monorail) capable of removing and
dismantling shell head, heavy tube bundles and distributors belts on
the shell-side.
The exchanger distributor belt shall be aligned with the shell side
nozzles and also with the concrete saddles, which facilitate marking of
civil works during engineering survey.
The exchangers must be positioned with the distributors facingoutwards the plant.
The plot plan must indicate at least two saddles; one fixed and another
sliding saddle. Horizontal saddle and free to move in the longitudinal
direction, due to thermal and pressure differentials, at the other saddle.
Around the exchanger, the following minimum distances must be
respected:
-
8/16/2019 5. Piping department.pdf
24/74
Page 210 of 462
S T P - 0 1 1 / 1 3
0.7 m between each exchanger (this number refers to the
maximum overall dimension, for example between the largest
flange of the distributors);
If there are intermediate groups for regulation or maneuver
valves, a passage equal to 0.9 m must be kept;
If there are no other constrains (to access to other components)
each group of 4 exchangers must be positioned 1.5 m apart from
each other in order to provide sufficient space for maneuvers and
movement of the operating personnel.
5.4.3.4
Vessels
The distance among vessels and other equipment is shown in table4.1.1.A.
The small vessels with vertical axes, containing chemical additives,
must be gathered on the plot plan in a single zone in order to centralize
the operation for their filling.
5.4.3.5 Centrifugal and Alternatives Compressors
The compressors must be positioned, if possible, in only one area (the
compressors may be grouped into one or more of the plant’s Units),
both to facilitate the engineering and the maintenance work: thisgrouping of more compressors with relevant motors permit the use of
only one building and only one monorail, if the closing area is required.
If not otherwise specified, the compressors are generally installed
outside.
If it is necessary to install compressors in a closed building, this will be
done keeping in mind the problem of ventilation which may be solved by
leaving the walls open up to 2.5 m greater than the service platform and
providing appropriate vents on the roof; in any case, we have to
consider the relevant density of the gas, air or steam that may be
released into the atmosphere during normal operation and at anyextreme hazardous conditions as foreseen.
Further problems may arise from the classification of dangerous areas,
with possible requirements for pressurization of the building.
-
8/16/2019 5. Piping department.pdf
25/74
Page 211 of 462
S T P - 0 1 1 / 1 3
During the positioning of the reciprocating compressors on the plot
plan, spaces must be provided for:
Draw off of pistons (the draw off will be generally indicated on the
machines design);
Possible pulsation dampers;
Possible intermediary coolers, etc;
Possible local panel
In the design of the compressor room on the plot plan, the following
must be kept in mind:
a. Sufficient space around the machine (about 1.5 m) greater than
what is already planned for the draw off of pistons;
b.
Sufficient space to permit the foundation construction in reinforced
concrete spaced in order to avoid transmitting vibrations;
c.
Utilize the respective spaces, under the work platform, to position
possible pulsation dampers, intermediary coolers;
d. Sufficient space to position the steam turbine, when foreseen, with
the relevant condenser (under the service platform). This spacemust be, around the turbine and the relevant operating equipment
(1.5 m minimum).
e. Align the pillars of the building in a way that they don’t interfere
with the machine’s foundations, this is to facilitate the ground
support of the service platform which must be independently
supported by the machines foundations which so that, should not
transmit inevitable machine vibrations;
f.
Provide an access available for means of transportation and
loading / unloading bay within the room;
g. Do not position any of the equipment or piping bundle, above the
compressors (except for the sealing oil tanks);
h. The K.O. drums must be located outside the compressor rooms.
-
8/16/2019 5. Piping department.pdf
26/74
Page 212 of 462
S T P - 0 1 1 / 1 3
5.4.3.6 Pumps
The horizontal pumps will normally be positioned under the pipe-rackwith the hydraulic part facing outwards. If the pumps are placed in
double rows, there must be a free space (minimum 3 m) between the
two rows for the vehicle movement.
When positioning the pumps on the plot plan, it is necessary to:
a.
Align the discharge nozzles with respect to the pipe-rack pillars (as
shown in fig. “Aligning and Pump Basement”);
b. Provide sufficient space (min 3m) behind the motors, or turbines,
to permit cables routing, access, transit for the personnel, with therelevant equipment, both for normal operating phases and for
maintenance interventions;
c. Hydraulic side of the pumps shall be oriented toward the direction
where fluids flow into the plant for pumps suction;
d.
Provide sufficient space between each pump in order to permit easy
transit for operative personnel and plant maintenance. That space
will be normally fixed to about 0.8 / 1 m minimum clear span.
e. Install a fixed monorail for the movement and substitution of spare
part or any other parts when it is not possible to have easy access
to equipment with mobile lifting transport.
In addition to what has been previously described, when positioning the
pumps it is necessary to comply with all the following safety
precautions (including what is shown in table 4.1.1A).
a.
The light hydrocarbon treating pumps with P > 3.5 MPa (relevant)
must not be positioned under the air coolers, but they may bepositioned under the pipe-rack;
b. The hydrocarbon treating pumps with T ≥ T+ (flash point) must not
be positioned under the air coolers and must also not be positioned
under the pipe-rack. Furthermore, they must have a distance at
least 4 ÷ 5 m from the flammable product treating pumps with T <
T+ (point of flammability);
-
8/16/2019 5. Piping department.pdf
27/74
Page 213 of 462
S T P - 0 1 1 / 1 3
c.
The pumps handling flammable products with T < T+ (point of
flammability) may be positioned both under the air coolers and the
pipe rack;
d.
Pumps handling hydrocarbon must be at a distance, as much as
possible, 4 ÷ 5 m from the equipment containing flammable
liquids, or combustibles. If this is impossible, it is necessary to
take precautions by providing adequate fire protection and an
adequate fire proofing systems;
e. The pumps must not be installed within dikes or storage tank
enclosure walls.
-
8/16/2019 5. Piping department.pdf
28/74
Page 214 of 462
S T P - 0 1 1 / 1 3
5.4.3.7
Air Coolers
Apart from particular requirements, the air coolers will generally be
installed above the pipe-racks, preferably in a central position relevant
to the connecting equipment, avoiding too close to equipment and/or
structures which may interfere.
To permit sufficient air passage and an efficient thermal exchange, the
following requirement must be considered:
a. Keep sufficient space between the motor service platform and the
upper pipe-rack floor. These requirements are normally met by
leaving a minimal distance of 1.6 m from the highest point of theobstacle, for example from the outside row of the pipe with the
largest diameter on the pipe-rack floor (including eventual
insulation);
b. In case of Air Coolers located within 9m each other, the outlet port
will be at the same elevation (this is to avoid the recirculation of
hot air);
c. No equipment may be placed over the air coolers.
When planning the plot plan for all of the components of the plant’sunit, it is necessary to consider that the air coolers need access road
and space for the maneuvering of cranes.
The relevant sizing will be set according to the following demands:
Installation of air coolers during construction;
Substitution of ventilators (motors, propellers, exhaust fans);
Substitution of air cooler parts and/or connected piping;
Substitution of tube bundles.
-
8/16/2019 5. Piping department.pdf
29/74
Page 215 of 462
S T P - 0 1 1 / 1 3
5.4.3.8
Hydrocarbon Storage Tanks (Atmospheric)
These tanks may be, according to their construction, fixed roof and/or
floating roof.
The fixed roof tanks are used for light hydrocarbons as petrol, crude oil,
naphtha.
To position a storage tank in the tank farm, following criteria have to be
considered:
a. The tank farm area for the crude oil storage must be located at the
highest point within the plant area and possibly where it does not
exist any booster pump in order to facilitate loading pump suction.
b.
The tank farm area of semi-refined products has to be located tothe unit of the plant aimed for loading.
c. The tank farm area for “finished products” is generally located near
the former (semi-finished products) and possibly towards the
shipment facilities.
The minimum distance between the tanks, the conformation and the
location of the containment dams and the sizes and capacity of the
relevant dikes will be defined on the basis of the codes of the country
where the Plant will be carried out.In lack of precise data, it is possible to assume:
a. The volume of the dike must be equal to that of the tank (more
than 10 cm of border on each side). If the dike contains more than
one tank, the volume must be equal to the tank with the maximum
capacity plus the submersed volume by the other tanks;
b. The height of the dike above ground level must not exceed 4 m;
c.
The height of the tank must not exceed 12 m of the dike wallsunless otherwise indicated by local codes;
-
8/16/2019 5. Piping department.pdf
30/74
Page 216 of 462
S T P - 0 1 1 / 1 3
d.
The size of the dike will be defined fulfilling the condition that any
straight line passing through the area of the tank’s roof (or the
upper edge, if the it’s a floating roof) and forming a 45° angle with
the vertical point falling within the perimeter inside of the dikeitself.
The dikes are generally formed up with soil covered by a layer of
concrete (this choice is rather preferable than concrete walls).
A passage way 1 m wide must be provided on the crest of the dikes and
shall have stairways outside the dike at a distance not more than 8 m.
5.4.3.9 Pumping Stations (“Off-Site” Areas)
During designing a plot plan, the altitude profile has to be considered tolimit the pumping station work; in addition in the design of the plot
plan, it is important to take into consideration the following
requirements:
a.
The elevation of the pump’s suction nozzles must be arranged in a
way to avoid the creation of pocket on the lines. These pockets
negatively influence the performance of the pump and can block
the total emptying of the connected tanks.
b.
The pumping stations must be positioned near the roads and musthave areas for operation and parking; this is to permit access (both
during normal operation and for maintenance), a rapid intervention
in case of emergency;
c. The layout of the connected piping must be optimized (to/from
pipe-way and to/from tanks).
5.4.3.10
Light Hydrocarbon Storage Tanks (Balls and Large Cylinders)
The storage tanks for light hydrocarbons can be spherical containers
(spheres) and/or horizontal cylindrical containers; they are used for
stocking liquefied petroleum gas (LPG) and semi-cooled products
(“Cigar” shape, type).
From the safety point of view, a proper solution to be adopted, in order
to avoid possible overheating with the possibility of explosion, could be
the one to use buried horizontal containers.
-
8/16/2019 5. Piping department.pdf
31/74
Page 217 of 462
S T P - 0 1 1 / 1 3
This solution is particularly recommended:
For storages near built-up areas; For high capacity storages;
For small storages (ex. intermediate products) adjacent to the
process Unit;
5.4.3.11 Flares
The distance of the flares from the process unit and from the
hydrocarbon storage tanks depends on the height on the heat generated
from the flame, in order to avoid to damage the equipment and
jeopardize the safety of personnel.
This distance will be defined, after a careful safety analysis, during the
execution of the Project.
The zones near the flares where there may be the presence of personnel
must be treated in accordance with API RP 521.
5.4.4
Free Spaces for Maintenance
a.
Access roads and inside of the plant’s limits:
1.
width of the principal access road 6.0m
2. width of the road within the Unit 4.0m
3. footh path width 1.0m
4. internal curve 6.0m
b. Headroom for the passage of large maintenance
vehicles at the principal access points of the plant,
measured from the roadway and the lowest point
of the pipe or structures elements:
6.1m
c. Headroom for the passage of railways, measured
by the summit of the rail and the lowest point
of the pipe; isolated or not structures
elements (to verify with local codes:) 6.5m
d. Minimum distance from rail axis to any obstacle
(to verify with local codes): 2.6m
-
8/16/2019 5. Piping department.pdf
32/74
Page 218 of 462
S T P - 0 1 1 / 1 3
e. Minimum height for the passage of maintenance
cranes in areas of the plant: 4.3m
f.
Headroom for maintenance access for
the pumps 3.2m
g.
Access space for pump maintenance , measured
by the end of the pump/motor to the external
edge of the structure and/or piping:
3.0m
h. Minimum distance between the road edge footh
path and equipment and/or piping
1.5m
i.
Minimum passage for personnel access among
equipment,structures and/or piping:
0.75m
j. Minimum overhead passage under piping 2.1m
or structures
k.
Minimum walkway width for walkways
connecting to the platforms or sleeper-ways 0.80m
5.4.4.1 Horizontal Heat Exchangers Installed on Structures
a. Fixed tube bundle exchangers:
Minimum space between structure limits
and the external distributor edges: 0.75m
b.
Removable bundle exchangers:
Minimum free space between the structurelimits and the external edge for the fixed shell: 0.75m
-
8/16/2019 5. Piping department.pdf
33/74
Page 219 of 462
S T P - 0 1 1 / 1 3
c.
“Double tube” or “fin-tube” heat exchangers:
Minimum free space between structure limits
and shell cover: 1.5m
Minimum free space between the structure
limits and piping connections: 0.75m
d.
For all types of exchangers, the minimum
distance between the lower nozzle flanges
and the structure will be: 0.2m
5.4.4.2
Air Coolers Mounted on Elevated Structures or Pipe-Racks
a. Free access from piping and/or equipment,
for the mounting of piping bundles by a crane 4.0m
b.
Free vertical space between the electrical motors
of fans and service walkways 1.8m
5.5
Piping Installation
This Section will provide the criteria regarding the installation of piping
connected to the various equipment of the Plant, with particular detail
regarding problems related to positioning, work accessibility,
maintenance and proper function.
5.5.1 Pipe-Racks
Normally, when more floors are necessary, the pipes are positioned as
follows: Service piping: upper floor
Process piping: lower floor
A typical distribution of the piping on the pipe-rack, on the basis of
services and size, is shown in the figure 1.
-
8/16/2019 5. Piping department.pdf
34/74
Page 220 of 462
S T P - 0 1 1 / 1 3
5.5.1.1 Pipe Spacing
The piping installed on pipe-racks will have sufficient space betweeneach other.
This space is necessary in order to carry out the operations following
the installations, those being: flanges clamping, welded joints, painting,
insulation, etc.
The pipe spacing (L) between two pipes, no jacketed, must at least
respect the distance resulting from the following formula:
.min252
)( ++
= Dt DF
mm L
where:
DF (mm) = external diameter of the piping flange with DN or greater
rating
Dt (mm) = external diameter of the piping with a smaller DN
Table 5.2.1A shows the pipe spacing (L) normally respected between
non-jacketed piping with a flange rating of 150# ÷ 900#.
-
8/16/2019 5. Piping department.pdf
35/74
Page 221 of 462
S T P - 0 1 1 / 1 3
Table 5.2.1.A – Pipe Spacing Between Non-Insulated Piping
(mm)
Note: for diameters or ratings not covered by the present table, apply the
formula already indicated.
If one or both of the pipes are jacketed and are steam traced, the pipe
spacing must be increased by the insulation thickness.
-
8/16/2019 5. Piping department.pdf
36/74
Page 222 of 462
S T P - 0 1 1 / 1 3
5.5.1.2 Branches
As general rule, the piping branches from the header are positioned:
Underside, for lines conveying liquids. This allows the self-
drainage, avoiding the likely risks caused by product stagnancy in
the pipelines (corrosion, water hammer, etc.)
On the top part for lines conveying air, gas or steam. This allows
to prevent the possibility of circulation of the relevant
condensates that may cause erosions, not considered, in the
choice of the appropriate material concerning the above
mentioned fluid.
The branches from the cooling water header, with lines of DN ≤ 1- 1/2",
are to be placed on the top part in order to avoid occlusions due to
slush.
The connection of outlet piping to the blow-down header are to be
placed on the top part and must be made at 90° for lines of DN ≤ 1-
1/2", or with an inclination of 45° toward the flow, for lines with DN ≥
2". This configuration is necessary for the following reasons:
Because of the low pressure within the line, the head loss mustbe reduced as much as possible.
The stress on the joints must be reduced as much as possible.
5.5.1.3
Positioning
The lines of DN >12"must be placed within the piping bundle and as
close as possible to the column of the Pipe Rack structure in order to
reduce the stress coming from the beams (see figure 1).
Steam and condensate headers, that generally need loops, must beplaced so that the loop mainly develops within the pipe-rack (see figure
1).
Piping facing downwards (for control valves, hose station, etc.) must be
placed toward the pipe-rack pillar in order to facilitate the supporting.
They must face outside the pipe rack reserving a free area of 500 mm of
clear light between the pipe surface and the edge of the pillar.
-
8/16/2019 5. Piping department.pdf
37/74
Page 223 of 462
S T P - 0 1 1 / 1 3
A span of about 31 m under the pipe rack must be free of pipes,
machines and equipment in order to allow the passage for service
vehicles.
5.5.1.4
Elevations
The bottom pipe elevation of the insulated lines must consider the
shoes height that are normally as follows:
100mm with insulation ≤ 80mm
150mm with insulation 85 ÷130mm
The blow down manifolds must have a minimum slope towards the
relevant separators equal to 2 per mil, so avoiding pocket.
-
8/16/2019 5. Piping department.pdf
38/74
Page 224 of 462
S T P - 0 1 1 / 1 3
Fig. 01 – Typical Section of Pipe-Rack
-
8/16/2019 5. Piping department.pdf
39/74
Page 225 of 462
S T P - 0 1 1 / 1 3
5.5.2 Pipe- Way
The piping installation criteria on the pipe-way are the same describedfor the pipe-rack with the exception of all process and service pipelines,
which will be installed at the same elevation; the minimum suggested
DN will be 1-1/2″ .
On the pipe-way, for pipelines with DN>30″ (750), the pipe spacing will
be estimated considering the possibility of access among the pipes
(about 300 mm of clear light).
5.5.2.1
Elevations
Piping must be installed at a bottom elevation equal to 400 mm. Such
elevation is valid for all of the process and service lines, regardless of
diameter. An exception to this rule regards the pipelines conveying
steam of which elevation is fixed in accordance with the following table.
Bottom of Pipe Minimum Elevation for Lines Conveying Steam
DN Line ≤ 10″ 12" ÷ 20" > 20
Elevation (mm) 400 600 650
The above mentioned minimum elevations are required in order to allow
the installation, where necessary, in the low part of condensate of
drainage groups by means of steam traps, the above mentioned groups
must be arranged to allow, with a minimum distance from the ground,
the operations in the relevant maintenance.
-
8/16/2019 5. Piping department.pdf
40/74
Page 226 of 462
S T P - 0 1 1 / 1 3
5.5.3 Installations on Pressure Equipment
5.5.3.1 Piping on Columns or Vessels
The piping installed on columns will be grouped in a free section, facing
the pipe-rack so avoiding, where it is possible, to cross the service
platforms.
The pipelines that descend on the columns will be placed away from the
equipment, in order to allow proper supports.
All the spillage lines of fractionating columns have to come down from
the nozzles, downward 3 m, at least, before changing direction.
5.5.3.2
Piping on Exchangers
The lines connected to the distributors nozzles shall be supported in
order to allow the disassembly of the spool. The pipelines connected to
the exchangers shall be designed and supported in order to facilitate
the removal of the tubes bundle, introducing, where necessary, coupling
flange for disassembly.
Typical installation of piping on exchangers is shown in the figure 3.
-
8/16/2019 5. Piping department.pdf
41/74
Page 227 of 462
S T P - 0 1 1 / 1 3
Fig. 02 – Typical of Piping Installation on Columns
-
8/16/2019 5. Piping department.pdf
42/74
Page 228 of 462
S T P - 0 1 1 / 1 3
Fig. 03 – Typical of Piping Installation on Exchangers
-
8/16/2019 5. Piping department.pdf
43/74
Page 229 of 462
S T P - 0 1 1 / 1 3
5.5.4 Piping Installations on Pumps, Compressors and Steam Turbines
5.5.4.1 Pumps
The pumps suction lines shall possibly be shorter in line according to
the requirements of the thermal expansion of the suction line. In any
case, pockets shall not be formed.
On centrifugal pumps, in case that the suction nozzle would be smaller
than the line, it will be used a reduction “eccentric type” placed with the
plane part upward. For the lines that are involved in transport of high
density fluids (slurry) or fluids, for which, pocket are expressly
forbidden, the eccentric reduction will be placed with the plane part
downward.
Concerning double suction pumps “side-side type”, a length of straight
pipe, equal to five times the diameter of the line, between the pump
nozzle and the first elbow if placed on the horizontal plane, shall be
foreseen. When the elbow is placed on the vertical plane, the straight
length could be omitted.
Typical of lines installation on double suction pumps
-
8/16/2019 5. Piping department.pdf
44/74
Page 230 of 462
S T P - 0 1 1 / 1 3
For the pipelines that are connected to threaded part of machines
(service line, seal lines, vent or drain lines) a flanged connection
between the machine and the block valve of the line, shall be foreseen.
When the connection of a temporary strainer is needed, this will be
installed as near as possible to the machine, between suction nozzles
and the first block valve. The route of the line and the supports, shall
allow the disassembly of the filter.
5.5.4.2 Compressors
In order to reduce vibrations, suction and discharge pipes reciprocating
compressors shall be positioned on the ground and hook up on it, as
near as possible to the machine, according to the thermal expansion
requirements.
In the case of lines involved in chemical washing, appropriate
connections or tube pipes to the machine, will be provided. The relevant
supports will be provided for the line filled with water or temporary
supports will be provided.
5.5.5 Storage Atmospheric Tanks
As far as the installation of these tanks is concerned, an adjustable
connection has to be provided.
The suction pipes from a tank, have to be installed to the minimum
allowed elevation in order to avoid the forming of pockets on the line
that could interfere with the operation of the pump and prevent the
entire emptying of the connected tank.
The firewater, used to convey water mixture and foaming-agent liquid,
have to be installed within the basin and on the ground to reduce as
much as possible the damage of the pipelines in case of accident.
The pipelines jointed to the distribution manifold nozzles of products
from/to tank, have to be gathered as much as possible in a manifold.
The relevant valves have to be positioned on the addle of the service
platform. The distance between centers among pipelines of manifold has
to allow the access for the assemblage and for the maintenance of the
relevant valves.
-
8/16/2019 5. Piping department.pdf
45/74
Page 231 of 462
S T P - 0 1 1 / 1 3
5.5.6 High Pressure Storage Vessels
For security reasons, only the pipelines directly connected to the
relevant high pressure storage vessels, could be installed in the storagearea.
The above mentioned pipelines have to be suitably supported
considering the requirements of expansion/contraction and vibrations.
Normally the connection to the vessel is carried out providing a single
line placed at the bottom of the vessel.
This single line has to be used for all the operations: filling, emptying
and drainage.
When, for specific operating conditions, the Process requires a returning
vapor line, this will be connected at the edge of the vessel. The distribution pipes of the product from/to the vessels have to be
grouped, in a manifold that, for security, has to be placed outside on
the partition wall.
To reduce at minimum the possibility of dripping, the threaded
connections must not be used inside the pipelines and the quantity of
the flanged connections has to be reduced to the minimum.
Concerning inlet and outlet piping, a drainage has to be provided. This
has to be placed after the first block valve in the length outward from
the manifold; the relevant discharged inflammable vapors shall be taken
out to a safety place.For the conditions of assembling execution, see the typical examples
shown in pictures 4, 5, 6 and 7.
-
8/16/2019 5. Piping department.pdf
46/74
Page 232 of 462
S T P - 0 1 1 / 1 3
Fig.04.- Typical Arrangement of Vessel Piping Layout
-
8/16/2019 5. Piping department.pdf
47/74
Page 233 of 462
S T P - 0 1 1 / 1 3
Fig. 05 – Typical Model of Piping Assembling
-
8/16/2019 5. Piping department.pdf
48/74
Page 234 of 462
S T P - 0 1 1 / 1 3
Fig. 06 – Details of Piping Assembling
-
8/16/2019 5. Piping department.pdf
49/74
Page 235 of 462
S T P - 0 1 1 / 1 3
Fig. 07 – Typical Models of Fire Fighting Assembling
-
8/16/2019 5. Piping department.pdf
50/74
Page 236 of 462
S T P - 0 1 1 / 1 3
5.5.7 Valves and Instruments
All of the valves which require operating intervention must bepositioned in a way so that the hand wheel is accessible from the
ground or from a platform. If it is positioned higher than 2.1m (hand
wheel axle) from the operating level, they will be operated by means of a
chain (this does not apply for valves which are 1 ½” or less). If the
valves are positioned under the operation levels, the hand wheel
extension will be brought to 1.2m over the operation levels. All valves up
to 1 ½” are considered accessible, for operation made from vertical fixed
ladders.
For the block valves positioned at the header branches, operation
devices are not foreseen.
The control valves must be accessible from the ground or from
platforms. When they are mounted on platforms, the control valves will
be positioned on the inner side of the handrail.
The safety valves must be accessible from the ground or from platforms.
When mounted on platforms, safety valves will be positioned on the
inner side of the handrail.
The valve for pressure instruments must be accessible from the ground,
from platforms or from fixed vertical ladders. If positioned at a height
higher than 3.6m from the ground, they will be accessible by portable
vertical ladders.
The temperature instruments will be accessible from the ground,
platforms or fixed vertical ladders. If positioned at a height higher than
3.6m from the ground, they will be accessible by portable vertical
ladders.
The valve for flow instrument will be accessible from the ground,
platforms or fixed vertical ladders. If positioned at a height higher than
3.6 from the ground, they will be accessible by portable vertical ladders.
If positioned on a pipe-rack, no fixed installation for accessibility will be
foreseen.
The glass level gauges will be accessible from the ground, platforms or
fixed vertical ladders.
The displacement or differential level gauges will be accessible from the
ground or a platform. If positioned with a bottom edge at a height
higher than 3 m from the ground, they will be accessible by a fixed
vertical ladder.
-
8/16/2019 5. Piping department.pdf
51/74
Page 237 of 462
S T P - 0 1 1 / 1 3
5.5.8 Installation of Piping Parts and Accessories
5.5.8.1
General
The piping will be arranged in a way which permits the removal of
pieces of equipment or parts of it which may require maintenance
operation (pipe bundle of the exchangers, pumps, etc.) without
removing the block valves or all pipe connected to the equipment itself.
The hot piping will be arranged or insulated so that the heat radiation
conditions within 40°C of the neighboring equipment do not damage the
surrounding equipment.
The piping will be gathered into groups whenever possible. These
groups will have different elevations in order to permit deviations,change of route and perpendicular intersections of the pipes without
interference among them.
The piping will be designed so that liquid and gas pockets are avoided.
When this is not possible, there will be a vent for the gas pockets and a
drain for the liquid pockets.
Dead legs on the piping will be avoided for pipes which transport
caustic products, acids, liquids which may solidify or gas which may
form a corrosive condensate.
There will be no process piping inside the control room. No steam or
condensate piping will be inside the electrical substation.
5.5.8.2 Installation of Gate Valves and Globe Valves
At the inlet and at the outlet of safety valves, the valve stem will be
always oriented horizontally.
On pipes containing dangerous liquids, the valve stem will never be
installed below the horizontal level.
On cryogenic service pipes, the valve stem will be oriented vertically or
at 45° from vertical.
Chain for valve handling shall not obstruct passage areas. The chain
will extend to 900 mm above the operation platform
All Car Seal Open (CSO)/ Lever Operated (LO) gate valves will be
installed with horizontal stem, in order to avoid that, in case of failure,
the wedge should fall due to the force of gravity, and obstruct the fluid
flow.
-
8/16/2019 5. Piping department.pdf
52/74
Page 238 of 462
S T P - 0 1 1 / 1 3
5.5.8.3
Check Valves Installation
Clapet check valve will be preferably installed horizontally. Vertical
installation will be in the case of upwards flow.
If a check valve is installed in such a way that when it closes liquid
accumulates in the pipes, a drain is required upstream from the valve.
5.5.8.4
Plug Valves and Ball Valves Installation
On the plug valves, and ball valves chain operation, with or without
extension, will be allowed only in exceptional cases.
The position indicator of gear-operated plug and ball valves shall bevisible from operational floor.
5.5.8.5 Butterfly Valves Installation
In the butterfly valves installation, it is necessary to verify that, during
the operation, the butterfly valve does not interfere with element inside
pipes (thermo-well pips, line reduction, internal coating).
If butterfly valve is not “Threaded connection type”, additional couple of
flanges will be installed when, downstream line, it has to be removedduring maintenance operations.
-
8/16/2019 5. Piping department.pdf
53/74
Page 239 of 462
S T P - 0 1 1 / 1 3
Fig. 08 – Valves With Stems in Vertical Position
-
8/16/2019 5. Piping department.pdf
54/74
Page 240 of 462
S T P - 0 1 1 / 1 3
Fig. 09 – Valves With Stems in Horizontal Position
-
8/16/2019 5. Piping department.pdf
55/74
Page 241 of 462
S T P - 0 1 1 / 1 3
Fig. 10 – Typical Example of Battery Limit Installation (placed on theground)
-
8/16/2019 5. Piping department.pdf
56/74
Page 242 of 462
S T P - 0 1 1 / 1 3
Fig. 11 – Typical Example of Battery Limit Installation (Placed on Pipe-
Rack)
-
8/16/2019 5. Piping department.pdf
57/74
Page 243 of 462
S T P - 0 1 1 / 1 3
5.5.8.6 Vents and Drains
Piping will be designed in order to avoid gas and liquid accumulation.
Otherwise:
On all liquid accumulation, drain valves will be installed.
On all gas accumulation, valved vents will be installed.
Vent diameter: 3/4″
Drain diameter:
3/4" for 3/4" to 8″
1” for 10" or larger lines.
An exception is made for lines containing heavy products, where the
diameter will be 1” minimum .
For vents and drains installed on high pressure lines or hydrogen lines,
the first connection nipple to main line will be SCH. 160 min.
Drains installed on hydrogen and LPG lines will be designed with a
double valve.
5.5.9 Control Valves
For control valve installation, sufficient clearance for actuator
accessibility and/or removal will be provided.
The plug will always be removable from the bottom of the valve
and the minimum clearance shall be agreed with the Instrument
Section.
The actuator’s diaphragm will be accessible from the top of the
valve and a 300mm clearance will be provided.
-
8/16/2019 5. Piping department.pdf
58/74
Page 244 of 462
S T P - 0 1 1 / 1 3
Control valves will be positioned preferably with the stem in a vertical
position. In special cases, the stem may be orientated up to 45°from the
vertical axis. The stem may never be orientated horizontally or
downwards.
In the control sets, a valved drain will be provided between the first
block valve and control valve.
5.5.10
Safety Valves
Installation criteria
The safety valves will be installed in accessible areas in order toensure operability and disassembling.
Safety valves will preferably be installed vertically.
The installation of these valves in a dead stretches of pipe (e.g. at
the end of horizontal pipes where normally there is no fluid flow),
have to be avoided.
Valves discharging into the atmosphere will be located at the
highest point of the line on which they operate. Valves
discharging into a closed system will be located at a minimum
distances from the header to which they are connected.
Inlet line
The safety valve inlet line will be vertical and as short as possible;
fittings used will be kept to a minimum to minimize the pressure
drop.
In order to reduce mechanical stress on safety valve and on
relevant inlet lines, it will be necessary to take into consideration
the reaction forces caused by valve opening, especially in the case
of discharge into the atmosphere.
A proper analysis of such forces and relevant effect on valve and
connected piping will be made applying the calculation criteria for
such forces as per ANSI B31.1 and per API 520.
Gate valves will be installed with horizontal stem in order to avoid
any failure, falling of wedge due to the gravity, and to obstruct the
fluid flow.
-
8/16/2019 5. Piping department.pdf
59/74
Page 245 of 462
S T P - 0 1 1 / 1 3
In case of joint assembly of a main safety valve and its spare,
block valve on the inlet and outlet lines will be installed creating a
system which does not allow the block valve to be closed on the
main safety valve without first opening the block valve on thespare safety valve, or vice versa. This system can be obtained by
mechanical interlock or using valves with padlocks.
For safety valves that operate at a temperature below zero degrees
Celsius and that discharge into the atmosphere, it is necessary to
avoid the formation of ice and condensation in the valve plug, due
to air humidity. For this purpose the safety valve will be installed
with the last part of the inlet line not insulated. In this case, the
not insulated part will be long enough to prevent reaching dew
point in the valve; otherwise the safety valve must be heated
(using steam or other proper means).
Outlet line – Discharge into the atmosphere
When a valve discharge into the atmosphere the outlet line shall
be directed upwards for gas discharge, and downwards for liquid
discharge.
For dangerous fluids, if a safe location discharge is expressly
required on the P&ID, the outlet pipe will be raised 3 m above any
walkway situated within 15m.
For those fluids for which a safe discharge location is notrequired, the outlet pipe will be oriented towards an area where
the passage of persons is not foreseen
Outlet pipe of safety valves discharging into the atmosphere will
have a 10mm diameter hole in the bottom to drain condensate or
rain water, if any. In case of dangerous fluids, the said hole will
be connected by piping to a safe area or to the sewer.
Outlet line – Discharge into a closed system
Safety valves discharging into a closed system will be installed atthe higher level than flare header, so that safety valve outlet line
is always sloping towards the header; the intake will be on the top
header, oriented at 45° in the flow direction. Horizontal intakes
will be allowed when the safety valve discharge pipe diameter is at
least one diameter smaller than of the header one.
-
8/16/2019 5. Piping department.pdf
60/74
Page 246 of 462
S T P - 0 1 1 / 1 3
If the safety valve has to be installed lower than header, a ¾”
valved drain line should be provided, at the minimum distance
from safety valve outlet flange, discharging, after checking of
process, into a recovery pot where liquid, after vaporization, shallbe connected to blow down header.
For the assembly of block valves on safety valve outlet lines, the
same rules will be observed as for the assembly of inlet line valve.
Special care will be taken in the safety valve outlet lines
arrangement, in order to minimize changes of direction.
Support for the above line will be designed in order to minimize
stress on the valve, taking into account that the line will have to
maintain its position with the safety valve.
5.5.11 Piping Characteristics
5.5.11.1
Line Diameters
Pipes and fittings with diameters of 1 ¼ ", 2 ½" , 3 ½ ",4 ½ " and 5” will
not be normally used. Where such diameters are required for
connections to equipment, the pipe length will be reduced to a
minimum.
5.5.11.2
Flanges and Unions
The use of flanges on pipes will be minimized and anyway limited to:
Connecting lines to equipment;
Connecting flanged elements installed on-line (valves, etc.);
On pipes which have to be removed for particular service and
maintenance.
Unions will not be used on flammable or toxic products lines. In any
case, the use of union will be limited to utility lines, 1 ½” or smaller
diameter and when the line rating is not larger than 600#.
Flat-faced flanges (FF) will be used for cast iron valves and/or
equipment nozzle joints.
-
8/16/2019 5. Piping department.pdf
61/74
Page 247 of 462
S T P - 0 1 1 / 1 3
5.5.11.3
Bends
Changes of direction will be made by means of elbows (forged, cast or
mitred) or bent pipe.
Elbows will be long radius type (R=1.5D) if not otherwise specified.
Miter bends will be made with 3,4 or 5 elements.
For changes direction, bent pipe can be used with a bending radius
longer than 1.5 times the pipe diameter, in particular, this solution will
be adopted for slurry lines, pneumatic transport lines, pigged lines,
utility lines with 11/2” or smaller diameter, (e.g., steam tracing, utility
lines of equipment, etc.).
5.5.11.4
Diameter Reductions
To reduce piping diameter, reducers or reducer nipples, weldedolet and
similar will be used; reduction flanges will be used only in exceptional
cases.
5.5.11.5
Branches
Branches will generally be at 90° and will be made with “T” pieces, pipe
to pipe branch connection with or without reinforcing plates orweldolets.
Pipe to pipe branch connections (with or without reinforcing plates),
with an angle smaller than 90°, will be used only for flow
requirements(slurry lines, safety valve discharge on flare headers, etc.)
Reinforcing plates will be defined as per ANSI B31.3 standard.
5.5.12
Steam Distribution Network
Where possible, the steam header will be positioned at one end of thepipe-racks and sleepers, for the installation of thermal expansion loop,
if any.
Steam headers will be blind flanged, (never with cap), in order to allow
the cleaning. When block valves are provided on header branches, they
will be installed on the upper horizontal length of pipe to allow the line
to drain on both sides.
On the lowest points on the end of steam header, pots will be provided
with steam traps.
-
8/16/2019 5. Piping department.pdf
62/74
Page 248 of 462
S T P - 0 1 1 / 1 3
5.5.13
Utility Stations
Service hose stations for water, air, steam and nitrogen supplies (last
one only where expressly required by the design specification) will be
located in the following areas:
Process and utilities production areas
At ground floor; hose stations will be arranged to reach all equipment or
pipes concerned, by means of 15 m hose length.
On structures; hose stations will be arranged to serve all the floor. Thewater hose station shall be limited to the first floor.
On fractionate columns; hose stations will be provided on all manholes
platforms and on the highest platform, with the exception of water.
For vertical structures and vessels, in general, utilities stations will be
installed on all floors.
Off-site area for storage and loading
Hose station will be provided in pumps room, in tank trucks and/or
railway loading area and in waste treatments area
5.5.14
Instrument Air Distribution
The instrument air distribution network will be completely separated
from the service air network; use will be only for plant instrumentation.
For each utility branch from the header, a block valve will be provided,installed at a minimum distance from the header.
Threaded piping instrument air distribution network shall be provided
with assembly joint by unions on 11/2” or smaller lines, and flanges on
2” or larger lines, to be installed about every 12m length of straight pipe
and every two changes of direction.
-
8/16/2019 5. Piping department.pdf
63/74
Page 249 of 462
S T P - 0 1 1 / 1 3
APPENDIXNotices on ferrous materials, used in the
Industrial Plants
I. Carbon Steels
The carbon steels are considered the alloys of iron and carbon usually
containing about from 0.02 to 1.2 % C and with the percentage of Mn
from 0.25 to 1% and further quantity of other e