1 final bgfcl report (r) · resettlement plan (rp) for drilling of 4 new wells (titas # 23-26) and...
TRANSCRIPT
1
Resettlement Plan
Document: Resettlement Plan Document Stage: Draft Project Number: 38164-013 Date: September 2013
BAN: Natural Gas Access Improvement Project
Southwest Area Integrated Water Resources Planning and Management
Prepared by Bangladesh Gas Fields Company Limited (BGFCL) for the People’s Republic of Bangladesh and the Asian Development Bank. This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
2
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
i
BANGLADESH GAS FIELDS COMPANY LIMITED (A Company of Petrobangla )
Birashar, Brahmanbaria-3400.
Resettlement Plan (RP) Gas Seepage Control and Appraisal
& Development of Titas Gas Field
PREPARED BY
ENVIRO CONSULTANTS LTD
35/A, 2nd Floor, Monipuripara, Tejgaon
Dhaka-1215, Bangladesh.
Tel: 880-2-8141439, Fax: 880-2-8141439
Cell: 01713117822, 01715327465
E-mail: [email protected]
Web: www.enviroconsultant.org
September 2013
ii
Abbreviation
ADB Asian Development Bank
AH Affected Household
APs Affected Persons
BGFCL Bangladesh Gas Fields Company Ltd
CCL Cash Compensation under Law
DC Deputy Commissioner
EA Executing Agency
EPs Effected People
FHHs Female Headed Households
GRC Grievance Redress Committee
GOB Government of Bangladesh
HHs Affected households
IOL Inventory of Loss
IR Involuntary resettlement
LA Land Acquisition
LAP Land Acquisition Proposal
LAO Land Acquisition Officer
M&E Monitoring and Evaluation
MOL Ministry of lands
MOPEMR Ministry of Power, Energy and Mineral Resources
PCC Public Consultative Committee
PD Project Director
PIC Project Implementation Committee
PIU Project Implementation Unit
PVAT Property Valuation Advisory Team
RAC Resettlement Advisory Committee
RAP Resettlement Action Plan
RP Resettlement Plan
R&R Resettlement & Rehabilitation
RV Replacement Value
SES Socio-economic Survey
UP Union Parishad
RU Resettlement Unit
iii
Table of Contents
Executive Summary ……………………………………………………. 1
1.0 INTRODUCTION……………………………………………………… 6
1.1 Project Background ............................................................................................... 6
1.2 Project Description ................................................................................................ 6
1.3 Project Location .................................................................................................... 6
1.4 Measures to Minimize Impact ............................................................................... 8
1.5 Objectives of the Resettlement Plan (RP) .............................................................. 8
2.0 SOCIO ECONOMIC INFORMATION OF THE PROJECT AREA ............... 10
2.1 Project Scope and Location ................................................................................. 10
2.2 Socio-Economic Scenario ................................................................................... 10
2.2.1 Socio-Economic Survey (SES) ............................................................................ 10
2.2.2 Economic and Social Conditions of Affected People .......................................... 10
3.0 FINDINGS OF RESETTLEMENT CENSUS SURVEY ................................... 16
3.1 Resettlement Census Survey ............................................................................... 16
3.2 Findings of Resettlement Census Survey ............................................................. 16
3.2.1 Type of Project Impacts ...................................................................................... 16
3.2.2 Impact on Agricultural Land ........................................................................................ 17
3.2.3 Ownership Pattern ............................................................................................................ 17
3.3 Impact on Income and Livelihood ....................................................................... 17
3.4 Project Impact on Poor, Indigenous People, Ethnic Minorities and Other
Vulnerable Groups Including Women ................................................................. 18
3.4.1 Socially Vulnerable Groups .............................................................................................. 18
3.4.2 Gender Impacts of the Project .......................................................................................... 18
4.0 RESETTLEMENT POLICY FRAMEWORK & ENTITLEMENT MATRIX.19
4.1 Review of Relevant Legislation........................................................................... 19
4.1.1 Acquisition and Requisition of Immovable Property Ordinance II, 1982 ........................ 19
4.1.2 Land Acquisition/Requisition Procedures ........................................................................ 20
4.1.3 Objection Against Requisition .......................................................................................... 22
4.1.4 Compensation for Requisitioned Property ........................................................................ 22
4.1.5 Matters to be considered in Determining Compensation .................................................. 23
4.1.6 Problems of Valuation and Compensation ....................................................................... 23
iv
4.1.7 Time Frame ...................................................................................................................... 24
4.2 LA Act and GOB Draft National Policy .............................................................. 24
4.3 ADB Policy on Involuntary Resettlement ............................................................ 26
4.3.1 Compatibility of GOB Provision and Asian Development Bank (ADB) Policy .............. 27
4.3.2 Comparison of ADB Policy on Involuntary Resettlement and National Policies ............ 28
4.4 Eligibility Policy and Entitlement Matrix ........................................................... 29
4.4.1 Eligibility Criteria ............................................................................................................ 29
4.4.2 Compensation and Entitlement Policy ............................................................................. 29
4.5 Valuation of Affected Properties ........................................................................ 31
4.6 Disposal of Acquired Properties ......................................................................... 31
5.0 CONSULTATION, PARTICIPATION AND DISCLOSURE .......................... 32
5.1 Consultation Process ........................................................................................... 32
5.2 Consultation Scope and Issues ............................................................................ 32
5.3 Identification of Key Stakeholders ...................................................................... 33
5.4 Feedback from Community Consultation ............................................................ 33
5.5 Disclosure of the RP ........................................................................................... 35
5.6 Plans for Further Consultation and Community Participation ............................. 35
6.0 INSTITUTIONAL FRAMEWORK AND IMPLEMENTATION SCHEDULE 37
6.1 Introduction ....................................................................................................... 37
6.2 BGFCL ............................................................................................................... 37
6.3 Other Agencies Involved in the Process ............................................................. 38
6.3.1 Deputy Commissioners (DCs) ......................................................................................... 38
6.4 Grievance Redress Mechanism............................................................................ 38
7.0 RESETTLEMENT COST ESTIMATE AND BUDGET ................................... 42
7.1 Cost Estimates ................................................................................................... 42
7.1.1 Land Cost .......................................................................................................................... 42
7.1.2 Compensation for Tenant Farmers ................................................................................... 43
7.1.3 Training for income generating activities ......................................................................... 43
7.1.4 Training for income restoration of wage labour .. ............................................................ 43
7.1.5 Assistance to Vulnerable Group ....................................................................................... 44
7.1.6 Compensation for Loss of Agricultural Income from Trees and Crops .......................... 44
7.2 Budget ................................................................................................................ 44
v
8.0 IMPLEMENTATION SCHEDULE ................................................................... 46
8.1 RP Implementation Schedule .............................................................................. 46
8.2 Implementation Schedule .................................................................................... 46
8.3. Pre-requisites of a Successful Implementation of RP ........................................... 48
8.4. Temporal Parameters of the RP ........................................................................... 48
8.4.1 Date of Start of Implementation ....................................................................................... 48
8.4.2 Date of Vacating the Work Site ....................................................................................... 48
8.4.3 Date of Completion of the Acquisition and compensation Process ................................. 48
9.0 IMPLEMENTATION SCHEDULE ................................................................... 49
9.1 Need for Monitoring ........................................................................................... 49
9.2 Monitoring at EA Level ...................................................................................... 50
9.3 Reporting Requirements ...................................................................................... 50
9.3.1 Plan for Internal Monitoring ............................................................................................ 50
9.3.2 Plan for External Monitoring ............................................................................................ 51
9.4 Time Frame and Reporting Requirements ........................................................... 52
Map 1 Brahmanbaria District Map Showing Project Location
List of Table
Table 1 Project Scope & Location
Table 2 Distribution of land ownership of the Affected Persons
Table 3 Owner, Tenant, Labor Holdings and others Household
Table 4 Occupation of head of households
Table 5 Literacy Rate
Table 6 Land ownership characteristics of Female headed households
Table 7 Distribution of Households income
Table 8 Sanitation System of the Project Area
Table 9 Arsenic contamination of ground water
Table 10 Households with Physically Retarded/ Crippled Persons
Table 11 Residential status of the AP households
Table 12 People Response the Disease
Table 13 Types of losses experienced by the Affected Households (HHs)
Table 14 Affected for Share Cropper
Table 15 Affected for Wage Labour
Table 16 Vulnerability Status of Affected Households
Table 17 Comparison of ADB Resettlement Policy with National Policies
Table 18 Compensation and Entitlements
Table 19 Summary of the Public Consultations
vi
Table 20 Value of land of Chhatian, Malihata, Jangilsar, Suhilpur and Sarail
Mouza According to Market Rate, Brahmanbaria based on Rate of LA
Department
Table 21 Compensation of tenant Farmer
Table 22 Training for Share Cropper
Table 23 Training for Wage labour
Table 24 Financial Assistance to Vulnerable Group
Table25 Summary Resettlement Budget
Table 26 Monthly Progress Report Format for Resettlement Monitoring
Table 27 Monthly Progress Report Format for Resettlement Monitoring
List of Photo
Photo 1Socio-economic Survey with stakeholder at Malihata village
Photo 2Socio-economic Survey with stakeholder at Malihata
Photo 3 Consultation with stakeholder at Budhol Union Parishad
Photo 4Consultation with stakeholder at Budhol Union Parishad
List of Figure
Figure 1 Location of the Sarail Project Area Well No 23 and 24
Figure 2 Organogram of Bangladesh Gas Fields Company Ltd. (BGFCL)
Figure 3 Organogram of the Office of the Deputy Commissioner (DC)
ANNEX
Annex-I Survey Questionnaire
Annex-II Mouza Map of Titas well no 23 and 24
Annex-III Mouza Map of Titas well no 25 and 26
Annex-IV List of Land Owner
Annex-V List of Participant in the Consultation Meeting
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
1
Executive Summary
Background of the Project
Bangladesh Gas Fields Company Limited (BGFCL) is a company of Bangladesh Oil, Gas &
Mineral Corporation (Petrobangla). The Company is the largest gas producer in the country
in national sector. To increase gas production BGFCL has planned to carry out drilling of 4
new wells (well nos. 23-26) and installation of 2 nos. process plants with associated facilities
in two different locations at Titas gas field under financial assistance of ADB. One of them
(well # 25 & 26 and one process plant) located at mauza Chhatian, Jangilsar, Malihata &
Suhilpur under Sadar upazila and other (well # 23 & 24 and one process plant) is located at
mauza Sarail, upazila Sarail both are under district Brahmanbaria. For implementation of the
project 15 acres of land need to be acquired, which are mainly agricultural land. A
resettlement plan (RP) is required to submit to ADB for this project. Major works planned
under the scope of the project are (i) Drilling of 4(four) appraisal cum-development wells
(Titas #23, 24, 25, & 26) and (ii) Installation of two nos. process plants at Titas Gas Field
under Sadar Upazila & Sarail Upazila, Brahmanbaria.
Land Acquisition Impact
For implementation of the project works will require 15 acres of land which cost around Tk.
196.5million and all the land is agricultural and 66 household will affected through land loss,
income from sharecrops loss under the project intervention.
Measure to Minimized the Impact
Efforts have been made by BGFCL in order to minimize the impacts and disruption of
livelihood. BGFCL has taken maximum possible extent and adequate measure to reduce the
adverse impact and which has been incorporated in the planning design of the project to
mitigate the unavoidable adverse impacts.
Objectives of the Resettlement Plan (RP)
The overall objectives of these work/services are to conduct detailed Resettlement Plan (RP)
and to obtain clearance from ADB. Resettlement Plan to be carried out as per ADB’s
Environmental policy (2009) and law/policy of Govt. of Peoples Republic of Bangladesh for
implementation of the project.
Stakeholder Participation and Disclosure Plan
This draft ResettlementPlan (RP) will be disclosed to the affected persons and submitted to
ADB for review and approval. Compensation and other assistances will have to be paid to
APs prior to displacement or dispossession of assets or 6 months prior to commencement of
construction activities whichever comes first. The RP will be summarized in an information
booklet in Bangla and disclose to APs.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
2
Matters to be Considered in Determining Compensation
In determining the amount of compensation, the Deputy Commissioner will take into
consideration the following factors:
• Cost of standing crops or trees on the land/property at the time of taking its possession by
the Deputy Commissioner.
• Dislocation from his other properties, if any.
• Injuries/adverse effect on his other properties or his income.
• Reasonable income of the property in between the service of notice and possession of the
property taken by the Deputy Commissioner.
Compensation and Entitlement
An Entitlement Matrix has been prepared on the basis of census and socio-economic survey
conducted in July 2013. It identifies the categories of impact based on the census and shows
the entitlements for each type of loss. The matrix describes the units of entitlements for
compensating the lost assets and various resettlement benefits. Cash Compensation under
Law (CCL) for lost assets (land) will be accorded to the owners through the DC as per market
value assessed through legal procedure. The resettlement benefit for indirect losses and
difference between replacement value and the CCL will be paid by BGFCL directly to the
APs.
Table Compensation and Entitlements
Type of loss Entitled Persons(s) Entitlements
1. Loss of agricultural
land
Legal owner(s) of
land as determined by
the DC,
and or determined by
the court
Value of land at current market price of the
equivalent replacement land. The DC office
determines the compensation amount based
on yearly average of recorded sale value
plus 50% additional cash compensation.
Refund of registration cost incurred for
replacement land purchase at the
replacement value.
Any difference between the awarded value
and the replacement value at the cut-off-
date (on the date of issuance of notice under
section 3 of Acquisition Act, 1982) will be
paid to APs as a cash grant.
APs will be provided with all possible
assistance to identify and purchase
replacement land.
APs severely affected by loss of agricultural
land (i.e., losing more than 20% of total
land holding) will receive a cash grant of
Tk.5000/- per family or Tk. 2000 per
decimal of concerned land, whichever is
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
3
lower. Suitable candidates will also be
provided with free training on income
employment.
2. Lose of access by
tenants/sharecroppers
to agricultural land
for crops production.
Farmers leasing in or
share cropping the
land that is defined to
be acquired for the
project at the time of
the socio-economic
survey.
No compensation for land.
One –time cash grant of Tk.5000/- per
family or Tk. 2000/-per decimal of
concerned land, whichever is lower.
Suitable candidates will also be provided
free training on income generating activities
and a subsistence allowance during the
training period. If necessary, access to credit
facilities to start self-employment will be
provided.
3. Loss of wages
income.
Persons engaged in
wage labor in
agriculture or non-
agriculture sectors in
the affected areas
whose means of
livelihood have been
affected.
One-time cash grant of Tk. 5000/-and
Wage employment with contractors and / or
training in income generating activities. If
necessary, access to credit facilities will be
provided to start self-employment activities.
A subsistence allowance will be provided
during the training period.
4. Loss of standing
crops
Compensation for one
year’s crop value to
crop owner
Advance notice to harvest crops.
Cash compensation equivalent to the market
value of one year’s income from the crops.
5. Vulnerable groups Members of
vulnerable groups
such as the landless,
very poor, female-
headed households or
households of the
elderly, physically
impaired or disabled
One-time cash grant of Tk.10000/- per
family
Provision of a land purchase grant for
landless households.
6. Unforeseen impact Concerned impacts Determined as per policy on unique
Findings at detailed design stage
Cut-off Date
An entitlement matrix for different categories of people affected by the project has been
prepared. People moving in the project area after the cut-off date will not be entitled to any
assistance.
After issuance of notice under section 3 by the DC and census cut-off date for non-
titleholders or a similar designated date declared by BGFCL, joint verification of the
acquired properties will be carried-out by the requiring and acquiring bodied.
All APs will be entitled to compensation and resettlement assistance based on severity
(significance) of impacts. Nevertheless, eligibility to receive compensation and other
assistance will be limited by the cut-off date. The cut-off date for compensation under law
(Ordinance II of 1982 with amendments) is considered for those identified on the project
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
4
right of way land proposed for acquisition at the time of service of notice under Section 3 or
joint verification by DC whichever is earlier. The cut-off date of eligibility for resettlement
assistance under this RP is the commencement date of the census which is the 2nd
July 2013.
The absence of legal title will not bar for APs from compensation and assistance.
Grievance Redress Monitoring Mechanism
Grievance Redress Committees (GRC) will be established for the subproject with
representation from the Executing Agency (EA), APs (including vulnerable groups), Local
Government Engineering Department (LGED) and private consultant. Other than disputes
relating to ownership rights under the court of law, the GRC will review grievances
involving all resettlement benefits, relocation, and other assistance forwarded by the
Resettlement Unit (RU) or APs. Grievances will be redressed within 2-4 weeks from the date
of lodging the complaints.
The grievance redress activities will be monitored by the GRC to be formed similar to PCC.
In effect, the GRC will work closely with the Affected Persons (APs) or group to identify the
grievances and redress the same in consultation with other members of the committee as well
as the APs. In this project land acquisition, crop damage, income losses etc. will be
compensated paid to the APs. Grievances will be settled with their full representation in
GRCs constitutes by BGFCL, local elected representative and AP representative. Grievance
will be redress within a month from the date of lodging of complaint.
Budget
Based on the above a budget provision has been made to cover all land acquisition,
compensation, and rehabilitation costs for the project. The budget provision was made in the
project Proforma in the amount of Tk. 196 million. In estimating land acquisition cost, last
one year’s average sale rates of different types of land in the project jurisdiction were
collected from the concerned sub-registry offices. These rates are sale value plus 50% as per
GoB policy of involuntary resettlement (compulsory nature of acquisition).
Summary Resettlement Budget
Cost in Taka
Loss of income of share croppers 60,000
Training cost of share croppers 168,000
Training for income restoration of wage labour 168,000
Compensation for Vulnerable 140,000
Crop Compensation for one year 60,000
Fees for External Monitoring 200,000
Tenant farmer 60,000
Land Acquisition (LA) Cost with Premium 189,009,450
Miscellaneous expenses for land acquisition @ 3% 5,670,284
195,5,35,734
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
5
Monitoring and Evaluation
The internal monitoring will be carried out by the project office in order to oversee the
performance of the resettlement plan implementation. This is often based upon a card system
kept in the monitoring office recording the entitlements due to and received by each affected
household. The card system can be manual or computerized.
The EA will established an external M&E to ensure complete and objective information.
Post-evaluation of resettlement committee is an integral part of the project cycle.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
6
1.0 INTRODUCTION
1.1 Project Background
Bangladesh Gas Fields Company Limited (BGFCL) is a company of Bangladesh Oil, Gas &
Mineral Corporation (Petrobangla). The Company is the largest gas producer in the country
in national sector. To increase gas production BGFCL has planned to carry out drilling of 4
new wells (well nos. 23-26) and installation of 2 nos. process plants with associated facilities
in two different locations at Titas gas field under financial assistance of ADB. One of them
(well # 25 & 26 and one process plant) located at mauza Chhatian, Jangilsar, Malihata &
Suhilpur under Sadar upazila and other (well # 23 & 24 and one process plant) is located at
mauza Sarail, upazila Sarail both are under district Brahmanbaria. For implementation of the
project 15 acres of land need to be acquired, which are mainly agricultural land. A
resettlement plan (RP) is required to submit to ADB for this project.
Major works planned under the scope of the project are (i) Drilling of 4(four) appraisal cum-
development wells (Titas #23, 24, 25, & 26) and (ii) Installation of two nos. process plants at
Titas Gas Field under Sadar Upazila & Sarail Upazila, Brahmanbaria.
1.2 Project Description
Implementation of the project comprises the following major components:
(i) Drilling of 4 (four) appraisal cum-development wells (Titas # 23, 24,25 & 26) and
(ii) Installation of two nos. process plants at Titas Gas field under Sadar Upazila & Sarail
upazilla, Brahmanbaria.
1.3 Project Location
Bangladesh Gas Fields Company Limited (BGFCL) has planned to carry out drilling of 4
new wells (well nos. 23-26) and installation of 2 nos. process plants with associated facilities
in two different locations at Titas gas field under financial assistance of ADB. One of them
(well # 25 & 26 and one process plant) located at mouza Chhatian, Jangilsar, Malihata &
Suhilpur under Sadar upazila and other (well # 23 & 24 and one process plant) is located at
mouza Sarail upazila Sarail both are under district Brahmanbaria. For implement this project
15 acres of land will be acquired, which are mainly agricultural land BGFCL need to submit
Resettlement Plan (RP) to ADB for this project. Mouza maps shown in Annex II and III.
All the four wells will produce total 120 MMSCFD natural gas and each well of the 4 wells
(Well no 23-26) will produce 30 MMSCFDwhich will facilitate a total flow of additional
natural gas supply to the national grid. Gas from the wells will be used for producing mainly
electricity which in turn will drive industries contributing to national GDP. Implementation
of the project will develop socio-economic environment of the area including poverty
alleviation by creation opportunities through industrial development. Besides, many unskilled
local people can be employed temporarily during project implementation period. This will
lead to the enhancement of skill of the personnel engaged in physical execution of the project
which in turn would help execution of similar projects in future.
Since there are no structure in the propose location of the project hence, implementation of
project physical works will not cause adverse involuntary resettlement impacts entailing
acquisition of land, other assets and displacement. The census survey undertaken brought
forth that the proposed project requires acquisition of about 15 acres of land –the all of which
comprises of agricultural land and no homestead and commercial assets. A total of 66
households constituting of 322 persons would be affected as a result of the project.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
7
Map 1 Brahmanbaria District Map Showing Project Location
Figure 1. Localtion of the Sarail Project Area Well No 23 and 24
Project area
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
8
1.4 Measures to Minimize Impact
Land is a vital component of the project for drilling of wells and installation of process
plants. For the purpose of minimizing the impact on affected people (APs), BGFCL has put
special attention in planning process to ensure minimum displacement or resettlement of
people during the development of gas well drilling site and installation of process plants.
BGFCL considered various options to decide on the most economical and effective
alternative to stay within minimum disturbance and avoid homestead resettlement. The
organization shared its knowledge and experience with local communities for minimizing
impact. Following measures have been adopted in order to minimize the ensuing Project
impact.
� Avoid archaelogical, religious structures and educational institution in determining
the access road for the project.
� As far as practicable, the alignment has avoided houses (permanent or temporary). In
particular, special care was taken to avoid any human settlement clusters.
� At all road crossing, prescribed clearance requirements will be strictly adhered to.
� The proposed alignments will be submitted to the Road & highway Department and
Brahmanbaria Upazila Parishad.
1.5 Objectives of the Resettlement Plan (RP)
The overall objectives of these work/services are to conduct detailed Resettlement Plan (RP)
and to obtain clearance from ADB. Resettlement Plan to be carried out as per ADB’s
Environmental policy (2009) and law/policy of Govt. of Peoples Republic of Bangladesh for
implementation of the project.
BGFCL will legally acquire the land by compensating owners for loss of land, and of other
assets such as trees and loss of income, under the legislative framework for land acquisition
in Bangladesh. The adverse social and resettlement impact will be mitigated in accordance
with ADB safeguard policies. This Resettlement Plan (RP) has been formulated to assist the
affected households (AHs) to restore their livelihoods and socio-economic conditions to their
pre-project status. The RP addresses both land acquisition and resettlement issues within the
legal framework of the Government of Bangladesh (GOB) and ADB`s policy on Involuntary
Resettlement.
The objectives of this RP is to mitigate all unavoidable impacts caused due to drilling of
wells, process plant, excess road and to provide guideline on people compensation and
assistance as per the norms of ADB. The Plan has been prepared on the basis of survey
finding of census survey on Involuntary Resettlement (2013). More particularly, the Plan
aims to make sure that:
� Affected persons/squatter gets compensation for their loss.
� Rehabilitation are identified and relevant facilities and services are provided.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
9
� Assistance is provided so that at least same level of wellbeing is achieved with the
project without it.
This Resettlement Plan (RP) will be disclosed to the affected persons and submitted to ADB
for review and approval. Compensation and other assistances will have to be paid to APs
prior to displacement or dispossession of assets or 6 months prior to commencement of
construction activities whichever comes first.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
10
2.0 SOCIO ECONOMIC INFORMATION OF THE PROJECT AREA
2.1 Project Scope and Location
Major works planned under the scope of the project are (i) Drilling of 4 (four) appraisal cum-
development wells (Titas # 23, 24,25 & 26) and (ii) Installation of two nos. process plants at
Titas Gas field under Sadar Upazila & Sarail Upazilla, Brahmanbaria.Project Scope &
Location Mouza, Upazilla, and District is shown in Table 1.
Table 1 Project Scope & Location
Project Components Mouza Upzila District Division
Drilling of 4 New Wells
and Installation of 2 nos.
process plant
Chhatian Sadar Brahmanbaria Chittagong
Malihata Sadar Brahmanbaria Chittagong
Jangilsar Sadar Brahmanbaria Chittagong
Suhilpur Sadar Brahmanbaria Chittagong
Sarail Sarail Brahmanbaria Chittagong
Source: Field visit
2.2 Socio-Economic Scenario
2.2.1 Socio-Economic Survey (SES)
This section covers some selected but relevant socio-economic aspects of the project area
relating to farm and non-farm households, tenancy, landless and agriculture labor holding and
the tenure system. This section also highlights the agriculture pattern/ practices in the project
affected area. The socio-economic scenario is derived from analysis of data collected from
socio-economic survey (SES) carried out across the project area.
he SES was conducted in the sample affected households using a household questionnaire.
The activities of SES were carried out to:
� Obtain demographic and other data information about pre-project incomes, productive
activities, and likely impacts of land acquisition on economy of the APs and the
community, land ownership and tenural arrangements, land-use patterns, occupations,
income and economic interdependency among the APs, and women’s economic
activities and income, and
� Establish a baseline for subsequent monitoring and evaluation of the implementation
of the RP and its impacts.
The findings obtained from SES are described in the following sections. The project area is
mainly used for agricultural activities. Table 2 presents summary of the land holding type of
the land owners or those who have interest in the land.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
11
Table 2 Distribution of land ownership of the Affected Persons
Mouza Agricultural land Holding in percentage
Virtually
landless (%)
(0.05-0.49
Acre)
Merginal
(0.50-1.49
Acre)
Small
(1.5-2.45
Acre)
Medium(2.5-
5.49 Acre)
Large (5.5+
Acre
Chhatian 25.00 33.34 25.00 8.33 8.33
Malihata 25.00 75.00
Jangilsar 27.27 36.36 9.09 27.28
Suhilpur 16.66 50.00 16.66 16.66
Sarail 30.76 38.48 15.38 7.69 7.69
Source: Field visit
The operation pattern of the households of the project area shown in Table 3. A little more
than one third of the farmers cultivate their own land. The other owners excepting one or two
operate the land themselves by engaging piecemeal labors on contract and no labor in
engaged on wage terms.
Table 3 Owner, Tenant, Labor Holdings and others Household
Mouza Owner Holdings Others
No. % No. %
Chhatian 8 72.72 3 27.28
Malihata 7 63.63 4 36.37
Jangilsar 2 66.67 1 33.33
Suhilpur 8 66.67 4 33.33
Sarail 9 69.23 4 30.77
Tenant farmers are also going to be affected although the numbers are very small. The tenant
farmers will receive compensation for their lost crops and will be provided with rehabilitation
assistance to restore their income-earning capacity.
There are three types of tenancy system in Bangladesh:
� 50% crop will be shared by the tenant if the tenant provides 50% of the total inputs in
the land.
� 33% of the crops will be shared by the tenant if the land owner provides the inputs;
and
� On a contract basis- the tenant provides a certain amount of money to the land owner
for utilizing or cultivating the land and enjoys the total return. Tenancy is done
sometimes on a seasonal basis.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
12
2.2.2 Economic and Social Conditions of Affected People
2.2.2.1 Occupation
Occupation indicates sources of income from work as well as social status. Business and
farming are the main occupation of the heads of households. Service has been appeared to be
the most important occupation for the head of holds. The total situation is summarized in
Table 4.
Table 4 Occupation of head of households
2.2.2.2 Literacy
The literacy rate of the head of households is 100 percenton total population excluding
Children below 5years of age is 35%. The situtations of the two groups are shown in Table 5.
Table 5 Literacy Rate
Education level Head of Households
No of persons Percent
Primary 23 65.71
SSC 3 8.57
HSC 2 5.72
Degree 3 8.57
Masters 4 11.43
Total 35 100
Occupation Head of Households
No of persons Percent
Business 15 30
Construction Worker 1 2
Farmer 14 28
Foreign Labor 1 2
House wife 3 6
Labor 1 2
Service 7 14
Student 3 6
Unemployment 4 8
Thikader 1 2
Total 50 100
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
13
2.2.2.3 Female Headed Households
During the survey it was found that the land ownership of the female households
demonstrates that the women have significant land of their own and they will loss only a
Medium fraction of their land. It appears that they are not in the vulnerable group. The female
headed households in the acquisition area are shown in the Table 6.
Table 6 Land ownership characteristics of Female headed households
Number of
households
Total land ownership (dec) Land lost (dec) Percentage
3 327 129 39.45
2.2.2.4 Household Income
There are five households which have low income at such a level that may be treated as
vulnerable. They have no income source other than agriculture. Various level of income
range is presented in Table 7. Tk. 5000-10000/month income level people household about
40%.
Table 7 Distribution of Households income
Income range No. % Avg. Total Exp.
≤= 5,000 5 10 3800 19000
5,000 - 10,000 20 40 8350 167000
10,000 - 15,000 11 22 13909 153000
15,000 - 20,000 7 14 20000 140000
≥= 20,000 7 14 30714 215000
2.2.2.5 Cropping Pattern
Most of the agricultural land of the project area are three cropping system. Their main crop is
rice. In Sarail mouza some of the farmers cultivate jute and vegetables.
2.2.2.6 Sanitation System
The SES finding shows in Table 8 that all most the people are used hygienic latrine. 66
percent of the target population use sanitary system and 33 percent use ring slab system.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
14
Table 8 Sanitation System of the Project Area
Sanitation No of persons Percent
Sanitary 33 66
Ring Slab 16 32
Katcha 1 2
Total 50 100
2.2.2.7 Water Facilities for Household Use
100% of the population use tubewell water for drinking and cooking purpose. In Sarail Union
are the most vulnerable for Arsenic contamination of ground water but Bodul and Suhilpur
Union are not found Arsenic contamination and shown in Table 9. They use pond water for
bathing and domestic uses. They have no facility of water supply system.
2.2.2.8 Cooking Fuel
The women use straw, leaves of plant, wood, husk, and cow dung for their cooking. In Sarail
few of households use supply gas but rest of the households use domestic fuel materials.
2.2.2.9 Households with Physically Retarded/ Crippled Persons
The proportion of physically or psychologically handicapped people is a significant around
18% of the project area. Table 10 shows the Households with Physically Retarded/ Crippled
Persons in the project area.
Table 10 Households with Physically Retarded/ Crippled Persons
Households with physically
retarded/ crippled persons
No of persons Percent
9 18
2.2.2.10 Residential Characteristics
The survey finding shows that all of the land owners live in houses built on their homestead
land. Their house type is given in the following Table 11.
No 36 72
Not Tested 1 2
Yes 12 24
Not Known 1 2
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
15
Table 11 Residential status of the AP households
Occupation Pacca Semi Pacca Tin
Business 7 4 4
Construction Worker 1
Farmer 3 2 8
Foreign Labour 1
House wife 1 2
Labour 1
Service 5 2
Student 1 2
Unemployment 1 1 2
Thikader 1
2.2.2.11 Health Condition
Surrounding of the Project area Common cold and Influenza are the main diseases the APs
suffer from. In Sarail Union almost all of the people first contacts with hospital, in other case
most of the people are first contact with village doctors.Table 12 shows the People Response
the Disease.
Table 12 People Response the Disease
Name of the Institutions/ person Hospital MBBS Quack Village Doctor
Percentage 30 2 2 66
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
16
3.0 FINDINGS OF RESETTLEMENT CENSUS SURVEY
3.1 Resettlement Census Survey
The resettlement census survey is a comprehensive survey that covered 100% households
getting affected by the project, irrespective of their entitlement or ownership status. This
survey was undertaken along the project by the consultant and trained survey team in July
2013.
The objective of the census survey was to identify the affected persons and generate an
inventory of social and economic impacts on the project affected persons, socio-economic
profile of the project affected people, their perceptions about the project and rehabilitation
and resettlement options. A questionnaire was prepared to collect detailed information on the
socio-economic status of the affected persons and households.
The data gathered during the Inventory of Loss (IOL) has been entered onto an electronic
database which identified each Affected Household (AH) and the way they are impacted and
losses they will incur. The objective of the IOL was to establish a detailed inventory of the
households and of physical assets likely to be affected by the project; develop a
socioeconomic profile of the AHs and affected persons (APs) there in, through the
participatory IOL and consultation meetings and obtain the views of AHs on likely benefits
and adverse effects of the project as well as their views on what measures need to be included
in the project to ensure mitigation of all adverse effects on them. The IOL also serves as a
benchmark for monitoring and evaluation.
3.2 Findings of Resettlement Census Survey
The census survey identified that a total of 66 legal HHs will be affected.
3.2.1 Type of Project Impacts
The census survey brought forth that the project will necessitate acquisition of 15 acres of
land- the majority of which is agricultural land. In total 66 households will be affected under
the project intervention. The detailed list of affected households is enclosed as Annex II.
Types of losses experienced by the Affected Households (HHs) is shown in Table 13.
Table 13 Types of losses experienced by the Affected Households (HHs)
Type of losses Total Number of Affected HHs Extent of loss
Agricultural land 66 15 acres
Source: Resettlement Census Survey 2013
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
17
3.2.2 Impact on Agricultural Land
Land will be permanently acquired for drilling of gas well, laying of gathering line and
installation of processing plant with access road. The census survey and interactions with the
affected households brought forth that a total of 15 acres of agriculture land belonging to a
total of 66 households would be affected as a result of the project. The analysis brought forth
that all the affected (15 acres) comprised of irrigated land which is used for cultivation.
3.2.3 Ownership Pattern
All the affected 66 households incurring impact on their agriculture land comprise of
titleholders and hold legal titles to the affected land.
3.3 Impact on Income and Livelihood
Loss of income from crops lost by farmers leasing in or share cropping lands will be
compensated with one-time cash grants of Tk. 5000 per family or Tk. 2000 per decimal of
affected land, whichever is lower. Suitable candidates will also provide free training on
income generating activities and a subsistence allowance during the training period. If
necessary, access to credit facilities to start self-employment will be provided. Landowner
cultivators will cash compensation equivalent to the market value of one year’s income from
the crops.
Person engaged in wage labor in agriculture or non-agricultural sectors whose means of
livelihood have been affected by acquisition of the land or property are dependent on will be
entitled to a onetime cash grant of Tk. 5000 and priority for wage employment with
contractors and/ or training in income generating activities, as well as a subsistence allowance
during the training period. If necessary, access to credit facilities to start a self-employment
will be provided.Table 14 shows the Affected Share Cropper.Table 15 shows the affected
wage labour.
Table 14 Affected for Share Cropper
Number of share cropper No. of Days
12 7
Table 15 Affected Wage Labor
Number of wage labour No. of Days
12 7
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
18
3.4 Project Impact on Poor, Indigenous People, Ethnic Minorities and Other
Vulnerable Groups Including Women
3.4.1 Socially Vulnerable Groups
Certain groups of population by virtue of their socio-economic realities are considered
socially vulnerable and thus in need of special consideration so that they can benefit from the
development project. These groups include:
� Those who are below the poverty line
� Those who belong to tribal groups
� Female-headed households
� Elderly and
� Disabled persons
Of the above groups, except for indigenous peoples and ethnic minorities, all the other above
enumerated vulnerable groups were identified in the project area during the course of the
census survey amongst the 66 households. The census survey identified a total of 14
households as vulnerable households and shown in Table 16.
Table 16 Vulnerability Status of Affected Households
Taking into account the socio-economic vulnerabilities of the affected households, specific
provisions will need to be incorporated in the RP to ensure that they are not marginalized in
the process of development.
3.4.2 Gender Impacts of the Project
Gender analysis was undertaken during the course of the resettlement census survey to look
into the current status and needs of the women in the study area and the potential impact of
the project. The Consultant team also interacted with Female Headed Households (FHHs)
and other women to take their views and perceptions on the project impacts. The interaction
and the resettlement survey did not bring forth any adverse gender impacts.
The project is anticipated to have direct adverse impacts on a total of 3 FHHs. All these 3
FHHs comprise of housewives. Two households shall incur impact on their agriculture land.
However, looking into their economic condition, they will now become vulnerable or
impoverished as a result of that.
Type of Vulnerability No. of Affected Households (HHs)
Below Poverty Line 5
Disabled Nil
Elderly 6
Female Headed Households (HHs) 3
Scheduled Tribes (STs) Nil
Grand Total 14 Vulnerable Affected HHs
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
19
4.0 RESETTLEMENT POLICY FRAMEWORK & ENTITLEMENT MATRIX
4.1 Review of Relevant Legislation
4.1.1 Acquisition and Requisition of Immovable Property Ordinance II, 1982
Implementation of development projects involves acquisition and/or requisition of large tracts
of land necessitating displacement of people as well as removal of crops and trees. This
causes great hardship to the affected people economically, socially and environmentally. In
most cases, the affected people are not the direct beneficiaries of the development projects.
The acquisition and/or requisition of property laws has been considered to be harsh. In recent
years this has attracted attention of planners and sociologists both within and outside the
country. The result of this attention is that resettlement or income rehabilitation; provisions
are being associated with all land requisition measures of this Project.
The first Land Acquisition Law was enacted in 1894 and was amended and expanded a
number of times until the partition of British India in 1947. “The Acquisition and Requisition
of Immovable Properties Ordinance” enacted in 1982 (with a few amendments) is the final
version of the relevant legal framework for acquisition of land in Bangladesh.
Requisition of immovable property is made in Bangladesh under the Acquisition and
Requisition of Immovable Property Ordinance 1982. This Ordinance replaced the Land
Acquisition Act, 1894 and the East Bengal (Emergency) Requisition of Property Act of 1948.
This Ordinance is (with a few exceptions, which will be discussed later) governing all cases
of acquisition and requisition by the government of immovable property for any public
purpose or in the public interest. It may be noted that contrary to the previous Act i.e. Act
XIII of 1948 this Ordinance deals only with immovable property (Land Acquisition /
Requisition Act I of 1894 also dealt with only immovable property i.e. land).
Notwithstanding the repeal of the 1894 and 1948 Land Acquisition Acts all proceedings and
matters relating to the acquisition and requisition of property under these Acts (including
applications and appeals pending before any Arbitrator or Court) continue to be heard or
disposed of as if these Acts were still in force.
Below follows a review of the most important features of the 1982 Ordinance. Wherever
necessary, references are also made to relevant administrative regulations and instructions. In
accordance with the Ordinance, the legal process is initiated by an application from the
requiring Body, which can be any governmental or non-governmental agency.
The Ordinance covers the case of temporary requisition (in part III) of property for a public
purpose or in the public interest. With prior approval of the government the DC can decide on
the requisition of any property for a period of two years. No prior approval will however be
required in case of emergency requisition (Sec-18). But with prior approval of the GOB
requisition period may extend more than two years.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
20
The DC may take possession of the requisition after, serving the requisition order. The
amount of compensation will be equal to the estimated rent which would have been payable
for the use and occupation of the property if it had been taken on lease for that period plus
compensation for estimated expenses for vacating and re-occupying the property (Sec-20). If
a person is not satisfied with the amount of compensation, or there is a dispute over
ownership, the DC may deposit the money in the Public Account (Sec-21).
A person who does not accept the award made by the DC may submit an application to the
Arbitrator for revision of the award within 45 days from the date of notice of the award (Sec
28). The Arbitrator is a Government appointed Judicial Officer, not below the rank of
Subordinate Judge (Sec. 27). A decision determined by the Arbitrator is higher than that
decided by the DC. An additional compensation for delay at the rate of 10 percent per annual
may be paid (Sec 32). As per amendment of 1994 the Arbitrator cannot defer the
compensation amount more than 10 percent of the DC's Awards (Sec-31).
An appeal against the decision by the Arbitrator can be made to an Arbitration Appellate
Tribunal, which consists of a member appointed by the government from among persons who
are or have been District Judges. A decision of the said Tribunal shall be final (Sec- 34).
4.1.2 Land Acquisition/Requisition Procedures
Land acquisition/requisition requires interaction between, on the one hand, the Requiring
Body (RB), which normally is a national infrastructure development government agency,
such as the Water Development Board (BWDB), Bangladesh Power Development Board
(BPDB), etc. in the present case the BGFCL. And, on the other hand, the Acquiring Body
(AB) which normally is the Ministry of Land which delegates some of its authority to the
Deputy Commissioner at the district level or the Commissioner at the divisional level.
The division of responsibility between the Requiring Body and the Acquiring Body is in
broad terms that the Requiring Body provides the technical input and the Acquiring Body the
legal input in the land acquisition/requisition process. It is the Requiring Body which must
ensure that the project, which is the basis for the acquisition/requisition of land, is approved
by the authorities and that funds are available. The Requiring Body must also justify the need
for land and other property on the basis of field surveys including detailed engineering design
and prepare all necessary documents required for decision making. At this stage the
Acquiring Body processes the land acquisition/requisition cases including determination of
the level of compensation and payment to the concerned people. When land
acquisition/requisition is completed, the land is handed over to the requiring Body.
The legal aspects of the land acquisition/requisition process starts with the RB submitting an
application to the Deputy Commissioner with a request to borrow land for a specific purpose.
The procedures for dealing with land requisition matters are established in a Government
Memo dated October 1985. The proposal must contain the following items:
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
21
� A Pro-forma indicating the amount of land required, a time-table for the requisition of
land and the purpose for which the land is to be borrowed;
� A Layout Plan, which shows the location of the project on a map;
� A Site Plan, showing the alignment in red ink on a Mouza map;
� A Land Schedule showing classification of land and ownership of plots to be
borrowed;
� Certificate of Minimum Requirement, issued by the Requiring Body stating that the
quantity of land proposed for requisition is the absolute minimum for a proper
implementation of the project; and
� Administrative Approval, comprising a copy of approved Project Pro-forma.
After receiving the proposal, the DC will arrange for field verification, jointly with the staff
of the Requiring Body. This includes a classification of the land to be borrowed and an
identification of trees and standing crops of value, which are involved.
The Requiring Body's application is then submitted to the District Land Allocation
Committee (DLAC) or the Divisional Land Allocation Committee (depending on the amount
of land required) for the allocation of land. The latter may in turn refer the proposal to the
Central Land Acquisition Committee (CLAC) for a decision. After clearance by the relevant
land Allocation Committee the DC issues the preliminary notice and, if required, hears
objections against the proposed requisition. If there are no objections, the DC may give the
formal approval for land requisition under the condition that the area to be borrowed covers
less than ten standard bighas. However, if there are objections and/or the requisition is above
ten standard bighas of land, the DC submits the application to the Commissioner or the
Ministry of Land for the final approval. The DC's submission shall be accompanied by the
DLAC's clearance, the DC's report on the objection petitions and information on the number
of households likely to be affected. In respect of project executed by the Upazila Parishad.
The government has authorized the Divisional Commissioner to make the final decision even
if the land to be borrowed is above 10 bighas.
After the final approval by the DeputyCommissioner (as the case may be), the case is referred
back to the DC for the assessment of compensation and the identification of the owner of the
plots to be borrowed. With the final approval to borrow land, the requiring body must place
required funds for payment of compensation with the DC. If the Requiring Body fails to do
that within sixty days from the date of receipt of the estimate for DC, for no fault of the
person interested all proceedings shall stand abated and a declaration to that effect by the DC
will be published in the official Gazette (Sec. -12).
Compensation is paid by the DC's office. There are no specific rules on where or in which
form compensation should be paid. Normally smaller amounts appear to be paid in cash
whereas larger amounts are paid by cheques to persons who are identified by the Chairman or
Members of the Union Parishad or by Gazetted Officers. In case the rightful owner of the plot
of land cannot be identified or there is conflict over ownership or the distribution of
compensation funds are deposited in the Public Account of the Republic.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
22
In case the person does not accept the award of compensation the person can go for
Arbitration according to the provisions of the land Acquisition Ordinance of 1982 or the
Emergency Land Acquisition Act of 1989.After payment of compensation the temporary
possession of the land is formally transferred to the Requiring Body.
4.1.3 Objection Against Requisition
An aggrieved party has the right to raise objection to the decision of the Deputy
Commissioner to borrow his property. To exercise this right the party in question will have to
refer his objection in writing within 15 days after the publication of the
acquisition/requisition notice. The Deputy Commissioner will then give the objector the
opportunity of being heard either in person or by an agent. After hearing the objection and
making further inquiry, if necessary, the Deputy Commissioner will prepare a report in this
connection within a period of the month.
In case the land/property to be borrowed exceeds 50 standard bighas, the Deputy
Commissioner will submit the record of the proceedings along with his report to the
Government (in the Ministry of Land I Property Minister) for a decision. When it is not so,
the recorded proceedings and the report will go to the Divisional Commissioner for a
decision. The decision in either case will be final.
Once decision has been made for borrowing any property the Deputy Commissioner will
serve notice in the prescribed manner to the effect that the property in question is to be
borrowed and that possession of the same will be taken and that claims to compensation by
the concerned parties can be made to him (DC). Such notice and will give detailed particulars
of the property in question and ask the concerned parties to appear before the Deputy
Commissioner in person, not before 15 days after publication of the notice, to claim
compensation according to rules. Such notice will also be served upon the occupier and all
other sharers if any of the property in question.
4.1.4 Compensation for Requisitioned Property
The Deputy Commissioner (DC), after examining the claims of compensation, will make an
award of compensation for the property. He will also divide the compensation among all
other sharers, if there is any.
Award of Compensation by DC.
(1) Where any property is requisitioned, there shall be paid compensation, the amount of
which shall be determined in the manner and in accordance with the principles set out
in the section 20.
(2) The DC shall, after giving the persons interested an opportunity of being heard in
respect of their respective interests in the property and the amount and particulars of
their claims to compensation for such interests and having regard to the provisions of
sub-section (5), make an award of:
(a) the compensation in the manner as may be prescribed; and
(b) the apportionment of the said compensation among all the persons known or
believed to be interested in the property, of whom, or of whose claims, he has
information.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
23
(3) The award made by the DC shall, except as hereinafter provided, be final.
(4) The DC shall give immediate notice of his award to the persons interested.
(5) The amount of compensation payable for requisition of any property shall consist of:
(a) a recurring payment, in respect of the period of requisition, of sum equal to the rent
which would have been payable for the use and occupation of the property if it had
been taken on lease for that period, and
(b) such sum, if any, as any be found necessary to compensate the persons interested for
all or any of the following matters, namely:
� expenses on account of vacating the requisitioned property;
� expenses on account of re-occupying the property upon release from
requisition; and
� damages, other than normal wear and tear, caused to the property during the
period of requisition, including the expenses that may have to be incurred for
restoring the property to the condition in which it was at the time of
requisition.
(6) Where any property is kept under requisition for more than two years, the DC shall
revise his award regarding the amount payable as compensation under sub-section
(5)(a)
4.1.5 Matters to be considered in Determining Compensation
In determining the amount of compensation, the Deputy Commissioner will take into
consideration the following factors:
• Cost of standing crops or trees on the land/property at the time of taking its possession by
the Deputy Commissioner.
• Dislocation from his other properties, if any.
• Injuries/adverse effect on his other properties or his income.
• Reasonable income of the property in between the service of notice and possession of the
property taken by the Deputy Commissioner.
4.1.6 Problems of Valuation and Compensation
The practice of not registering inherited land and property in the name of the present owner;
in combination with an outdated and disorganized land record system means that the
identification of the recipients of compensation becomes very time consuming. The imperfect
land record system also provides scope for manipulations.
In many reported cases, payment is not made in full, even if there is an agreement between
the parties. A field survey reported that nearly 90 percent of the concerned households
incurred extra legal expenses. In the assessment of land acquisition for the construction of
Jamuna Multipurpose Bridge, it was reported that the recipients had to pay the officials
around ten percent of the awarded compensation as a service charge.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
24
Non-payment or delayed payment of compensation is, however, not only due to a slow
functioning of the district administration. The policy of disbursing government funds for land
acquisition in three or four installments, spread out over the year, means that the district
administration may not have sufficient funds available when payment is due.
The property owners incur high transaction expenses for travelling to and from the district
office to claim the rights and to receive compensation. Objections against acquisition are
often heard and payment of compensation is normally done in the district town.
4.1.7 Time Frame
(a) Payment of compensation must be made before the authority takes possession of the
property (Ordinance 1982).
(b) Compensation must be paid or deposited within a period of one year from the date of decision of requisition. All proceedings shall stand abated on the expiry of that period (Ordinance 1982).
(c) Persons with interest or right over the property to be acquired have 10 days in the 1989 Act and 15 days in the 1982 Ordinance to submit claims for compensation.
The 1989 Act emphasizes quicker compensation by introducing the concept of provisional
compensation" which is to be determined within 10 days of the order of requisition Land can
be borrowed on payment of provisional compensation. However, the final compensation is to
be determined within three months from the date of requisition.
The administrative set up for land administration has two tiers under the Ministry of Land
Administration and Land. At the Divisional level there is an Additional Commissioner
dealing with land administration under the Commissioner. At the District level there is an
Additional Deputy Commissioner in charge of land administration. Under him there is at least
one land Acquisition Officer and several Assistant Land Acquisition Officers. The number of
officers depends on the size of the District Dhaka, as an example, has five Land Acquisition
Officers. Non-gazetted officers include Kanungos (normally two per district but more in
larger districts), surveyors, etc.
4.2 LA Act and GOB Draft National Policy
The legislative framework for the land acquisition in Bangladesh is the Acquisition and
Requisition of Immovable Property Ordinance of 1982 (Ordinance II of 1982), and the
subsequent amendments to the Ordinance. Under this Ordinance, the Government can acquire
any land, building, crop, trees and other properties on the land for any public purpose or in
the public interest. The philosophy underlying the Ordinance is that persons whose properties
are compulsorily acquired should be compensated at market/ replacement price of land and
property. Subsequent amendment in 1993 to the Ordinance increased the amount of
compensation from 25% to 50% on the assessed value of the property to match its
replacement value. Another significant amendment to the Ordinance was made in 1994 which
provides for payment of compensation to share-croppers for loss of income. The Ordinance,
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
25
however, only recognized the titled owner(s) of the property but the non-titled users (for
example, renters and illegal occupants/ squatters) are not eligible to any compensation.
The Deputy Commissioner (DC) processes land acquisition under the Ordinance and pays
compensation to the legal owners of the acquired land. The Ministry of lands (MOL) is
authorized to deal with land acquisition through the DCs. Khas (government owned land)
lands should be acquired first when a project acquires both khas and private land. If a project
acquires only khas, the land will be transferred through an inter-ministerial meeting following
the preparation of acquisition proposal submitted to DC/ MOL.
The landowner has to establish ownership by producing a record-of-rights in order to be
eligible for compensation under the law. The record of rights prepared under Section 143 to
144 of the State Acquisition and Tenancy Act 1950 (revised 1994) are not always updated
and as a result legal land owners have faced difficulties trying to “prove” ownership. The APs
must also produce rent receipt or receipt of land development tax, but this does not assist in
some situations as a person is exempted from payment of rent if the area of land is less than
25 bighas (3.37 ha).
The Government of Bangladesh has prepared a draft national policy on involuntary
resettlement, which is consistent with the general policy of the Government that the rights of
those displaced by development projects shall be fully respected, and persons being displaced
shall be treated with dignity and assisted in such a way that safeguards their welfare and
livelihoods irrespective of title, gender, and ethnicity.
The policy on involuntary resettlement recognizes that:
▪ All those displaced involuntarily by either projects or non-project impacts like erosion
and eviction must be resettled and rehabilitated in a productive and sustainable
manner.
▪ People who are resettled must be able, through their own efforts and/ or with support
as may be required, restoring or improving upon their level of living.
▪ Cash compensation shall be paid in development projects at replacement value to
those displaced for land and other assets acquired based on established prior
ownership and/ or user rights. In addition to cash compensation and resettlement, a
benefit sharing will be considered where feasible.
▪ Cultural and customary rights of people affected by projects are to be protected,
particularly those belonging to adivasis (indigenous people) and ethnic minorities.
▪ Gender equality and equity in all stages and processes of resettlement and
rehabilitation will be fully respected.
▪ Affected persons will be informed and consulted in a transparent manner, including
formal disclosure of project impacts and mitigation measures.
▪ Vulnerable groups, including landless, adivasis, poor women headed households,
physically challenged people, elderly and falling below the nationally defined poverty
line (by the government) displaced by project or non-project impacts, are entitled to
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
26
additional benefits and assistance in a manner that addresses their specific needs
related to socio-economic vulnerability.
▪ Similarly, affected persons and/ or businesses on government/ leased in land will be
eligible for compensation for loss of access to land and sites.
4.3 ADB Policy on Involuntary Resettlement
The Asian Development Bank’s (ADB) policies and operations manuals, in particular the
policy on Involuntary Resettlement (1995) and Operations Manual F2 on Involuntary
Resettlement (2003) recognize the address the R&R impacts of all the affected persons
irrespective of their titles and requires for the preparation of RP in every instance where
involuntary resettlement occurs. These ADB policies are the guiding policies to identify
impacts and to plan measures to mitigate various losses of the subproject.
ADB policy guidelines are summarized below:
� Involuntary resettlement (IR) should be avoided or reduced as much as possible by
reviewing alternatives to the project.
� Where IR is unavoidable, AP should be assisted to re-establish them and improve their
quality of life.
� Gender equality and equity should be ensured and adhered to
� AP should be fully involved in the selection of relocation sites, livelihood compensation
and development options at the earliest opportunity. RPs should also be prepared in full
consultation with AP, including disclosure of RP and project related information.
� Replacement land should be an option for compensation in the case of loss of land, in the
absence of replacement land, cash-for-land compensation should be an option available
each AP.
� Compensation for loss of land, structures, other assets and income should be based on full
replacement cost and should be paid promptly. This should include transaction costs.
� All compensation payments and activities should be completed prior to the
commencement of civil works.
� RP should be planned and implemented with full participation of local authorities.
� In the event of necessary relocation, APs should be assisted to integrate into host
communities.
� Common property resources and community/ public services should be provided to AP.
� Resettlement should be planned as a development activity for the AP.
� AP who does not have documented title to land should receive fair and just treatment.
� Vulnerable groups (households below the recognized poverty line; disabled, elderly
persons or female headed households) should be identified and given appropriate
assistance to substantially improve their living standards.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
27
4.3.1 Compatibility of GOB Provision and Asian Development Bank (ADB) Policy
A detailed review of the GOB Provisions and the ADB Policy on IR was undertaken wherein the
two were compared. Following the various National land laws on land acquisition & requisition,
the Draft National R&R Policy-2007, and incorporating ADB Policy on Involuntary Resettlement
(1995) and Operations Manual F2 on Involuntary Resettlement (2006), the basic principles for the
project will include the following elements:
i. The land acquisition and resettlement impacts on persons affected by the projects
would be avoided or minimized as much as possible through alternate design options.
ii. Where the negative impacts are unavoidable, the persons affected by the project and
vulnerable groups will be identified and assisted in improving or regaining their
standard of living.
iii. Information related to the preparation and implementation of resettlement action plan
will be disclosed to all stakeholders and people’s participation will be ensured in
planning and implementation. The resettlement action plan will be disclosed to the
APs in local language.
iv. Land acquisition for the project would be done as per the Acquisition and Requisition
of Immovable Property Ordinance 1982 and subsequent amendments during 1993-
1994. Additional support would be extended for meeting the replacement value of the
property.
v. The affected persons who does not own land or other properties, but have economic
interests or lose their livelihoods will be assisted as per the broad principles described
in this document.
vi. Before taking possession of the acquired lands and properties, compensation and
Resettlement & Rehabilitation (R&R) assistance will be paid in accordance with the
provisions described in this document.
vii. An entitlement matrix for different categories of people affected by the project has
been prepared. People moving in the project area after the cut-off date will not be
entitled to any assistance.
viii. Appropriate grievance redress mechanism will be established to ensure speedy
resolution of disputes.
ix. All activities related to resettlement planning, implementation, and monitoring would
ensure the involvement of women and other vulnerable groups.
x. Consultations with the APs will continue during the implementation of resettlement
and rehabilitation works.
xi. There should be a clause in the contract agreement that the construction contractor will
compensate any loss or damage in connection with collection and transportation of
borrow-materials.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
28
4.3.2 Comparison of ADB Policy on Involuntary Resettlement and National Policies
The comparison of ADB Resettlement Policy with National Policies is shown in Table 17.
Table17 Comparison of ADB Resettlement Policy with National Policies
ADB Policy Current National Policy and
Reference to Document or
Precedence
Involuntary resettlement should be avoided where
feasible
The same
Where population displacement is unavoidable, it
should be minimized by exploring all viable project
options
Yes, alternative placement or
alignment preferred
People unavoidably displaced should be compensated
and assisted, so that their economic and social future
would be generally as favorable as it would have
been in the absence of the project
That is the National Policy in
Bangladesh. This has been strictly
planned and being implemented in
JMBP and JBRLP projects.
People affected should be informed fully and
consulted on resettlement and compensation options
That is the view in Bangladesh
The absence of a formal legal title to land by some
affected groups should not be a bar to compensation.
In particular compensation should be paid to
households headed by women and other vulnerable
groups, such as indigenous peoples and ethnic
minorities, and appropriate assistance provided to
help them improve their status
It was not so before, but now this is
kept in view
As far possible, involuntary resettlement should be
conceived and executed as a part of the project
It was not before, but now it is kept
in view
The full costs or resettlement and compensation
should be included in the presentation of project costs
and benefits
That is the feeling now in
Bangladesh
Costs of resettlement and compensation may be
considered for inclusion in Bank loan financing for
the project
Yes, it is felt that it should be done.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
29
4.4 Eligibility Policy and Entitlement Matrix
4.4.1 Eligibility Criteria
All APs will be entitled to compensation and resettlement assistance based on severity
(significance) of impacts. Nevertheless, eligibility to receive compensation and other assistance
will be limited by the cut-off date. The cut-off date for compensation under law (Ordinance II of
1982 with amendments) is considered for those identified on the project road land proposed for
acquisition at the time of service of notice under Section 3 or joint verification by DC whichever
is earlier. The cut-off date of eligibility for resettlement assistance under this RP is the
commencement date of the census which is the 2nd
July 2013. The absence of legal title will not
bar for APs from compensation and assistance.
4.4.2 Compensation and Entitlement Policy
An Entitlement Matrix has been prepared on the basis of census and socioeconomic survey
conducted in July 2013. It identifies the categories of impact based on the census and shows the
entitlements for each type of loss. The matrix describes the units of entitlements for compensating
the lost assets, and various resettlement benefits. Cash Compensation under Law (CCL) for lost
assets (land) will be accorded to the owners through the DC as per market value assessed through
legal procedure. The resettlement benefit for indirect losses and difference between replacement
value and the CCL will be paid by BGFCL directly to the APs. The entitlement matrix detailing
the entitlements for the losses is presented in Table 18 below.
Table 18 Compensation and Entitlements
Type of loss Entitled Persons(s) Entitlements
1. Loss of agricultural
land
Legal owner(s) of
land asdetermined by
the DC,
and or determined by
the court
Value of land at current market price of the
equivalent replacement land. The DC office
determines the compensation amount based
on yearly average of recorded sale value
plus 50% additional cash compensation.
Refund of registration cost incurred for
replacement land purchase at the
replacement value.
Any difference between the awarded value
and the replacement value at the cut-off-
date (on the date of issuance of notice under
section 3 of Acquisition Act, 1982) will be
paid to APs as a cash grant.
APs will be provided with all possible
assistance to identify and purchase
replacement land.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
30
APs severely affected by loss of agricultural
land (i.e., losing more than 20% of total
land holding) will receive a cash grant of
Tk.5000/- per decimal of concerned land,
whichever is lower. Suitable candidates will
also be provided with free training on
income employment.
2. Lose of access by
tenants/sharecropp
ers to agricultural
land for crops
production.
Farmers leasing in or
share cropping the
land that is defined to
be acquired for the
project at the time of
the socio-economic
survey.
No compensation for land.
One –time cash grant of Tk.5000/- per
family or Tk. 2000/-per decimal of
concerned land, whichever is lower.
Suitable candidates will also be provided
free training on income generating activities
and a subsistence allowance during the
training period. If necessary, access to credit
facilities to star self-employment will be
provided.
3. Loss of wags
income.
Persons engaged in
wage labor in
agriculture or non-
agriculture sectors in
the affected areas
whose means of
livelihood have been
affected.
One-time cash grant of Tk. 5000/-and
Wage employment with contractors and / or
training in income generating activities. If
necessary, access to credit facilities will be
provided to start self-employment activities.
A subsistence allowance will be provided
during the training period.
4. Loss of standing
crops
Compensation for one
year’s crop value to
crop owner
Advance notice to harvest crops.
Cash compensation equivalent to the market
value of one year’s income from the crops.
5. Vulnerable groups Members of
vulnerable groups
such as the landless,
very poor, female-
headed households or
households of the
elderly, physically
impaired or disabled
One-time cash grant of Tk.5000/- per family
Provision of a land purchase grant for
landless households.
6. Unforeseen impact Concerned impacts Determined as per policy on unique
Findings at detailed design stage
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
31
4.5 Valuation of Affected Properties
The District Land Acquisition office takes help of relevant departments for determination of price
of land and other properties. Normally, the Public Works Department, the Forest Department,
Sub-Registrar’s Office, etc. are consulted. Land price from the Sub-Registrar’s Offices for
preceding one year from the date of serving notice under Section 3 is considered for valuation of
land. But in most cases, the price remains below the market rate. To ensure that the APs can
replace the lost property, the transacted price, recorded price, existing price and expected prices
are averaged to reach at Replacement Value (RV). For valuation of affected property, a legal body
called Property Valuation Advisory Team (PVAT), with representatives from acquiring body, and
Local Government Engineering Department (LGED) will be formed by Ministry of Power,
Energy and Mineral Resources (MOPEMR).
PVAT will representatives from the BGFCL as the Convener, and representatives from theLEGD
as the member and representative from the DC as member.A land and property valuation survey
based on the price recorded from formal and informal sources will determine the Replacement
Value (RV) of land and structure and be recommended by PVAT to MOPEMR. BGFCL will pay
the difference between RV and Cash Compensation under Law (CCL). Land purchase can’t be a
bar in playing the difference. Stamp duty and land registration fees will be paid to the AP, if
replacement land purchase is confirmed. Further, the teamwill assist in all possible ways,
including finding land for purchasing replacement land etc. After issuance of notice under section
3 by the DC and census cut-off date for non-titleholders or a similar designated date declared by
BGFCL, joint verification of the acquired properties will be carried-out by the requiring and
acquiring bodied. The Joint Verification Team records the quality and quantity of the affected
properties on the spot. A representative of the PVAT will also be present in the JVT as a member
of the team. The PVAT will computerize the Joint Verification data to be used for payment of
compensation/ resettlement benefits.
4.6 Disposal of Acquired Properties
After payment of compensation, APs would be allowed to take away the materials salvaged from
their dismantled houses and no charges will be levied upon them for the same. A notice to that
effect will be issued by BGFCL intimating that APs can take away the materials. Payment of
compensation will be made at least 1 month prior to the actual possession of the acquired
land.Further, all compensation and assistance will be paid to all APs prior to commencement of
civil works. The possession will be handed over to the contractor after payment of compensation/
assistance to the APs is completed.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
32
5.0 CONSULTATION, PARTICIPATION AND DISCLOSURE
5.1 Consultation Process
Experience indicates that involuntary resettlement generally gives rise to severe problems for
the affected population and they are generally apprehensive that they will lose their
livelihoods. These problems may be reduced. People are properly informed and consulted
about the project, about their situation and preference, and are allowed to make meaningful
choices. This serves to reduce the insecurity and opposition to the project which otherwise
are likely to occur. The objectives of stakeholder consultation process are thus:
� To involve the affected people
� To avoid social litigation
� To make people aware of the benefits and risks to ensure acceptability of the project
� To identify stakeholders and to hold group meeting with the stakeholders
� The consultation will be done in phased manner.
5.2 Consultation Scope and Issues
BGFCL and the Consultant identified the concerned stakeholders depending on the land
requirement for development of wells, and processing facilities along with access road.
During the consultations, efforts were made by the survey team to:
• Ascertain the views of the APs, with reference to land acquisition and project impacts.
• Understand views of the community on Resettlement and Rehabilitation (R&R) issues
and rehabilitation options.
• Obtain opinion of the community on issues related to the impacts on community
property and relocation of the same
• Finally, to establish an understanding for identification of overall developmental goals
and benefits of the project.
Key stakeholders particularly affected persons and community, were asked for their views on
the overall project overall as well as more specific discussion about their perception on land
acquisition process, compensation process and views on alternative options. Table 19 below
sums up the key outcomes of the public consultations.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
33
Table 19 Summary of the Public Consultations
Participants Topics/ Issues Discussed Response/ Expectation/ Suggestions of
Participants
UP
Chairman,Member
and affected
people.
� Land acquisition
� Positive and Negative
impact on environment
� Lack of education
institution
� Employment opportunity
� Gas Supply
All the participants expressed their
willingness to contribute their land for
successful implementation of the project.
They appealed for opportunity of using
project road to go into non-acquisition
land.
5.3 Identification of Key Stakeholders
BGFCL and the Consultant will identify the potential stakeholders based on area. BGFCL
follows the principle of minimum use of agricultural land. Furthermore, all measures will be
taken to ensure no disturbance to the homestead, properties and other structures along the
sensor lines. Attempts would be taken in such a way that no people will be affected due to
socio-economic development of the gas field areas.
The detailed identity and list of APs for the gas fields will be done by BGFCL during project
implementation. This list identifies the land owner list of APs and the specific entitlement
under the provision of Land Acquisition Act of Bangladesh as well as Asian Development
Bank guideline. On identification, the stakeholders will be consulted at different location.
Based on the response of the APs, compensation would be paid, for which adequate budget
provision exists.
5.4 Feedback from Community Consultation
Consultation with the affected community was undertaken on 02/07/2013 and the feedbacks
obtained from these are summed up below:
� All the participants expressed their willingness to contribute land for successful
implementation of the project.
� They demanded for supplying gas to all residents
� They requested for employment of un-employed persons in the area according their
qualification.
� They also appealed for opportunity of using project road to go in non-acquisition land.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
34
Photo 1 Socio-economic Survey with
stakeholder at Malihata village
Photo 4 Consultation with stakeholder at
Budhol Union Parishad
Photo 2 Socio-economic Survey with
stakeholder at Malihata village
Photo 3 Consultation with stakeholder
at Budhol Union Parishad
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
35
5.5 Disclosure of the RP
The process of public participation in the implementation of the RP will be assured through
consultation procedures. Consultation will be made through a Public Consultative Committee
(PCC). The PCC will be formed with the representation of relevant government agencies.
The committee will address any grievance raised by the APs within the framework of the
existing law of the country and the policies adopted by BGFCL and the guidelines of ADB.
A summary of this Resettlement Plan (RP) will be translated into Bangla and will be made
available to the affected people by BGFCL for review and comments on the policy and
mitigation measures by means of project-level Disclosure workshops prior to loan
negotiation. Copies of summary RP will also be made available at the local level public
offices to stakeholders for local inputs prior to award of civil work contract. The proceedings
of the disclosure workshop and the feedback received will be sent to ADB for review. The
summary of the final RP will also be disclosed on the ADB Website and BGFCL website.
Bangladesh Gas Fields Company Ltd. is the EA of the project and responsible for in
implementing this RP, will update, publish and distribute the booklet explaining the impact of
the project, compensation policies for APs, resettlement options/strategies for households,
and tentative implementation schedule of the project. Further steps will be taken (i) to keep
the affected persons informed about land acquisition plan, compensation policy and
payments, and (ii) to ensure that APs will be involved in making decisions concerning
relocation and implementation of the RP.
In case of change in project design thereby entailing change in resettlement impacts, are
evaluation and updating of this RP will be undertaken. The updated RP will be disclosed to
the APs, endorsed by the EA and will be submitted to ADB for approval prior to award of
civil works contracts for the subproject. The updated RP, not just the summary will be
disclosed to the APs as well as updated on the ADB website after ADB review and approval.
5.6 Plans for Further Consultation and Community Participation
The effectiveness of the R&R program is directly related to the degree of continuing
involvement of those affected by the project. Several additional rounds of consultations with
APs will form part of the project implementation. Executive agency will be conducting these
consultations during RP implementation, which will involve agreements on compensation,
assistance options, and entitlement package and income restoration. The consultation will
continue throughout the project implementation. The following set of activities will be
undertaken for effective implementation of the plan:
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
36
• The EA will conduct information dissemination sessions in the project area and solicit the
help of the local community/ leaders and encourage the participation of the AP’s in plan
implementation.
• During the implementation of RP and concerned BGFCL officers will organize public
meetings, and will appraise the communities about the progress in the implementation of
project works.
• Consultation and focus group discussions will be conducted with vulnerable groups like
women to ensure that the vulnerable groups understand the process and their needs are
specifically taken into consideration.
• In order to ensure participation of community a Public Consultative Committee (PCC) at
Thana (Upazila) level would be formed to supervise the compensation payment to APs.
The PCC would include representative of the Deputy Commissioner of Brahmanbaria
District, the respective Upazila Nirbahi Officer, local elected public representative of
BGFCL and representative of LGED in the area. Formation of such a PCC will be
functionally equivalent to Resettlement Coordination and Monitoring Committee
(RCMC) enunciated in the ADBs Resettlement guideline. Such committees are also vital
for enunciated in the project monitoring and implementation take place effectively and
that monitoring can provide feedback into project implementation.
• The PCC will supervise payment to APs which will include membership of AP
representatives. The PCC will visit points geographically close to APs for payments of
compensation.
• In addition, regular update of the program and resettlement component of the project will
be placed for public display at the project offices.
• Lastly, participation of APs will be further ensured through their involvement in the
Grievance Redress cell.
Lastly, EA through project office will maintain ongoing interactions will APs to identify
problem and undertake appropriate remedial measures
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
37
6.0 INSTITUTIONAL FRAMEWORK AND IMPLEMENTATION SCHEDULE
6.1 Introduction
This chapter deals with the main tasks and responsibilities of the institutions in planning,
negotiating, consulting, approving, coordinating, implementing, financing, monitoring and
evaluating land acquisition and resettlement. The responsible institutions are the Executing
Agency, Deputy Commissioner’s Office, Donor Agency, etc. In fact, these institutions will be
required to work jointly and in close cooperation with each other. Given the emphasis on this
cooperation and integration, development of an effective institutional framework is a must.
BGFCL will be the Executing agency (EA) of this project, DC and LAO will constitute legal
body who, on behalf of the Govt. will undertake the process of land acquisition and facilitate
implementation of the RP.
6.2 BGFCL
BGFCL will be the Executing Agency for the project, a Project Implementation Unit (PIU)
headed by a Project Director, at the head office that will be responsible for the overall
execution of the project.
The task/ responsibilities of the Project Director of BGFCL will include the following:
� Project planning and making provision of RP budget
� Review of RP report and making comments on the report
� Maintaining liaison with the different concerned Govt. Officials, donor agency and
the consultants
� Supervision of the tasks of the resettlement implementation committee
� Transfer of fund to the Deputy Commissioner (DC) in due time for meeting
acquisition compensation cost
� Contribute to the works of Public Consultative Committee (PCC)
� Motivation of APs
The Project Director would be in charge of the land acquisition and resettlement
management. He/ she will work in close coordination with the respective field-based offices
on day-to-day activities of the resettlement implementation. The PD through the field offices,
LA Office will execute and the LA and RP implementation work. He/she will also ensure
coordination between the relevant departments, the GRC, RAC, PVAT and the project
affected people (APs).
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
38
6.3 Other Agencies Involved in the Process
6.3.1 Deputy Commissioners (DCs)
The DCs have the power to acquire land and to assess compensation of property thus
acquired. The 1982 Ordinance provides the power to the DC, who conducts the acquisition
through the Land Acquisition Officer (LAO) of concerned districts. The LAO (or his/her
officers) along with BGFCL staff will conduct joint physical verification of property on the
land in accordance with the Land Acquisition Proposal (LAP) to be submitted by BGFCL as
soon as the detailed design and alignments for the projects interventions will be available.
The DC office is responsible for the entire acquisition process from notification to affected
households to award of compensation to owners of property and payments of compensation.
Upon fulfillment of criteria of the LA office (i.e. necessary documents to make payment) the
LA officials will prepare cheque and disburse to the EPs. If possible the LAO will disburse
cheque in the concern Union Parishad office in presence of the UP Chairman issuing prior
notice to the concern EPs. BGFCL shall liaise with DC office to complete the land
acquisition process in a timely fashion. However, the LAO will prepare estimates of LA and
request placement of fund from the BGFCL. The LAO will also share the award and payment
date with the BGFCL field office to facilitate processing of resettlement data.
6.4 Grievance Redress Mechanism
Grievance Redress Mechanism will be established to ensure stakeholders participation in the
implementation process. Through public consultations, the APs will be informed that they
have a right to grievance redress from the BGFCL. The APs can also call upon the support of
the RP Implementing committee engaged to implement the RP to assist them in presenting
their grievances or queries to the GRC. Other than disputes relating to ownership right under
the court of law, GRCs will review grievances involving all resettlement assistances,
relocation and other supports. Grievances will be redressed within a month from the date of
lodging the complaints.
The GRC will be formed Union level for any grievances involving resettlement benefits,
relocation, and other assistance. The GRC for each Union will comprise of the Project
Director BGFCL, RP implementing committee, one Local Elite, one representative of APs
and a legal Advisor as Observer to extent legal support to the committee.
The GRCs will be formed and activated during land acquisition process to allow APs
sufficient time to lodge complaints and safeguard their recognized interests. Where land
acquisition will not be involved but relocation of structures or vacating land from cultivation
will be required, the GRCs will facilitate resolution of complaints regarding categorization of
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
39
vulnerable affected persons, types of structures and eligibility for compensation and
assistance within the set guidelines and provisions of the resettlement plan. Any complaints
of ownership or other suits, to be resolved by judiciaries system, will not be resolved in
GRCs.
The Grievance Redress Committee (GRC) to be formed will be similar to Public Consultative
Committee (PCC). In effect, the resettlement consulting organization will work closely with
the APs to identify the grievances and redress the same in consultation with other members of
the committee as well as the APs. The activities of grievance redress will be monitored by the
organization monthly. While the detailed Organogram of the BGFCL is encloses herewith as
Figure2the Organogram of the office of Deputy Commissioner is presented below as
Figure3.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
40
Figure 2 Organogram of Bangladesh Gas Fields Company Ltd. (BGFCL)
MANAGING DIRECTOR
General Manager (Planning
& Development)
Project Director
Project Engineer
(Seepage &Work
over)
Project Engineer
(Drilling)
Project Engineer
(Process)
Project Geologist
General Manager (Planning &
Development)
MANAGING DIRECTOR
Deputy Manager
(Work over)
Deputy Manager
(Drilling)
Assistant Manager
Assistant Manager Assistant Manager
Manager
(Coordinator) Project Accountant
Project Materials
Coordinator
1XComputer Operator
1XClerk
3XDriver
4XAttendant/Record keeper
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
41
Figure 3 Organogram of the Office of the Deputy Commissioner (DC)
Deputy Commissioner
(DC)
Additional Deputy
Commissioner
(ADC) General
Additional Deputy
Commissioner
(ADC) Revenue
Additional District
Magistrate (ADM)
Additional
Deputy
Commissioner
(ADC)
Revenue
Land Acquisition Officer
(LAO) General
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
42
7.0 RESETTLEMENT COST ESTIMATE AND BUDGET
7.1 Cost Estimates
The estimate for land acquisition by the DC will be prepared by his/her LA section and
placed to BGFCL for transfer of the fund to the account of the DC. The additional benefits as
per the policy will be paid directly by the EA. However, the Implementing Committeewill
assist BGFCL to assess the quantity of losses and the eligible persons for resettlement
benefits and prepare a resettlement budget. BGFCL will approve the budget and arrange
payment of additional compensation and resettlement grants to EPs.
The project office BGFCL will ensure that the land acquisition and resettlement budgets are
delivered on time to the DC and the resettlement account of the field office of BGFCL.
BGFCL will also ensure that the RP is submitted to ADB for concurrence, and that fund for
compensation and entitlement under the RP are fully provided to APs prior to the award of
the civil work contact.
The methodology for assessing unit compensation values of different items is as follows:
� Land to be valued at replacement cost based on land sales survey during
implementation of RP. Advanced tax will be deducted at time of paying
compensation, applicable as per law.
� Annual crops will be valued at highest market rates. One round the year production
from agricultural land will be considered for crop compensation.
The valuation survey registered recent current crop sales at markets and was based on AP and
community consultation (including relevant local government agencies). The conclusion of
the survey is that in most cases the actual transaction values are higher than the values
officially documented and registered.
7.1.1 Land Cost
The project will not involve relocation of any persons as the most of the land are agricultural
lands. The rate of land by type is estimated based on last 12 months average. The
compensation rate along with cost of compensation is given in theTable 20.
Table 20 Value of land of Chhatian, Malihata, Jangilsar, Suhilpur and Sarail
Mouza According to Market Rate, based on Rate of LA Department, Brahmanbaria
Mouza Agricultural land (per
decimal) rate as per
market survey in Tk.
Land Cost (per
decimal) with 50%
premium in Tk.
Amount
of land
(decimal)
Amount in
(Tk.)
Chhatian (Bodul) Tk.74,000 Tk.111,000 320.5 35575500
Malihata (Bodul) Tk.74,000 Tk.111,000 342.2 37,984,200
Jangilsar (Bodul) Tk.74,000 Tk.111,000 88.25 9,795,750
Suhilpur
(Suhilpur)
Tk.90,000 Tk. 135,000 132.4 17,874,000
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
43
Sarail (Sarail) Tk.95,000 Tk. 142,500 616.0 87,780,000
Total land area in decimal proposed for
acquisition
1,499.35 189,009,450
Total Cost in Tk. Eighteen crore ninety lac nine thousand four hundred fifty only.
7.1.2 Compensation for Tenant Farmers
There are 12 households who are sharecropper need to be compensated. In keeping with the
provisions entailed in the Entitlement Matrix, The tenant will be paid compensation at a rate
of Tk. 5,000 per household or Tk. 2,000 per decimal whichever is lower. The Compensation
for Tenant Farmers is shown in Table 21.
Table 21 Compensation for Tenant Farmers
Number of share cropper Assistance per household Amount (in Tk.)
12 5,000 60,000
7.1.3 Training for income generating activities
Trainings for undertaking income generation activities will also organize for the sharecropper
tenants. Seven day training with daily allowance of Tk. 2000 will be organized for the 12
tenants. The cost of training of tenants is detailed in Table22 below.
Table 22 Training for Share Cropper
Number of share
cropper
No. of Days Rate (L.S) Amount (Tk.)
12 7 2,000 168,000
7.1.4 Training for income restoration of wage labour
Trainings for undertaking income generation activities will also organize for the sharecropper
tenants. Seven day training with daily allowance of Tk. 2,000 will be organized for the 12
tenants. The cost of training of tenants is detailed in Table 23 below.
Table 23 Training for Wage labour
Number of wage
labour
No. of Days Rate (L.S.) Amount (Tk.)
12 7 2,000 168,000
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
44
7.1.5 Assistance to Vulnerable Group
119. Additional financial assistance of Tk. 10,000 shall be extended to a 14 vulnerable
affected households identified during the census survey and is shown in Table 24.
Table 24 Financial Assistance to Vulnerable Group
Number of Vulnerable
households
Rates (L.S) Amount (Tk.)
14 Vulnerable Affected HHs 10,000 140,000
7.1.6 Compensation for Loss of Agricultural Income from Trees and Crops
This category of impacts includes standing trees on affected private and public lands. In the
case of privately owned land, the affected family will be the entitlement beneficiary and in
the case of public land, the concerned Government agency or the socially recognized owners
will be entitled to receive the compensation. In all cases the beneficiary will be entitled to
cash compensation equivalent to one year's income for crops at the current market price.
However, in the proposed project locations there are no trees so no compensation will
require.
7.2 Budget
Based on the above costs, a budget provision has been made to cover all land acquisition,
compensation, and rehabilitation costs for the project. The budget provision was made in the
Project Proforma in the amount of Tk. 196 million. In estimating land acquisition cost, last
one year’s average sale rates of different types of land in the project jurisdiction were
collected from the concerned sub-registry offices. These rates are 50% as per GoB policy of
involuntary resettlement (compulsory nature of acquisition) as detailed in the last column of
the entitlement matrix. This is to mention here that cost of other items have also been
estimated of the RP budget at per present rates is presented in Table25.
Table25 Summary Resettlement Budget
Resettlement Cost Items Cost in Taka
Loss of income of share croppers 60,000
Training cost of share croppers 168,000
Training for income restoration 168,000
Compensation for Vulnerable 140,000
Crop Compensation for one year 60,000
Fees for External Monitoring 200,000
Tenant farmer 60,000
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
45
Land Acquisition (LA) Cost with Premium 189,009,450
Miscellaneous expenses for land acquisition @ 3% 5,670,284
Total in word in Tk. Nineteen crore fifty five lac thirty five
thousand seven hundred thirty four only
19,55,35,734
All types of compensation payment against land acquisition and others will be disbursed as
soon as possible.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
46
8.0 IMPLEMENTATION SCHEDULE
8.1 RP Implementation Schedule
It is likely that the overall project will be implemented over a 3 Year Period commencing
after loan approval. As part of advance actions following loan negotiations, the EA will
establish the project office, appoint implementation committee for resettlement
implementation and establish GRC.
Apart from this, the M&E consultants will be engaged at the time of the commencement of
the land acquisition process. All compensation and other assistances1will be paid to all APs
prior to commencement of civil works.
The implementation schedule will be finalized considering possible changes of events during
the project implementation period after detailed design of the project.
8.2 Implementation Schedule
The itemized activities of the Resettlement Plan (RP) will be scheduled to meet the legal time
frame and timely implementation of the Project work. Land acquisition or borrowing is an
essential part of project implementation. A project having sufficient lead time between fixing
project alignment and actual start of construction does not face any difficulty in borrowing
land. The procedure of land acquisition as well as resettlement in Bangladesh is presented in
this chapter.There are few pre-requisites to be completed before going into the process of
land acquisition.
• Pre-requisites:
• approval of project document like DPP/TAPP
• approval of project plan
• approval of land plan and land schedule
• administrative approval of land requirement from the ministry, and
• budget provision for land acquisition.
When these pre-requisites are fulfilled a step-wise of land acquisition process is followed:
• Step-wise land acquisition process
• submission of land acquisition proposal by the requiring body to the Deputy
Commissioner
• holding District Land Acquisition Committee meeting and providing land allocation
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
47
• serving Notice under Section 3 to the affected persons
• joint verification
• serving notice under Section 6 to settle any dispute
• estimation of jointly verified property for cost compensation and informing requiring
body
• acceptance of estimate of cost compensation placement of fund to the Deputy
Commissioner by the requiring body
• serving Notice 7 by the Deputy Commissioner to the affected land owners for
disbursement of compensation
• disbursement of compensation as per estimate to the affected persons.
• giving possession of land to the requiring body.
This whole process takes about 12 months time. The steps of land acquisition process are
given below: The joint verification will finalize:
i) ownership of the plot;
ii) area of the plot with classification, and
iii) installations and vegetation on the plot
a) housing with type, size, materials used etc.
b) shops, business unit, rural industry etc.
c) tube wells, latrines etc.
d) standing crops with types and covered area, and
e) standing trees with types and number and sizes.
Final approval of acquisition will then be obtained from the DC if the land requirement is
equal or less than 50 bighas (1,650 decimal). On the other hand, if the requirement of land is
over 50 bighas, the approval will be given by the office of the Prime Minister processed
through the Ministry of Land. After obtaining approval of acquisition from the appropriate
authority, notice under Section 6 will be issued and time allowed for final hearing of any
dispute or objection is 30 days. Simultaneously, estimate of the cost of acquisition will be
done as per set rules and approved rates of items and submitted by DC office to the requiring
body. Upon receipt of the estimate from DC office, the requiring body will examine the
estimate and get the estimate sanctioned by the appropriate authority. Notice under Section 7
is then issued after the acceptance of the assessment by the Requiring Body and time allowed
for placing funds with DC office is 60 days. On receipt of the fund from the requiring body,
DC office starts paying the affected land-owners as per estimate items and cost and give
possession of the required land to the requiring body. After placement of fund compensation
will be given to the project affected persons one month before the appraisal and the field
development activities.
Enviro Consultants Ltd. (ECL) has been engaged to make a detailed assessment of the losses
to property, crops, and prepare detailed RP. The team of experts consisting of an
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
48
Environmentalist, Sociologist, and other disciplines, along with BGFCL personnel were in
the field to collect necessary data. Land acquisition including payment of compensation will
be completed before taking possession of the land. Compensation for damages of crops due
to acquisition of land will be paid as per Bangladesh law and ADB guidelines during the
survey phase of the Project, which involve digging for placing of explosives. A committee
will be form to facilitate in the implementation process of the RP.
8.3. Pre-requisites of a Successful Implementation of RP
A successful implementation of the Resettlement Plan (RP) has three main pre-requisites.
First, there is a need of a clear understanding of the tasks involved, their sequencing in time
and linkages with each other. Second, there has to do a well-conceived organization set up
with well-learned and efficient staff to carry out various tasks. Third, there is a need for a
carefully prepared time schedule (i.e. work plan) synchronizing resettlement/acquisition with
civil works.
8.4. Temporal Parameters of the RP
There are three important dates that need to be kept in plan in developing the implementation
schedule of the RP in order to achieve the objectives and synchronize it.
8.4.1 Date of Start of Implementation
The implementation process formally starts when the RP is agreed upon between the GoB
and the Asian Development Bank. It is expected that this will happen sometime by the
beginning of December 2013.
8.4.2 Date of Vacating the Work Site
The work site will need to be cleared off and handed over to the civil work contractors for
digging of spot holes which is free from all encumbrances on and from January, 2014.
The nature of works are such that the land to be taken permanently. Access to the well sites
and process plant areas will remain restricted. Only authorized person can access for
operational purposes.
8.4.3 Date of Completion of the Acquisition and compensation Process
The process of acquisition, which in a broader sense, includes economic rehabilitation. The
need for monitoring these impacts and undertaking appropriate corrective measures in terms
of grievance redress will be felt more intensely during this period, which should last at least
six months from the time of acquire. Assuming that the total process will completed at the
end of June 2014.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
49
9.0 MONITORING & EVALUATION
9.1 Need for Monitoring
Monitoring and Evaluation (M&E) are critical activities in involuntary resettlement in order
to ameliorate problems faced by the APs and develop solutions immediately. Monitoring is a
periodic assessment of planned activities providing midway inputs. It facilitates change and
gives necessary feedback of activities and the directions on which they are going, whereas
evaluation is a summing up activity at the end of the project assessing whether the activities
have actually achieved their intended goals and purposes. In other words, M&E apparatus is a
crucial mechanism for measuring project performance and fulfillment of the project
objectives.
Day-to-day monitoring of RP implementation and impacts shall be the responsibility of the
Project Director. A committee may be established by BGFCL will conduct field level
monitoring and assess and report on the daily operation of land acquisition and resettlement
activities. The range of activities and issues that will be monitored will include:
� the process of information dissemination and consultation with APs
� number of persons affected by category of loss
� valuation of assets at replacement value
� delivery of compensation at replacement cost for lost assets and rehabilitation
measures according to entitlement
� grievances made and settled
� clearance of project sites and coordination with civil works and
� identification of problems and corrective measures implemented or required
The benchmark for project level monitoring will come from the census and inventory of lost
assets data and the baseline socio-economic survey. The mechanisms to be used in the field
level monitoring include:
� Review of AP files and pre-project baseline data on APs
� Informal survey of APs
� Identification and selection of an appropriate set of indicators for gathering and
analyzing information on resettlement impacts
� Key informant interviews
� In-depth case studies to investigate special issues, and community/public meetings
The monitoring will commence with commencement of the project implementation and shall
continue throughout the implementation of the project. The Executing Agency (EA) for the
project is responsible for organizing and resourcing monitoring and evaluation efforts.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
50
9.2 Monitoring at EA Level
The EA usually has full responsibility for internal monitoring. Monitoring takes place against
the activities, entitlement, time frame and budget set out in RP. The record system is
supplemented by periodic survey designed to measure change against the baseline established
during the initial and survey work. The periodic survey focuses on the receipt of entitlements
by people affected based on benefits indicators.
Monitoring indicators will be selected to address specific contents of the activities and
entitlement matrix. Sample monitoring indicators from which indicators can be developed
and refined according to the circumstances. The indicators will relate to rehabilitation and
compensation for land loss as no relocation will be needed may include:
� Have all the APs properly identified
� Have the resettlement officers received the scheduled fund
� Have the fund been distributed for RP
� Have all land have been given possession in time
� Have all social preparation has take place
� Have the APs used grievance redress procedure
� What was the outcomes of grievance redress
� How the grievances were resolved
� Have all APs received payment a per resettlement matrix on time; and
� Have income restoration activities being implemented.
9.3 Reporting Requirements
9.3.1 Plan for Internal Monitoring
The internal monitoring is often based upon a card system kept in the monitoring office
recording the entitlements due to and received by each affected household. The card system
can be manual or computerized.
During the implementation phase, the assigned person from the organization tighter with the
project appointed organization, if needed, will prepare monthly reports on the progress of
resettlement activities and forward copies of the reports to the Donor. A format for
resettlement implementation monitoring has been devised (Table 26) for monthly monitoring
and data collection by field officials. BGFCL will prepare a post-resettlement evaluation
report at the end of the project activity. The report should provide evidence whether adverse
effects of the project have been mitigated adequately or at least pre-project standard of living
and income have been restored as a result of the RP.
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
51
Table 26 Monthly Progress Report Format for Resettlement Monitoring
Component Unit
Total
Completed
%
Cumulative
Achievement
Progress During
Reporting Month
Status &
Remark
1. Resettlement
Preparation:
-Identification of APs
-Group meeting with
APs
-Compensation for crop
2. Payment of
Compensation
Land:(agriculture/home
stead)
Compensation for crop
3.Grievance
resolution
Grievance redress cases
Grievance redress
outcome
Resolutions of GR
4. Income Restoration
Activity
Income restoration
grant
9.3.2 Plan for External Monitoring
The EA will established a committee including local government and elected representative
to ensure complete and objective information. Post-evaluation of resettlement is an integral
part of the project cycle. Independent evaluation can be done by an outside research or
consulting agency.
The key tasks during external monitoring will include:
� Review and verify the internal monitoring reports prepared PIC
� Review of socio-economic baseline census information of pre-displaced persons
� Identification and selection of impact indicators
� Impact assessment through formal and informal surveys with the affected persons
� Consultation with APs, officials, community leaders for preparing review report
Resettlement Plan (RP) for Drilling of 4 New Wells (Titas # 23-26) and Installation of 2 nos. Process Plants at
Titas Gas Field.
52
� Assess the resettlement efficiency, effectiveness, impact and sustainability, drawing
lessons for future resettlement policy formulation and planning
Post-Resettlement Evaluation: Six monthafter completion of all RP activities, the project
appointed organization/ or the organization itself in case of small number of cases, Shall
carry out an evaluation of resettlement to assess the effectiveness, impact and sustainability
of entitlements, and to learn strategic lessons for future policy formulation and planning.
9.4 Time Frame and Reporting Requirements
During the implementation phase, the executive committee will prepare monthly reports on
the progress of resettlement activities and forward copies of the reports to the Donor. A
format for transfer of land implementation monitoring has been devised for monthly
monitoring and data collection by field officials (Table No. 27). BGFCL will prepare a post-
transfer of land evaluation report at the end of the Project activity.
Table27 Monthly Progress Report Format for Resettlement Monitoring
Component Unit
Total
Completed
%
Cumulative
Achievement
Completed Progress During
Reporting
Month
Status &
Remarks
1. Land
Acquisiti
on for
RP
2. Payment of
Compensation
: for crops
damage