1.040/1.401 project management - mit · 2019-09-12 · addendum no.1 to all prospective bidders...
TRANSCRIPT
Dr. SangHyun Lee
1.040/1.4011.040/1.401
Project ManagementProject ManagementSpring 2007Spring 2007
Project Organization Part 2 & 3Project Organization Part 2 & 3Payment & Award MethodPayment & Award Method
Department of Civil and Environmental EngineeringDepartment of Civil and Environmental EngineeringMassachusetts Institute of Technology Massachusetts Institute of Technology
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Fundamental IdeasFundamental Ideas
Contractors are often highly risk averseContractors are often highly risk averseFor risks that contractor For risks that contractor cancan’’t t control, may be willing to pay a control, may be willing to pay a risk premium (charge less for contract) to owner to take overrisk premium (charge less for contract) to owner to take overFor risks that contractors For risks that contractors cancan control, may be willing to control, may be willing to managemanagerisk than to pay a risk premium (charge less for contract)risk than to pay a risk premium (charge less for contract)
Fundamental IdeasFundamental Ideas
Structure contract so thatStructure contract so that
Risks contractor can better handle are imposed on contractor Risks contractor can better handle are imposed on contractor (i.e. contractor will lose $ if don(i.e. contractor will lose $ if don’’t control)t control)
To be competitive, will have to To be competitive, will have to managemanage thesethese
Risks owner can better handle are kept by ownerRisks owner can better handle are kept by owner
Fundamental BalanceFundamental Balance
Impose Impose highhigh enough risk incentive to get contractor do job efficiently enough risk incentive to get contractor do job efficiently
–– within the specifications of the contractwithin the specifications of the contract
E.g. Incentive to finish on time, incentive to stay within budgeE.g. Incentive to finish on time, incentive to stay within budgett
Impose Impose lowlow enough risk to have reasonably low bidenough risk to have reasonably low bid
Impose according to contractor ability to tolerateImpose according to contractor ability to tolerate
Derivative Results of Risks: Derivative Results of Risks: Impact on Construction TimingImpact on Construction Timing
More risk on contractor, the longer will delay construct.More risk on contractor, the longer will delay construct.Also, in terms of costAlso, in terms of cost
Given uncertainty, contractor will charge more up frontGiven uncertainty, contractor will charge more up front
Owner doesnOwner doesn’’t want to pay a huge amount up frontt want to pay a huge amount up front
Owner can expedite Owner can expedite –– by paying higher price (risk premium) to by paying higher price (risk premium) to contractor or by shouldering riskcontractor or by shouldering risk
Remember; delay can have major costs Remember; delay can have major costs –– but so can wrangling but so can wrangling over change orders!over change orders!
Addenda and Change OrdersAddenda and Change Orders
Addenda Addenda Any changes that arise before bid opening and during the Any changes that arise before bid opening and during the bidding period become part of the bid packagebidding period become part of the bid package
Change OrdersChange OrdersAny changes that arise after the contract is signed due to:Any changes that arise after the contract is signed due to:
Different Site ConditionsDifferent Site Conditions
Errors/ Omissions in the Contract DocumentsErrors/ Omissions in the Contract Documents
OwnerOwner’’s Requirements Requirement
OthersOthers
Requires adjustments in scope, time, and cost.Requires adjustments in scope, time, and cost.
Note on Change OrdersNote on Change Orders
Changes contract (cost/schedule/scope/etc.)Changes contract (cost/schedule/scope/etc.)
Can lead to costs beyond contract specificationCan lead to costs beyond contract specification
Anticipated costs incorporated in Anticipated costs incorporated in ““contingencycontingency””
Often 1Often 1--10% on top of agreed upon price10% on top of agreed upon price
Often only paid for additional direct costsOften only paid for additional direct costs
Big problem if disruption in workBig problem if disruption in work
Source of very large riskSource of very large risk
Addenda Addenda -- ExampleExample
Source: Fisk, 2003
CITY OF PALM SPRINGSENGINEERING DIVISION
ADDENDUM NO.1
To all prospective bidders under Specifications for Re-roofing the Police Department Building, City Project No. 93-52, for which bids are to be received by the City of Palm Springs at the office of the purchasing manager at 3200 East Tahquitz Canyon Way, Palm Springs, California 92262 until 4:00 pm on Tuesday 21 March 1995.
I. The existing three bid schedules in the Specifications and Drawings for this contract have been revised. Bid schedules “A”, “B”, and “C” have been changed and revised bid Schedules have been included as a part of this Addendum No.1.
II. The Specifications as originally issued, along with revised Schedules “A”, “B”, and “C” shall be used in submitting bids, and acknowledgement of receipt of this Addendum No.1 shall be entered on Page 1 of the Bid. Failure to provide such acknowledgement shall render the bid as non-responsive and subject to rejection.
BY ORDER OF THE CITY OF PALM SPRINGS
13 March 1995 By Robert J. Rocket, PECity EngineerCivil Engineer C 28209
Change Order Change Order -- ExampleExample
Source: Fisk, 2003
E.R. FISK & ASSOCIATESP.O. Box 6448 Orange CA 92613.6448 CHANGE ORDERPROJECT TITLE: Dalles Hydroelectric Project PROJECT No.: F-409 CONTRACT NAME: w34-6759 CONTRACT DATE: 29 OCT 1990 CONTRACTOR: International Constructors, Inc.
The following changes are hereby made to the contract Documents: Construction of access bridge abutment No.1 drainage system; and Reset two penstock bearing plates. All in accordance with revised DWG S-17209 Revision 3, dated 28 August 1991.
JUSTIFICATION: Unforseen soil conditions
CHANGE TO CONTRACT PRICEOriginal Contract Price: $ 13,231,053.00Current Contract Price as adjusted by previous change orders: $ 13,257,760.00The Contract Price due to this change order will be increased by $ 14,342.00The new Contract Price due to this change order will be: $ 13,272,102.00
CHANGE TO CONTRACT TIMEThe Contract time will be increased by 21 calendar daysThe date for completion of all work under the contract will be 24 June 1992.
APPROVALS REQUIREDTo be effective, this order must be approved by the Owner if it changes the scope or objective of the project., or may otherwise be required under the term of the Supplementary General Conditions of the Contract.
Requested by: Proj Mgr – E.R. Fisk & Associates (date 28 Aug 1991)Recommended by: E.R. Fisk & Associates (date 28 Aug 1991)Ordered by: Dalles Power Company (date 02 Sep 1991)Accepted by: International Constructors, Inc. (date 09 Sep 1991)
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Lump Sum or Fixed PriceLump Sum or Fixed Price
The Owner knows the actual cost of the project before it begins The Owner knows the actual cost of the project before it begins
Contractor required to achieve the project at the Bid/NegotiatedContractor required to achieve the project at the Bid/NegotiatedContract ValueContract Value
Minimize the risk for the Owner if the project is well estimatedMinimize the risk for the Owner if the project is well estimated, , contractual documents accurate, and project clearly definedcontractual documents accurate, and project clearly defined
Lump Sum or Fixed PriceLump Sum or Fixed Price
High risk for the Contractor in case of many unforeseen problemsHigh risk for the Contractor in case of many unforeseen problems
Generally utilized with the Traditional Method & usually not posGenerally utilized with the Traditional Method & usually not possible sible with Fast Trackwith Fast Track
Usually a high incentive to finish early at low costUsually a high incentive to finish early at low cost
Cost Versus Price for Lump SumCost Versus Price for Lump Sum
Source: Macomber, 1989
} }
}B
C
A
$10,300
Final Cost
A = If final cost is $9,500, contractor profit is $800 (8.42%)
B = If final cost is $10,000, (as expected), contractor profit is $300 (3%)
C = If final cost is $10,500, contractor loss is $200 (-1.9%)
Fina
l Pri
ce
$9,5
00
$10,
000
$10,
500
Lump-Sum Contract
(Price is fixed at $10,300) Figure by MIT OCW.
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Unit Price ContractUnit Price Contract
Agreement on the price charged per unit by the Contractor to theAgreement on the price charged per unit by the Contractor to theOwnerOwner
Contractor overhead must be integrated in the UnitContractor overhead must be integrated in the Unit’’s Pricess Prices
The lowest bidder is normally selectedThe lowest bidder is normally selected
Necessity of an Owner presence on site to measure the actual Necessity of an Owner presence on site to measure the actual quantitiesquantities
Unit Price ContractUnit Price Contract
Highly dependant on the accuracy of the estimation of the Highly dependant on the accuracy of the estimation of the quantities given by the Owner/Designerquantities given by the Owner/Designer
Difficult to accurately quantify the work necessary Difficult to accurately quantify the work necessary
Contractor can make a more profit because payment is based on acContractor can make a more profit because payment is based on actual tual quantities but he can also lose money in the same wayquantities but he can also lose money in the same way
The total cost for the Owner can be greater than plannedThe total cost for the Owner can be greater than planned
UnitUnit Price: ExamplePrice: Example
Activities:Activities:FootingsFootings 80 $/sq ft80 $/sq ftColumnsColumns 1,550 $/unit1,550 $/unit
Scheduled quantities:Scheduled quantities:FootingsFootings 100 sq ft100 sq ftColumnsColumns 9 units9 units
Contract initial value:Contract initial value:80 * 100 + 1,550 * 9 = 14,750 $80 * 100 + 1,550 * 9 = 14,750 $
Example: Pile DrivingExample: Pile Driving
Too risky to just charge fixed priceToo risky to just charge fixed price
Geotechnical uncertainties make length of piles uncertainGeotechnical uncertainties make length of piles uncertain
Risk allocationRisk allocation
Price risk more under contractor control (efficiency, crew and Price risk more under contractor control (efficiency, crew and equipment selection): to contractorequipment selection): to contractor
Length out of contractor control: to ownerLength out of contractor control: to owner
Owner must precisely monitor length usedOwner must precisely monitor length used
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Cost Plus Percentage FeeCost Plus Percentage Fee
The Owner is paying The Owner is paying the actual costthe actual cost plus a fixed percentage feeplus a fixed percentage fee
High risk for the OwnerHigh risk for the Owner
Maximum flexibility for the OwnerMaximum flexibility for the Owner
Used only if the pricing could not be calculated in any other waUsed only if the pricing could not be calculated in any other way y and if it is urgentand if it is urgent
No financial insurance of ultimate costNo financial insurance of ultimate cost
Cost Plus Percentage FeeCost Plus Percentage Fee
Little incentive to reduce costs Little incentive to reduce costs
The Contractor agrees to do his/her best efforts to achieve the The Contractor agrees to do his/her best efforts to achieve the goalsgoals
Whatever the quality of the work, the reward is the same but theWhatever the quality of the work, the reward is the same but theowner gets the quality he/she pays forowner gets the quality he/she pays for
Permits collaboration at the early stages of the ProjectPermits collaboration at the early stages of the Project
Cost Versus Price for Cost Plus %Cost Versus Price for Cost Plus %
Source: Macomber, 1989
$11,025
$10,500
$9,975
$9,5
00
$10,
000
$10,
500
}}
}
A
B
CFi
nal P
rice
Final Cost
A = If final cost is $9,500, contractor profit is $475 (5%)
B = If final cost is $10,000, contractor profit is $500 (5%)
C = If final cost is $10,500, contractor profit is $525 (5%)
Time-and-Materials Contract
(Price = cost plus 5%)Figure by MIT OCW.
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Cost Plus Fixed FeeCost Plus Fixed Fee
Cost may vary but the fee remains firmCost may vary but the fee remains firm
The fee is independent of the duration of the projectThe fee is independent of the duration of the project
Used only if the pricing could not be determined in an alternatiUsed only if the pricing could not be determined in an alternative ve mannermanner
No financial insurance of ultimate costNo financial insurance of ultimate cost
Cost Plus Fixed FeeCost Plus Fixed Fee
Little incentive to reduce costs but high incentive to finish eaLittle incentive to reduce costs but high incentive to finish earlyrly
The Contractor agrees to make best efforts to complete the workThe Contractor agrees to make best efforts to complete the work
Promotes collaboration at the early stages of the projectPromotes collaboration at the early stages of the project
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Guaranteed Maximum Price (GMP)Guaranteed Maximum Price (GMP)
Variation of the Cost Plus a Fee by having a cap, or GMPVariation of the Cost Plus a Fee by having a cap, or GMP
The Contractor assumes any additional costs after the The Contractor assumes any additional costs after the ““CeilingCeiling””Point is reachedPoint is reached
Similar to CPFF but quality may be sacrificed to avoid increasesSimilar to CPFF but quality may be sacrificed to avoid increases in in cost beyond GMPcost beyond GMP
Variation: Usually, GM Shared Savings Variation: Usually, GM Shared Savings -- Below the guaranteed Below the guaranteed maximum, savings are shared between Owner and Contractormaximum, savings are shared between Owner and Contractor
Cost Versus Price for GMPCost Versus Price for GMP
Source: Macomber, 1989
}}
A
B
C$10,500
$10,000
Fina
l Pri
ce
Final Cost
Guaranteed-Maximum-Price Contract
(Price = cost of work plus fixed fee of $500 with a maximum price of $10,500)
A = If final cost is $9,500, contractor profit is $500 (5.26%)
B = If final cost is $10,000, contractor profit is $500 (5%)
C = If final cost is $10,500, contractor profit is $0 (0%)
$9,5
00
$10,
000
$10,
500
Figure by MIT OCW.
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Principles of Incentive ContractsPrinciples of Incentive Contracts
TARGET COST: $20,000TARGET FEE: $1500SHARING RATIO: 80/20 %
•CUSTOMER PAYS 80 % OF OVERRUN
•CONTRACTOR PAY 20 % OF OVERRUN
•PROFIT IS $1500 LESSCONTRACTOR’S 20 %
•CUSTOMER KEEPS 80% OF UNDERRUN
•CONTRACTOR KEEPS 20% OF UNDERRUN
•PROFIT IS $1500 PLUSCONTRACTOR’S 20 %
Note: Limitations may be Imposed on Price or Profit
EXAMPLE
Additional Profits are Possible by Lowering Cost Customer and Contractor Share Cost Savings
Source: Kerzner, 2000
$20,000
Incentive Contracts: ExampleIncentive Contracts: Example
Fixed Price Incentive FeeFixed Price Incentive Fee•Sharing: 70/30 (O/C)
•Target Cost: 10,000
•Target Fee: 850
•Target Price: 10,850
•Price Ceiling: 11,500
Fixed Price Incentive Fee
-4000
-2000
0
2000
4000
6000
8000
10000
12000
14000
9000 10000 10928 11300 11500 12000 13000
Profit
Final Price
Incentive Contracts: ExampleIncentive Contracts: Example
Cost Plus Incentive FeeCost Plus Incentive Fee•Sharing: 85/15 (O/C)
•Target Cost: 10,000
•Target Fee: 750
•Maximum Fee: 1350
•Minimum Fee: 300
More financial risk for the owner in a CPIF, the target fee is usually less than in an FPIF contract and the contractor’s portion of the sharing ratio is small
Cost Plus Incentive Fee
0
2000
4000
6000
8000
10000
12000
14000
16000
4000 6000 9000 10000 13000 14000
Profit
Final Price
ContractorContractor’’s Riskss Risks
FFPCPPF Risk For Contractor
HIGHLOW
LEGEND
FFP FIRM FIXED PRICE-LUMPSUMCPPF COST PLUS PERCENTAGE FEE
Source: Kerzner, 2000
Contractual Risk AllocationContractual Risk Allocation
100 %RISK Allocation
Lump-Sum (Fixed Price)100 %
CO
NTR
AC
TOR
’S R
ISK
OW
NER
’S R
ISK
RISK SHARING METERModified from Kerzner, 2000
0 %
0 %
Fixed-Price w/ Economic Price Adjustments
Fixed-Price Incentive
Cost-Plus Incentive
Cost-Plus Fixed Fee
Cost-Sharing
Cost-Plus Percentage
ConclusionConclusion
When the market is not very good, clients insist on fixed price When the market is not very good, clients insist on fixed price bids bids whereas when the project offers are numerous, it is more difficuwhereas when the project offers are numerous, it is more difficult to lt to obtain those conditionsobtain those conditions
The Choice of payment scheme (i.e., contract type) must depend oThe Choice of payment scheme (i.e., contract type) must depend on:n:
The accuracy of the estimationThe accuracy of the estimation
The ultimate cost known since the beginning or at least the maxiThe ultimate cost known since the beginning or at least the maximummum
The desired riskThe desired risk
The priority of the goal of quick completion of workThe priority of the goal of quick completion of work
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Competitive Bidding Competitive Bidding –– Lowest PriceLowest Price
Traditional & Widely UsedTraditional & Widely Used
Time consuming process involving a bidding period as well as a bTime consuming process involving a bidding period as well as a bid evaluation & id evaluation & review period prior to issuing notice to proceed with constructireview period prior to issuing notice to proceed with constructionon
Work awarded to lowest bidderWork awarded to lowest bidder
Project constructed with specified quality at lowest priceProject constructed with specified quality at lowest price
Formal procedure for public agenciesFormal procedure for public agencies
Two main typesTwo main typesOpen Form: Bid open & read publiclyOpen Form: Bid open & read publiclyClosed Form: No public openingClosed Form: No public opening
Contractor estimates cost of building project along with profitContractor estimates cost of building project along with profitUnitUnit--PricePriceLumpLump--SumSum
Loss is absorbed by the Contractor, if actual cost exceeds contrLoss is absorbed by the Contractor, if actual cost exceeds contracted amountacted amount
Issues with BidsIssues with Bids
Low bidders can be unreliableLow bidders can be unreliablePrequalify aggressively!Prequalify aggressively!
Pressure for lowest bid can createPressure for lowest bid can createCutting cornersCutting corners
LowLow--quality personnelquality personnel
Bad feelingsBad feelings
Growing Frequency: innovative bidding methodGrowing Frequency: innovative bidding methodMultiMulti--parameter bidding (e.g., low bid + other factors)parameter bidding (e.g., low bid + other factors)
To Bid or Not to BidTo Bid or Not to Bid
Strategic Goals of the CompanyStrategic Goals of the Company
Capabilities of the CompanyCapabilities of the Company
Location of the WorkLocation of the Work
Bid LogisticsBid Logistics
LicensingLicensing
PrePre--QualificationQualification
BondingBonding
Scope of WorkScope of Work
Resource RequirementsResource Requirements
BondingBonding
Protection for Owner against ContractorProtection for Owner against Contractor’’s Defaults DefaultThe Miller Act (1935) The Miller Act (1935) –– the level of bonding required for federally funded projects. the level of bonding required for federally funded projects.
Source: Halpin and Woodhead, 1998
Owner Contractor
Surety(BondingCompany)
BondingBondingBid Bond: will the selected bidder start the project? Bid Bond: will the selected bidder start the project?
PublicPublic~20% or as low as 5% of Bid~20% or as low as 5% of Bid
PrivatePrivate5% to 10% of Bid5% to 10% of Bid
Performance Bond: will the contract work be completed and complyPerformance Bond: will the contract work be completed and comply with project with project specification?specification?
100% Complete Job at Bid Price100% Complete Job at Bid Price
Payment Bond: will a contractor pay any associated charges (e.g.Payment Bond: will a contractor pay any associated charges (e.g., subcontractor fee)? , subcontractor fee)? Cover Unpaid Bills by ContractorCover Unpaid Bills by Contractor
50% for < $1M50% for < $1M40% for $1M < X < $5M40% for $1M < X < $5M2.5M for > $5M2.5M for > $5M
Most Institutions Now Require 100%Most Institutions Now Require 100%
Bonding Capacity CalculationBonding Capacity CalculationNo Track Record: (5 or 6) No Track Record: (5 or 6) ×× Net Quick Assets Net Quick Assets Old Reliable Record: (40+) Old Reliable Record: (40+) ×× Net Quick AssetsNet Quick Assets
Net Quick Assets = Quick Assets Net Quick Assets = Quick Assets –– Current LiabilitiesCurrent LiabilitiesSource: Halpin and Woodhead, 1998
MIT Wood Inc.MIT Wood Inc.
Bonding Capacity Bonding Capacity $2,500,000$2,500,000
Potential New JobsPotential New JobsPP1: $750,000PP1: $750,000PP2: $1,000,000PP2: $1,000,000
Current Jobs as SubCurrent Jobs as SubP1: $1,000,000; 25% CompleteP1: $1,000,000; 25% CompleteP2: $1,000,000; 50% CompleteP2: $1,000,000; 50% Complete
Current Job as GCCurrent Job as GCP3: $500,000; 50% CompleteP3: $500,000; 50% Complete
BondingBondingPotential New JobsPotential New Jobs
PP1: $750,000PP1: $750,000PP2: $1,000,000PP2: $1,000,000
Current Jobs as Sub Current Jobs as Sub PerformancePerformance
P1: $1,000,000*0.75 = $750,000P1: $1,000,000*0.75 = $750,000P2: $1,000,000*0.50 = $500,000P2: $1,000,000*0.50 = $500,000
Current Job as GC Current Job as GC PerformancePerformance
P3: $500,000*0.50 = $250,000P3: $500,000*0.50 = $250,000PaymentPayment
P3: $500,000*0.50*.0.50 = $125,000P3: $500,000*0.50*.0.50 = $125,000
Used Up BondingUsed Up Bonding$1,625,000$1,625,000
Available BondingAvailable Bonding$875,000$875,000
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
NegotiationNegotiation
PrePre--selected Contractorselected Contractor
Common practice for private ownersCommon practice for private owners
Owner picks Contractor on basis of:Owner picks Contractor on basis of:ReputationReputationOverall qualifications to do the jobOverall qualifications to do the job
Typical financial contract types are:Typical financial contract types are:Cost Plus FeeCost Plus FeeGuarantee Maximum Price (GMP)Guarantee Maximum Price (GMP)
OutlineOutline
Payment SchemesPayment SchemesFundamentalsFundamentalsLump sumLump sumUnit pricesUnit pricesCost plus percentage feeCost plus percentage feeCost plus fixed feeCost plus fixed feeGuaranteed maximum priceGuaranteed maximum priceIncentiveIncentive
Award MethodsAward MethodsBiddingBiddingNegotiationNegotiationBest ValueBest Value
Best Value
Used by the Federal GovernmentProvides a uniform set of procurement regulationsRequest for Proposal (RFP) states:
Relative importance of priceTechnical meritTechnical evaluation criteria and their weights
Selection of Contractor is based on the best value of the proposed work
PriceTechnical Factors