1 intermountain power project stability enhancement (ippse) system presentation to wecc remedial...

81
1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010 Ontario Hilton Ontario, CA

Upload: aiden-sawyer

Post on 27-Mar-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

1

INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM

Presentation to

WECC Remedial Action Scheme Reliability Subcommittee

April 30, 2010Ontario HiltonOntario, CA

Page 2: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

2

INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM

Presented by: Ken Silver-Electrical Service Manager (Manager of

Energy Control and Extra High Voltage Stations ) Travis Smith-Assistant Manager (Manager of

Intermountain Converter Station) Brian Cast–Electrical Engineer (Grid Operation and

Energy Prescheduling Supervisor ) Ken Lindquist – System Protection Engineer

Attendees: Ken Silver, Mukhlesur Bhuiyan, Travis Smith, Tom

Snyder, Brian Cast, Saif Mogri, Ken Lindquist, Carlos Garay and John Hu

Chuck Wu (On Phone)

Page 3: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

3

Agenda

1. System Overview – Ken Silver2. Performance and Operational History – Travis

Smith3. System Studies – Ken Lindquist4. System Design – Travis Smith5. Arming Function – Brian Cast6. Operation and Monitoring – Brian Cast7. Operating Procedures for Abnormal Conditions -

Ken Silver8. Commissioning, Maintenance, and Testing – Travis

Smith9. Conclusions – Travis Smith

Page 4: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

4

1. System Overview

Page 5: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

5

1. System Overview

The Purpose of Intermountain Power Project Stability Enhancement (IPPSE) is to ensure WECC system stability after outages to the Intermountain Power Project DC system (IPPDC). This is achieved by arming predetermined remedial actions prior to the occurrence of a disturbance associated with the IPPDC.

Due to IPPDC system upgrade from 1920MW to 2400MW, the IPPSE is submitted for review.

Page 6: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

6

1. System Overview

Remedial Actions Required:The Intermountain Power Project (IPP) Contingency Arming System (CAS)has been implemented to mitigate IPPDC disturbances by tripping one or twoIPP generating units. The IPP CAS has been in operation since 1986. Thedesign and operations of this RAS has been reported to WECC on April 1986with a report entitled “Intermountain Power Project Contingency ArmingSystem: One Unit Operation” and on August 1992, with a report entitled“Intermountain Power Project Contingency Arming System: Non-Credibilityof Remedial Action Scheme Failure.”

Formal Operating Procedure:The IPP CAS consists of arming-charts where real-time power output of theIPP generating units and the IPPDC line flows are used to select the no-unit,one-unit or two-unit arming of remedial actions. The IPP CAS and associatedoperating procedures are included with the LADWP’s Energy Control CenterEnergy Management System (ECC-EMS) computers.

Page 7: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

7

1. System Overview IPP DC Upgrade Project

Page 8: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

8

1. System Overview Intermountain Power Project System

Page 9: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

9

1. System Overview System Map

Page 10: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

10

1. System Overview Intermountain One-line Diagram

One Line Diagram: Adelanto

Page 11: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

11

2. Performance and Operational History

Page 12: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

12

2. Performance and Operational History

The existing IPPSE was installed May 10, 1986

A design criteria of one operational failure in 3 years was used.

How have we done ?

Page 13: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

13

2. Performance and Operational History

In 24 years there have been 28 actions. Seventeen of which occurred prior to August 1992.

There have been 6 failures 5 of which occurred prior to August 1992.

The system did not achieve its goal from 1986 to 1992. However from 1992 to the present, the system has achieved its goals.

Page 14: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

14

2. Performance and Operational History

What Changed in 1992?

A problem with the Monopolar Out signal was discovered and corrected.

A design change was initiated to allow for 1 restart in Monopolar Operation.

Page 15: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

15

2. Performance and Operational History

Success

After the modifications, the system operated correctly.

Page 16: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

16

3. System Study

Page 17: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

17

3. Study Process Summary

Co-ordinate with Impacted System Operators (PacifiCorp) in preparing study plan and study conditions.

Determine Impact on the WECC System. Determine Maximum “IPP Net Import”

Capability. Determine Generation Tripping delay times. Determine IPP Contingency Arming Scheme

(CAS) Operational Nomograms.

Page 18: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

18

3. System Condition Studied IPP DC Upgrade

Page 19: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

19

3. Utah South Conditions

Stressed TOT2 to Path RatingTOT2C

TOT2B

Page 20: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

20

3. “Net IPP Import” Sensitivity(Post-Transient Power Flow)

Voltage Deviation at ABAJO 66kV Bus

-0.110

-0.100

-0.090

-0.080

-0.070

-0.060

-0.050

-0.040

-0.030

-0.020

-0.010

0 200 400 600 800 1000 1200

Net IPP Import (MW)

Vo

ltag

e D

evia

tio

n (

Ab

ajo

69k

V u

nd

er C

on

tin

gen

cy)

(pu

)

Threek-Peak-Sigurd Out

IPP Bipole Out Full RAS

WECC N-2 Criteria

Line Loading of Sigurd - Three Peak 345kV Line

1600

1700

1800

1900

2000

0 200 400 600 800 1000 1200

Net IPP Import (MW)

Sig

ura

d-T

hre

ePea

k L

ine

Flo

w (

Am

s)

Huntington-Pinot-SpanishFork DLO

IPP Bipole Out - Full RAS

Line Emergency Rating

* IPP DC Will Operate with Maximum “Net IPP Import” of 600MW – Limited by Line Overload

Page 21: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

21

3. Determine Delay Generation Tripping

Accommodate possible DC restart sequence after a DC fault;

To lessen the stress by possibly using a less stressful turbine or boiler trip.

DC Fault Restart 1st 2nd 3rd

Deionization Time (ms) 225 325 425

Deionization Time (cycles) 13.5 19.5 25.5

Cumulative (cycles) 13.5 33 58.5

Simulate CAS time (cycles) (trip unit)

18 40 70

Generator Tripping

Methods

Time to 0 Output

Comments

Electrical Trip < 10 CyclesMost Stressful on

boilers and turbines

Boiler Trip~ 42 Second

s

15 second Delay 20 seconds to

100MW, 6 second to

breaker Open

Turbine Trip~ 23 Second

s

15 second delay, 2 seconds to

100MW, 6 seconds to

breaker Open

Page 22: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

22

3. Stability Plot for Loss of Bipole with Restart (for DC Fault Only)

(Worst Stressed Condition)Trip 1 Unit after First Restart Failed and Second Unit after the Second Restart FailedTrip Both Units after First Restart Failed

* CAS Will Trip Units after 1 Restart Attempt Failed

Page 23: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

23

3. Stability Plot for Loss of Bipole with Delayed CAS Generation Tripping for Lower IPP DC Schedule

IPP DC Schedule 1500MW IPP DC Schedule 1400MW

* CAS Will Delay Generation Tripping for IPP DC Schedule 1400MW or Less

Page 24: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

24

3. Delayed CAS Generation Tripping for Loss of 1 Pole

Short Term Overload Capability of IPP DC

Page 25: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

25

3. Delayed CAS Generation Tripping for Loss of 1 Pole (IPP AC Fault Trip 1 Unit + MWC

Generations)Delayed Tripping

* CAS Will Delay Generation Tripping for Loss of 1 Pole

Fast TrippingNo RAS

Page 26: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

26

3. IPP CAS Generation Tripping Level Operating Nomogram for Bipole Operation for the Loss of

Bipole

IPP STS Operating Nomogram(For Loss of Bipole in Bipolar Operation)

(Studied Cases Marked)

1908

1907

1830

1796 1795

1758

1758

0

400

800

1200

1600

2000

2400

0 400 800 1200 1600 2000 2400

IPP + MWC Gen (MW)

ST

S D

C S

ched

ule

(MW

)

(Nomogram Limit) Trip all Gen - 1 RS

Trip 1 unit + MWC gen - 1RS

Trip MWC Only - Delayed

NoRAS

0 Import Line

Trip All Gen - Studied

Trip All Gen - Studied

Trip 1 Unit + MWC gen - Studied

No RAS - Studied

Unreliable Operating Region

Limited by Post-transient Sigurd-Three Peaks Flow (A) (Limit 1800A)

IPP STS Operating Nomogram(For Loss of Bipole in Bipolar Operation)

0

400

800

1200

1600

2000

2400

0 400 800 1200 1600 2000 2400IPP + MWC Gen (MW)

ST

S D

C S

ched

ule

(M

W)

(Nomogram Limit) Trip all Gen - 1 RS

Trip all Gen - Delayed

Trip 1 unit + MWC gen - 1RS

Trip 1 unit + MWC gen - Delayed

Trip MWC Only - Delayed

NoRAS

Linear (0 Import Line)

Unreliable Operating Region

Page 27: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

27

3. IPP CAS Generation Tripping Level Operating Nomogram for Bipole Operation for the Loss of

1 Pole

IPP STS Operating Nomogram(For Loss of 1 Pole in Bipolar Operation)

(Studied Cases Marked)

0

400

800

1200

1600

2000

2400

0 400 800 1200 1600 2000 2400

IPP + MWC Gen (MW)

STS

DC

Sch

edul

e (M

W)

Trip 1 unit + MWC gen- Delayed

Trip MWC Only - Delayed

No Ras

0 Import Line

Trip 1 Unit + MWC - Studied

Trip MWC - Studied

NoRas - Studied

Unreliable Operating Region

Limited by Post-transient Voltage

Deviation of 5% at Abajo 69kV bus

IPP STS Operating Nomogram(For Loss of 1 Pole in Bipolar Operation)

0

400

800

1200

1600

2000

2400

0 400 800 1200 1600 2000 2400

IPP + MWC Gen (MW)

STS

DC

Sch

edul

e (M

W)

Trip 1 unit + MWC gen- Delayed

Trip MWC Only - Delayed

No Ras

Linear (0 Import Line)

Unreliable Operating Region

Page 28: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

28

3. IPP CAS Generation Tripping Level Operating Nomogram for Mono-pole Operation for the Loss of

1 Pole

IPP STS Operating Nomogram(For Loss of Pole in Mono-polar Operation)

0

400

800

1200

1600

2000

2400

0 400 800 1200 1600 2000 2400IPP + MWC Gen (MW)

ST

S D

C S

ched

ule

(M

W)

Trip 2 unit + MWC gen - Delayed

Trip 1 unit + MWC gen - Delayed

Trip MWC Only - Delayed

NoRAS

Linear (0 Import Line)

Unreliable Operating Region

IPP STS Operating Nomogram(For Loss of Pole in Mono-polar Operation)

(Studied Cases Marked)

0

400

800

1200

1600

2000

2400

0 400 800 1200 1600 2000 2400

IPP + MWC Gen (MW)

ST

S D

C S

ched

ule

(M

W)

Trip 2 unit + MWC gen - Delayed

Trip 1 unit + MWC gen - Delayed

Trip MWC Only - Delayed

No Ras

0 Import Line

Trip 2 units VDev -Studied

Trip 1 Unit - Thermal Limit Studied

Trip 1 Unit - VDev Limit Studied

No RAS - Studied

Unreliable Operating Region

Limited by Post-transient Sigurd-Three Peaks Flow (A) (Limit 1800A) and Voltage deviation 5% at Abajo

Page 29: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

29

3. Study Summary

IPP DC limited to net AC Import capability of 600MW under maximum Utah South export conditions

CAS will Trip Units after 1 Restart Attempt Failed CAS will Delay Generation Tripping for IPP DC

Schedule 1400MW or Less CAS will Delay Generation Tripping for Loss of 1

Pole - Limited by Voltage Deviations

Page 30: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

30

4. System Design

Page 31: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

31

4. System Design

Design Philosophy

1. Meet the System Studies Guidelines2. Insure Redundancy3. Reduce the Hardware4. Centralize the Logic

Page 32: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

32

4. System Design

Following the guidelines established by the system studies were the driving force in the design of the IPPSE.

All parameters of the studies have been met which also allowed for a simpler more efficient design.

Only 1 operational failure in 3 years is allowed.

Page 33: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

33

4. System Design

Page 34: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

34

4. System Design

The Bipole Controls are a completely redundant

Mach 2 Control System designed by ABB. All protection actions are routed through this

control system. The IPPSE Logic is fully contained in this system

thus reducing the system hardware requirements. All remedial outputs are generated from this

control system.

Page 35: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

35

4. System Design The remedials from the IPPSE Logic

have been simplified into two outputs.

Monopolar Out Bipolar Out

Based on these two signals and the Nomograms, all IPPSE actions are appropriately taken.

Page 36: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

36

4. System Design

Generator Trip Remedials

Electrical Trip (86 Lockout)

Turbine Trip

Boiler Trip

Page 37: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

37

4. System Design

IPP Digital Microwave System

Original analog system installed 1985

System was replaced with Harris Stratex (now Aviat Networks) digital microwave radios in 2004

LADWP operated and maintained

Page 38: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

38

4. System Design IPP Microwave Power Redundancy Propane Back up Generators 24 VDC Power Plants

Page 39: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

39

4. System Design

IPP Microwave One Line

Page 40: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

40

5. Arming Function

Page 41: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

41

5. Arming Function

Overview:

Arming is automated by an application running in LADWP’s energy management system.

Nomograms, called “charts”, specify the arming level.

Each chart has a series of curves that provide arming levels as a function of IPP net generation (including Milford generation) and the DC line flow.

The application selects charts based on monitored power system conditions and the specific trigger being armed.

Page 42: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

42

5. Arming Function

Charts:

One curve per remedial action.

Arming is a function of net gen vs. DC flow.

Top-most curve provides DC flow limit.

Added remedial actions will require an increase in the number of curves per chart.

Page 43: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

43

5. Arming Function

Chart Sets:

There may be up to five triggers for remedial actions.

Each trigger has its own arming for remedial action.

Therefore, there is one chart per trigger.

The set of charts for the triggers is a “chart set”.

Page 44: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

44

5. Arming Function

Chart Set Selection:

There are multiple chart sets to accommodate varying system conditions.

Chart sets are functionally organized into rows and columns.

Columns are selected based on monitored line flows.

Rows are selected based on line outages and IPP operating modes.

Page 45: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

45

5. Arming Function

Chart Set Selection (cont’d):

Original design provided for 24 columns.

Although they no longer affect arming, three power flows are still monitored: Pacific AC Intertie, Arizona–California, and Utah South.

The system study indicates nomogram sensitivity to Utah South power flow, so use of multiple columns may become necessary.

Page 46: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

46

5. Arming Function

Imports:

Chart shows a 600-MW import limit.

IPP AC lines have 1317-MW import capability.

Chart is worst-case scenario.

Other cases allow more imports.

Page 47: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

47

5. Arming Function

Import Example:

A 72-MW on Sigurd–Three Peak may allow a 400-MW in imports.

This can be implemented via multiple columns or via dynamic shifting of affected curves.

Page 48: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

48

5. Arming Function

Summary of Arming Function Changes:

Increase in the number of curves per chart due to increase in number of remedial actions.

Decrease in the number of charts per chart set due to decrease in the number of triggers.

Increase in the number of chart set columns and/or addition of dynamic curve adjustments due to varying AC import limits depending on Utah South flow.

Page 49: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

49

6. Monitoring and Operation

Page 50: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

50

6. Monitoring and Operation

Overview:

LADWP’s Energy Control Center (ECC) and IPP both have monitoring capability.

The arming application runs at the ECC, but either site can arm manually.

Except for automatic arming, the RAS operation occurs entirely at IPP, but is monitored by both sites.

The slides that follow show monitoring and operation as seen at the ECC.

Page 51: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

51

6. Monitoring and Operation

The interface at the ECC includes the following displays:

Curves & DC Limits Columns & Charts Panel Status (i.e. RAS Status) AnnunciatorsThese displays are summarized and shown in the slides that follow.

Page 52: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

52

6. Monitoring and Operation

Curves & DC Limits:

Shows summary data in upper-right corner.

Provides for viewing and update of curves and charts.

Shows remedial action selected for each active chart.

Shows DC limits from charts and other nomograms.

Page 53: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

53

6. Monitoring and Operation

Curves & DC Limits Display

Page 54: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

54

6. Monitoring and Operation

Changes to Curves & DC Limits:

System studies do not show a need for separate nomograms for DC limits from Utah North, Utah South, or Northeast/Southeast flows.

DC limit for power flows flow will be inherent in the contingency arming limit from the selected charts.

Dynamic offsets to curve data, when implemented, will be shown on this display.

Page 55: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

55

6. Monitoring and Operation

Columns & Charts:

Shows power flows for chart set column selection.

Shows line status.

Shows plant operating mode.

Shows column and chart set selection in the summary data in the upper-right corner.

Page 56: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

56

6. Monitoring and Operation

Columns & Charts Display

Page 57: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

57

6. Monitoring and Operation

Changes to Columns & DC Charts:

Column selection is no longer influenced by Pacific AC Intertie and Arizona–California flows.

Additional columns may be needed to model the effects of Utah South flow on AC import capability.

Page 58: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

58

6. Monitoring and Operation

Panel Status:

The RAS is currently implemented at IPP via redundant hardware systems called “panels”.

Each arming control point is wired to operate both panels from a single control operation.

Each panel independently reports its status.

Arming controls can be issued via the arming application or manually via SCADA control actions.

Page 59: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

59

6. Monitoring and Operation

Panel Status (cont’d):

Provides a control and pair of state indications for each combination of trigger and remedial action that may be armed.

Provides for manual entry of an arming pattern when in MANUAL mode and shows the application-determined arming pattern when in AUTOMATIC mode.

Shows panel status values. Shows triggers actuated. When a trigger is

actuated, the RAS will execute any remedial actions armed for that trigger.

Page 60: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

60

6. Monitoring and Operation

Panel Status Display

Page 61: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

61

6. Monitoring and Operation

Changes to Panel Status:

The application currently implements the arming matrix by using an obscure feature to control multiple arming state points with a single control operation. (This is much quicker than using time-consuming discrete control actions for each arming state point.)

This set of arming state points to specify remedial actions for each trigger will be replaced with a single analog point for each trigger that specifies the remedial actions to execute.

The RAS implementation will be part of the DC control system.

Page 62: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

62

6. Monitoring and Operation

Annunciator Displays:

The RAS trigger inputs are actually aggregations of multiple triggering inputs from relay and DC control systems.

For this reason, the RAS trigger inputs are in some places called “super triggers”.

The annunciator displays show each trigger input and identify the super triggers that it activates.

Page 63: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

63

6. Monitoring and Operation

Annunciator Display 1

Page 64: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

64

6. Monitoring and Operation

Annunciator Display 2

Page 65: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

65

6. Monitoring and Operation

Annunciator Changes:

According to system studies, many of the triggering inputs will no longer require remedial actions.

Only triggering inputs for monopole and bipole blocks will continue to be relevant.

The number of super triggers needed will reduce from five to two.

The triggering inputs no longer requiring remedial action may be retained on the annunciator displays for reference.

Page 66: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

66

6. Monitoring and Operation

Summary of Monitoring and Operation Changes:

The RAS function will be located in the DC control system.

Arming will be specified via analog arming levels rather than discrete digital states.

Arming may use real-time power flow to bias affected nomogram curves.

Additional remedial actions are being added. The inputs that affect remedial action arming and

execution are being updated according to study results.

Page 67: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

67

7. Operating Procedure for

Abnormal System Conditions

Page 68: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

68

7. Operating Procedures for Abnormal System Conditions

The RAS operates incorrectly (failure to operate or false operation)

As soon as the IPPSE has failed or operated improperly, generation and DC flows will be curtailed to a point where remedial action is not required. The condition will be maintained until repairs can be made or the RAS is proven to be stable.

Page 69: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

69

7. Operating Procedures for Abnormal System Conditions

One part of a redundant RAS system is unavailable so that complete redundancy is no longer assured

Personnel will be dispatched immediately to work on the unavailable system to restore it to operational status as soon as possible. Curtailment is not required in this condition.

Page 70: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

70

7. Operating Procedures for Abnormal System Conditions

When unscheduled, or unplanned and not coordinated, unavailability of the subject RAS (complete loss of RAS) impacts operation

Generation and DC flows will be curtailed to a point where RAS is not required or until such time as the RAS becomes available again.

Page 71: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

71

7. Operating Procedures for Abnormal System Conditions

When a partial or total loss of input data required for arming decisions

All input data required for arming originates from Intermountain Converter Station (ICS) and Intermountain Generating Station (IGS). The ICS operator will manually set the proper arming as directed by the Energy Control Center (ECC). The ICS operator has the ability to determine and set proper arming independent of ECC.

Page 72: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

72

8. Commissioning, Maintenance and Testing

Page 73: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

73

8. Commissioning, Maintenance, and Testing

Commissioning Testing of the IPPSE Logic will begin

during the Factory Acceptance Tests in Sweden. This will begin in May 2010.

Commissioning of the new system will begin in October of 2010 when the first Mach 2 control comes on line.

The IPPSE system will be fully operational by Mid December 2010.

Page 74: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

74

8. Commissioning, Maintenance, and Testing

Maintenance All critical components such as

communication links, test switches and computers are monitored by the new Alarm Reporting and Monitoring System (ARMS)

Emergency maintenance can be done on line without degrading the system. Only redundancy will be lost.

Scheduled Maintenance is every 2 years.

Page 75: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

75

8. Commissioning, Maintenance, and Testing

Testing Testing will be “End to End”, from ECC to the

Generator and Milford Intermountain Line 1 Blocking Switches.

Each arming level in the Nomograms will be tested to assure that the proper remedial is sent to the blocking switch.

All intermediate signals, remedial outputs and trip signals will be recorded for analysis.

Page 76: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

76

9. Conclusions

Page 77: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

77

9. Conclusions

System Studies Guidelines

System studies were extensive and the results were incorporated into the system design.

All system hardware and software is monitored for correct operation.

Page 78: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

78

9. Conclusions

Redundancy

All Protections, Control Systems, Communication Systems and Monitoring Systems are completely redundant.

Page 79: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

79

9. Conclusions

Reduce and Simplify the Hardware

The input triggers have been reduced from 19 to 2.

The Nomograms have been reduced from 38 to 3.

Page 80: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

80

9. Conclusions

Centralize the Logic

All IPPSE Logic is now contained in the HVDC Mach 2 control system.

Page 81: 1 INTERMOUNTAIN POWER PROJECT STABILITY ENHANCEMENT (IPPSE) SYSTEM Presentation to WECC Remedial Action Scheme Reliability Subcommittee April 30, 2010

81

Questions?