Market Operator User Group Meeting1
Market Operator UserGroup Meeting
22nd of May 2012SONI Offices, Belfast
Conference Call:- LoCall: 0818 301 111 Local Access: +353 1 664
8888 Pin: 481 953
2
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
2Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
House Keeping
Please note the location of the fire exits.
If you are on the conference call we would ask that you keep your phone on Mute unless you are asking a question
3
Market Operator User Group Meeting 3
4
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
4Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
5
Market Operator User Group Meeting5
Key Performance Indicators
Nov-1
1
Dec-1
1
Jan-
12
Feb-1
2
Mar
-12
Apr-1
290%
95%
100%
Ex-Ante Delivery TargetActual
Nov-1
1
Dec-1
1
Jan-
12
Feb-1
2
Mar
-12
Apr-1
290%
95%
100%
Ex-Post Initial Delivery TargetActual
Nov-1
1
Dec-1
1
Jan-
12
Feb-1
2
Mar
-12
Apr-1
285%
90%
95%
100%
Invoicing Delivery TargetActual
Nov-1
1
Dec-1
1
Jan-
12
Feb-1
2
Mar
-12
Apr-1
290%
95%
100%
Credit Cover Increase Notice Delivery
TargetActual
6
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
90%
95%
100%
Customer Service Queries Target
Actual
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
0
5
10
15
SEMO Resettlement Queries Target
Actual
Market Operator User Group Meeting6
Key Performance Indicators
Publish MIP/LR
Operational Date Trade Date Run Type LR Peak SMP MIP Peak SMP Published
08/03/2012 09/03/2012 Ex-Ante (EA) €567.85 €216.75 MIP
15/03/2012 14/03/2012 Ex-Post Indicative (EP1)
€542.17 €247.86 MIP
23/03/2012 24/03/2012 Ex-Ante (EA) €521.09 €563.06 MIP
27/04/2012 28/04/2012 Ex-Ante (EA) €979.92 €68.14 MIP
28/04/2012 29/04/2012 Ex-Ante (EA) €981.20 €76.88 LR
28/04/2012 24/04/2012 Ex-Post Initial (EP2) €675.58 €208.81 LR
Market Operator User Group Meeting7
Pricing Issues
Run Type
Issue Resolution
All Late Publication Reports published late to the website and / or
MPI.
Late Transfer MIUN’s transferred late.
The Ex-Ante market schedule was published after market deadline at 16:46 28/04/2012 instead of 13:00 28/04/2012 for Trade Date 29/04/2012Due to an operational error.
The Ex-Post Indicative market schedules have all been published on time.
The Ex-Post Initial market schedules have all been published on time.
The Modified Interconnector Unit Nominations for the Ex-Ante were transferred at 14:09 instead of 12:00 for Trade Date• 29/04/2012 Due to a process issue.
The Modified Interconnector Unit Nominations for the Ex-Ante were transferred at 15:00 instead of 12:00 for Trade Date• 03/05/2012 Due to a system defect.
8Market Operator User Group Meeting
Settlement Issues
9
Run Type Issue Cause and Resolution
Indicative Energy & VMOC Late Publishing
System Issue
21st March(> 1 hr late)
29th March (> 1 hr late)
Bank Holiday
16th March(>1 hr late)
17th March (> 1 hr late)
18th March (> 1 hr late)
File Submission
17th April(> 1 hr late)
The delays were a result of performance issues affecting Market Systems. A short term solution is in place to improve performance. However, SEMO is working on a permanent fix with the vendor.
This was an operational oversight due to the Bank Holiday Monday. Statements and PIRs were published at the earliest opportunity the next working day.
Meter Data files were not submitted by MRSO on time. Indicative Settlement was delayed by one working day as a result
Initial Energy & VMOC Missing Combined Loss Factors
Data Submission
2nd – 10th March 2012
CLAFs for three Units were not submitted by EirGrid TSO which affected Energy Payments. Ad hoc resettlement was necessary to rectify Week 10 2012. This was resettled and invoiced 11/05/2012.
Market Operator User Group Meeting 9
Settlement Issues
10
Run Type Issue Cause and Resolution
Invoicing - Week 13 ‘11 M+13 Currency Costs
Operational Error
23rd March – 4th April 2011
Currency values were not correctly applied to Week 13 2011 RS Energy invoices due to an operational error. M+4 values instead were applied in error. Further update to be given in relation to a resolution.
Initial Capacity - April 2012 P Type Statements Published
Operational Error
7th April 2012
Meter values for the 7th of April 2012 was mistakenly imported as Indicative (P) prior to the processing of Initial Capacity due to an operational error. As a consequence, P type files were published and a volume of data was missing from Capacity PIRs. F type Statements and PIRs were produced after invoices were published. Invoicing was not affected as a result of this issue.
Market Operator User Group Meeting10
11
Recent Registrations / De-Registrations
Party
There have been three new Party Registrations in the SEM since the last MOUG
Church Hill Energy Limited
Crighshane Energy Limited and
Gaelectric Energy Storage Ltd.
Units
Generation – Registrations There have been four new Generator Unit Registrations in the SEM since the last MOUG; Three in the N.I jurisdiction and one in
the ROI jurisdiction N.I – AES Ballylumford Limited, Church Hill Energy wind farm and Crighshane Energy wind farm ROI - Activation Energy DSU.
Market Operator User Group Meeting / June 30th 2009
11Market Operator User Group Meeting
12
Recent Registrations / De-Registrations
Unit
Supply - Registrations There have been three new Supply Unit Registrations in the SEM since the last MOUG; All in the ROI jurisdiction LCC Power Limited, Activation Energy TSSU and Endesa Ireland Ltd.
De-Registrations There have been three Unit De-Registrations in the SEM since the last MOUG; All in the N.I jurisdiction. Bord Gais Supply Unit, NIE PPB Generator Unit and SSE Ireland Interconnector Unit
Unit Type Change There have been ten Unit Type Changes in the SEM since the last MOUG; Six APTG to VPTG and four PPMG to PPTG
Market Operator User Group Meeting / June 30th 2009
12Market Operator User Group Meeting
13
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
13Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
14
Participant Connection Issues
Issue: Java error(JMS Messaging) – connection issues experienced by a Participant when
submitting COD.
Resolution: SEMO’s internal investigation was passed to the CMS vendor to cross reference and to revert
to SEMO with a plan to resolve. Issue was identified as a Java Messaging error. SEMO implemented elevated monitoring to catch the error & resolve. – This is has been
successful.
Next Steps: A workaround has been received and tested in current AMIE pre-production. The workaround script ‘recycles’ MI services on two MI servers.
SEMO is proposing to run the workaround script each evening at 7:50pm – no MI events are running and from a review of the logs no participant activity.
This process takes 15mins and connection requests during this period may fail. Deployment of the workaround script is due on Tuesday(22/5/12) This message queuing service is changing in IDT. Participants are currently testing with the new messaging service in place - IDT
Market Operator User Group Meeting / June 30th 2009
14Market Operator User Group Meeting
15
CMS Oracle Database Archiving
Background Since 1st November 2007, all the data provided to SEMO or generated by SEMO has
been stored on the live system. This has impacted on system performance and the ability of SEMO to migrate
data for IDT.
The Plan: To improve performance of settlements and ensure that the migration of the Central
Market Systems Database from the current AIME environment to IDT can be achieved within a 12 hour window.
SEMO is proposing to archive the settlement data in the CMS on the 8 th June. This will require the CMS to go off-line for 12 hours.
6pm 8/6/12 to 6am 8/6/12
Once the archiving solution is implemented: The CMS database will contain 26 months of live data on line. SEMO will archive twice a year. 7 years of data will be available between offline and online
Market Operator User Group Meeting / June 30th 2009
15Market Operator User Group Meeting
16
CMS Oracle Database Archiving
Additional Archiving Information
All Data can be provided on request, however if resettlement is required for periods beyond the 26 months, then data will need to be retrieved from the archive, based on a granularity of 1 month, which will require a full market outage.
The resettlement process time line and Market Outage will be communicated in accordance with the normal process, ( The likelihood of this type of resettlement being required is very low)
SEMO will have the capacity for Seven years in relation to SAN requirements to hold data off line.
The benefits of this are, increased performance and the ability to migrate within the 12 hour window.
The challenges are, if data is required following a dispute, or a general query the response/resolution time may be increased as the data will need to be retrieved from the offline store, and a market outage will be required.
Market Operator User Group Meeting / June 30th 2009
16Market Operator User Group Meeting
17
AIME SSL Server Certs Renewal
CMS AIME Web Servers The following AIME web server SSL certs need to be renewed
STL.ALLISLANDMARKET.COM (DUBLIN) – EXPIRING 01/07/2012 STL.ALLISLANDMARKET.COM (BELFAST) – EXPIRING 01/07/2012 MARKET.ALLISLANDMARKET.COM (DUBLIN) – EXPIRING 01/07/2012 STLPR.ALLISLANDMARKET.COM (DUBLIN) – EXPIRING 01/07/2012 STLPR.ALLISLANDMARKET.COM (BELFAST) – EXPIRING 01/07/2012 MAMOI.ALLISLANDMARKET.COM (DUBLIN / BELFAST) – EXPIRING 05/07/2012
SEMO is proposing to renew these certs on Tuesday the 29th of May –
A CMS outage from 6pm to 12 midnight is required.
Market Operator User Group Meeting / June 30th 2009
17Market Operator User Group Meeting
18
IDT Technical Update
Environment Build All production & non production environments are built with application code
installed. Two physical production clusters. Six pre-production environments. Total of 204 servers have been built.
Market Trail Running against a physical setup. Dedicated technical support resource. New URL’s for Market Trail. Using the same AIME pilot Certs New test FTP site
Market Operator User Group Meeting / June 30th 2009
18Market Operator User Group Meeting
SEM R2.0.0: Intra-Day TradingRelease Scope
The following Change Requests are in scope for the SEM R2.0.0 release:
CR Ref Mod Ref Description
CR222 Mod_18_10 Intra-Day Trading
CR244 N/A SO Security (Option 1)
CR256 Mod_43_10 Price Taker Generator Units and Firm Access
CR284 Mod_18_10 Data to be Utilised when MSP Software Cancellation Run occurs
CR287 N/A Inclusion of Breach Amount in the Credit Risk Report
19
Market Operator User Group Meeting19
SEM R2.0.0: Intra-Day Trading
Key Milestones Vendor Functional Design Approval 29 July 2011 √ Complete
Technical Overview Workshop 03 Aug 2011 √ Complete
MPUD and Technical documentation 29 Aug 2011 √ Complete
Participant Engagement Plan 09 Sep 2011 √ Complete
Vendor Coding and Unit Testing 11 Nov 2011 √ Complete
Factory Test Complete 23 Dec 2011 √ Complete
SIT Execution 03 Jan 2012 Closing May 21st
Market Trial Execution 30 Apr 2012 In Progress
Proposed Deployment* 20 Jul 2012
* Subject to successful completion of testing.20
20
SEM R2.0.0: Intra-Day Trading Schedule
High-level project schedule
21
21
SEM R2.0.0: Market Trial Timeline
Pre-MT
Market Trial Execution
1 Week 3 Weeks 2 Weeks
· Ad-Hoc Testing
· Back-up databases
· Draft exit report
Sta
ge
Sco
pe
23/04 27/04 30/04 22/06 06/0725/06
Pre-Market Trial Post-Market Trial
· Set-up MT environment
· Back-up databases
· Verify digital certificates
· Test connectivity
· Full running of market including:
Ex-Ante processing
Indicative Ex-Post processing
Initial Ex-Post processing
Energy Settlements
Capacity Settlements
• Abnormal market running
including:
Cancellation of an MSP run
· Discrete test scenarios
· Testing IDT Specific Functionality
IDT Specific Interface
Test
End-to-End Test
Ad-Hoc Test /
Exit MT
18/05 21/05 5 Weeks
22
Market Operator User Group Meeting22
SEM R2.0.0: Intra-Day TradingMarket Trial
Connectivity testing completed on schedule on April 27th.
IDT Specific Interface Testing completed on schedule on May 18th.
End-To-End phase underway – due for completion June 22nd.
Ad-Hoc test phase scheduled for June 25th to July 6th. • If Participants have specific requests for the ad-hoc phase these
must be submitted well in advance to the market helpdesk to enable SEMO
to ensure relevant data etc is prepared.• SEMO will evaluate and respond to all requests.• Proposed scenarios will be published in advance.
23
Market Operator User Group Meeting23
SEM R2.0.0: Intra-Day TradingMarket Trial – Items Encountered
XML Report Control Characters: One Participant identified that control characters (CR, Line Feed) in XML reports were affecting the consumption of data into their back-end systems.
Outcome: While not strictly a defect, our vendors have provided a software update to resolve this.
Status : Item re-tested and closed.
24
Market Operator User Group Meeting24
SEM R2.0.0: Intra-Day TradingLegacy FTP - Report Timing
Some Participants continue to use the Legacy FTP site for provisioning of “Public Data” from the Central Market Systems.
As previously communicated it is not intended to upgrade the Legacy FTP site for future releases.
IDT release will impact the Legacy FTP site as follows:Where there are multiple versions of the same report (i.e. for each Gate Window) these will be copied to the FTP site as normal but they will have the same target filename. This will result in previous versions of the report to be overwritten.
For example • PUB_D_CODInterconnecotrUnits_EA,• PUB_D_CODInterconnecotrUnits_EA2 and • PUB_D_CODInterconnecotrUnits_WD1
will be copied to the Legacy Ftp site as • PUB_D_CODInterconnecotrUnits
25
Market Operator User Group Meeting25
SEM R2.0.0: Intra-Day TradingReport Timing and MPUD
At Participant request we have staggered the publication of some of the D+1 Public reports so there is sufficient time for the affected Participant to poll these from the FTP site.
Feedback on this proposal was requested from all Participants (via Market Helpdesk) and no objections were raised.
The MPUD (V1.3) was updated to reflect the changes and was issued on15/05/2012.
Changes were implemented in the CMS in time for End-To-End phase of Market Trial.
Change Summary:• EA Reports will be published at 9:00am TD+1;• EA2 Reports will be published at 10:45am TD+1; and• WD1 Reports will be published at 13:55pm TD+1.
• Notes: • T&SC Obligations specify these reports must be published by 14:00 TD+1. • Affects Public reports only.
26
Market Operator User Group Meeting26
SEM R2.0.0: Intra-Day TradingLegacy FTP Site
Participants are reminded that the Legacy FTP site should not be utilised for business critical data provision. Participants who continue to use this facility run the risk of data loss.
The Legacy FTP site will be decommissioned by SEMO at some point in the
future – consultation on timeline will be held with the industry.
In preparation for decommissioning, Participants should switch focus to the SEMO website data facility or utilise the MPI in the Central Market Systems for “Public Data” provisioning.
27
Market Operator User Group Meeting27
SEM R2.0.0: Intra-Day TradingMarket Trial Support Channels
Daily Conference Calls at 3pm. Participants are strongly urged to participate in these to keep themselves informed on latest developments, schedule etc.
Market Trial issues/queries can be submitted to IDT project team via the Market Helpdesk.
Please use template when submitting items to the Helpdesk.
SEMO Website: Latest news, updates etc.; IDT Newsletter; Publication of all Market Trial related issues and queries on a bi-weekly
basis (Wednesdays & Fridays).
Monthly Project Management Forum (PMF) conference calls.
28
Market Operator User Group Meeting28
SEM R2.1.0 (Oct 2012) Release UpdateApproved Scope
The following CRs have RA approval for inclusion in the SEM R2.1.0 release:
CR Ref Mod Ref DescriptionCR207 N/A Automation of FMOC Calculation
CR254 Mod_40_10 Dwell Times While Ramping
CR255 Mod_42_10 Single Ramp Rate
CR258 Mod_01_11 UI Payments for Generator Units
CR259 Mod_06_11 SRA Cancellation through the MPI
CR260 N/A Additional MI-AMP Feed
CR261 N/A Removal of Orphan Trading Site Settlement Points
CR266 N/A Change of Effective Date in the MPI
CR267 N/A Wind and Load Forecast Data
CR274 Mod_10_11 Interconnector Under Test
CR275 Mod_12_11 Interconnector Losses
CR280 Mod_21_11 UI Payments for ELUs Constrained On
CR286 N/A Publication of Zero IUNs when no PQ Pairs available
29
Market Operator User Group Meeting29
SEM R2.1.0 (Oct 2012) Release UpdateParticipant Impacts
The SEM R2.1.0 scope will have an impact on interfaces between the CMS and Participant systems.
To support this release, SEMO will put in place the necessary framework to give maximum visibility and opportunity for engagement to Participants, including: Interface documentation set (e.g. MPI User Guide, MPUD); Functional Workshops; MOUG Updates; and Market Test phase.
Design discussions with vendors nearing completion.
30
Market Operator User Group Meeting30
SEM R2.2.0 (Apr 2013) Release UpdateModification Proposal Scope
The following CR has RA approval for inclusion in the SEM R2.2.0 release:
The Release Cut-off Date for the SEM R2.2.0 release is: FRIDAY, 22ND JUNE 2012
Any Non-Code Change Requests to be considered for this release should be submitted to the SDS mailbox ([email protected]) before this date.
CR Ref Mod Ref DescriptionCR281 Mod_17_11 Addition of D+3 Dispatch Instruction report
31
Market Operator User Group Meeting31
SEMO Website – IDT impacts
June 2012– Website Upgrade for IDT• IDT ready – handling of all new reports and IDT data• Improved Training and Registration Pages• Improvements to behaviour of Operational Indicators• Single log in access for Alert Me and Dynamic Reports• Continued….
32
Market Operator User Group Meeting32
SEMO Website – IDT impacts
June 2012– Website Upgrade for IDT – continued• New Dynamic Reports
• Daily Exchange Rate
• Generator Forecast Data
• Interconnector Flow
• Nomination Profile – Demand Side Units
• Nomination Profile – Standard Units
• Technical Offer Data – Demand Side Units
• Technical Offer Data – Standard Units
• Defect corrections Dynamic Reports• Improved presentation of KPI Reports
33
Market Operator User Group Meeting33
SEMO Website – IDT Upgrade
The SEMO website will be “IDT Ready” to handle IDT data in advance of IDT go live (mid June 2012):
34
Market Operator User Group Meeting34
SEMO Website – IDT Upgrade
Improved Registration and Training Pages
35
Market Operator User Group Meeting35
SEMO Website – IDT Upgrade
Improved Registration and Training Pages
36
36
SEMO Website – IDT Upgrade
Improvements to behaviour of Operational Indicators
• RED – Messages stay red until closed (not just red TODAY)
• Amber – Warning conditione.g. Advance notification of alert for current or future operational run
• All Red – Critical situation • e.g. Market Systems outage
37
Market Operator User Group Meeting37
SEMO Website – IDT Upgrade
Single log in access for Alert Me and Dynamic Reports
Alert subscribers who do not already have a password will be invited to create a password
38
Market Operator User Group Meeting38
SEMO Website – IDT Upgrade
New Dynamic Reports
• New Dynamic Reports• Daily Exchange Rate
• Generator Forecast Data
• Interconnector Flow
• Nomination Profile – Demand Side Units
• Nomination Profile – Standard Units
• Technical Offer Data – Demand Side Units
• Technical Offer Data – Standard Units
39
Market Operator User Group Meeting39
SEMO Website – IDT Upgrade
Improved Presentation of KPI Reports
40
Market Operator User Group Meeting40
41
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
41Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
42
Query Statistics 13th of March – 1st of May 2012
No. of calls older than 20 working days: 4
42Market Operator User Group Meeting
43
Query Statistics 1st July 2011 – 31st August 2011
Market Operator User Group Meeting 43
General Query KPI’s
General Query KPI – 20 Working Days
Quarter 1 Quarter 2 Quarter 3 Quarter 4
95.13% 96.35% 99.16%* N/A
44
* Currently although as this quarter still open subject to change
Market Operator User Group Meeting44
45
Disputes: 13th of March – 1st of May 2012
SEMO has received two disputes since the last MOUG. No disputes have been resolved since the last MOUG. There are currently four Disputes Open.
45Market Operator User Group Meeting
History of SupportWorks in OperationsIntraday Trading Changes
• Query Management System Upgrade – SupportWorks
• Improvements to the Limited Communications Process
• Amendment to Authorised Persons Category B
Customer Service - Intraday Trading
46
Market Operator User Group Meeting46
History of SupportWorks in OperationsBrief History of System
• Introduced in 2007 for Market Go-Live
Predominantly introduced for the tracking of Formal Queries at the time of implementation
Little functionality introduced since original implementation
Customer Service – Query Management System
47
Market Operator User Group Meeting47
Customer Service – Query Management System
Current Situation
• Primarily used to Manage Formal and General Queries
SupportWorks is used for:• Tracking queries• Statistical Reporting• Audit information• Measuring KPI’s
48
Market Operator User Group Meeting48
Customer Service – Query Management System
Improvements
• More efficient handling of Queries
• Introduction of a Web Portal
Customers would log their own queries via public website
Informational prompts to help customers resolve their queries before contacting the Helpdesk
49
Market Operator User Group Meeting49
Customer Service – Query Management System
Benefits
• What this will mean for You:
Improved turnaround times
Greater transparency with regard to query management process
Can receive additional documentation through this on line portal (release information etc.)
50
Market Operator User Group Meeting50
Customer Service – Limited Communications Failure
Limited Communications Failure Process Improvement
• LCF submission via the new Web Portal
• Participant Action
Participants log in and complete the digital form with bid information Send a one page fax to SEMO with the following details:
Call Reference – generated from Web Portal Authorised Persons Name Authorised Persons Password:
51
Market Operator User Group Meeting51
Customer Service – Limited Communications Failure
Limited Communications Failure Process Improvement
• SEMO Steps:
SEMO review call detail logged in Query Management System SEMO validates the fax detail:
Call Reference Authorised Persons Name Authorised Persons Password:
If the fax passes validation the .xml file created as part of the call logging process is loaded to the CMS
SEMO notifies Participant of success/failure of the file load. *Participants are still required to call the Market Operations hotline
52
Market Operator User Group Meeting52
Customer Service – Review Authorised Persons
To Facilitate new Credit Formal Query
With Intra-Day Trading (IDT), an additional Formal Query process will be introduced with regard to the calculation of Required Credit Cover (RCC).
To Submit this type of query the participant must be listed as an Authorised Person – with category B permissions
Please review and ensure the correct staff are listed prior to go live
53
Market Operator User Group Meeting53
54
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
54Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
Treatment of Firm Access Quantities in the SEM
Firm Access Quantity
“… the quantity of Output that a Generator Unit has firm rights under a Connection Agreement to be able to export onto the system at the point of Connection” - T&SC Glossary;
Connection is generally represented in the SEM as the Trading Site;
Trading Site is group of generators that are “…covered by a single Connection Agreement…” - T&SC Glossary; “…are located on a Contiguous Site…” - T&SC Glossary;
In the SEM, Firm Access Quantity is recorded against the Trading Site;
55
Market Operator User Group Meeting55
Treatment of Firm Access Quantities in the SEM
Firm Access Quantity
Connection offered up to contracted Maximum Export Capacity (MEC);
If not fully firm, then Firm Access Quantity applied;
Where a unit is fully firm to its MEC but has higher installed capacity, the quantity greater than the MEC is non-firm in the SEM;
In the SEM, FAQ of a Trading Side = Sum(Registered Capacity) – Sum(Non-Firm Capacity);
56
Market Operator User Group Meeting56
Treatment of Firm Access Quantities in the SEM
Firm Access Quantity
Maximum Generator Capacity = Registered Capacity
Registered Firm Capacity is a derived quantity based on a pro-rata of the FAQ for the site across the installed units on the site – not used in the SEM
Non-Firm Capacity is derived based on Maximum Generator Capacity – Registered Firm Capacity
57
Market Operator User Group Meeting57
Treatment of Firm Access Quantities in the SEM
How FAQ is used
Used in the calculation of Actual Availability;
Applies to all settlement classes (PPMG, PPTG and VPTG);
Not used in the calculation of Eligible Availability for Capacity Payment;
“The Market Operator shall calculate values of Availability Profile …without consideration of access limitations.” – T&SC, 4.54;
58
Market Operator User Group Meeting58
Treatment of Firm Access Quantities in the SEM
How FAQ is used
The Generator Unit values in the Market Participant Interface are not used in these calculations;
Actual Availability is calculated dynamically for each Trading Period for each Generator Unit where the Trading Site is not fully firm;
Calculation takes account of Availability Profile of each Generator Unit on the Trading Site; The Firm Access Quantity of the Trading Site; The Dispatch Quantity of each of the Generator Units on the Site; The on site demand, where registered explicitly (Trading Site Supplier Unit);
59
Market Operator User Group Meeting59
Treatment of Firm Access Quantities in the SEM
How FAQ is used
Step 1:
This takes the Firm Access Quantity for the site, …adds any metered demand on site (served behind the connection point), …and allocates the FAQ to each unit, pro-rata to their Availability Profile
60
Market Operator User Group Meeting60
Treatment of Firm Access Quantities in the SEM
How FAQ is used
Step 2:
This calculates an Access Quantity for each Generator on the Trading Site …which is the smaller of the Availability Profile, …and the unit Firm Access Quantity. Note, that the unit Firm Access Quantity here is compared against the Dispatch
Quantity. Therefore, if the unit is dispatched by the TSO above its allocated Firm Access Quantity, the higher value is used.
61
Market Operator User Group Meeting61
Treatment of Firm Access Quantities in the SEM
How FAQ is used
Step 3:
This calculates an Access Quantity for the Trading Site …which is the smaller of the summed Availability Profile of all Generators, …and the Trading Site Firm Access Quantity, including any demand served
behind the connection point. Note, that the Trading Site Firm Access Quantity here is compared against the
summed Dispatch Quantities for all units on the site. Therefore, if the combined dispatch for the site is above its allocated Firm Access Quantity, the higher value is used.
62
Market Operator User Group Meeting62
Treatment of Firm Access Quantities in the SEM
How FAQ is used
Step 4:
This calculates an Actual Availability for each Generator on the Trading Site …where the units have been dispatched to their total Access Quantity, then this
is used, …where the units have been dispatched below their Access Quantity, again the
Access Quantity is used (because this expression calculates to zero), …where the units have been dispatched above their aggregate Access Quantity,
their Access Quantity is increased by the difference, pro-rata across the site.
63
Market Operator User Group Meeting63
Treatment of Firm Access Quantities in the SEM
How FAQ is used
Example: Please note this Excel is for sample purposes only
AP DQ MD FAQst FAQuh AQuh SAQ AQ-DQ AAUnit 1 50 20 40 40 20 40Unit 2 50 20 40 40 20 40
Supplier 0SAQ 80 80
64
Market Operator User Group Meeting64
Treatment of Firm Access Quantities in the SEM
How it impacts
For Predictable Price Makers, availability for use in the determination of market schedules is limited by Firm Access Quantity;
Modification 43_10 – introduces the Actual Availability value for Variable Price Takers when constrained down;
This means MSQ for VPTs will be limited by their Firm Access Quantity;
Modification becomes effective from next software release (SEM R 2.0);
65
Market Operator User Group Meeting65
Treatment of Firm Access Quantities in the SEM
Next steps
SEMO and EirGrid TSO have completed a review of values recorded in the SEM registration system;
Have reviewed values of – Firm Access Quantity for each Trading Site; Maximum Generator Capacity (Registered Capacity) for each Generator Unit; Registered Firm Capacity*; Non-Firm Capacity*;
Discrepancies have been identified in the set up of some Sites/Units;
We will be contacting affected Participants with details of data as recorded in our system and what is understood to be the correct data;
We will ask affected Participants to confirm the correct data;
66
Market Operator User Group Meeting66
67
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
67Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
68
68Market Operator User Group Meeting
Questions?
Q&A Session
69
Agenda
Releases and Infrastructure 11:00
Market Analysis 11:55
Market Operations 10:35
Customer Service 11:40
Review of Action Items 10:30
69Market Operator User Group Meeting
Finish 12:30
Questions and Answers 12:15
70
Thank You for your AttendanceThank You for your Attendance
Next MOUG Conference Call: 12th of June 2012
Next MOUG: 17th of July 2012 in Dublin
Market Operator User Group Meeting 70