1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged and next steps 3/ Jumps investigations 4/ Plans for the next 6 months

Upload: bruno-warner

Post on 18-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

1

Commissioning status and plans

ILIAS - June 14th 2005Matteo Barsuglia

1/ what happened in the last month

2/ New sensitivity: a preliminary noise budged and next steps

3/ Jumps investigations

4/ Plans for the next 6 months

Page 2: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

2

1/ What happened in the last month

Page 3: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

3

C5 sensitivity (Dec 2004)

C4, recombined 7W input power

C5, Recycled 0.7 W input power

Page 4: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

4Laser frequency

refl_3f_phaseref

rec_quad

rec_phase

Asy_phase

‘detection’ mode

• DARM controlled with Asy_phase

• CARM with rec_phase

• MICH with rec_quad

• PRC with refl_3f_phase

May 17th: realignment of B5 (rec beam photodiode)

B5 photodiode (rec beam)

Page 5: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

5

Minirun M3 – may 19th

Proper minirun M3 Restoring C5 science mode

Page 6: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

6

Comparison with M2 – May 5th

Page 7: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

7

Jumps during M3

~5 jumps

Page 8: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

8

Sensitivity on May 20th

• Roll-off Michelson at 50 Hz (100 Hz during C5)

• LO board upgraded

• Local control upgraded

C5 sensitivity

Page 9: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

9

Michelson roll-off @ 50 Hz

1/ Elliptic roll-off at 50 Hz

unity gain frequency at 6-7 Hz

Page 10: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

10

May 19th-26th: a good week

‘ no jumps’

Page 11: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

11

May 23rd sensitivity

• Low noise coil drivers on arm mirrors (1/25)

Page 12: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

12

Marionetta and tidal control f < 10 mHz

10 mHz < f < 10 Hz

f > 10 Hz

Recycled ITF

internal power

Force on marionetta

Force on mirror

• Marionetta and tidal control tested with recycled interferometer

• Residual correction seems to be compatible with Virgo specifications

Page 13: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

13

May 27th, Jumps again

Injection realignment

ITF relocked 50’

Some locks with jumps some locks without jumps

realignment quadrant mode-cleaner

Work on NI vertical damping

Page 14: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

14

50’ lock on Thursday evening

No evident jumps

Power fluctuations maybe higher than normal

Page 15: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

15

May 27th, Jumps again

Injection realignment

ITF relocked 50’

Some locks with jumps some locks without jumps Only work:

realignment quadrant mode-cleaner

Work on NI vertical damping

Page 16: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

16

Friday May 27th , the bad

Zoom on a jump bench of the first plot

Page 17: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

17

Friday 27th, the good

Page 18: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

18

Friday 27th , the good

New sensitivity curve (with BS coils drivers x4 resistors) – obtained during one of the “good” locks

Zoom on the 50-100 Hz region

• with resistors x4 BS and arm mirrors should contribute at the same level

Page 19: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

19

Sensitivity evolution

May 27th

Page 20: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

20

Last week

Page 21: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

21

photodiode centering checks May 30th - June 1st

Photodiodes B1p, B5, B5_2f, B2_3f

• PR-NI configuration

• other mirrors misaligned by 10 mRad

• maximize AC or DC signal

Photodiodes B8

• North cavity configuaration

• other mirrors misaligned by 10 mRad

• maximize DC signal

All photodiodes were found centered

Page 22: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

22

June 1st: demod phases checks

Demod phases (with respect to May 17th)

• B2_3f –170-150 (maximizing P/Q for a line on PR using the CITF)

• B5_2f –43-23 (maximizing sideband crossing, using the CITF)

• B5 –34-28 (minimizing frequency noise on Acq, using north cavity only)

• B8 OK (minimizing frequency noise on Acq, using north cavity)

- Are the tuning criterions right ?

- Why these phases changes?

Page 23: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

23

M4 – changes in B2_3f_phase

-150 (“good” phase)

-110

Page 24: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

24

M4 – new BS local controls

Page 25: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

25

Improvements in low frequency sensitivity – june 3rd

- Black = may 27th (+ x4 resistors on BS)

- red = June 3rd (+ new controls on BS and gain decreased by factor 2 on WI and NI)

Page 26: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

26

Sensitivity evolution – low freq

C5

June 3rd

Page 27: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

27

2/ Sensitivity: a preliminary noise budget and the next actions

Page 28: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

28

C5 May 2005

sensitivity curve

electronic noise (shutter closed)

shot noise

Virgo nominal sensitivity

x 40

x 4Phase noise

Sensitivity – high frequency

(Input power = 0.7 W)

Page 29: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

29

Volts/sqrt(Hz)

ACp noise (>5000 Hz)

ACq signal (0-100Hz)

= 0.39 rad/Hz

Volts

During C5:

= 0.48 rad/Hz

Now:

= 0.39 rad/HzNo big improvement on

But a big reduction of B1_ACq! Improvement of local controls?

C5

May 27, 2005

29

M3 data

Phase noise measurements

Page 30: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

30

Power fluctuations

Contrast

1 mW / 20 W ~ 5e-5

Internal power (rescaled) Dark fringe power (W)

Page 31: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

31

What is the bump?

Volts/sqrt(Hz)

ACp noise (1600-3000 Hz)

ACq signal (0-100Hz)

=> The amplitude of the bump does not vary with B1_ACq like phase noise

Volts

?

31

Page 32: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

32

High frequency: actions • Oscillator phase noise

Several parallel solutions:

• Local oscillator distribution electronics replaced

• Main oscillator to be replaced market evaluation on going

• Prototype for active compensation of the ‘wrong’ quadrature (ASI servo a la LIGO) ready to be tested

• Linear alignment should help to reduce the ‘wrong’ quadrature

When oscillator phase noise is killed

limit will be (?) by electronic and shot noise change injection bench power x10

• Electronic noise constant

• Shot noise scales as

• Still factor 5 missing with respect to the design (1 kW on BS)

• Increase transmission of the mode-cleaner (now 50%)

• Increase PR reflectivity planned 0.920.95

P

Page 33: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

33

Sensitivity: low frequency

May 23rd and 25th

• Coherence with auxiliary degrees of freedom control noises (PRC and MICH)

• Coherence with BS angular control signals

• The signals are coherence each others: need cross-coherence computation to identify the individual components

Page 34: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

34

Sensitivity: low frequency

BS_zCorr

BS_txCorr

PR_zCorr

Individual contributions

20 Hz40 50

BS_zCorr

Page 35: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

35

June 01 (M4) & May 25

The coherence between B1_ACp and BS (tx, z), PR (z) correction is reduced

the 3 channels are coupled and BS_txCorr was the main source of the noise

Now, B1_ACp coherent with WI_txCorr

35

Sensitivity: decrease angular noises

Page 36: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

36

Low frequency: actions

• Local controls:

• They will be switched off when automatic alignment will work : wait to commission the automatic alignment

• Small improvements on going

• Actuators noise:

• Low noise coils driver (1/25) don’t limit the sensitivity

• on BS (1/4) same level that the arm mirrors

• Auxiliary degrees of freedom

• Roll-off optimization (now at 50 Hz)

• Analysis of the noise source and propagation

• Non diagonal driving matrix elements

Page 37: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

37

Reduce the control noises

Page 38: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

38

Reduce the control noises

• Alreay tested in LIGO

Page 39: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

39

Reduce the control noises: simulation

• Siesta simulation

• Influence of the BS noise in the low frequency part of the spectrum

• Tentative of suppression through addiction of non-diagonal terms in the driving matrix

No reduction

Perfect TF

15% error in the TF

Page 40: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

40

3/ Jumps investigations: ideas and next actions

Page 41: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

41

Jumps – some ideas

• Optical defect:

• Clipping from IB mirrors

• Beam quality not enough

• Bad management of the secondary beams from BS at the injection level

• Clipping, stry light from BS

• …

• Coupling with global alignment (I.e. Anderson effect)

• Locking problem (I.e.bad setting of the demodulation phases)

• Electronic hidden problem

• Problem related with the ITF parameters (I.e. recycling cavity flat-flat)

Why sometimes (~ week) it works very well?

Page 42: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

42

0/ What was done in the last month

• Stray light hunting widely done on the reflected beam

• Realignment of photodiodes:

• Establishment of a check procedure based on simple optical configuations (power recycling – north input cavity, north cavity)

• Monitoring of the photodiode position through CCD cameras (not on all the beams)

• Experiments to understand the relationships between jumps and mirror misalignments

• put low frequency lines on all the mirrors, at 8% (lock more robust)

Page 43: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

43

Jumps vs mirrors alignment

Mirrors angle combination

“jumped” state

Standard state

May 20th data, 8 %

• If confirmed at the dark fringe can be an indication of an optics defects (clipping, stray light..)

Page 44: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

44

1/Injection realignment: may 26th

Injection realignment

ITF relocked by Vincenzo 50’

Some locks with jumps some locks without jumps Only work:

realignment quadrant mode-cleaner

Work on NI vertical damping

Page 45: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

45

1/Injection re-alignment: history

• One of the local control laser of the injection system was almost dead (power 40% less than normal)

• This laser is one of the angular references of the bench (the “fine” mode)

• During the replacement the reference becomes a CCD camera (the so called “rough mode”)

• Differences between the rough mode and the fine mode can makes differences in the injection bench position

• Once the new laser is installed the beam is aligned with respect to the reference cavity, attached at the bench

• The mode-cleaner is re-locked, and the beam incoming in the interferometer is realigned through picomotors after the mode-cleaner

Page 46: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

46

1/Injection re-alignment: actions

• Find some indications of how the injection bench has moved with respect to the original position (I.e.how much we should move the picomotors after the mode-cleaner to realign the beam at 3 km)

• Try to reconstruct the injection bench rotation (300 microrad in the interferomter plane)

• Move the injection bench in the inverse direction (today) and re-align the beam consequently

• Re-lock the interferometer

• If necessary, make a further scan

Page 47: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

47

1/Injection re-alignment: future

• 2 new features:

• BMS: beam monitoring system: a reference (on the ground) for the beam alignment

• The beam is aligned with respect to the mode-cleaner dihedron

Page 48: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

48

2/ Beam splitter stray light

The BS “front” view

Page 49: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

49

2/ Beam splitter stray light

Image sequence

ITF unlocked Step 7 (8%)

Dark fringeITF unlocked

Page 50: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

50

3/ Fringes on the north&west cavity reflected beams

North cavity well aligned

(PR, WI misaligned by 10 millirad, WE misaligned by 500 microrad)

• seen also on west cavity (same fringes)

- from the input beam ?

- from input mirrors AR ?

Page 51: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

51Laser frequency

refl_3f_phaseref

rec_quad

rec_phase

transW_phase

4/ Change the locking scheme: the standard scheme

‘acquisition’ mode

• DARM controlled with transW_phase

• CARM with rec_phase

• MICH with rec_quad

• PRC with refl_3f_phase

Page 52: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

52Laser frequency

refl_3f_phaseref

rec_quad

rec_phase

Asy_phase

‘detection’ mode

• DARM controlled with Asy_phase

• CARM with rec_phase

• MICH with rec_quad

• PRC with refl_3f_phase

4/ Change the locking scheme: the standard scheme

Page 53: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

53

refl_3f_quad

Ref_phase

Asy_phase

‘detection’ mode

• DARM controlled with Asy_phase

• CARM with rec_phase ref phase

• MICH with rec_quad refl_3f_quad

• PRC with refl_3f_phase

4/ Change the locking scheme: the new scheme

Laser frequency

refl_3f_phase

Page 54: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

54

4/ Change the locking scheme

• Idea :

• eliminate the suspect of spurious effect on the beam REC (B5)

• eliminate the suspect of some not understood coupling between locking signals

• Planning: 2 steps

1/ MICH: rec_quad ref_3f_quad Measurement and software this week

2/ CARM (laser freq.): rec_phase ref_phase Measurements next week

Page 55: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

55Laser frequency

refl_3f_phaseref

rec_quad

rec_phase

Asy_phase

‘detection’ mode

• DARM controlled with Asy_phase

• CARM with rec_phase

• MICH with rec_quad

• PRC with refl_3f_phase refl_phase

5/ Change the locking scheme: eliminate the 3f photodiode

Page 56: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

56

5/ Change the locking scheme: eliminate the 3f photodiode

• Idea :

• Problems with the 3f photodiode (signals generation, electronics, demod phase tuningm,…)

• Move the control on a standard photodiode (ref_phase)

• Results:

• Already tried (jumps still present)

• To repeat : was done when B5 photodiode (rec beam) was misaligned

• Problems

• Offset in the ref beam (B2 beam)

• Planning

• Try again, with offset compensation – see what happens to the offset changing the CARM/frequency control error signal

Page 57: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

57

6/ B2 offset

• Interferometer locked in detection mode

• PRC controlled with ref_3f_phase photodiode (B2_3f_phase)

40-50 mW offset present since the beginning (even in the periods with no jumps)

Page 58: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

58

6/ B2 offset: simulation

Offset constant versus misalignement up to 1 microrad

Page 59: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

59

6/ B2 offset vs beam shape: simulation

Suspended bench External bench

Standard inputfile

PRC ‚flat‘ surface withRC (vertical)=-10km

Reflected beam shapes computed with finesse

Page 60: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

60Laser frequency

refl_3f_phaseref

rec_quad

rec_phase

transW_phase

‘acquisition’ mode

• DARM controlled with transW_phase

• CARM with rec_phase

• MICH with rec_quad

• PRC with refl_3f_phase

7/ Better decouple the locking matrix

Driving and sensing coupling

Page 61: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

61

changes in B2_3f_phase

-150 (“good” phase)

-110

Page 62: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

62

7/ Better decouple the locking matrix

• Planning:

• Driving matrix already decoupled

• Experiment to decouple better the sensing matrix started

Page 63: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

63

8/ Close the automatic alignment

• Status:

• 7/10 loops closed

• Optical offsets found in the quadrant

• Reconstructed offsets can be also 10-15 microrad

Offset from working point

Loop engaged

Page 64: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

64

8/ Multiple-zeros in the error signals with misalignments

The PRC signal approaches a multiple zeros behavior by setting the demodulation phase tens of degree off the nominal value (41°)

Page 65: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

65

Jumps: actions summary

• Scan the injection system alignment

• Change locking scheme

• Continue work on linear alignment

• Understand better the BS centering

• simulation work with Finesse and Siesta

Page 66: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

66

4 / Plans for the next 6 months

Page 67: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

67

Planning – 6 months • June-July 2005

• Close linear alignment

• Investigate bistabilities

• July 29th- August 12th

• C6 run

• September-October

• Injection bench and power recycling mirror replacement

• Sub-systems upgrades

• November - December

• Injection bench commissioning

• Restart of the interferometer

• Noise hunting

Page 68: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

68

Benefits to replace IB and PR

• Benefits to change IB:

• mirrors clip the beam

• beam is astigmatic

• secondary beam BS not separated

•ISYS alignment is not stabe

- Jumps can be related with IB

- Even if jumps are not related with IB more clean status

- Present IB: power reduced situation can change with x10 power

• Benefits to change PR:

• Resonances ~ 100 Hz region removed, better control

• Lens removed: ITF alignment simpler

Page 69: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

69

Activities during the injection bench stop

• Suspensions upgrades

• Modification of the accelerometer electronics

• Vertical inertial damping

• Replacement of the local control lasers

• Software upgrades

• Documentation effort

Page 70: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

70

Inertial damping upgrade/1

Motivation: Interferometer operation is critical with strong winds or earthquakes

• Seismic noise is re-injected via position control (LVDT)

• Crossover LVDT/accelerometers~ 70 mHz too high

• The reduction of the LVDT control bandwidth is prevented by the low frequency response of the accelerometers

Page 71: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

71

Inertial damping upgrade/2

If IP legs are not parallel the top table tilts as it translates

Non-parallelism can be obtained in two ways

1/ Mechanical imperfections

2/ Twist by rotational offset (dominant)

Tilt induces a “fake” low frequency signal in the accelerometers the “cradle” effect

Page 72: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

72

Inertial damping upgrade/3

• Non parallelism eliminated by signal processing techniques

• Allows to reduce crossover 7050 mHz an reduce the reintroduction of seismic noise by a factor 3

• implemented on all the long suspensions

• To reduce further the crossover we need to amplify the accelerometer electronics to beat the ADC noise

• tested succesfully on a suspension: reduction of a factor 10 of the seismic noise with respect to standard crossover (70 mHz)

• Plan to extend the result to all the suspensions during the injection bench stop

Page 73: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

73

Injection bench commissioning/ restart of the interferometer

• Close injection bench local controls

• Re-Lock the input mode-cleaner

• Align the beam into the interferometer (x10 power)

• Re-measure locking paramters

• Re-lock the recycling interferometer

Page 74: 1 Commissioning status and plans ILIAS - June 14 th 2005 Matteo Barsuglia 1/ what happened in the last month 2/ New sensitivity: a preliminary noise budged

74

Summary

• Problem of jumps not yet solved

• Many possibilities but not clear indications

• Sensitivity improvements in the short windows without jumps

• h~ 2e-21, factor 4 from dark (and shot) noise of B1 photodiode

• spectrum non stationnary – need automatic alignment

• Noise hunting preparation on going

• Plan to make a 2 weeks run during summer , if jumps problem is solved

• Injection bench change scheduled for early september (2 months stop)