Financial Management & Comptroller
1
2011 ASMC PDI
Navy Workshop DN02
Object Class: Building Blocks for Budget Preparation and Execution
June 1, 2011
2
Financial Management & Comptroller
2
DN02 Object Class: Building Blocks for Budget Preparation and Execution Overview – Object Class Information and Uses
Object Data Submissions and Reviews during the typical Budget Cycle
Object Data from the Echelon I/Departmental perspective
Object Data from the Echelon II /BSO perspective
Questions
Agenda
3
Financial Management & Comptroller
3
Check out BG 11-1G guidance, Enclosure (4), BOCS processes and procedures:
Or you can push some BOCS buttons…
Check the Program Budget Information Center (PBIC) for the latest gouge at:
https://fmbweb1.nmci.navy.mil/fmb32/PBIC.htm
BOCS Note of the Day
FMB
BSO BSO BSO
FMB FMB
4
Financial Management & Comptroller
4
Building Blocks: Overview
Object Class Categories in a classification system that represent obligations by the
items or services purchased by the Federal Government OMB Circular A-11
Object classes describe obligations according to their initial purpose, not the end product or service
Example: A federal employee is paid to construct a building The obligation is under personnel compensation and benefits, not OCC 32.0 When categorizing other contracts, have to consider to purpose What if the government pays a contractor to construct the building
Why report object class information – 31 USC 1104(b) requires the President’s Budget to present obligations by object class for each account
Object Data is displayed in Appendix of the Budget of the United States of America at the front of each individual appropriation section
The DON also submits Object Class information for OCO requests and Supplemental funding
5
Financial Management & Comptroller
5
Building Blocks: Overview
Uses of Object Class Data Budget Submissions - President’s Budget/OSD BES/DON Budget
Submission
Budgetary data use for pricing Navy Working Capital Fund rates and pricing for WCF exhibits (25.3) O&M object class data makes up the OP-32 exhibit within the OP-5 OP-08 data is used to update CIVPERs object data (OCC 11 through 13) PB-15 Advisory and Assistance Services exhibit is derived from OCC 25.1 Fuel pricing in ICC’s 400, 401 and 937 reflective of the OP-26 exhibit
OSD Interest in Object Class Information Trends for 25.1 and 25.2 through PB11 and PB12 – Contract Services In both years, significant Contract Services reductions have been developed
from these trends OSD has stipulated (PB12) a 10% reduction in 25.1/25.2 across years
OMB and Congress review Object Class Information for trends as well
6
Financial Management & Comptroller
6
Building Blocks: Overview
Submissions Object class submitted three times during the program/budget review
DON Budget Submission (~June) OSD Budget Estimate Submission (BES) (~July) President’s Budget (~January)
Time compression in recent years has made the Department’s PB submission for object data challenging
OSD RMDs have typically been published later than previous years Final RMDs coupled with DON end game decisions to get to final balancing Scheduling rush to publish controls…needed for building budgets Results in inadequate time to develop, submit and review Object Data in
BOCS (generally takes about 2 weeks to build submit and review)
Data bases are generally closed by the time object data is available in BOCS
Path ahead for FY 2013 budget cycle
7
Financial Management & ComptrollerBOCS Submission Process
FMB32Locks BOCS
RecordsAdd = A,S &G
Status = L
BSO SubmitBOCS • Wholecloth• Delta
BOCS Profilechecks by FMB32
(BA & Supp)
FMB AnalystReview & Approve
BOCS 15%Checks by APPN
& OCC
LOADCIS
PRCPDiagnostics
OP-08Diagnostics
LOAD PRCPOP 32
Q&A
OP-32 to CISDiagnostics
OP-32 to O-1Diagnostics
Q&A
PROCESS• BSOs formulate and submit BOCS data by
OCC, ICC, AIC• FMB Analysts review for consistency with
budget descriptions• Once complete, FMB analysts approve
records in Add = A,S,G• FMB32 reviews for balance w/PBIS by BA
and LI, and profiles• FMB32 does check for 15% limit for OCC
starting with 25XX where (2521 total / 25XX Total) < 15% • Data is then loaded to PRCP and CIS• OSD system diagnostics must be reviewed
for any differences
LOAD PRCPOP 08
~ 2 Week Process
BSO FMB FMB
FMB
FMB
FMB32
FMB32
FMB32
OSD
OSD
OSD
OSD
8
Financial Management & Comptroller
8
MAR APR MAYFEB
Object Data Reviews - POM/DON Processes
JUN JUL
DatabaseRollup
Add new yearsto FYDP (POM year)
DoN Pricing Factors Gdnc
POM/PR Review by Navy and Marine Corps
Budget Guidance and Controls for DoN Submission
Fiscal Guidance by CAPE (POM year)
Blue/Green Split
Integrated Program Budget Guidance
from CAPE/OSD(C)
DoN Budget Submission
(Budgets, Issue Papers, PBIS, BOCS)
DoN Budget Review
SecNavDecisions and
Balancing
POM to Budget Handoff
Budget Guidance and Controls for BES Submission
PBCGs
BeginBES
BudgetPREP
OSD Ldrshp FMBFMB1/2/4FMB3ServicesBSOs
DoN Mid Year Reviews
DoN PVT Reviews
Hill Staff Briefings, Committee Hearings HAC/SAC/HASC/SASC
Committee Action HAC/SAC/HASC/SASC
New FMB Application Development
Fxnl Xfr
DoN In-Sourcing Review
BSO Budget Formulation
LdrshpUpdates
Object Data Review
9
Financial Management & Comptroller
9
J Booksto Hill
SEP OCT NOVOSD BES
Data Submit#
FMB/BSOInflationClean-up
AUGFMB/BSO
RMDClean-up
#
SignedRMD Issued
By OSD
FMBJ Book Review
BSOJ Booksto FMB
Load SDCS
PrintJ Books
Security Review
Highlights Book
• RMD = Resource Management Decision• RMD 800 = OSD Issues• RMD 802 = Inflation (Pay, Purchase, Fuel)• RMD 426 = WCF Adjustments
OSD/OMB Review
SNaPDue
Inflation RMD 800and RMD 426
Draft RMDsand PDMs
FMB23Load
R&D XML
Rollout Brief Prep
BudgetControls
#
BSOBOCS
DEC JAN FEBOSD BESJ Books
#
Issue Papersassigned to
CAPE/OSD(C)
FMB/BSOFY10 EOYClean-up
#
FMB/BSOFY10 Congr
Action Clean-up#
300 Series3 D’s
Final BudgetSubmission
To OMB
BSOReclamas
FMBAppeals
FMB/BSOEarmark
Reporting
OSD FMBFMB1/2/4FMB3FMB/BSO BSORequires GDNC #
Object DataReview
10
Financial Management & Comptroller
10
Object Data Challenges
Object Data Submissions Proficiency
Handling the information only three times per year Command turnover and impact to corporate knowledge base
Approach to Object Data System updates – Wholecloth versus Delta ERP enhancements and the drive for improved data fidelity End of Year Actuals reporting Object Class Information is starting to instill discipline in budgetary
processes – natural carryover to execution
Timing and Schedule Continued refinement of processes to improve product at the PB Automation and unintended tradeoffs
11
Financial Management & Comptroller
11
Headquarters Perspective
Object Data is now more important than ever DON focus areas
Data accuracy paramount for standard budgetary work Contractor Services trends (25.1/25.2) must be consistent and decreasing
across budget display years 15% checks ((25.2/Sum of 25) < 15%) New BOCS code has been deployed to reduce difficulty in loading data
OSD trends Appetite for Object Data, trends, and perceived errors OSD is constantly using data trends to determine new areas in the budget to
exploit for their review OSD is already looking at alternative methods to re-engage Contractor
Services efforts – FPDSNG and other contract data sources
The future Object Data, while limited in detail today, will evolve as we go forward to
new levels of accuracy and detail Advances in Navy ERP and other automation
12
Financial Management & Comptroller
12
Process Flow for budget formulation
Connection between BOCs budget formulation and budget execution
BSO Key Takeaways
Object Data from the BSO perspective
13
Financial Management & Comptroller
BSO Process Flow for update of BOCSF
MB
BS
OA
PP
NC
oord
inat
or
BS
OC
omp
trol
ler
An
alys
t
BS
OP
MO
FMB Issues call to update BOCS
Pull last BOCS
submission
Reconcile APPN level changes
Review for programmatic
changes
Update for latest budget changes
Review in concert with formulation
changes
Receives final input for each
program
Consolidates BOCS
Receives BSO upload
Data provided to NWCF activities to support A-11
14
Financial Management & Comptroller
Connection between BOCS and Execution
AA 17 0 1506 U5B1 253 00019 0 050120 2D 000000 A00000039869
ACRN Ser
vice
Des
ign
ator
Las
t D
igit
of
Beg
inn
ing
FY
Ap
pro
pri
atio
nSubhead O
bje
ct C
lass
Su
bal
lotm
ent
Authorized
Accounting Activity
TransactionType (normally 2D)
All Zeroes
Local UseClaimant/PEOBudget Activity
Cost Code
BC
N
Last 10 digits of the Cost Code are unique to each PR
Sequential two digit alpha numeric that changes with each
unique chargeable objectEvery financial transaction executed is connected to OCC and BOCs via LOA4
APPN BA LI BSO PEO SUBLI OCC ICC AICD/R ISSUE $2011 $2012 $2013
WPN 02 2101 19 C 00 2511 0932 XN D 70325 141 143
WPN 02 2101 19 C 00 2511 0934 ZN D 70325 4544 4415
WPN 02 2101 19 C 00 2521 0989 00 D 70325 2130 2164
WPN 02 2101 19 C 00 2531 0987 00 D 70325 1006 1094
WPN 02 2101 19 C 00 2533 0610 N1 D 70325 6278 5449
WPN 02 2101 19 C 00 2533 0611 N2 D 70325 5426 4664
WPN 02 2101 19 C 00 2533 0612 N3 D 70325 5233 4613
WPN 02 2101 19 C 00 2533 0614 NG D 70325 35 36
WPN 02 2101 19 C 00 2601 0412 CO D 70325 266867 280883
Example of BOCS Data
15
Financial Management & Comptroller
BSO Key Takeaways
Ensure Budget Adjustments reflect appropriate Object Class Codes CSS Efficiencies to OCC 251 etc.
If actuals do not match plan…be prepared to explain Programmatic explanation is key
Timely update of execution actuals
BSOs utilize execution detail to monitor OCC execution vs. plan
17
Financial Management & Comptroller
17
PBDD
PBIS BOCS
CIS PRCPSDCS
FYDP
MAX
BS
OD
ON
OM
BO
SD
Object Data• Different Structure• Critical for Annual Accounts• APPN/BA/LI/OCC/ICC/AIC• Used extensively in Inflation
Budgetary Data• Must be at the appropriate level of detail• Sub-LI coding is critical to the display• APPN/BA/LI/PE/CT/SUBLI/SI/Constr
• SDCS is feeder system, for FYDP
• PE driven•
APPN/RIC/SPC• Display
only
• CIS is APPN, BA, SPC – Aggregate Control set here
• PRCP is same level of detail as PBIS
• Both feed SDCS for TOA
• Manpower and RF TOA
• MAX is both TOA and Object Data used for creating the PB
BSOLegacy Systems ERP
• No direct link for budget info
ObjectData
OP-32OP-08
The Data Systems
Dash 1’s
EDS
BSO Input
DFAS
FMB