1.0 executive summaryenvironmentclearance.nic.in/writereaddata/online/tor/22...dumper and surface...

23
Pre-Feasibility Report for Mandakini-B Coal Mining Project (Capacity-20.0 MTPA) DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 1 of 22 1.0 EXECUTIVE SUMMARY Mandakini–B Coal Block, is located in Talcher Coalfields in Angul district of Odisha State. The block with for a total area of 20.73 sq. km. has been allocated to NTPC Ltd., for captive mining for supply of coal to their Telangana Super Thermal Power Project by Ministry of Coal, Government of India vide F.No.103/33/2015NA dated 8th Aug 2016 Exploration of Mandakini–B Coal Block is divided into two parts namely Mandakini-B (South) and Mandakini-B (North). Exploration of Southern Part/Phase-I (10.57 sq. km.) is complete and the Geological Report is available with NTPC. Mining Plan of 20 MTPA peak rated capacity of Southern Part/Phase-I is submitted to MoC for approval. Exploration on Northern Part (10.16 Sq.km) is still in progress. Mandakini-B Coal Block in Talcher Coal Field having an area of 20.73 sq. km. (2073 Ha) is present in villages Changuria, Santrabandh, Sunaripal, Takua, Bainda, Balipata, Changudia, Debipatanapur, Kakudia, Kalyanpur, Sanbirabarpur and Santrabondh, district Angul in Odisha state. Mining is proposed to be carried out by open-cast method. Combination of Shovel-Dumper and Surface miner, Front End Loader cum Dumper are proposed for OB removal and Coal extraction. Drilling & Blasting is proposed for OB and Interburden. Crushing is proposed for reduction of coal from ROM to (-100) mm size coal. 60 T Coal Body dumpers proposed for coal evacuation within the mine. Coal from the CHP will be transported through a surface conveyor to the Silos/Load out point located beyond the northern boundary of the block, loading into railway wagon through rapid loading system and to be dispatched through the railways. Proposed production from the mine is 20 MTPA. The coal shall be transported from Mandakini-B to Telangana STPP which is at distance of approximate 950 km. The salient features of the project are given in Table 1. TABLE 1 SALIENT FEATURES OF THE PROJECT Project name Mandakini-B Coal Mining Project (Capacity-20 MTPA) Project proponent NTPC Ltd. Villages in block area Changuria, Santrabandh, Sunaripal, Takua, Bainda, Balipata, Changudia, Debipatanapur, Kkakudia, Kalyanpur, Sanbirabarpur and Santrabondh Coordinates Latitude: 21° 04' 16" to 21° 07' 33.5" N Longitude: 84° 56' 06" to 84° 59' 51" E Area Total 2078 ha. (ML area: 2073.00 ha. and outside of ML area: 5 ha) Pre Mining land use ownership and pattern Sl. No. Type Area in ha I. Within ML 1 Tenancy Agricultural 1246

Upload: others

Post on 07-Mar-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 1 of 22

1.0 EXECUTIVE SUMMARY

Mandakini–B Coal Block, is located in Talcher Coalfields in Angul district of Odisha State. The block with for a total area of 20.73 sq. km. has been allocated to NTPC Ltd., for captive mining for supply of coal to their Telangana Super Thermal Power Project by Ministry of Coal, Government of India vide F.No.103/33/2015NA dated 8th Aug 2016

Exploration of Mandakini–B Coal Block is divided into two parts namely

Mandakini-B (South) and Mandakini-B (North). Exploration of Southern Part/Phase-I (10.57 sq. km.) is complete and the Geological Report is available with NTPC. Mining Plan of 20 MTPA peak rated capacity of Southern Part/Phase-I is submitted to MoC for approval. Exploration on Northern Part (10.16 Sq.km) is still in progress.

Mandakini-B Coal Block in Talcher Coal Field having an area of 20.73 sq. km.

(2073 Ha) is present in villages Changuria, Santrabandh, Sunaripal, Takua, Bainda, Balipata, Changudia, Debipatanapur, Kakudia, Kalyanpur, Sanbirabarpur and Santrabondh, district Angul in Odisha state. Mining is proposed to be carried out by open-cast method. Combination of Shovel-Dumper and Surface miner, Front End Loader cum Dumper are proposed for OB removal and Coal extraction. Drilling & Blasting is proposed for OB and Interburden. Crushing is proposed for reduction of coal from ROM to (-100) mm size coal. 60 T Coal Body dumpers proposed for coal evacuation within the mine. Coal from the CHP will be transported through a surface conveyor to the Silos/Load out point located beyond the northern boundary of the block, loading into railway wagon through rapid loading system and to be dispatched through the railways. Proposed production from the mine is 20 MTPA. The coal shall be transported from Mandakini-B to Telangana STPP which is at distance of approximate 950 km.

The salient features of the project are given in Table 1.

TABLE 1 SALIENT FEATURES OF THE PROJECT

Project name Mandakini-B Coal Mining Project (Capacity-20 MTPA) Project proponent NTPC Ltd. Villages in block area

Changuria, Santrabandh, Sunaripal, Takua, Bainda, Balipata, Changudia, Debipatanapur, Kkakudia, Kalyanpur, Sanbirabarpur and Santrabondh

Coordinates Latitude: 21° 04' 16" to 21° 07' 33.5" N Longitude: 84° 56' 06" to 84° 59' 51" E

Area Total 2078 ha. (ML area: 2073.00 ha. and outside of ML area: 5 ha)

Pre Mining land use ownership and pattern

Sl. No.

Type Area in ha

I. Within ML 1 Tenancy Agricultural 1246

Page 2: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 2 of 22

Settlements 160 2 Government Water

Bodies/Tanks 39

Roads 8 3 Forest &

Open scrubs 621

Sub - Total (I) 2073 II. Outside the ML*

1 Forest 5 Sub - Total (II) 5

TOTAL (I+II) 2078 *5 Ha additional land is required outside the block for the Conveying corridor to load out point of Mandakini-B mine.

Coal reserves Sl. No.

Description Reserves (Mt)

1 Gross Geological Reserve upto Seam IE

1065.188

2 Gross Geological Reserves blocked in batter and barrier, not considered for mining

297.260

3 Gross Mineable reserves (1 - 2) 767.933 4 Net Mineable Reserves (@10%

Geological Loss) 691.140

5 Total Extractable reserves (@5% Mining Loss)

656.580

Rated capacity 20 MTPA Life of the mine 39 years including 2 years of construction Stripping ratio 2.25 (m3/t) Total OB Generation

1479.82 MCM

Method of Mining Opencast (OC) Method, by combination of Shovel-Dumper and Surface Miner

Blasting Required for overburden and coal prior to excavation Working days 3 shifts of 8 hour each for 330 days Manpower Approx. 1700 Transportation Conveyor system proposed at surface for conveying and

loading into railway wagon through rapid loading system located beyond the Northern Boundary of the Mine

Expected cost of the project

₹ 4580 Crores (approx.)[ Fully departmental]

Elevation 112.82 m to 147.04 m above Mean Sea Level (MSL) Topography Plain country with gentle undulating topography with

general slope towards north east. A small hillocks are located in the northern part of the block.

Water requirement 1.09 MGD (Potable - 0.28 MGD; Industrial – 0.81MGD) Source of water Potable: Bore-wells/Rainfall/ground water;

Page 3: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 3 of 22

Industrial: Treated mine discharged water Power requirement Mine – 18 MVA Power source 1. Power at 220 kV from Rengali Grid Sub-station of

OPTCL 2. Power at 132 kV from Chainpal Sub-station of

OPTCL 3. In addition, Kaniha Power plant is also being

considered, if technically feasible. 2.0 INTRODUCTION

2.1 Identification of project and project proponent

Project: Mandakini – B Coal Mining Project (Capacity-20.0 MTPA)

The Mandakini–B coal mining project is located in Talcher Coalfields in Angul district of Odisha state. The block has been allocated to NTPC Ltd., for captive mining for supply of coal to their Telangana Super Thermal Power Stations by Ministry of Coal, Government of India vide F.No.103/33/2015NA dated 8th Aug 2016 for a total area of 20.73 sq. km.

Mining Plan for the block prepared by CMPDIL envisages a production capacity

of 20 MTPA. Project proponent

NTPC Limited (A Govt. of India Enterprise), is the largest power generating company in India. It was set up by Government of India (GoI) in November, 1975 with the objective of planning, promoting and organizing integrated development of thermal power in the country. NTPC was conferred “Maharatna” status by GoI in 2010. NTPC is now emerging as a well-diversified company on its way of becoming an Integrated Power Major, having entered into hydro power, coal mining, power trading, equipment manufacturing, power distribution business and renewable energy generation. Presently, NTPC generates power from Coal, Gas, Hydro and Renewable (i.e. Solar and Wind) projects. With an installed capacity of 52,946 MW (as on December, 2018), NTPC is the largest power generating major in the country. Additional capacity of about 21,000 MW is under construction at various locations in India. NTPC is also allotted 10 coal blocks, out of which 2 are in operation. About 6 MTPA coal is being produced from Pakri barwadih coal mine and about 0.5 MTPA from Dulanga coal mine.

2.2 Need for the project and its importance to the country and or region

Coal is the most important and abundant fossil fuel in India. It accounts for 55% of the country's energy need. The country's industrial heritage was built upon indigenous coal.

Page 4: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 4 of 22

Commercial primary energy consumption in India has grown by about 700% in the last four decades. The current per capita commercial primary energy consumption in India is about 350 kg/year which is well below that of developed countries. Driven by the rising population, expanding economy and a quest for improved quality of life, energy usage in India is expected to rise. Considering the limited reserve potentiality of petroleum & natural gas, eco-conservation restriction on hydel project and geo-political perception of nuclear power, coal will continue to occupy centre-stage of India's energy scenario. Indian coal offers a unique eco-friendly fuel source to domestic energy market for the next century and beyond.

Through sustained programme of investment and greater thrust on application of

modern technologies, it has been possible to raise the production of coal from a level of about 70 million tonnes at the time of nationalization of coal mines in early 1970's to 676.48 (Provisional) million tonnes (All India) in 2017-18 (Source: http://coal.nic.in/content/coal-indian-energy-choice assessed on 29.05.2018).

The importance of coal as a fuel for power generation cannot be overestimated.

The economic development of any country largely depends upon its industrial progress and the industrial development of a country largely depends upon its possessing a sufficiently large stock of this most valuable mineral product. Coal is regarded as the backbone of power generation in India. There is huge demand for power in India. Power is essential and most important factor for industrial and business set up. India’s coal position is quite encouraging and it offers good prospects for the development of this industry. During 2011, India was the third largest coal producing country in the world. Hence, coal is an important constituent of the present Indian economy. The total reserves of coal in India have been over 290 billion metric tons. The coalfields in India are located mostly in Odisha, Madhya Pradesh, Chhattisgarh, Uttar Pradesh, Meghalaya, Telangana, West Bengal, Sikkim, Arunachal Pradesh and Bihar. The power sector is the largest consumer of coal followed by the iron & steel and cement segments. India is the world’s fifth largest energy consumer, accounting for 4.1% of the global energy consumption. Of the total electricity consumed in the country, approximately 80% is produced from coal (Source: https://www.importantindia.com/21958/importance-of-coal-in-indian-economy assessed on 29.05.2018).

2.3 Demand-supply gap

The overall long-term demand of coal is closely linked to the performance of the end-use sectors. In India, the end-use sectors of coal mainly include electricity, iron and steel and cement. Demand from the unorganized small scale sector comprising primarily of the brick and ceramic industry is relatively large though infirm as users switch between coal, firewood and biomass depending on their relative prices. Other industries using coal have only a marginal impact on the long-term demand for coal.

As per the Report of the Working Group for coal & lignite in the terminal year of

XII Plan (2016-17), the total demand of coal in different projections was at 980.50

Page 5: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 5 of 22

million tonnes. Of these, the demand for non-coking is assessed at 913.30 million tonnes and coking coal at 67.20 million tonnes. As against these demands the production of non-coking coal is projected at 683.30 million tonnes and coking coal at 31.70 million tonnes in the terminal year of XIIth Plan. The total supply projection of coal through various sources i.e. CIL in 556.40 million tonnes (coking coal are in 15.74 million tonnes and non-coking in 540.66 million tonnes); SCCL in 57 million tonnes under non-coking coal and others are in 101.60 million tonnes (15.96 million tonnes are in coking coal and 85.64 million tonnes in non-coking coal). This leaves a gap of 265.50 million tonnes between demand and indigenous availability comprising of 35.50 million tonnes of coking coal and 230.00 million tonnes of non-coking coal is to be met through imports. (Source: Indian Minerals Year Book 2017, IBM, March 2018).

Some of this shortfall will be met by supplies from captive coal blocks and rest

through imports. Also, the choice between the supplies from domestic and imported coal is mainly driven by timely availability of coal from domestic sources, quality requirements and the economics of landed cost of coal at the end-use plant. Captive coal mining in India was, gradually, being permitted by amending the Coal Mines Nationalization Act, primarily in iron and steel making, power generation and cement production. Hence, it became important for India to secure coal through imports from international market to meet their significantly rising coal demand. However, import is mainly dependent on availability of coal in global market, increasing competitive scenario and affordability

The Mandakini–B Coal Block has been planned for a targeted capacity of 20 MTPA. The production will be used in Telangana Super Thermal Power Project of NTPC. Beside this, coal, if required will be supplied to other power plants of NTPC as per applicable rules.

2.4 Imports vs. indigenous production

The proposed mine lies within India, hence import not applicable. 2.5 Export possibility

There will not be any export of coal from the coal mine. Coal shall be used in Telangana Super Thermal Power Project of NTPC Ltd. Coal from the block shall be transported to railway siding located beyond the Northern Boundary of the Mine through 60 T dumpers and Conveyor System from the surface of the mine. The coal has to be transported from Mandakini-B to Telengana STPP which is at distance of approximate 950 km.

2.6 Domestic/ export markets

Entire coal produced from the mine shall be used in Telangana Super Thermal Power Project of NTPC Ltd. Beside this, balance coal, if required will be supplied to other power plants of NTPC as per applicable rules.

2.7 Employment generation (direct and indirect)

Total manpower required for the mine will approximately be 1700 persons and the project is likely to generate indirect employment opportunities. The

Page 6: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 6 of 22

employment opportunities will include almost all categories, viz. management, supervisory, highly skilled, skilled, semi-skilled, and unskilled workmen etc.

3.0 PROJECT DESCRIPTION

Mandakini-B coal block is located in Talcher Coalfield in district Angul of Odisha State. Mining is proposed to be carried out in single pit by Open-cast method whose mining plan is submitted to MOC. Blasting has been envisaged in mining operations. Shovel Dumper are proposed for removal of overburden and Surface Miner for extraction of coal, loading and in-pit transportation by combination of FEL and Dumpers. Proposed production from the mine is 20 MTPA. There are 25 seams including their splits (Barakkar – IX, VIII, VII, VI, IV/V, III & II = 16; Karharbari – IA to IE = 9) in the planned pit areas of the quarriable block. Considering that there are 25 seams and equal nos. of inter burden layers to be tackled, shovel dumper combination with surface miner has been recommended. To tackle about 1479.82 million m3 of OB (most of the years) and over 20 MTY of coal from several locations in the mine, comparatively medium and higher size shovels of 10 - 12 m3 bucket capacity have been envisaged along with matching capacity of rear dumpers. Transport of coal shall be done by 60T/100T rear dumpers from mine pit to crusher house.

3.1 Type of Project including interlinked and interdependent projects

The coal from the mine will be used for Telangana Super Thermal Power Project of NTPC Ltd. Beside this, balance coal, if required will be supplied to other power plants of NTPC as per applicable rules. Environmental Clearance was accorded to Telangana STPP (2x800 MW) vide letter dated J-13012/112/2010.IA.II(T) dated 20.01.2016. The coal requirement of Telangana STPP (2x800 MW) would be 8 MTPA.

3.2 Location with coordinates

The mine area of Mandakini–B Coal block is present in villages Changuria, Santrabandh, Sunaripal, Takua, Bainda, Balipata, Changudia, Debipatanapur, Kakudia, Kalyanpur, Sanbirabarpur and Santrabondh, district Angul in Odisha state. Please refer Annexure I for the location map of the project. The block forms a part of Survey of India Topo sheet No. F45 M16 (Old. T.S. No. 73C/16) on R.F. 1:50,000 bounded by following co-ordinates Latitude : 21°04'16" to 21°07'33.5" N Longitude : 84°56'06" to 84°59'51" E

3.3 Details of alternate sites & Environmental considerations

Mandakini-B coal block is site specific coal block allotted by Ministry of Coal therefore, no alternatives sites have been considered. Environmental considerations and protection measures assume greater importance for the project. Company shall ensure that the proposed mine causes minimum adverse impact on the area.

Page 7: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 7 of 22

The proposed project is planned to meet all environmental norms and further improve the environment in the area. Regular environmental monitoring shall be carried out by the company at the mine site in line with the requirements of the Odisha State Pollution Control Board and Ministry of Environment, Forests and Climate Change.

Environmental considerations There are no National Parks, Wildlife Sanctuary, and Biospheres Reserves within

25 km of radius from the project boundary. However, there are several water bodies and forest present within the study area of the project. The brief details of various water bodies, forest, etc. are given in Table 2.

TABLE 2 DETAILS (WITHIN 15 KM RADIUS) OF WATER BODIES, FORESTS &

MOUNTAINS FROM PROJECT BOUNDARY

S. No.

Description Direction

I RIVERS/WATER BODIES/FORESTS 1. River Brahmani E 2. Gauduni Nala NW 3. Gadari nalla E 4. Bankhuli Nalla E 5. Tikra Nadi N 6. Pond, Santrabandh NE 7. Pond, Santrabandh N 8. Pond, Santrabandh NW 9. Pond, Santrabondh S 10. Pond, Changuria SW 11. Pond, Changuria SE 12. Pond, Kakudia SW

II FOREST 1. Kosala RF ESE 2. Similisahi RF S 3. Derenga PF NE 4. Kankurupal R.F. W 5. Sunarihyaran P.F 6. Nialu R.F. N 7. Tamakia R.F. N 8. Chhendipada R.F. SW 9. Brahmanabil R.F. S 10. Baihanali R.F. S

Page 8: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 8 of 22

S. No.

Description Direction

11. Banasinga R. F. SE 3.4 Size or magnitude of operation

The ML area of Mandakini–B Block is 2078 Ha. The peak rated capacity of mine shall be 20 MTPA.

3.5 Project description with process details

Open-cast mining method is selected in view of workable thickness of coal seams and favourable overburden to coal ratio (2.25 m3/t). Average Seam gradient is from 4-7 degrees. Shovel & Dumper combination and Surface miner is recommended in view of multiple seams and equal nos. of inter burden layers to be tackled, an equipment system which is capable of dealing many layers at a time (flexibility) of operations with the help of smaller units has been recommended as shovel dumper combination. For tackling 20 MTPA and 34 - 50 Mm3 OB from several locations in the mine, comparatively medium and higher size shovels of up to 10 to 12 m3 bucket capacity have been envisaged along with 100 T matching capacity of rear dumpers for OB and 100 – 110 T surface miner along with 5-7 cum Front End Loaders in combination with 60 T Dumpers (Coal Body) for coal have been envisaged. Single pit has been planned for mining. The block has an East-West strike and dipping on the Northern side. It is proposed to open the mine from the Southern side and access the Seam I E which would form the pit floor. The minimum depth of Seam I E is around 90 m. As the working front advances Northwards, upper seams would be encountered. During later years the mine shall be advance towards South in the dip side. Coal production shall start in P–1 i.e., 1st production year (initial 2 years has been considered for construction phase mentioned as C1 and C2). From P – 8 (i.e., 8th production year of mining operations) the mine will achieve the peak rated capacity of 20 MTPA. The mining operations proceed towards North and in-pit dumping of overburden starts P – 6 year. To cater the production of 20 MTPA mine-end conveyor system is proposed. Refer the surface plan, geological plan and geological section is given in Annexure II, Annexure III and Annexure IV respectively The total life of mine is 39 years (2 years of construction + 37 years of production) and given in Table 3.

Page 9: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 9 of 22

TABLE 3 CALENDAR PROGRAM (COAL & OB) OF MANDAKINI-B

Production

Years Coal Production

(Mt) OB Removal

(Mm3) Strip Ratio

(m3/t) C 1 C 2 P 1 2.00 8.04 4.02 P 2 4.00 11.52 2.88 P 3 6.00 22.15 3.69 P 4 8.00 27.77 3.47 P 5 10.00 33.71 3.37 P 6 13.00 35.12 2.70 P 7 16.00 35.34 2.21 P 8 20.00 43.28 2.16 P 9 20.00 34.31 1.72 P 10 20.00 34.19 1.71 P 11 20.00 30.33 1.52 P 12 20.00 34.35 1.72 P 13 20.00 39.57 1.98 P 14 20.00 39.57 1.98 P 15 20.00 37.10 1.86 P 16 20.00 36.57 1.83 P 17 20.00 36.57 1.83 P 18 20.00 36.57 1.83 P 19 20.00 36.57 1.83 P 20 20.00 36.57 1.83 P 21 20.00 40.39 2.02 P 22 20.00 43.35 2.17 P 23 20.00 43.35 2.17 P 24 20.00 43.35 2.17 P 25 20.00 43.35 2.17 P 26 20.00 43.35 2.17 P 27 20.00 47.89 2.39 P 28 20.00 49.13 2.46 P 29 20.00 49.13 2.46 P 30 20.00 49.13 2.46 P 31 20.00 49.56 2.48 P 32 20.00 50.34 2.52 P 33 20.00 50.34 2.52 P 34 20.00 50.34 2.52 P 35 20.00 51.96 2.60 P 36 20.00 66.88 3.34 P 37 17.58 58.77 3.34 Total 656.58 1479.82 2.25

Page 10: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 10 of 22

3.6 Mining method

Open-cast mining method has been selected for the proposed mine. Drilling –blasting shall be done to excavate coal and overburden. Shovel Dumper Mining Technology shall be used for overburden and Surface Miner along with Front End Loader Dumper for coal. Details of mining method and sequence is already discussed in section 3.5 above.

3.7 Raw material required along with estimated quantity, likely source,

marketing area of final product’s, Mode of transport of raw material and Finished product

Diesel is required for transportation vehicles, operation of HEMM and generators in case of emergency. The ROM coal from active faces/different benches will be transported by 60 T dumpers to the CHP and from there sized coal shall be transported to MGR system envisaged beyond Northern boundary of the Block.

Average grade of Coal Mined out would be G 11 (Avg. GCV of about 4175

Kcal/kg). Application of Surface Miner in Coal will reducing drilling & blasting substantially thus reducing the impact of pollution.

3.8 Resource optimization/ recycling and reuse envisaged in the project

ROM coal directly received from the mine through surface miner is expected to have -100 mm size.

The resources which are used in the mining will be recycled by various methods. Spent oil from transformers, once in one or two years shall be sold to the authorized vendors. The used oil from vehicles will also be recycled through authorized vendors. The sump shall be made at low points on the floor of the quarry. The working benches/internal dump shall be graded suitably so that the entire water will flow down to the sump. For all industrial usage of water, the treated mine water pumped out from the sumps will be used.

3.9 Availability of water its source, energy / power requirement and source 3.9.1 Water Requirement: Total requirement of water is estimated as 1.09 MGD for the

block (Potable - 0.28 MGD; Industrial - 0.81 MGD). Source: Borewells/Ground water/Rainfall has been assumed to be the source of

potable water requirements. For all industrial usage of water, the treated mine water pumped out from the sumps will be used after treatment of suspended solids.

3.9.2 Power

Power requirement for the mine is estimated as 38 MVA which shall be sourced from 220 kV from Rengali Grid Sub-station of OPTCL and 132 kV from Chainpal Sub-station of OPTCL. In addition, possibility of Kaniha Power plant is is being

Page 11: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 11 of 22

studied, if technically feasible. Three substation is envisaged to receive power at 33kV from 2 x 20 MVA, 132/33 kV substation.

3.10 Quantity of wastes to be generated (liquid and solid) and scheme for their

management / disposal

No space outside the block is available /envisaged for dumping of overburden. Entire overburden generated during the life of the mine shall be dumped inside the block boundary. OB generated shall be dumped at a location in the Northern part within the block boundary. External dumps within the mining lease shall accommodate the 438.15 Mm3, out of 1479.83 Mm3 generated during the life of the mine. Remaining 1041.68 Mm3 of OB shall be accommodated in in-pit dumping during different stages of mine.

During the life of mine, 56.23 Mm3 of top soil shall be generated. For the initial 10 years of Mining operation, top soil shall be stacked at a designated location in South Pit. Estimated land requirement for stacking is 26 ha. The requirement of land shall cease to operate from 10th year onwards as because scrapped top soil shall be spread over the dump for land reclamation. Stacking of top soil shall be achieved in two tiers. The bottom tier shall be of 3m in height while top tier shall be of 2 m or shall below height not exceeding the limit as per prescribed norms.

Solid waste generated from manpower shall be mostly of organic and recyclable in nature. The organic waste will be composted and used as manure while domestic effluents will be treated in septic tanks and soak pits. Effluent treatment plant is envisaged for treatment of water discharge from workshop as well as domestic waste. In order to ensure the discharge of clean water into the natural drainage, main/intermediate sump capacity shall be made at suitable locations to arrest the suspended solids. In order to monitor and subsequent management of water quality, monitoring stations shall be located near settling pit. Drains are provided around the dump/coal stock yard to collect run-off water and diverting it into settling ponds before discharging it into natural water courses. Effluents from the workshop shall in the effluent treatment plant with Zero Liquid Discharge (ZLD).

3.11 Schematic representations of the feasibility drawing which give

information of EIA purpose

The present surface plan is given in Annexure II and the geological plan and section is given in Annexure III & IV.

4.0 SITE ANALYSIS

The area of Mandakini-B Coal block is present in villages Changuria, Santrabandh, Sunaripal, Takua, Bainda, Balipata, Changudia, Debipatanapur, Kakudia, Kalyanpur, Sanbirabarpur and Santrabondh, district Angul in Odisha state.

Page 12: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 12 of 22

The block forms a part of Survey of India Toposheet No. F45 M16 (Old. T.S. No. 73C/16) on R.F. 1:50,000 and bounded by following co-ordinates

Latitude : 21°04'16" to 21°07'33.5" N Longitude : 84°56'06" to 84°59'51" E The block exhibits plain country with gentle undulations at places with general

slope towards North East. In general, the elevation of ground varies from 111.82m near borehole CTNM -27 to 147.04m near borehole CTBK – 54 above Mean Sea Level (MSL).

4.1 Connectivity

The block falls in the Angul district of Odisha state. The block is well connected to nearest town city and state capital through all-weather road.

Road: The Block is well connected to the district headquarter Angul via Kosala at a distance of 40 km by all-weather road. The block is located at a distance of 14 km from Kaniha Super Thermal Power Station of NTPC. The blocks come under Chhendipada Tehsil and police station which is located at a distance of about 8 km. Railway Station: The nearest rail stations is Talcher on Talcher – Cuttack line of East- Coast railway and is about 32 km from the block. Airport: The nearest Airport is at Bhubaneswar, State Capital of Odisha which is about 170 km (by road). Port: The nearest port is at Paradip at Bay of Bengal is situated at a distance of 220 km from the block.

4.2 Land form, land use and land ownership

The ML area of Mandakini–B Block is 2078 Ha. Out of this, 30.11% is designated as forest land, Tenancy land is 67.63%, Government/non-forest land is 2.26%. The land use map is given as Annexure V. Present and post mining land use is given in Table 4 and 5, respectively.

TABLE 4

PRESENT LAND USE (Ha) Sl. No.

Type Area in ha

I. Within ML 1 Tenancy Agricultural 1246

Settlements 160 2 Government Water Bodies/Tanks 39

Roads 8 3 Forest & Open

scrubs 621

Page 13: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 13 of 22

Sub - Total (I) 2073 II. Outside the ML*

1 Forest 5 Sub - Total (II) 5

TOTAL (I+II) 2078 *5 Ha additional land is required outside the block for the Conveying corridor to load out point of Mandakini-B mine.

TABLE 5

POST MINING LAND USE

Sl.No

Type Area in ha

1 Mine Excavation Void 323 2 Backfilled : Stabilized slopes and approach roads 423 3 Backfilled: Plantations 276 4 Plantation on External Dump 480 5 Stabilized slopes and approach roads on external

dumps 244

6 Plantation on dismantled conveyor corridor 25 7 Undisturbed ground /Safety zone / Embankments /

Surface approach roads /green belt 307

Total 2078 4.3 Topography

The area is represented by a plain country with very gentle undulations at places. The general slope in the block is northeast. In majority of the block, the topography is gradual and smooth. In general, the elevation of ground varies from 111.82m near borehole CTNM -27 to 147.04m near borehole CTBK – 54 above mean sea level.

4.4 Infrastructure Facility

Complete site facilities are important for smooth working of any mine. Core infrastructure like Service and residential buildings, workshops, stores, statutory facilities, magazine, sub-stations, office complex, different community buildings etc., shall be provided.

4.5 Climatic data from secondary sources

Temperature:

The area experiences a tropical climate with very hot and dry in summer during May – June and winter is very pleasant during December – January. Monsoon break towards the end of June and continues upto end of October. Annual mean rainfall of the district is 1421 mm and maximum temperature is 49°C in summer

Page 14: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 14 of 22

and minimum temperature is 6.7°C in winter season. It has three distinguishable seasons: a The summer season starts from May to June. The temperatures rises upto

49°C accompanied by high humidity.

b The rainy season starts from the mid of June and continues till November with an average annual mean rainfall of 1412 mm with the average number of rainy days being 70.

c Winter season prevails during the period of December – February. The temperature varies from 6.7°C to 38.1°C.

Relative Humidity:

Since the climate is tropical, the relative humidity varies from 31% in March to 88% in July. Rainfall:

Mandakini-B Coal block being a virgin block, has no Meterological station. The nearest station is at Angul Meteorological Station of IMD where daily rainfall is recorded. The rainfall per day varies from 0 to 121.6 mm (with a mean of 3.2 mm for the year 2016). The average annual rainfall is about 1421 mm. The monsoon season breaks towards the end of June and continues till end of October.

4.7 Social infrastructure available

Hospitals, school, banks etc. are present in the villages in buffer zone (within 15 km radius of project area). Social infrastructures are existing as per Census 2011.

5.0 PLANNING BRIEF 5.1 Planning concept

The Mandakini–B Coal Mine Block has been allocated to NTPC Ltd., for captive mining for supply of coal to their Telengana Super Thermal Power Project by Ministry of Coal, Government of India. The current Mining Plan envisages a production capacity of 20 MTPA from Block.

Mandakini–B mine shall produce peak capacity of 20 MTPA. It is planned to

dispatch coal from mine surface to MGR system located beyond the Northern Boundary of the block through 60 T dumpers and Conveyor System. From there coal shall transported to end use power plant of NTPC Ltd. By Indian Railway.

5.2 Population projection

Manpower required for 20 MTPA production based on 330 working days shall be approximately 1700. In Addition to 1700, the manpower requirement of Security, Watch & Ward, Canteen, Rest House/Guest House, maintenance persons for colony & office, Coal Laboratory, Water Supply & Sanitation, light Vehicles and other misc activities will be met through outsourcing estimated as 85.

Page 15: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 15 of 22

5.3 Land use planning (break up along with green belt etc.)

The present land use of the project area is referred in Table 4. Proposed land use at the end of life of mine is given in Table 5 in Section 4.2 earlier.

5.4 Assessment of infrastructure demand (physical & social)

An assessment of the current social infrastructure available in the villages of study area (10 km radius) to the mine lease area in education, health, post and telegraph, banks and communication has been done using Census 2011 data. Core infrastructure, like power distribution system, road, telecommunication, housing, service buildings viz. office, store, First Aid centre, canteen etc. will be established at the mine site.

5.5 Amenities / facilities

An assessment of the current amenities available in the villages in and adjacent to the mine lease area in education, health, drinking water, power supply, post and telegraph, banks, communication and approach road has been done using The site service facilities such as mine office, stores, workshop, canteen, first-aid centre, rest shelter and pithead bath will be provided at the mine site.

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial area (processing area)

The activity wise detail of present land use is given in Table 4 and at the end of life of mine is given in Table 5 of Section 4.2 earlier.

6.2 Residential area (non-processing area)

The residential buildings and allied facilities of Mandakini–B Coal Block shall be constructed within the NTPC Kaniha Power Plant located at a distance of about of 15 Km from the mine block.

6.3 Green belt

In order to combat pollution effects arising out of the mining operations and to improve the ecological and aesthetic status of the area, a comprehensive three tier green belt development programme will be implemented. Keeping in view the environmental problems, plantation programme shall be prepared to mitigate the problems. The areas considered for plantations shall be as follows:

All along the roads and around office, stores, workshop etc. In all vacant/barren places near the quarry area Waste dump in stages Over the backfilled area Peripheral portion of mining lease Industrial sites, service building areas

Page 16: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 16 of 22

6.4 Social infrastructure

With the mine operation, amenities for communication, education, health, canteen, etc. shall be developed by Company and maintained in and around the project area. These amenities will be available to local people also, who are directly associated with the project. Even those not associated in the project related activities shall be benefited by these amenities. With the continuation of the mine, there will be substantial improvement in the overall economy of the local people in the form of additional income through employment, development of infrastructure in surrounding areas such as transport facility, health and education, shops and ancillary industries. Over and above, the people can avail the medical/ educational facilities that will be established by the company in the area. Water can also be supplied free of cost on need based and in consultation with district administration. Overall, the villagers will be encouraged to be self-sufficient. The objective of CSR is to: Significantly improve the physical quality of life Create opportunities for livelihood Improve the level of education including adult education Create health awareness among women and Ensure availability of safe drinking water

6.5 Connectivity

i. Road: Refer section 4.1. ii. Railway Line/Airport/Port: Refer section 4.1.

6.6 Drinking water management (source & supply of water)

Refer section 3.9.1 6.7 Sewerage system & industrial waste management

The resources which are used in the mining will be recycled by various methods. Effluent from workshop will be treated in the effluent treatment plant with Zero Liquid Discharge (ZLD). Sufficient standby capacity will be provided in the main/intermediate sumps, so that the suspended solids generated due to mine workings settle down and comparatively cleaner water is discharged to the natural water course. The sump shall be made at low points on the floor of the quarry. The working benches/internal dump shall be graded suitably so that the entire water will flow down to the sump. For all industrial usage of water, the treated mine water pumped out from the sumps will be used. Drains will be provided around quarry/dump/coal stock yard to collect run-off water and diverting it into settling ponds before discharging it into natural water courses. Domestic effluents will be treated in septic tanks and soak pits.

6.8 Solid waste management

Refer section 3.10. 6.9 Power requirement & supply / source

Refer section 3.9.2.

Page 17: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 17 of 22

7.0 REHABILITATION AND RESETTLEMENT PLAN

Socio Economic Survey of the area including number of PAPs/PAFs, their categories and their livelihood etc., is being carried out by “Nabakrushna Chaudhary Centre for Development Studies”. As per 2011 Census, tentative number of houses is around 1800 and the population likely to be affected is about 7500 in Mandakini-B coal block. Detailed assessment will be undertaken once the socio-economic survey studies are complete. The rehabilitation package provided for the displaced persons would be in conformity with the Govt. of India norms and as per the guidelines of the Govt. of Central and State Governments.

8.0 PROJECT SCHEDULE & COST ESTIMATES 8.1 Project Schedule

A number of statutory clearances are required to start coal mining activities. In addition, pre-construction and construction activities related to Land acquisition, R & R, Diversion of roads/HT lines, permanent power, coal evacuation corridor etc., needs to be carried out in a time bound manner.

The first year of coal production would be 2021–22. Beside this, balance coal, if required will be supplied to other power plants of NTPC as per applicable rules. Project implementation activities are presented in Annexure VI.

8.2 Cost Estimates

The Mining plan of Mandakini-B is under approval from Ministry of Coal. The contract for preparation of feasibility report has been awarded to CMPDIL, Ranchi. The tentative project cost estimate will be about approx. ₹ 4580 Cr. The actual project cost estimate & specific investment shall be available after preparation of feasibility report.

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

Mandakini-B is an open-cast mine with a peak rated capacity 20 MTPA. The total life of mine is 39 years including 2 years of construction period. The environmental impacts can be kept at minimum by adopting proper mitigation measures.

Page 18: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 18 of 22

Annexure-I

Page 19: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 19 of 22

Annexure-II

Page 20: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 20 of 22

Annexure-III

Page 21: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 21 of 22

Annexure-IV

Page 22: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 22 of 22

Annexure-V

Page 23: 1.0 EXECUTIVE SUMMARYenvironmentclearance.nic.in/writereaddata/Online/TOR/22...Dumper and Surface Miner Blasting Required for overburden and coal prior to excavation Working days 3

Pre-Feasibility Report for Mandakini-B Coal Mining Project

(Capacity-20.0 MTPA)

DOC. NO.: 7021/999/GOG/M/001 REV. NO.: 0 REV. DATE: 22.02.2019 Page 23 of 22

Annexure-VI