15.11.2005fabio montecassiano infn pd & cern ph/cmm1 status of cabling on yb+2 15.11.2005 fabio...

12
15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

Upload: isabella-chase

Post on 02-Jan-2016

226 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 1

Status of cabling on YB+2

15.11.2005

Fabio MontecassianoINFN PD @ PH/CMM

Page 2: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 2

Contents

• Work done so far on YB+2

• The problems we have met

• About fibers installation

• Next step

Page 3: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 3

Status of S10• Copper cables and fibers for both DT

and RPC are installed.(The picture on the left was taken before the end of installation)

• Below a detail about how the fibers enter inside the MB2’ minicrate

Page 4: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 4

Status of S11

• Copper cables for both DT and RPC are installed.

• Also copper cables for the missing MB4 are installed. Their radial part is rolled on the face of the foot waiting for the chamber.

• Fibers not yet installed. This week IHEP staff will learn about how to do this job.

Page 5: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 5

Rack side

RPC sgn cables S11

RPC sgn cables S10

Link Board crate

DT tr & ro S10 & S11DT LV S10

RPC sgn S10(support has to be installed)

Box to store DT

TTC fibres extra L

(It can be extracted)

Page 6: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 6

The problems we have met (now solved)

• Due to a very difficult access to the minicrate once installed the S10’s cables (1st sector to be done) we was requested to change the radial layout.

• Some “no flight zone” for the RPC cables over the minicrates was defined by the experts and the RADIAL LAYOUT was redone according.

• In order to meet the new specifications– we put more layers of cables in the Z

direction, increasing the packing factor and being compatible with the latest mechanical requirement for the radial-tray and its cooling cover.

– we accepted some crossing among cables. At the end of the work they was not so many.

OLD NEW

RADIAL LAYOUT RESHAPING

• Fiber access to each minicrate was also re-designed.

• The S11 layout is now very similar to the S10 one (HV <-> LV inverted).This will simplify the installation.

Page 7: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 7

The problems we have met

• The requested extra length added to each cable is 1.5m (as stated Integration Office). With the round up we reach 2m or more for some cables.

• The experience done in these 2 sectors test shows that it’s very difficult to store that amount of extra lengths.

• Furthermore, whether possible we would avoid to cut and connectorize cables inside towers

I’m remapping all DT cables for next sectors using shorter cablesAlready realesed (full doc)

– MB.LV.mc

– MB.LV.fe

Under working– MB.HV

– MB.CA.tr & ro

• 3x MB.MCA.veto and 3 MB.CA.sc cables have to be produced by IHEP(About 1 day work of 2 techinician)

Extra Lengths storing

Page 8: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 8

i.e. MB.LV.mc @ S7, S8, S9

Extra Lengths = round up to 1m

Page 9: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 9

About fibers installation -1

• We tested the fibers protections (a divisible corrugated tube) on S10 defining the procedure of installation.

• For each sector there are 4-5 tubes, one per minicrate, carrying the 2 fibers (TTC+SC) up to a box in the periphery of the sector. From there 2 tubes of the same size (1 per type of fibers, each one contening 4-5 fibres + spares) will run up to the racks.

MB1 mc

MB2 mc

MB3 mc

MB4 near S11 mc

towards racks

TTC fibres

SC fibres

box in the periphery

MB4 near S9 mc

• Procedure per 1 sector– cut radial tubes (4-5 x 3m average)

according to mc and box position– cut peripheral tube (2x 20m average)

according with box and path for rack– upload

Page 10: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 10

About fibers installation -2

• Procedure per 1 sector– cut radial tubes (4-5 x 3m average)

according to mc and box position– cut peripheral tube (2x 20m average) according with

box and path for rack– upload radial tube with the 2 fibers– insert the 4-5 tube in the box’s slots and reorganize

fibers in two omogeneus group– upload the TTC long tube with all ttc fibres of sector– upload the SC long tube with all slow ctrl fibres of

sector

• At the end of the above procedure all fibres are protected by the tube and can be installed as a ‘cable’

Page 11: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 11

About fibers installation -3

• The installation of fibres inside the minicrate can be done only by expert technician.

TTC fibre

SC fibreVeto cable

End of corrugated tube protecting the fibres

Page 12: 15.11.2005Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB+2 15.11.2005 Fabio Montecassiano INFN PD @ PH/CMM

15.11.2005 Fabio Montecassiano INFN PD & CERN PH/CMM 12

Next step• In order to install MB4 chamber inside S9 and S11 we will install all cables trough the feet, that

are the DT’s signal copper cables from S7, S8 and S9(being S10 already done) . Some small mechanical work is still to be done (trays for S7 and S8)

MB4 S9 and S11 can be installed• We will install also all DT cables of S12First racks can be finalized (X2J21, X2J22, X3J22)

Sector collector crate serving sectors from 7 to 12HV crates serving S10-S11-S12LV crates Serving S10-S11-S12 (RPC LV cables only S10 and S11)

Racks X2A21 and X3J22 can be also cabled for HV and LV of S7 S8 S9