1 columbiagrid activities supporting integration of renewable generation presentation to the market...
TRANSCRIPT
![Page 1: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/1.jpg)
1
ColumbiaGrid Activities Supporting Integration of Renewable Generation
Presentation to the Market Interface Committee
At the October 30, 2008 Meeting in Marina Del Rey
By
Paul F. ArnoldVice President, ColumbiaGrid
![Page 2: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/2.jpg)
2
ColumbiaGrid Activities Supporting Integration of Renewable Generation
Background – ColumbiaGrid Efforts on Redispatch
In 2007, ColumbiaGrid under contract with it’s members provided an independent evaluation of BPA’s 2007 Redispatch Pilot Program– Redispatch is much more effective than curtailment to control line
overloading. – Identified need for broader participation, including generators
outside the BPA BA– But low utilization of generators and infrequent opportunity for
redispatch is a problem to incent market participation– Added Load Following to increase generator participation and
solve huge problem with wind integration
![Page 3: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/3.jpg)
3
ColumbiaGrid Activities Supporting
Integration of Renewable Generation
Background- Developing Intra-hour Load Following
• Intra-hour Load Following can be done using similar redispatch scheduling protocols
• Market participants can bid incs and decs to transfer energy to and from Balancing Areas to create regulating room for intermittent Wind Generation
![Page 4: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/4.jpg)
Intra-Hour Regulating ReliefIncreasing-Need for Regulating Relief - Simplified Diagram
A
C
B
D
Area B Requires 100 MW Increasing Regulating Reserve
TechnicalPlatform
ColumbiaGrid
Gen/IPP/D provides 50 MW INCGen/BA/C provides 20 MW INC
Gen/IPP/A provides 30 MW INC
30 MW
20 MW
50 MW
20 MW
Bidding-Platform
IPPGenD
IPPGenA
GenC
GENS
BA/PO (transacting party)
ICCP Data Link
BA’s
DataSharing
DataSharing
Intra-hour Block Energy Sell Bids (“INC”)Intra-hour Block Energy Buy Bids (“DEC”)
DataSharing
4
![Page 5: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/5.jpg)
Intra-Hour Regulating ReliefDecreasing-Need for Regulating Relief - Simplified Diagram
A
C
B
D
Area B requires 100 MW Decreasing Regulating Reserve
TechnicalPlatform
ColumbiaGrid
Gen/IPP/D takes 50 MW DECGen/BA/C takes 20 MW DEC
Gen/IPP/A takes 30 MW DEC
30 MW
20 MW
50 MW
20 MW
Bidding-Platform
IPPGenD
IPPGenA
GenC
GENS
BA/PO (transacting party)
ICCP Data Link
BA’s
DataSharing
DataSharing
Intra-hour Block Energy Sell Bids (“INC”)Intra-hour Block Energy Buy Bids (“DEC”)
DataSharing
5
![Page 6: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/6.jpg)
6
ColumbiaGrid Activities Supporting Integration of Renewable Generation
BPA Wind Integration Projection
![Page 7: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/7.jpg)
7
ColumbiaGrid Activities Supporting Integration of Renewable Generation
What is Needed?• Ability to regulate for intermittent resources, mostly wind
• Ready Access to Generation Resources– Within the Balancing Area– Outside the Balancing Area
• Methodology– Dynamic Scheduling– Intra-hour Load Following– Other
![Page 8: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/8.jpg)
8
ColumbiaGrid Activities Supporting Integration of Renewable Generation
What is Needed?• Opportunity- for Generators to bid Intra-hour Load Following and Dynamic Scheduling over
a wide area
• Visibility -Tools for balancing authorities/grid operators to access bidding generators across a wide area
• Cooperation- Active participation by BAs who can directly benefit and by BAs who can facilitate dynamic scheduling and intra-hour services
![Page 9: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/9.jpg)
9
ColumbiaGrid Activities Supporting
Integration of Renewable Generation What is Needed?• Standard Business Practices – Flexible to allow mid-hour scheduling and tagging (make
the schedule change and tag after the fact like reserve sharing?)
• Automation--Ultimately need to support up to 10 minute changes (automate the scheduling and tagging process?)
• Manual-- Need to make mid-hour changes across multiple balancing authorities is urgent (one or several changes per hour?)
![Page 10: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/10.jpg)
10
ColumbiaGrid Activities Supporting
Integration of Renewable Generation
Getting Regional Interest • ColumbiaGrid made a presentation at the WECC MIC
meeting in March 2008 on its efforts to develop Redispatch and Energy Balancing markets which generated interest from WestConnect and NTTG parties.
• In May 2008, ColumbiaGrid approached NTTG to consider a Joint Initiative which we both agreed to explore.
![Page 11: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/11.jpg)
11
ColumbiaGrid Activities Supporting Integration of Renewable Generation
Joint Initiative• At a June 30 NTTG meeting in Boise, broad concepts
were introduced and ColumbiaGrid, NTTG, and WestConnect representatives agreed to explore co-sponsoring a Joint Initiative.
• On July 8 in Portland, the first exploratory stakeholder meeting was held
• Joint Initiative meetings were held in Reno on August 26 and in Salt Lake on September 29
![Page 12: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/12.jpg)
12
ColumbiaGrid Activities Supporting
Integration of Renewable Generation
Joint Initiative Goals and Focus
• Goal: work jointly with other sub-regional groups, utilities and interested persons to find solutions to broader regional problems.
• Current problem focus: integration of rapidly growing amounts of variable-output generation (primarily wind generation) into existing balancing authority areas.
![Page 13: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/13.jpg)
13
ColumbiaGrid Activities Supporting
Integration of Renewable Generation Joint Initiative--Two Strike Teams and One Think Tank• The Infrastructure Strike Team is focused on delivering a common
communications infrastructure and protocols for dynamic scheduling—jointly staffed
• The Products and Services Strike Team is focused on delivering Intra-hour Load Following services -- jointly staffed
• The Think Tank is a broader stakeholder group that provides policy and direction and is jointly facilitated by ColumbiaGrid, NTTG, and WestConnect
![Page 14: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/14.jpg)
14
ColumbiaGrid Activities Supporting Integration of Renewable Generation
Joint Initiative- Parties involved:
• BPA, Snohomish, Tacoma, SCL, Grant, CG staff
• PAC, PGE, Idaho, Northwestern, NTTG staff
• APS, Excel, WestConnect staff
• OATi, WECC staff, PPC, NIPPC, and others
![Page 15: 1 ColumbiaGrid Activities Supporting Integration of Renewable Generation Presentation to the Market Interface Committee At the October 30, 2008 Meeting](https://reader036.vdocuments.us/reader036/viewer/2022081602/55150e4f550346a80c8b5a23/html5/thumbnails/15.jpg)
15
ColumbiaGrid Activities Supporting
Integration of Renewable Generation
Joint Initiative- Defining Success
• Get Intra-hour services and/or dynamic scheduling approaches to implementation within 10 to 18 months
• Get used to thinking in terms of regional problem solving and getting things done