1 proposition 98 eminent domain impacts to project delivery april 10, 2008 presented by caltrans -...
TRANSCRIPT
1
Proposition 98
Eminent Domain Impacts to Project Delivery
April 10, 2008
Presented by CALTRANS - Bimla Rhinehart
Tab 37
2
Current Procedures/Facts• Caltrans acquires property exclusively for public
transportation purposes.
• Caltrans has to prove to the CTC the property sought is necessary for a transportation purpose.
• Property owners are responsible for their attorney’s fees
and litigation expenses unless the court finds after trial:– Owner’s demand was reasonable.
– Caltrans final offer was unreasonable.
• Caltrans’ annual right-of-way acquisition costs are estimated to average $150-$200 million per year
3
Proposition 98 Impacts on Caltrans Projects
• Cost of transportation projects will increase significantly.
• Adds significant time to the acquisition of property.
• Adds costs for the property acquired for public use.
4
Proposition 98 Impacts on Caltrans Projects (Cont’d.)
1 ) Withdrawing the deposit does not waive the right to challenge the acquisition.– The Commission’s Resolution of Necessity
(RON) is more easily challenged
– The acquisition of the property right will be delayed indefinitely pending:– Separate legal hearings.
– Litigation on the right to take.
5
Proposition 98 Impacts on Caltrans Projects (Cont’d.)
2 ) Caltrans will be required to pay for all of the property owner’s attorney’s fees and litigation expenses:
– Whenever a judgment is rendered for more than the amount Caltrans has offered.
6
Proposition 98 Impacts on Caltrans Projects (Cont’d.)
3 ) If Caltrans sells an excess parcel:– A good faith effort must be made to locate the property owner
from whom the property was acquired.
– A written offer must be made to sell the property at the price that Caltrans paid for the property (gift of public funds?).
– This provision does not specify what constitutes a good faith effort, nor set a time limit on the right of first refusal.
– Similar to SB 1650 enacted 1/1/07.
7
Proposition 98 Impacts on Caltrans Projects (Cont’d.)
4 ) Expands the definition of what constitutes “just compensation.” Includes temporary business losses, relocation
expenses, business reestablishment costs, and “other actual and reasonable expenses incurred.”
– Caltrans’ ability to obtain property for possible public-private partnership projects would be impaired.
8
Fiscal Impact
Estimated annual project delay (4-6 months) costs:
approximately $18 million.
Additional eminent domain litigation expenses due to: Increased number of lawsuits and trials.
Expanded entitlement to attorney fees and litigation expenses: approximately $41 million annually.
9
Proposition 98 Impact Summary
Lengthens the project delivery process by extending the property acquisition process and increases project costs.– Separate hearings and/or litigation to decide if the property is
needed for the project.
– “Just compensation” becomes more subjective
Increase in eminent domain actions because: Caltrans would pay property owners' attorney fees and
litigation expenses if the owner recovers $1 more than Caltrans final offer.
10
Questions?