11 november 2002 “fp6 integrated projects” leonidas karapiperis research dg...
TRANSCRIPT
11 November 2002
“FP6Integrated Projects”
Leonidas KarapiperisResearch DG
europa.eu.int/comm/research/fp6/networks-ip.html
211 November 2002
A wider range of better differentiated instruments
New instruments
Integrated projects (IP)
Networks of excellence (NoE)
Article 169 (joint implementation of national programmes)
Traditional instruments
Specific targeted research projects
Co-ordination actions
Specific support actions
311 November 2002
Principles guiding their design (I)
Simplification and streamlining
to minimise the overheads for all concerned whether applicant, contractor or the Commission
to speed up procedures, especially time-to-contract
Flexibility and adaptability
to enable instruments to be applicable throughout the priority themes
to enable projects to evolve
411 November 2002
Principles guiding their design (II)
Increased management autonomy
to eliminate unnecessary micro-management
While preserving public accountability and protecting interests of the Community
511 November 2002
Classification of the instruments
Instrument Purpose Primarydeliverable
Scale
IP
NoE
Art. 169
STREP
CA
SSA
objective-driven research
tacklefragmentation
joint MSprogrammes
research
coordination
support
knowledge
structuring
knowledge and/or
structuring
knowledge
coordination
support
med-high
med-high
high
low-med
low-med
low-med
611 November 2002
Instruments to be used in priority (I)
Calls for proposals will identify which instruments are to be used, which have priority, and for what
From the outset, IPs and NoE will be the priority means
for implementing those themes where it is already deemed appropriate
while maintaining the use of specific targeted research projects and coordination actions
711 November 2002
Instruments to be used in priority (II)
In 2004, the Commission will arrange an independent evaluation of the use of the instruments
may lead to an adjustment of their relative weightings
811 November 2002
Purpose of Integrated Projects (I)
Designed to generate the knowledge required to implement the priority thematic areas of FP6
by integrating the critical mass of activities and resources needed
to achieve ambitious, clearly defined scientific and technological objectives
Essentially an instrument for supporting objective-driven research of a European dimension
911 November 2002
Meaning of integration in IPs
Each IP should comprise a coherent set of component parts
Internal architecture may vary depending on topic, scope and managerial approach of each IP
Forms of integration:“vertical” - full value chain of stakeholders
“horizontal” - multidisciplinarity
“sectoral” - private/public
“financial” - synergy with other schemes (EIB, Eurêka)
10
11 November 2002
Activities
Activities integrated by a project may cover the full research spectrumshould contain objective-driven research
technological development and demonstration components as appropriate
may contain a training component
the effective management of knowledge will also be an essential feature
the whole carried out in a coherent management framework
11
11 November 2002
What is the scale of critical mass (I)?
Concerning resources: each IP must assemble the critical mass of resources needed to achieve its ambitious objectivesactivities integrated may range up to several tens of
million euro
but no minimum threshold, provided necessary ambition and critical mass is achieved
12
11 November 2002
What is the scale of critical mass (II)?
Concerning the partnership: minimum of three participants from three different Member States or Associated States, of which at least two should be Member States or Associated candidate countriesbut in practice likely to be substantially more
SME participation is strongly encouraged
‘third country’ participants may be included, with a possibility of Community financial support for entities from certain groups of countries
13
11 November 2002
What is the scale of critical mass (III)?
Concerning its duration: typically 3 to 5 yearsbut more if necessary to deliver the objectives
14
11 November 2002
Proposal submission (I)
Through calls for proposalsmay be preceded by expressions of interest to help
focus calls and assist in consortium building
Simplified proposal-makingrequiring only sufficient “management-level” detail
reflecting evolutionary nature of the projectsummary description of activities for entire durationdetailed implementation plan only for first 18 months
15
11 November 2002
Proposal submission (II)
Possibility of two-stage submission
Proposers should make sure they address all the issues which will be examined during evaluation
16
11 November 2002
The negotiation process
Possible assistance of external experts
Main issues to be tackled:
finalise objectives and deliverables of the project
agree maximum level of Community grant
agree outline implementation plan for whole duration of project
agree detailed implementation plan for first 18 months
agree principles for changing consortium composition
17
11 November 2002
Reporting and payments schedule (I)
The consortium submits annual report containing:
an outline of previous 12 months’ activities
financial documents on the costs incurred (including cost certificates and management-level justification)
a detailed implementation plan and associated financial plan for the following 18 months
18
11 November 2002
Reporting and payments schedule (II)
Upon acceptance of above by the Commission:
final settlement of payment for period concerned (subject to any ex-post audit)
outstanding advance supplemented up to 85% of the anticipated Community contribution for following 18 months
19
11 November 2002
Payments and reporting schedule(example of a 4 year contract)
Activity report
Reported costs
Activity report Detailed work plan
Reported costs Adjusted advance
Activity report Detailed work plan
Reported costs Adjusted advance
Activity report
Reported costs
Detailed work plan
Adjusted advance
Detailed work plan
Initial advance
0 6 12 18 24 30 36 42 48
Months
20
11 November 2002
Evolution of the consortium without additional funding
Replacement of a participant consortium may do so if need arises
normally without a competitive call
Expansion of the consortium the consortium may itself decide to take in new
participants the contract will specify when this must involve a
competitive call organised by the consortium
competitive calls will comply with principles of: transparency, equal treatment, equal access use of independent experts
21
11 November 2002
Evolution of the consortium with additional funding
The Commission may decide to launch calls open to on-going Ips in order to:
involve particular types of participantse.g. SMEs
cover new activitiese.g. take-up measures
22
11 November 2002
Monitoring
Robust monitoring of each IP by the Commission
by one or possibly a team of project officers
throughannual review mid-term or milestone review (optional)final review
involving external experts at all stages
23
11 November 2002
Audits
Commission may also carry out audits
financial (at least one per IP)
technical
technological
ethical
24
11 November 2002
More Information on the instruments
Regularly updated website on the instruments europa.eu.int/comm/research/fp6/networks-ip.html
Brochures and leaflets on the new instrumentsAvailable at Heysel Conference and on Europa as
above
Presentation slideson Europa as above
Guide on “Participating in European Research”
On integrated projects [email protected]