092916 navigating the commercial permitting … fire department (dfd) sudp and environmental health...
TRANSCRIPT
![Page 1: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/1.jpg)
Navigating the Permitting Processfor Commercial Projects plus
2015 IECC HighlightsSeptember 29, 2016
1
![Page 2: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/2.jpg)
THANK YOU!
• Gensler - Jon Gambrill & Virginia Armstrong• Exponent, Inc.• Colorado Code Consultants• Group 14 Engineering
Please sign in if you wish to receive ICC or AIA CEUs
2
![Page 3: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/3.jpg)
1. SDP Process2. Zoning and Building Codes3. Logging in Plans for Building Permits
Initial Log-in Process Commercial Permitting Resources Resubmittals vs. Modified Drawings Permit Pick-up
4. Plan Review Teams Architectural / Structural Mechanical / Plumbing Electrical Denver Fire Department (DFD) SUDP and Environmental Health
5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred Submittals – 1 Asbestos, Lead Paint, Water Supply - Lead Pipe Linkage Fee
6. Inspections7. Questions
Agenda
3
BUILDINGCOMMUNITY
8. IECC Highlights 9. Questions
![Page 4: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/4.jpg)
Know Your Zoning, Landmark and Parkway Status
Web Resource:
Use the DevelopDENVER map to find the zoning, landmark, and floodplain status for your property as well as the commercial project coordinator and
wastewater and transportation engineers assigned for your area.
https://denvergov.org/maps/map/developmentservices
4
![Page 5: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/5.jpg)
Map Amendments (Rezoning)
• www.denvergov.org/rezoning
• Because the process amends the city’s official zoning map, a rezoning is also referred to as a “map amendment.”
• Public Process to change zone district
• Changes rules for structures, uses, and parking
• Does NOT approve a specific development
5
![Page 6: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/6.jpg)
Site Development Plan (SDP) or Commercial Zoning Review Process
6
![Page 7: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/7.jpg)
Development Review
Site Development Plan (SDP)• Site development review required for
new development and major additions. Excludes single-family and duplex.
• Cases managed by Project Coordinators (PC)– Facilitate multi-agency review – Provide comments to applicant
7
www.denvergov.org/ds
Commercial Zoning Review• Applicable to any commercial or multi-family tenant-finish, existing buildings,
and use permits, etc.
![Page 8: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/8.jpg)
Concept SDP Review
Formal SDP and Building
Permit Reviews
Building Permit
Issuance / Construction
Constructionand
Zoning Inspections
Final Acceptance/Occupancy
Timeline
8
Site Development Plan (SDP) Phase Plan Review, Permitting & Inspection Services
* Timeline can change due to zoning and/or Public Works variances, building code Administrative Modifications, etc.
General Timeline*
SDP Phase: 3-5 review cycles
Total to Building Permit: 6-9+ Months
![Page 9: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/9.jpg)
Concept Phase
• Contact project coordinator (PC)
• Submit concept plan, which is reviewed by referral agencies
• Attend concept review meeting
• Receive comments (outline of next steps)
No Fee for this phase!
9
![Page 10: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/10.jpg)
Project Coordinator (PC)Assignment Areas
10
To find your PC, go to:
https://denvergov.org/maps/map/ developmentservices
![Page 11: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/11.jpg)
Referral Agencies
11
Parks & Recreation14. Forestry15. Parks Planning
Public Works7. Floodplain8. Policy and Planning9. Site Eng. Trans.10. Site Eng. Wastewater11. Solid Waste12. Special Districts13. Survey
Other Agencies16. Asset Management, Real
Estate17. City Attorney’s Office18. Dept. of Disability Rights 19. Emergency Management20. Environmental Health21. Fire Department22. OED
Outside Agencies23. CDOT Referral24. Denver Public Schools 25. Denver Water26. Metro Wastewater27. RTD28. Urban Drainage 29. Xcel Energy
CPD1. Building 2. GIS 3. Landmark4. Planning Services5. Urban Design6. Zoning
![Page 12: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/12.jpg)
Concept PhaseSubmittal Requirements
• Application• Current zoning• Identify streets• Vehicular access, parking• Building footprints• “Build-to” line identifying
“building form” from DZC• Preliminary building
elevations (in design review districts)
12
• Setbacks• Water quality / detention*• 100 yr. detention /
calculations*• Sanitary sewer
calculations*• Finished floor elevation*• Hydrant and water lines• Easements
![Page 13: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/13.jpg)
Development ReviewFormal Phase
• This is the first technical submission of plans• 3 – 5 resubmittals are typical to expect• Reviews by referral agencies (3 – 4 weeks)• Building permitting phase starts during
formal SDP reviews with “OK” from PC• Final SDP is submitted and recorded• Receive zoning permit for construction
13
![Page 14: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/14.jpg)
Formal SDP ReviewSubmittal Requirements
• Updated Project Initiation Sheet
• Fees (due at second formal submittal)
• Site Development Plan set
14
• Cover Sheet• Survey• Site Plan• Floor Plans• Parking Plan Sheet(s)
• Utility and Grading Plan• Landscape Plan• Architectural Building
Elevations• Photometric Plan
![Page 15: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/15.jpg)
Development ReviewVariances/Timing
• Encroachments into public ROW– Tier I & II (Administrative Review) – 2 to 4 weeks– Tier III (City Council Approval) – 6 to 9 months
• Public Works street variance – Administrative Review – minor 2 to 3 weeks, major 3 to 6 months
• View Plane variances – Requires Planning Board approval
• Zoning variances – Board of Adjustments approval – 2 to 3 months
• Zoning administrative adjustments – 2 to 3 weeks
• Easement relinquishment and ROW vacation – 3 to 6+ months
15
![Page 16: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/16.jpg)
16
Zoning and Building Codes
![Page 17: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/17.jpg)
Denver Zoning Code (DZC) and Former Chap. 59
• www.denvergov.org/zoning
• Administered by the Zoning Administrator
• Role of DZC– Implements the city’s vision for the
future of Denver– Guides orderly development of the City
• Regulates:– Structures – where, how big– Uses – permitted by right, permitted
with limitations, not permitted– Parking – where, how much
17
![Page 18: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/18.jpg)
A Tale of Two Codes
18
Former Chapter 59 (FC59)The “Old” CodeAdopted in 1956
Denver Zoning Code (DZC)The “New” CodeAdopted in 2010
![Page 19: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/19.jpg)
Former Chapter 59(“Old Code”)
19
![Page 20: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/20.jpg)
2016 Denver Building and Fire Code
• www.denvergov.org/buildingcode
• 2016 Denver Amendments
• 2015 Series– International Building Code– International Existing Building Code– International Plumbing Code– International Mechanical Code– International Residential Code– International Fuel Gas Code– International Fire Code– International Energy Conservation Code
• 2014 – National Electrical Code
20
![Page 21: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/21.jpg)
21
Logging in Plans for Building Permits
![Page 22: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/22.jpg)
Log-in Team
22
• Ingrid Antoine• Dionne Bell-Hudson• Alicia Bock• Thaddeus Boles• Cheryl Booker
• Qiana Fletcher• Nadine Garcia• Sabrina Keil• Angela Merritt• Bette Rhone
Angela Abeyta (Supervisor)
![Page 23: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/23.jpg)
Commercial ReviewProject Types
• Commercial Walk-Through Review– Less than $500K (no structural modifications)– No change of occupancy or DEH review– First come, first serve: 8 a.m. to 11:30 a.m.– Same-day permit
• Intermediate Project Log-in– Up to $1M– First come, first serve: 8 a.m. to 4 p.m. or by appointment– 4-6 week initial review
• Major Project Log-in– $1M and over– First come, first serve: 8 a.m. to 4 p.m. or by appointment– 8-10 week initial review
For more info: www.denvergov.org/buildingcode ADMIN 131
23
![Page 24: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/24.jpg)
How to Check In
For counter services, check-in opens at 8 a.m. by phone, by text, in
person, or online
• Call: (720) 880-3670
• Text: “denver dev” to (626) 414-3210
• In person: Wellington E. Webb Building201 W. Colfax Ave., 2nd Floor, Denver, CO 80202
• Online: www.denvergov.org/ds
Or through PocketGov
24
Counter hours always available online at www.denvergov.org/ds under “Contact Us”
![Page 25: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/25.jpg)
Permit Counter Time Changes
Permit counter to open at 9 a.m. on Tuesday, October 11, and Tuesday, October 18
The Development Services Permit Counter will open at 9 a.m., instead of 8 a.m., on Tuesday, October 11, and Tuesday, October 18, in order for staff to attend training events.
25
![Page 26: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/26.jpg)
Scheduling Appointments
26
An appointment is required to log-in for the following project types:
• If project has gone through the SDP process and you have a Project Coordinator (PC), or
• It is a Type Approved (TA) project, or
• You are picking up multiple permits (e.g., townhome projects)
To schedule an appointment, email [email protected] have your PC request an appt. (for SDP projects)
![Page 27: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/27.jpg)
To Start Plan Review
From Log-in Counter to the Cashier• Once drawings are accepted at the log-in counter, you must go
to the cashier and pay the plan review fee
• Please note, plan review cannot be assigned until the plan review fee is paid!
27
![Page 28: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/28.jpg)
To Have a Successful Log-in
28
Top Log-in Tips
• Include structural calculations• Have MEP plans • Have code analysis containing
correct building code references, including method of IECC compliance
• Plans have the original stamp and signature
• Have your zoning permits or “ok” from PC to log in
• Bound plans
Check out our commercial building guides and resources online:
www.denvergov.org/buildingcode
![Page 29: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/29.jpg)
Resubmittals vs. Modified Drawings
29
• Resubmittal: Drawings submitted to respond to plan review comments – Submit via the “Resubmittal” queue at the Permit Counter– Have project log-in number with you– Approx. 4-6 week review depending on project type– ONLY resubmit sheets containing changes - cloud changes
• Modified drawings: Submitted as a change AFTER permit has been issued– Must submit a description of what is modified and why– Submit via the “Log-in” queue at the Permit Counter– Gets a new, separate log-in number– Once approved, receives a separate permit
Making Improvements
“Resubmittal day” and major project
meetings
![Page 30: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/30.jpg)
Picking Up Your Permit
• Must be a licensed contractor in Denver– Proof required (contractor license card, company check, or company
credit card)
• Commercial construction permit is issued first, sub-permits are issued via Quick Permit (in person, fax, or email)
• Commercial construction permit pick-up at “Logged in Plan Pick-up” queue, or schedule an appointment if required
• Check made payable to the “Manager of Finance”
• Email Angela Abeyta for fee amount: [email protected]
• To access fee schedules and the ADMIN 138 fee policy: www.DenverGov.org/dsfees
30
![Page 31: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/31.jpg)
31
Plan Review Teams
![Page 32: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/32.jpg)
Architectural/Structural Review Team
32
Eric Browning, PE (Supervisor)
• Alex Abel, PE• Vince Anderson, PE• Dave Johnson, PE• Tim Kirby, PE• Daniel Krausz, AIA• Keith Ostrander, PE• Keith Peetz, PE• David Renn, PE• Street Schellhase, PE
![Page 33: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/33.jpg)
Tips from the Architectural/Structural Review Team
33
Make sure to double-check your submittal for the following:
• Provide a complete submission— Incomplete submittals usually lack calculations, specifications, code
analysis, lateral analysis and detailing for townhomes, door schedules, UL assemblies including head-wall assemblies, and/or accessibility details.
• Ensure occupant load for occupancy and toilet fixtures is based on “Function” of Table 1004.1.2 of the 2015 IBC and not on “Use” in Chapter 3
• Continuity of fire-resistant rated assemblies — Examples: fire walls, fire barriers, fire partition, smoke barriers, smoke
partitions, and head-wall assemblies with specific UL, Gypsum Association, or IBC Chapter 7 prescriptive cross references
![Page 34: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/34.jpg)
Mechanical/PlumbingReview Team
34
Danny Boncich, PE (Supervisor)• Chuck Bartel, PE• Keith Fox, PE• Kirk Gallaher, PE• Bret Pica, PE
![Page 35: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/35.jpg)
Tips from the Mechanical/Plumbing Review Team
35
Make sure to double-check your submittal for the following:
• Fire and smoke dampers to match the rated walls, per the Architectural Drawings– Reference: drawing coordination and Sections 607 of IMC, 716 of IBC, and SMACNA
Standards
• Kitchen hood design details – These are often not provided or are missing information. Reference: Sections 506,
507, and 509 of IMC and NFPA 964
– For adequate separation between exhaust and intakes, property lines, other buildings, etc., reference: Sections 401.4 and 401.5 of IMC
• Outside air calculations – These are often not provided or are incorrect.
– Occupancy loads, effectiveness or efficiencies not correct. Reference: Section 403 of IMC
![Page 36: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/36.jpg)
Electrical Review Team
36
Carol Pafford, PE (Supervisor)
• David Carlson, PE• Reynaldo Ornelas, PE• Kevin Simpson, PE• Kevin Lieu, PE
![Page 37: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/37.jpg)
Tips from the Electrical Review Team
37
Make sure to double-check your submittal for the following:
• Two sets of electrical plans with signature and seal of Professional Engineer in responsible charge– This is particularly an issue in resubmittals.
• Adherence to the requirements of DBCA 133.2.10– Examples: Incomplete electrical designs often lack a one-line diagram,
fault current/short circuit current analysis, load calculation analysis, grounding, overcurrent ratings, conductor and conduit sizes, panel schedules
• Provide a complete submission– Often, there are no electrical drawings submitted at all.
![Page 38: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/38.jpg)
Denver Fire Department (DFD)Review Team
38
David Clark, PE (Supervisor)
• Adam Andrzejuk, PE• Tony Caro, PE• Brad Emerick, PE• David Hill, PE• JD Lanz, PE• Brian Lucas, PE• George Morkovin, PE• Roman Rede, PE
![Page 39: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/39.jpg)
Tips from the DFD Review Team
39
Make sure to double-check your submittal for the following:
• A narrative description of the scope of work for which a permit is sought– This will soon be required in the 2016 DBC Amendments
• Code analyses that account for noncompliant existing conditions, or existing conditions made noncompliant by the proposed change in use
• Deferred Submittals:– HazMat Quantities– Generators– Smoke Control– Sprinklers
![Page 40: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/40.jpg)
Tips from the DFD Review Team for High-Rise Facilities
40
Make sure to double-check your submittal for the following:
• Direct access to the fire service elevator(s) from the Fire Command Center (FCC)
• Piping and HVAC cannot pass through the FCC
• FCC proximity to the main entrance
![Page 41: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/41.jpg)
SUDP and Environmental Health
41
• Sewer Use and Drainage Permitting (SUDP) Department – Part of the Wastewater Management Division of Public Works– Reviews and permits sanitary and storm sewer drainage systems
for all construction projects– Reviews construction plans, collects fees, and issues permits
• Department of Environmental Health (DEH) – Projects that require a Health Review include restaurants, other
retail food-related uses, publicly accessible pools, early childcare, schools, marijuana dispensaries, marijuana infused product (MIP) kitchens, and marijuana extraction facilities
![Page 42: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/42.jpg)
Tips from the SUDP Review Team
42
Make sure to double-check your submittal for the following:
• Complete Utility Site Plans – Show all sanitary, storm, and water facilities
• All supporting documents – These are often overlooked: Restaurant Menus, Food & Beverage
Questionnaire, Kitchen Equipment, Industrial Waste Survey, Legal Agreements, Complete Application Forms, etc.
• Resubmit any changes in the scope of work – Changes to the plans will need a resubmittal, most notably for changes to
waterline size, and sanitary or storm relocation/resizing
For SUDP info: www.DenverGov.org/SUDP
![Page 43: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/43.jpg)
Make sure to double-check your submittal for the following:
• A complete Plan Review Guide with fixture counts, water calculations, menu, and equipment specification sheets
• Hand sinks in required areas
• Hot water heating systems sized to provide hot water to all required fixtures during all hours of operation
• Provide the location of approved mop/utility sink
• A full equipment plan and schedule for facility – Provide plans and documentation for the entire facility rather than just
the scope of work
For DEH info: www.denvergov.org/DEH
43
Tips from the DEH Review Team
![Page 44: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/44.jpg)
44
Administrative Policy Updates
Visitwww.denvergov.org/buildingcodeto access current policies
![Page 45: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/45.jpg)
Policy ReviewPrep Demo “Early Start” Permit 131.2
45
A time-saver for customers
• Plans are submitted and permits can be pulled prior to plan review being completed (project must be logged in for review)
• Construction can be completed up to the point of rough inspection
• Requires separate trade or subcontractor permits
• Rough inspections cannot be called until permits are released
• Requires affidavit from Arch. & Engineers stating documents are 100% complete
• B & M Use Group (some S1 & S2 uses)
• No structural work can be considered
![Page 46: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/46.jpg)
Policy ReviewSimultaneous Zoning/Building 130A
46
Another time-saver for customersWork in progress:
• Will allow certain projects to have both the zoning and building code reviews completed at the same time (at risk)
• There are several test cases in process
• A formal policy should be adopted in 30-60 days
• Please submit your comments to the draft policy (handed out) to [email protected]
![Page 47: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/47.jpg)
Policy ReviewDeferred Submittals
47
• Deferred Submittal: The portions of a design that are not submitted at the time of application, but which are to be submitted within a specified period
• Alternatives to be allowed under 2016 DBC Administrative Policy 133.5:
• If “deferred submittal” items are ready, submit them with the primary building permit submittal
• Submit deferred submittal items at the time of the first resubmittal. Scope is included in the primary building permit
• Submit deferred submittal(s) for review and permit in the traditional sense, following the review and permit for the primary building permit
![Page 48: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/48.jpg)
Policy ReviewFoundation/Superstructure Submittals
• MUST have specific scope of work for each trade/discipline on the plans for each phase
• Fees and timing of submittals– Building portion of project in 2 parts (25% plan review and permit
premiums per part)
– Building portion of project in 3 or more parts (50% plan review and permit premiums per part)
– For multi-part projects, the submittal of the second package shall notprecede the first resubmittal of the first package
• This provides greater efficiency in plans review, response, and permitting and ultimately saves time and costs for the developer or owner
48
![Page 49: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/49.jpg)
New Initiatives Partnering for Safer Building
• Asbestos Inspection
– For permits in existing buildings, customer must provide the asbestos inspection acknowledgement form at time of building log in
– By the end of the first quarter 2017, customer must provide proof of asbestos inspection to receive building permits when the area to be disturbed exceeds the public and commercial building “trigger level”
• Lead Paint Process
– Childcare facilities and schools built before 1978 need to have a certified lead paint contractor on board to remediate any lead paint
– By end of the first quarter 2017, customer must provide the certified lead paint contractor for any building permits to be issued for these facilities
49
![Page 50: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/50.jpg)
New Initiatives Partnering for Safer Building
• Asbestos Process– Prior to 1/2/17 – acknowledgment– After 1/2/17 – certified verification
• Lead Paint Process– Prior to 1/2/17 – acknowledgment– After 1/2/17 – certified RRP letter
• Water Supply Line Verification– Prior to 1/2/17 – acknowledgment– After 1/2/17 – certified Denver Water verification
50
![Page 51: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/51.jpg)
Affordable Housing Linkage Fee
• Fee is applicable to new gross square footage (not parking) – will require a new application form to be submitted at building permit log-in
• Takes effect 1/1/2017 for building permits for new construction and additions
• Plan ahead– Commercial or multifamily projects in SDP review must have logged in an SDP
concept plan before Friday, 12/30/16 (allow AT LEAST 3 days to do so)– Non-SDP projects must have logged in plans for building permit review by 12/30/16
– Major changes requiring a new SDP submittal after 1/1/17 are subject to the fee
Sq. ft. fees will be adjusted by CPI annually starting in 2018
51
Project Type Fee, per sq. ft.
Single-family / duplex / IRC townhomes $0.60
Multi-family, including IBC townhomes $1.50
Commercial development -- Hotel, office, retail, other OR Civic, public or institutional $1.70
Commercial development -- Industrial, manufacturing, wholesale and agricultural $0.40
![Page 52: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/52.jpg)
52
Inspections
![Page 53: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/53.jpg)
Building Inspections
53
• Commercial building inspections called the day before are completed the next day, dependent on volume and type of requests received– After hours inspections
– Special inspections
Inspection Challenges
• There is a limit to the amount of work that can be inspected on one visit for large commercial and multi-family projects
• Going beyond the approved scope– TIP: Frame inspections require all other trades prior to requesting this inspection
Information on scheduling inspections and avoiding re-inspection fees: www.DenverGov.org/buildinginspections
![Page 54: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/54.jpg)
Other Inspections
DEH• Contact Kerwin Nance at (720) 865-2832 to schedule 2 – 3 days in advance
Z/NIS• Contact 311 to schedule Z/NIS construction inspections
– Bulk plane, setback verification, signs, final building sign-off
SUDP• Contact (303) 446-3759 to schedule
– Must be a licensed plumber or sewer contractor to call in an inspection
• Inspections requested by 3:30 pm are completed the next day, as demand allows– After hours inspections available by request
54
![Page 55: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/55.jpg)
DFD Inspections and Testing
• All fire protection systems (e.g., fire alarms, sprinklers)
• Life-safety (e.g., exit sign, smoke & CO alarms)
• Smoke control testing
• Phased occupancy
• Contact (720) 913-3480 to schedule 1 – 2 weeks in advance
55
Other Inspections
![Page 56: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/56.jpg)
56
Questions
![Page 57: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/57.jpg)
57
IECC Highlights
![Page 58: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/58.jpg)
Denver IECC Policies
58
IECC R101, R103, C101, C103, C408 Submittal Requirements Policy
• Provide separate energy drawings (new buildings, additions, renovations, change in use, and change in occupancy)
• Method of compliance should be clearly noted in the code analysis (prescriptive, performance, method 3 - energy rating index)
• 2015 IECC or ASHRAE 90.1-2013
• Commission agent required to be named at permit issuance
• Preliminary commission report required prior to TCO or CO
• Intent is to create faster plan review, assist during the inspection process, and create more energy-efficient / compliant buildings
• Other IECC Policies
• Section C202 - Approved Agency
• Section C408.2.4 – Commissioning Compliance Checklist
![Page 59: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/59.jpg)
Where to Find the IECC Policies
• Available for download from www.denvergov.org/buildingcodeunder “Building code policies”
59
IECC R101, R103, C101, C103, C408 Submittal
Requirements Policy
Other IECC Policies
![Page 60: 092916 Navigating the Commercial Permitting … Fire Department (DFD) SUDP and Environmental Health 5. Administrative Policy Updates Prep-Demo - 131.2 Simultaneous Review - 130A Deferred](https://reader033.vdocuments.us/reader033/viewer/2022051800/5aca13e77f8b9a6b578d6f94/html5/thumbnails/60.jpg)
Contact Us
Contact Development Services
Main office hours and all other services8 a.m. to 4 p.m.
PhoneGeneral inquiries: 720-865-2705Cashier: 720-865-2780Building permit records: 720-865-2790 or 720-865-3020 (fax)
60
Mailing Address:Development Services
201 W. Colfax Ave., Dept. 205Denver, CO 80202