1. Introduction • Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership etc., by the nature of the survey itself e.g. hydrographic, terrestrial, astronomic, according to the scale or accuracy of the survey, the type of instrument or instruments used e.g. » prismatic compass, » level » theodolite, » photograph (terrestrial or aerial).

Upload: jocelyn-kearney

Post on 28-Mar-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

1. Introduction

• Surveying Method chosen depends on:• by the purpose of the survey e.g. map making, location of specific

points, definition of land ownership etc.,

• by the nature of the survey itself e.g. hydrographic, terrestrial, astronomic,

• according to the scale or accuracy of the survey,

• the type of instrument or instruments used

– e.g. » prismatic compass, » level » theodolite, » photograph (terrestrial or aerial).

Page 2: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

1. Introduction

• Other factors:

• Curvature of earth

over 5 km, vertical angle difference will approach 2.5 minutes which can readily be detected even with most basic theodolite.

• Errors

collimation errors in instruments need to be calibrated otherwise “rivers could flow uphill”

Surveying involves

• transfer of levels between two points

• measurement of angles and lengths.

• requires solution of triangular shapes using basic trigonometry (or by graphical means).

• If distances are large: planar geometry no longer applies.

Page 3: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

• Geodetic surveys allow for curvature of Earth– 1:2500 scale maps actually vary in scale

– On extreme east and west coasts, scale is approximately 1:2501

– Reference is taken along 2 oW where scale is 1:2499

– Along Greenwich Meridian and 4oW scale is 1:2500

1. Introduction

• Surveying Instruments can be very accurate– Instruments in ENV are capable of accuracies of 1 part in 20000 with ease if

used correctly.

• Maps in UK are based on cartesian co-ordinates – North is represented by a bearing of 000.

– East a bearing of 090,

– South-west a bearing of 225 etc.

• Referencing: True North: Grid North: Magnetic North– .

Page 4: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

• Point location - radial line and distance method. .2. Basic Surveying Methods

Difference in the Easting (E) is given by:-

sin.E

Northing difference (N)is given by:-

True co-ordinates of the second point:-

Easting = Northing =

cos.N

sin.Eo

cos.No

where is the length of the line, and is the bearing

where Eo is Easting and No is Northing of the reference station.

N

O

This method can ONLY be used if there is an INBUILT reference direction in the instrument - e.g. magnetic north

Page 5: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

• Point location - radial line and distance method. .

• No inbuilt reference

2. Basic Surveying Methods

N

O

R

Two horizontal angles are ALWAYS needed

i.e. a reading to R (a reference object) as well as object of interest

Applies to most instruments:

• Total Stations

• Theodolites

• Levels etc

Page 6: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

• Point location - Resection

2. Basic Surveying Methods

A

B

CN

Coordinates of A and B are known

Point C found from bearings at A and B

or bearings from C to A and B

A

B

C

B

A

BA

C

C

P

D

External Triangle of

Errors

Internal Triangle of Errors

Methods to distribute errors are needed

Page 7: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

2. Basic Surveying Methods• Point location - Traverse Methods

ba

cA1

ba

cA1

A2

ba

cA1

e

d

Open Traverse

Errors accumulate

Closed Traverse

Errors can be distributed

Closed Loop Traverse

Errors can be distributed

Page 8: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

2. Basic Surveying Methods

• Point location - Offset Methods

A B

2

1

D1

D2

d1

d2

Useful for mapping features

Not suitable where accuracy is required

Page 9: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

2. Basic Surveying Methods

tandhH Ho

)(sin

sinsindhH

12

12Ho

• Level Ground

• Base Accessible

• Level Ground

• Base Not Accessible

• Height Measurement

Page 10: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

2. Basic Surveying Methods

sindH S

1So hsindhH

• Height Measurement

H

d s

H

• Sloping Ground

• Base Accessible

• Observations to same height above ground

• Sloping Ground

• Base Accessible

• Observations to different height above ground

Page 11: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

2. Basic Surveying Methods

)tantan(cosdH 122S2

2So1 sindhH

• Height Measurement• Sloping Ground

• Base Accessible

• Base and Top above and below observer

H1

H2

Page 12: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3. Planning a Survey

• Careful Planning is needed– A single missed reading will make whole survey of no

value– Need to provide checks– Abstract raw data in field– Repeat readings if necessary before leaving site.– Remember an extra set of readings may take 15

minutes - but to remobilise and set up again may take many hours

– schedule breaks effectively.

Page 13: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements

• A clear statement of purpose of survey is needed• e.g.

• mapping vegetation boundaries; estimating river bank plan shape or erosion rates;

• determining flow characteristics in rivers; • establishing fixed reference stations for future use; • locating the point at which a particular set of measurements have

been taken; • measurement of the profile of a slope; • assessment of regions liable to flooding. • scale of the map required (if relevant).

. The purpose of the survey will dictate the scale and accuracy required and ultimately the methods to be used.

Page 14: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements

• Secondary Planning Requirements include:- • what equipment is actually available

• what time is available

• what man-power is available

• what access and transport are available.

• over what distance will the surveying party be spread during the surveying?

• Will it be necessary to return to the same site at a later date to take repeat measurements, and if so when (within a few days, or several weeks or months later?).

• How will contact between members of the surveying team be maintained at distance?

Page 15: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements

• Mapping vegetation boundaries: – accuracy ~ 1:1000 (1 m is represented by 1 mm),

– Suitable surveying methods:

• compass and tape traverses,

• chain and offset mapping,

• point resection using a prismatic compass. • height variations, Abney levels will often be adequate.

– Alternative methods, if the equipment is available,

• use of a surveyor's level and tachymetery, • use of electro-magnetic distance measurement.

Page 16: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements

• Water Slope Measurement

– Difference in water surface elevation in a river is small,

– Measurement requires accurate measurement of height differences over distances which are usually between 10m and 500m apart.

– A good surveying level for which the collimation error is known is required.

– Otherwise river may appear to flow uphill!!

Page 17: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements

• Fixed Control Points– Measurements will be needed to the nearest millimetre

(centimetre) even if associated mapping detail is not required at this level of accuracy.

– Sometimes, such as in the vegetation survey, simple methods can be used including prismatic compasses to establish stations,

– Control stations will be located more accurately using a theodolite and associated equipment.

Page 18: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements

• Surveying River Banks– Methods

• Radial Line Techniques using tachymetry for general plan shape of meanders (general profile ~5m).

More accurate methods involving the establishment of short permanent base lines on the bank parallel to the long stream direction of the river are needed for erosion studies.

accurate profiles of bank are determined using metre rule offsets from this reference line to the edge of the river bank.

Decisions neededwhat constitutes the edge of the channel?

~10 - 20 m

Page 19: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.2 Basic Requirements• Size of Survey Party:-

• what equipment is to be used for accuracy

• access for vehicles

• e.g.

– a theodolite requires a tripod and targets

– may also require targets mounted on tripods

– could require a minimum of three tripods and ancillary equipment.

• Often makes sense to establish control stations separate from detailed purpose of survey

• Communication

– Radios

– Flags?

• Markers: Permanent: Temporary????

Page 20: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.3 Booking of Data

• in waterproof notebooks– should be logical– should always be done in the field– if necessary it can be transcribed BUT the ORIGINAL BOOKING

MUST ALWAYS be accessible.– Cross checking should be booked in field– Critical Information which should always be present

• Purpose of Survey: (River Bank Mapping at Maes Mawr)• Date: Time: Weather: • Specific Location • Sketch of Area• Booker’s Name:• Observer’s Name

Page 21: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.4 Permissible ErrorsSurveying Method Maximum Error

Prismatic Compass * 0.5 o

Tripod Mounted Compass * 0.05o

Angular Measurement with a Level 0.1 - 1.0o

Angular Measurement using a theodolite (depends on instrument). 1 - 20 seconds Level transfer using a Surveyor's Level 20 mm per kmDistance measurement using tape 1 part in 400+Distance measurement using catenary taping 1 part in 1500+Distance measurement using a subtense bar - depends on configuration 1 part in 2000 - 10000Electro magnetic distance measurement * 5 mm irrespective of distanceClosing error in a compass and tape traverse 1 part in 400

Closing error in a theodolite and EDM traverse 1 part in 10000Closing error on a set of angles at one station (20 second instrument) * 20 seconds Closing error in a triangle (20 second instrument) * 30 seconds

Page 22: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.5 Treatment of Errors

• Systematic Errors– collimation errors in instrucments

– magnetic errors affecting all readings at a particular location

– Systematic errors (unless large) can be compensated - will always be present and calibration is important.

• Random Errors– observer variations in reading a scale

148.1 148.2 148.0 148.1 148.1

148.1 148.2 147.9 148.1 148.2– Mean is 148.1 - standard deviation is 0.09

Page 23: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.5 Treatment of Errors

• Snedecor’s Rule

Number of Observations

Approximation of Standard Deviation

5 R / 210 R / 325 R / 450 R / 4.5

100 R / 5

Where R is range of readings

Page 24: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.5 Treatment of Errors

• Random Errors

148.1 148.2 148.0 148.1 148.1

148.1 148.2 147.9 149.3 148.2

– Mean is 148.22 - should this value be used?

– Exclude 149.3 and mean is 148.10

– standard deviation is 0.10

– value of 149.3 is 12 standard deviations from mean and should be excluded.

• Gross Errors should always be discarded

Page 25: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.6 Provision of Checks• Going to repeat a survey is time consuming• Always provide a check– pace out a distance– sight on three positions rather than basic two– if measuring three stations - take readings at all three stations - sum of angles should be 180o

• For Level transfers – e.g. elevation profile of longstream of river

• trace river from start to finish• transfer level back along back - differences should be same• if errors are unacceptable (e.g. 20 mm per 1 km) then repeat until consistency is achieved

148.1 148.2 148.0 148.1 148.1

148.1 148.2 147.9 149.3 148.2

– Mean is 148.22 - should this value be used?

– Exclude 149.3 and mean is 148.10 – standard deviation is 0.10– value of 149.3 is 12 standard deviations from mean and should be excluded.

• Gross Errors should always be discarded

Page 26: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.7 An example of Bad Planning

• ENV students doing their third year project in 1992 in Derbyshire

• needed to map meanders

• decided to use radial line method and tachymetry using level

• measured A to RO

Lady Bower Reservoir

A

B

C

D

E

RO

• moved to B

• measured radial lines at A

• measured radial lines at B

• measured B to A

• moved to C• etc

Despite careful planning points B, C, D and E could not be located!

Page 27: 1. Introduction Surveying Method chosen depends on: by the purpose of the survey e.g. map making, location of specific points, definition of land ownership

3.7 An example of Bad Planning

A

B

C

RO

What should have been done?

Before leaving Derbyshire, map should have been plotted.

Before moving from A to B

measure A to B

When at B measure from B to A