1.040/1.401 project management spring 2007 supporting information for as #3
DESCRIPTION
1.040/1.401 Project Management Spring 2007 Supporting Information for AS #3. Dr. SangHyun Lee. [email protected]. Department of Civil and Environmental Engineering Massachusetts Institute of Technology. The Construction Team: Office Engineer. In Charge of reviewing and analyzing: Submittals - PowerPoint PPT PresentationTRANSCRIPT
1.040/1.4011.040/1.401
Project ManagementProject ManagementSpring 2007Spring 2007
Supporting Information for AS #3Supporting Information for AS #3
Dr. SangHyun [email protected]@mit.edu
Department of Civil and Environmental Department of Civil and Environmental EngineeringEngineering
Massachusetts Institute of Technology Massachusetts Institute of Technology
The Construction Team: The Construction Team: Office EngineerOffice Engineer
In Charge of reviewing and analyzing:In Charge of reviewing and analyzing:
SubmittalsSubmittals
RFI’sRFI’s
Start / Stop and Produce Drawing ReviewsStart / Stop and Produce Drawing Reviews
Coordination of the SubcontractorsCoordination of the Subcontractors
The Construction Team: The Construction Team: ForemanForeman
Experienced crewmember who is in charge of a group of four to eight crafts people in the Experienced crewmember who is in charge of a group of four to eight crafts people in the same crewsame crew
Representing the crew and communicating with the field superintendent on technical, Representing the crew and communicating with the field superintendent on technical, human and safety issueshuman and safety issues
If no field superintendent is employed, then her duties are split between the general If no field superintendent is employed, then her duties are split between the general superintendent and the foremen. In this case, foreman would typically report time sheets superintendent and the foremen. In this case, foreman would typically report time sheets and assure that all crewmembers follow safety precaution.and assure that all crewmembers follow safety precaution.
SubmittalsSubmittals
RFI’sRFI’s
Start / Stop and Produce Drawing ReviewsStart / Stop and Produce Drawing Reviews
Coordination of the SubcontractorsCoordination of the Subcontractors