1 isms transition at the west valley demonstration project larry myszka, isms/conops manager west...
TRANSCRIPT
1
ISMS Transition at the West Valley
Demonstration Project
Larry Myszka, ISMS/CONOPS ManagerWest Valley Environmental Services LLC
2
Timeline
Contract awarded to WVES on June 29, 2007
Contract transition required submittal of a Safety Management System Description (SMSD) within 60 days of contract award SMSD could either be new (for DOE approval), or adoption
of the existing DOE approved WVNSCO SMSD
3
Timeline (Continued)
During the transition, WVES evaluated and chose to adopt the existing SMSD Required annual FY ISMS objectives, measures, and
commitments were embodied within the WVNSCO SMSD Required WVES to make adjustments to ensure consistency
with the new contract scope and to cover the remaining portion of the FY
WVES submitted the adopted SMSD, with the adjusted objectives, measures, and commitments, to the DOE Contracting Officer on August 28, 2007
DOE approved the SMSD on October 31, 2007
4
Status of ISMS Verification
During the second week of the new contract, a 12 person DOE team made up of DOE HQ., DOE WVDP personnel and non-WVDP personnel conducted a validation of the ISMS Program
Found "the currently approved WVDP ISMS is implemented and effective”
No ISMS Deficiencies were identified One area for improvement Two findings Four observations Five noteworthy practices
5
Conclusions
Adoption of the existing, proven ISMS & SMSD made contract transition smoother
Focused primarily on objectives, measures, and commitments relative to new scope and time frame
Majority of site staff retained from incumbent Safety culture of workers carried over Knowledge of ISMS
Combination of above made validation two weeks into the new contract without any deficiencies possible