0312 ~') 11~~gmw.consrv.ca.gov/shp/apsi_siteinvestigationreports_ocr/apsi_0… · 18/12/1989...
TRANSCRIPT
'
,,-- .
' !
; I ;
t_
.. '
! ·- -..
SOIL, FOUNDATION AND GEOLOGICAL ENGINEERS
0312
~') 11~~ 11!.l Ml',,{)/
.. Ii j!P-••
•
•
• • • • • • I
• •
,;,~ ·.CO i
·CO ~
, .
. .:
i
., :;
\), ..._ -0 I - --• • ', - • .. •' 'f_ -\ 2009at1'' '' ,
- ' -- - -. 1 I I \
Figure 3-4
•
•
•
•
•
•
•
•
•
•
•
on PRO~~fpj;~PrNT ;~~~··l) ' .:·,·~·~iJ', ~
13575 Lake Chabot Road San Leandro, California
for SIGNATURE PROPERTIES
By
TERRASEARCH, INC .
•
•
•
•
•
•
•
•
•
•
•
·-~ GEOTECHNICAL ENGINEERS AND GEOLOGISTS
,.~ 'l~l~ltltA S~Altt~H INt:. 15e<I NORTH FOURTH STREET, SAN JOSE, CALIFORNIA 95112-4676, (408) 453-1180
Project No. 6063 18 December 1989
Signature Properties 6612 OWens Drive Pleasanton, CA 94566
Attention: Mr. Jim McKeehan
Subject:
Refs;
Gentlemen:
San Leandro Rock Quarry 13575 Lake Chabot Road San Leandro, California GEOTECHNICAL ENGINEERING INVESTIGATION
l) Geologic/Seismic Investigation Report By TERRASEARCH, INC. Dated August 2, 1989
2) Environmental '.resting Results By TERRASEARCH, INC. Dated July 24, 1989
3) Fault Location Investigation By Cleary Consultants, Inc. Dated December 27, 1977
In accordance with your authorization, TERRASEARCH, INC., has investigated the geotechnical conditions at the subject site of the proposed residential development in San Leandro, California .
The accompanying report presents our conclusions and recommendations based on our investigation. Our findings indicate that the site is physically suitable for the proposed construction provided.the recommendations of this report are carefully followed and are incorporated into the plans and specifications •
I 11840 DUBLIN BOULEVARD, DUBLIN, CALIFORNIA 94568, (415) 833-9297
2349 NORTH WATNEY WAY, BLDG. A, FAIRFIELD, CALIFORNIA 94533, (707) 422-3292
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
Should you have any questions relating to the contents of this report or should additional information be required, please contact our office at your convenience •
Reviewed by:
~~~~. Principal Engineer
Very truly yours, TERRASEARCH, INC.
~~.e/ • :' : . ~. ·~·; 1! . t11Hiibiinr
Staff Engineer
Copies: 6 to Signature Properties
(ii)
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 Decmeber 1989
TABLE OF CONTENTS
LETTER OF TRANSMITTAL
GEOTECHNICAL ENGINEERING INVESTIGATION
Purpose and Scope Proposed Development Site Location and Description Soil Conditions Liquefaction Potential Evaluation
DISCUSSIONS, CONCLUSIONS AND RECOMMENDATIONS
General Demolition Grading Slopes Drainage Remedial Measures and Mitigation of
Existing Slide Foundations Slab-On-Grade Construction Retaining Walls Pavement Areas General Construction Requirements
GUIDELINES FOR REQUIRED SERVICES
LIMITATIONS ANO UNIFORMITY OF CONDITIONS
APPENDIX A
Field Investigation Site Plan (Figure 1) Logs of Test Borings (Figures 2 through 8) Typical Landslide Reconstruction Detail
(Figure 9) Landslide Buttress Detail (Figure 10) Typical Subdrain Section (Figure 11)
(iii)
Page No .
1 1 2-3 3-4 4-5
6-7 7-8 8-11
11-13 13-14 14-15
15-17 17-19 19-21 21-22 22-24
25-26
27-28
30 31 32-38 39
40 41
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 Decmeber 1989
APPENDIX B
TABLE OF CONTENTS (continued)
Page No.
Laboratory Investigation 43 Summary of Laboratory Test Results (TABLE I) 44
APPENDIX C
Recommended Grading Specifications Guide Specifications For Rock Under
Floor Slabs
(ivl
46-54 55
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
GEOTECHNICAL ENGINEERING INVESTIGATION
Purpose and scope
The purpose of the investigation for the proposed residen
tial development on Lake Chabot Road in San Leandro, Cali
fornia, was to determine the surface and subsurface soil
conditions at the subject site. Based on the results of the
investigation, criteria were established for the grading of
the site, the design of foundations for the proposed struc
tures, and the construction of other related facilities on
the property. Our investigation included the following:
a. Field reconnaissance by the Soil Engineer;
b. Drilling and sampling of the subsurface
soils;
c, Laboratory testing;
d. Analysis of the data and formulation of con-
clusions and recommendations;
e. Preparation of this written report .
Proposed Development
The proposed development consists of single-family houses,
appurtenant streets, and retaining walls .
1
•
•
•
•
•
•
•
•
•
Site Location and Description
Project No. 6063 18 December 1989
The subject site lies just east of the City of San Leandro
on the upslope (south) side of Lake Chabot Road. The sub
ject property is in County Territory, but its western boun
dary is the easterly City Limit (see Figure l). The proper
ty extends about 1,500 to 1,700 feet south from the road and
is about 2, 0 00 feet wide.
acres .
The parcel includes about 59
The quarry which the property contains was first started in
the 1880's on the north end of a northwest trending ridge.
Nearly the entire property was quarried, and very few natur
al slopes remain. The native slope immediately above Lake
Chabot Road is densely forested and ranges between 1: 1 and
2:1 (horizontal to vertical) in inclination. A grass
covered, 2:1 slope near the south border of the site is the
only other significant remaining natural slope .
As a result of the quarrying operation, overburden material
was disposed of on site. It appears that the western por
tion of the site still contains the bulk of this fill. The
fill appears to have been placed as uncontrolled fill •
2
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
Total relief on the site is about 500 feet, with elevation
ranging from about 305 feet at the northwest corner to 805
feet at the southeast corner. Most of the cutslopes have
been finish-graded. The major north-facing slope on the
south side of the site is cut at between 1.5:1 and 2:1 with
benches every 25 to 30 vertical feet, However, a 60-foot
high cut at the center of the site has no benches and has an
inclination of about 1: 1. Other unfinished quarry slopes
near the center of the site are nearly vertical and 50 to 75
feet high. Some small trees have been planted on the cut
slopes, but most of the vegetation consists only of grass
and low weeds. About a dozen man-made structures are pres
ent in the north part of the site. These include a resi
dence, an office, several barns and sheds, and crushing/
screening facilities.
This description is based on a site reconnaissance by the
Engineering Geologist and a 100-scale topographic plan by
Bissell & Karn, Inc., dated April, 1987.
Soil Conditions
The on-site surface and subsurface conditions in the upper
layer overlying bedrock vary over the site depending on
whether the borings were made in cut, fill, or undisturbed
soil. The majority of the underlying soil is considered low
to medium expansive except for some of the near-surface
3
•
•
•
•
•
•
•
•
•
)
Project No. 6063 18 December 1989
soils encountered in the undisturbed native soil. The soils
encountered consisted of reddish-brown, dense
gravelly clayey sands or gravelly sandy clays,
soil horizon, bedrock was encountered.
to hard,
Below the
No groundwater was encountered at the time of exploration .
Fluctuations in the groundwater table are anticipated with
variations in the seasonal rainfall.
A more thorough description and stratification of the soils
encountered are shown on the "Logs of Test Borings". The
results of the laboratory tests are presented in TABLE I,
Results. " The approximate "Summary of Laboratory Test
locations of these borings
Plan", Appendix A.
are shown on Figure 1, "Site
Liquefaction Potential Evaluation
Liquefaction occurs primarily in relatively loose, satur
ated, cohesionless soils. Under earthquake stresses, these
soils become "quick", lose their strength and become incap
able of supporting the weight of the overlying soils or
structures,
The data used for evaluating liquefaction potential of the
subsurface soils consisted of: the penetration resistance,
the soil description, the relative density of the materials,
and the groundwater conditions.
4
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
Based on the data obtained and in view of the cohes.ive type
soil characteristics, it is our opinion that the near-sur
face soils are not prone to liquefaction .
5
•
•
•
•
•
•
•
•
•
•
•
~neral
Project No. 6063 18 December 1989
DISCUSSIONS, CONCLUSIONS AND RECOMMENDATIONS
1. The site is suitable for the proposed residential devel
opment provided the recommendations presented in this report
are incorporated into the project plans and specifications.
2. All Grading and Foundation Plans for the development
designed by the project Civil Engineer must be reviewed by
the Soil Engineer prior to contract bidding or submittal to
governmental agencies so that plans are reconciled with soil
conditions, and sufficient time is allowed for suitable miti
gative measures to be incorporated into the final grading
specifications.
3. TERRASEARCH, INC., should be notif1ed at least two work
ing days prior to site clearing, grading, and/or foundation
operations on the property. This will give the Soil Engi
neer ample time to discuss the problems that may be encount
ered in the field and coordinate the work with the con
tractor.
4. Field observation and testing during the grading and/or
foundation operations must be provided by representatives of
TERRASEARCH, INC., to enable them to form an opinion regard
ing the adequacy of the site preparation, the acceptability
6
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
of fill materials and the extent to which the earthwork con
struction and the degree of compaction comply with the speci
fication requirements. Any work related to the grading and/
or foundation operations performed without the full know
ledge and under the direct observation of the Soil Engineer
will render the recommendations of this report invalid .
Demolition
5. Prior to any grading, demolition of the site should be
completed. Demolition should include the complete removal
of all subsurface structures, concrete, septic tanks, gas
and oil tanks (if any), storm inlets, foundations, asphalt,
machinery, equipment, debris and trash, with the exception
of i terns specified by the owner for salvage. The owner
should specify the saving or removal of shrubs or trees on·
the site, In addition, all underground structures must be
located on the grading plans so that proper removal may be
carried out.
6. Excavations made by the removal of any structure should
be left open by the demolition contractor for backfill in
accordance with the requirements for engineered fill. The
removal of underground structures should be done under the
observation of the Soil Engineer to assure adequacy of the
removal and that subsoils are left in proper condition for
placement of engineered fills. Any soil exposed by the demo
lition operations, which is deemed soft or unsuitable, shall
7
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
be excavated and removed as required by the Soil Engineer
during grading. The demolition operation should be approved
by the Soil Engineer prior to commencing grading operations.
Any resulting excavations should be properly backfilled with
engineered fill under the observation of the Soil Engineer.
Should the location of any localized excavation be found to
underlie any structure, backfill should be compacted to a
minimum relative compaction of 95% or the excavation widened
to include the footprint of the structure and backfilled to
the specifications for engineered fill as recommended in the
"grading" section herein.
Grading
7. Areas containing uncontrolled fill are shown on Figure 1.
The depth of this fill varies from 2 to 20 feet as depicted
on the "Site Plan." The shallow fill has been subjected to
activity during the life of the quarry operations and
appears to be in a dense condition. The depth of fill in
the area designated as deep fill varies from north to south
with the maximum depth in the area of Boring 1. Therefore,
prior to grading on the site, the area of uncontrolled deep
fill should be excavated to native ground. The native
ground shall be properly prepared, scarified, moisture con
ditioned, and compacted to a minimum relative compaction of
90% based on ASTM Test Procedure Dl557-78 .
8
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
8. Subexcavation in the area designated as shallow uncon
trolled fill is not contemplated at this time. However,
should the material be found to be loose or organics are
encountered during the grading operation, mitigation
measures need to be implemented as required by the Soil Engi
neer in the field .
9. The surface of the site in areas to be filled should be
stripped to remove all existing vegetation and/or other dele
terious materials. It is estimated that stripping depths of
4 to 6 inches may be necessary, however, the actual depth of
stripping should be determined in the field by the Soil Engi
neer. Stripped material from the site may not be used as
engineered fill but may be stockpiled and used later for
landscaping purposes. Any existing wood debris should be
removed from the site. Any existing loose fill should be
excavated to undisturbed native ground. Materials generated
from loose fills may be used as engineered fill with the
approval of the Soil Engineer provided they are not contamin
ated by debris.
10. Following site stripping, the top 6 inches of exposed
native ground should be scarified and compacted to a minimum
degree of relative compaction of 90% slightly above optimum
moisture content as determined by ASTM Dl55 7-7 8 Laboratory
Test Procedure . After stripping and recompacting the native
subgrade, the site may be brought to the desired finished
grades by placing engineered fill in lifts of 8 inches in
9
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
uncompacted thickness and compacted to the relative compac
tion requirements in accordance with the aforementioned test
procedure. All soils disclosed during our investigation,
except those within the top few inches of organically contam
inated material, would be suitable for use as engineered
fill when placed and compacted at the recommended moisture
content.
11. If the 'overburden expansive soil is not needed for
later use as topsoil around the structures, then it is recom
mended that this material be buried underneath deep fill so
that one type of foundation is used over the entire site.
12. Should select import material be used to establish the
proper grading for the proposed development, the import
material should be approved by the soil Engineer before it
is brought to the site and should meet the following require
ments:
a. Have an R-Value of not less than 25;
b. Have a Plasticity Index not higher than 12;
c. Not more than 15% passing the No. 200 sieve;
d. No rocks larger than 6 inches in maximum size.
Import material meeting the requirements stated above should
be compacted to a minimum relative compaction of at least
90% as determined by ASTM 01557-78 Laboratory Test Procedure.
All engineered fill should be placed in lifts not exceeding
8 inches in uncompacted thickness.
10
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
13. All exploratory trenches and test pi ts that were exca
vated for the geologic and environmental investigations
(References 1, 2, and 3) were loosely backfilled. There
fore, all pits affecting proposed foundations, streets,
curbs, or other grade features should be re-excavated and
backfilled with engineered fill in accordance with the grad
ing requirements of this report, These trenches and pi ts
should be shown on the grading plan by the Civil Engineer .
Slopes
14. Where fill is to be placed on an existing slope having
a surface gradient steeper than 5: 1 (horizontal to verti
cal), the surface soils are to be removed and these areas
keyed and benched horizontally into competent soil materials
prior to placement of engineered fill. A toe key excavation
should be placed at the base of all such fills. The width
and depth of the keyways will be determined by the Soil Engi
neer during the grading operations based on soil conditions.
Subsequent keyed benches should be not less than 1. 5 times
the grading equipment width and 3 feet in vertical height .
15. Cut and fill slopes may experience severe erosion when
grading is halted during rainy weather. Before work is
stopped, a positive gradient away from the slopes must be
11
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
established to carry the surface runoff water away from the
slopes to areas where erosion and sediment can be con
trolled.
16. Concrete or asphalt-lined drainage facilities should be
installed above all cut and fill slopes greater than 15 feet
in vertical height or where the natural drainage is directed
toward the slopes from the large drainage areas above. The
purpose of the drainage facilities is to divert the excess
surface runoff water from the slopes and, consequently, mini
mize sloughing or erosion of the slope surface.
17. After the completion of the slope grading, erosion pro-
tection must be provided . Slope planting, preferably with
deep-rooted native plants, must be completed on all exposed
surfaces of cut and fill slopes. Graded slopes should not
be left exposed through a winter season without the comple
tion of erosion control measures and slope planting .
18. Cut and fill slopes should not be steeper than 2:1 (hor-
izontal to vertical) .
may be constructed at
vertical).
Cutslopes made in competent bedrock
a gradient of 1-1/2:1 (horizontal to
19. Fill
progresses
slopes must be compacted as the filling operation
by (1) using sheepsfoot-type rollers in conjunc-
tion with proper moisture conditioning, or (2) over-construc
ting the fill slopes and cutting back the looser surface
12
,• '
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
soils to a firm and adequately compacted designed slope
grade. Track-walking of slope surfaces does not provide
adequate soil densities and is an unacceptable method of
slope compaction.
Drainage
20. The slope gradients are based on strength characteris
tics of the materials under conditions of normal moisture
content that would result from rain water falling directly
on the slope but do not take into consideration the addition
al seepage forces from springs or subsurface water areas.
Areas of observed seepage, as discovered during grading oper
ations, should be provided with subsurface drains below the
surface of the slope as directed by the Soil Engineer. Sub-
surface drainage facilities may include gravel blankets,
rock-filled trenches, horizontally-drilled drains, or perfor
ated pipe within filter gravel as shown on Figure 11 •
21. It will be necessary to install subsurface drains
beneath the fills to be placed in the swale areas, particu
larly, where boggy areas were encountered and in all other
seepage areas where disclosed during the grading operations.
This is necessary in order to provide drainage to these
areas and to ensure stability of the fills and provide a
stable base for placement of fill, where required. It is
recommended that all subsurface drains be installed accord
ing to the "Recommended Grading Specifications. " No ponding
of storm water is to be permitted on cut or fill pads during
prolonged periods of inclement weather .
13
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
22. The location of the subdrains will be defined by the
Soil Engineer during the revision of the Grading Plan. The
final location, addition, or deletion of subdrains will be
determined in the field by the Soil Engineer during the grad
ing operations .
23. Drainage benches should be provided at 30-foot inter
vals of vertical height for cut and fill slopes. For slopes
over 30 feet high, the benches should be placed at the mid-
point of the slope. Intermediate benches are not required
for slopes less than 30 feet in height. Drainage benches
should also be provided at all locations of changing slope
gradient. Minimum 6-foot wide benches are recommended with
lined "V" type swales or interceptor ditches leading to a
controlled discharge point. Caution must be exercised so
that the uphill lip of the concrete or asphalt swale is prop
erly backfilled to prevent infiltration of surface water
beneath the ditch which may result in saturated soils and a
slope failure.
Remedial Measures and Mitigation of Existing Slide
24. The slide mapped on the Site Plan within the area to be
developed are shallow and are located in areas where fill is
contemplated . Therefore, the entire unstable area must be
14
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
excavated and the material generated from the excavation
incorporated in the fill. No unusual procedures are re
quired for this phase of work. Should subdrains be deemed
necessary during the removal of the unstable mass, they will
be implemented as deemed necessary in the field based on
soil and site conditions .
25. The minor slides mapped on existing cutslopes above the
area of development are considered "popouts" and are small
in nature. These slides do not seem to pose any hazard to
the development. Any mitigation at this time shall consist
of removing any debris that may have deposited on the
benches below to ensure that those benches will carry sur
face runoff as they were originally intended to do. Should
any slide repair be contemplated, the method of mitigation
is shown schematically on Figure 9.
Foundations
26. The proposed building structures can be satisfactorily
supported on either a spread footing foundation system or a
pier and grade beam system provided that the site is pre
pared as previously recommended.
27. Spread footings may be used where soil conditions are
uniform over the entire building pad. The footings should
have a minimum depth of 18 inches below the lowest adjacent
pad grade (trenching depth). Design bearing pressures for
15
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
footings should not exceed 2,000 p.s.f. due to dead loads,
2,200 p.s.f, due to dead plus live loads, and 2,500 p.s.f .
due to all loads which include wind or seismic. Perimeter
footings are to be reinforced with a minimum of two No, 4
bars, one at the top and one near the bottom of the footing.
Additional reinforcement will be as determined by the founda
tion design engineer and in accordance with structural
requirements.
28. To accommodate lateral building loads, the
resistance of the foundation soil can be utilized.
passive
Where
spread footings are used, the passive soil pressures can be
assumed to act against the front face of the footing below a
depth of one foot below the ground surface. It is recom-
mended that a passive pressure equivalent to that of a fluid
weighing 250 p.c.f. be used. For design purposes, an allow
able friction coefficient of 0.35 can be assumed at the base
of the spread footings .
29. Should cracks develop in the foundation trenches before
the placing of concrete, the trenches should be soaked until
all cracks are effectively sealed. The Soil Engineer should
observe the soaking in the field prior to the concrete being
poured, if deemed necessary.
30. As an alternative foundation system, it i.s recommended
that the proposed building structures be supported on a
drilled cast-in-place friction pier and perimeter grade beam
16
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
type foundation. The piers should have a minimum diameter
of 12 inches and should extend a minimum depth of 6 feet
into native or compacted soil. The piers should be designed
on the basis of skin friction acting between the soil and
that portion of the pier that extends below a depth of one
foot below the finished grade. For the soils at the site,
an allowable skin friction value of 500 p. s. f. can be used
for combined dead and live loads. This value can be
increased by one-third for total loads which include wind or
seismic forces. Reinforced concrete grade beams should be
used to support the perimeter walls and, if desired, certain
bearing walls of the building structures. Reinforcing steel
should be provided as necessary for structural support and
continuity of pier and grade beam. Spacing should be deter
mined, as required, by the load distribution but minimum
spacing should not be less than 3 pier diameters, center-to
center •
Slab-on-Grade Construction
31. It is expected that the concrete slabs-on-grade may
experience some cracking due to the nature of soils present
on the site. To reduce the potential cracking of the slabs
on-grade, the following recommendations are made:
a. All areas to receive slabs should be wetted
until a moisture equilibrium condition is
reached as deemed necessary by the Soil Engi
neer .
17
•
•
•
•
•
•
•
•
•
•
•
b.
c.
Project No. 6063 18 December 1989
A minimum of 4 inches of
crushed rock material should
the finished subgrade and
gravel or clean
be placed between
all the slabs to
serve as a capillary break between the subsoil
and the slab. See the "Guide Specifications
For Rock Under Concrete Slabs", Appendix C.
Slabs should be reinforced with a minimum of
wire mesh . Care should be taken to center the
reinforcement in the slab.
d. All slabs should be properly reinforced to
meet structural design criteria. The rein
forcement shall be placed in the center of the
slab unless otherwise designated by the design
engineer .
e. Slabs at door openings should be constructed
with a curl or a thickened edge extending a
minimum of 6 inches into native ground or
compacted fill
f. Slabs supporting floor coverings should be
provided with measures to prevent condensation
caused by temperature differentials from harm-
18
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
ing floor coverings. One way to protect the
floor covering is to place a waterproof mem
brane between the granular layer and the floor
slab. In addition, two inches of wetted sand
should be placed over the membrane to minimize
puncture and facilitate curing of the concrete .
The sand and the membrane are to be placed
over the 4-inch layer of gravel or clean sand
and crushed rock recommended herein .
Retaining Walls
32. If retaining walls are incorporated into the design and
construction of the proposed
parameters should be used.
dwellings, the following design
The retaining walls should be
designed to resist lateral pressures exerted from a media
having an equivalent fluid weight as follows:
Gradient of Back Slope
Flat 2:1
Equivalent Fluid Weight (p.c.f.)
Unrestrained
45 65
Passive Resistance lp.c.f.)
250 250
Coefficient of Friction
0.35 0.35
In addition, restrained retaining walls should be designed
to resist an additional uniform pressure of 100 p.s.f. for
the entire height of the wall .
19
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1969
33. The above criteria are based on fully-drained condi
tions. For these conditions, we recommend that a filter
material blanket be placed behind the wall. The blanket
should be a minimum of 12 inches thick and should extend
the full height of the wall to within 12 inches of the sur
face. If the excavated area behind the wall exceeds 12
inches, the entire excavated space behind the 12-inch blan
ket should consist of compacted engineered fill or gravel
blanket material. A 4-inch perforated drain pipe should be
installed in the bottom of the filter blanket and should be
underlain by at least 4 inches of filter type material.
Adequate gradient shall be provided to discharge water that
collects behind the wall to an adequately controlled dis
charge system away from the structure foundations and nearby
engineered fills. A filter fabric may be required in con-
junction with the filter material. The granular crushed
rock or gravel filter material should meet the following
gradation;
Sieve Size Percentage Passing
l" 100
3/4" 90-100
3/8" 40-100
No. 4 25-40
No . B 18-33
No. 30 5-15
No. 50 0-7
No . 200 0-3
20
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
34. The retaining walls should be supported on a spread
footing system and should be a minimum of 2 feet below adja
cent pad grade.
Pavement Areas
35. Preparation of Subgrade: After underground facilities
have been placed in the areas to receive pavement removal of
excess material has been completed, the upper 6 inches of
the subgrade soil shall be scarified, moisture conditioned
and compacted to a minimum relative compaction of 95% in
accordance with the grading recommendations specified in
this _report .
36. Aggregate Base: All aggregate base material placed
subsequently should also be compacted to a minimum relative
compaction of 95% based on the ASTM Test Procedure Dl557-78 .
The construction of the pavement in the parking and traffic
areas should conform to the requirements set forth by the
latest Standard Specifications of the Department of Transpor
tation of the State of California and/or City of San
Leandro, Department of Public Works.
37. Pavement Sections: No specific tests were performed to
determine the pavement section in the proposed parking
areas. However, based on our experience with similar soil
materials, a tentative pavement section of 2-1/2 inches of
21
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
asphal tic concrete on 8 inches of aggregate base material
may be utilized. When the subgrade is established, the
necessary samples can be obtained; and an accurate pavement
section can be designed at that time.
General Construction Requirements
38. All finish grades should provide a positive gradient to
an adequate discharge point in order to provide rapid remov
al of surface water runoff away from all foundations. No
ponding of water should be allowed on the pad or adjacent to
the foundations. Surface drainage must be provided as
designed by the project Civil Engineer and maintained by the
property owners at all times .
39. Liberal lot slopes and drainage must be provided by the
project Civil Engineer to remove all storm water from the
pad and to prevent storm and/or irrigation water from seep
ing beneath the houses. Should surface water be allowed to
seep under the structures, foundation movement resulting in
structural cracking will occur. In addition, all site drain
age must be provided as designed by the project Civil Engi
neer and maintained by the property owners at all times to
minimize foundation movement.
40. Where roof gutters are used, downspouts from the
gutters should be provided with closed pipe conduits or
splash blocks to carry storm water away from the structures
and graded areas and, thus, reduce the possibility of soil
saturation adjacent to the foundations and engineered fills •
22
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
41. Flower beds or planters should be avoided adjacent to
the building foundations. Should planters be constructed,
foliage requiring little irrigation should be installed to
prevent water from affecting the foundation .
42. Utility trenches extending under building areas should
be backfilled with native on-site soils or approved import
materials. Backfill should be properly compacted to ensure
against water migration underneath the structure •
43. Utility trenches extending underneath all traffic areas
must be backfilled with native or approved import material
and compacted to a relative compaction of 90% to within 6
inches of the subgrade. The upper 6 inches should be com
pacted to 95% relative compaction in accordance with ASTM
Dl557-78 Laboratory Test Procedure. Backfilling and
compaction of these trenches must meet the requirements set
forth by the City of San Leandro.
44. Applicable safety standards require that trenches in
excess of 5 feet must be properly shored or that the walls
of
of
the trench slope back to provide safety for installation
lines. If trench wall sloping is performed, the inclina-
23
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 lB December 1989
tion should vary with the soil type. The underground
contractor should request an opinion from the Soil Engineer
as to the type of soil and the resulting inclination.
45. With respect to state-of-the-art construction or local
requirements, utility lines are generally bedded with granu
lar materials. These materials can convey surface or subsur
face water beneath the structures. It is, therefore, recom
mended that all utility trenches which possess the potential
to transport water, i.e., backfilled with granular material,
be sealed with a compacted impervious cohesive soil material
or lean concrete where the trench enters/exits the building
perimeter. This impervious seal should extend a minimum of
2 feet away from the building perimeter .
46. The high cutslopes along the southeastern boundary of
the development may experience some raveling with the pas
sage of time. It may be desirable to construct a debris
bench and a cyclone fence at the toe of the slope to ensure
that no debris encroaches on the road .
24
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
GUIDELINES FOR REQUIRED SERVICES
The following list of services are the services required and
must be provided by Terrasearch, Inc., during the project
development. These services are presented in check list for
mat as a convenience to those entrusted with their implemen
tation.
The i terns 1 i sted are included in the body of the report in
detail. This list is intended only as an outline of the
required services and does not replace specific recommenda
tions and, therefore, must be used with reference to the
total report .
The importance of careful adherence to the report recommenda.
tions cannot be overemphasized. It should be noted, however,
that this report is issued with the understanding that each
step of the project development will be performed under the
direct observation of Terrasearch, Inc •
The use of this report by others presumes that they have
verified all information and assume full responsibility for
the total project .
25
Project No. 6063 18 December 1989
• Item Desci:iption R=quired l'bt Requii:ed
• 1. Provide foundation design·para!T);Oters x
2. F2view grading plans and specifications x
3 • Review foundation plans ar:d specifications x
4. Cbserve and provide reccmuendations regard-iflj demolition x •
s. Cbserve and provide r-eccmnendations regard-in:J site stripping x
6. Cbserve and provide reccrnnendations on rroisture conditioning, ranoval, and/or pre- x • canpaction of unsuitable existing soils
7. Observe ar:d provide recarmendations on the installation of subdrain facilities x •
8. Observe arrl provide testing services on fill areas and/or imp:irtea fill materials x
9. Review as-graded plans arrl provide additional foundation reccmnendations, if necessai:y x •
10. Observe arrl provide canpaction tests on x sanitary sewers, storm drain, watei: lines, and PG&E trenches
11. Cbserve foundation excavations and provide I supplemental recarmendations, if necessary, x • pdor to placing concr-ete
12. Observe and provide moisture conditioning x recarrnendations foi: foundation areas prior
• to placing concrete •
13. Provide design parameters for retaining v.alls x 14. Provide geologic observations and recan112nda-
tions for keyway excavations and cutslopes x during grading • 15. &cavate and reccrnpact all geologic ti:enches x and/or test pits
•
• 26
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
LIMITATIONS AND UNIFORMITY OF CONDITIONS
1. lt should be noted that it is the responsibility of the
owner or his representative to notify TERRASEARCH, INC., in
writing, a minimum of two working days before any clearing,
grading or foundation excavations can commence at the site.
2. The recommendations of this report are based upon the
assumption that the soil conditions do not deviate from
those disclosed in the borings and/or test pits and from a
reconnaissance of the site. Should any variations or unde-
sirable conditions be encountered during the development of
the site, TERRASEARCH, INC., will provide supplemental recom
mendations as dictated by the field conditions.
3. This report is issued with the understanding that it is
the responsibility of the owner, or his representative, to
ensure that the information and recommendations contained
herein are brought to the attention of the Architect and
Engineer for the project and incorporated into the plans and
that the necessary steps are taken to see that the Contrac
tor and Subcontractors carry out such recommendations in the
field .
27
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
LIMITATIONS AND UNIFORMITY OF CONDITIONS
(continued)
4. At the present date, the findings of this report are
valid for the property investigated. With the passage of
time, significant changes in the conditions of a property
can occur due to natural processes or works of man on this
or adjacent properties. In addition, legislation or the
broadening of knowledge may result in changes in applicable
standards. Changes outside of our control may render this
report invalid, wholly or partially. Therefore, this report
should not be considered valid after a period of two ( 2)
years without our review, nor should it be used, or is it
applicable, for any properties other than those investi
gated .
5. Not withstanding, all the foregoing applicable codes
must be adhered to at all times .
28
•
•
•
•
•
•
•
•
•
•
•
APPENDIX A
Field Investigation
Site Plan
Logs of Test Borings
Typical Landslide Reconstruction Detail
Landslide Buttress Detail
Typical Subdrain Detail
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
FIELD INVESTIGATION
The field investigation was performed on 5 December 1989 and
included a reconnaissance of the site and the drilling of 7
exploratory borings at the approximate locations shown on
Figure 1, "Site Plan."
The borings were drilled to a maximum depth of 28 feet below
the existing ground surface. The drilling was performed
with a truck-mounted rig using power-driven, six-inch diam
eter continuous flight augers. Visual classifications were
made from the auger cuttings and the samples in the field.
As the drilling proceeded, undisturbed core samples were
obtained by means of a 2-inch, Q.D., split-tube sampler.
The sampler was driven into the in-situ soils under the
impact of a 140-pound hammer having a free fall of 30 inches.
The number of blows required to advance the sampler 12
inches into the soil were adjusted to the standard penetra
tion resistance (N-Value) .
The samples were sealed and returned to our laboratory for
testing. Classifications made in the field were verified in
the laboratory after further examination and testing .
The stratification of the soils, descriptions, location of
undisturbed soil samples and standard penetration resistance
are shown on the respective "Logs of Test Borings", Appen
dix A .
30
•
•
•
•
•
•
•
•
• )1'/ "' ' ' I ~ ~.
·{_____ ~ · .
•
•
j -,.,_
l ./
=
Approximate lill'.its of s..liallow uncontrolled fill
1'.pproxirnate limits of deen tmcontrolled fill
Landslic1.e C.e.1:-iris
APPROXIMATE LOCATION OF TEST BORINGS
T~lfl~A S~Al~t:H INt:. FIGURE NO. ~ - SI''l'!. "!1\N
ProJect No. 6063 18 DccG."lbe_r 1989
---~- ... LOGGED BY D?) DA TE DRILLED 12/5/89 BORll'KI DIAMETER 6" BORING NO, l •
15 j$ ....:,!? b ~ ~8_ 3i;;: ~~ MISC.
.8 :3 .,; ~ "ii! ...: .!!b "2;;: ..._, "' LAB s SOIL DESCRIPTION .o - <!' [ i .r ~ ~ .. . "' C>. ~ ;;:::: "iii • - Q '-! .- ... .. ..
~ C>.
:i ""' RESULTS
c .:i"' ..., "' .. _s;: "' "' =>- a> ..... C',f Q u • -~1~~
-Seddish-brown Gr'1velly S.1\ND w/Silt,
- - ''< medium d1?nse, noist (FTI.L) Sli/ l-l
~). 16 -- 9 ... - ,.. - . i;1~: - - J1~if} ... 5- :~~f~
1-2 ~1 SP.me as al:ove 14 -- 9 - -~~
•
·.t.-..,.\~ - f~~:~~ .... ,;i.. - -
I - - EeCXJITEs looser
. 10 · Y•
•
l-3 %~ 10 - 7 - . ·~· .. - - h~~~: - - .~:"!j.:
~{~· . -. 15-
1-4 :~ 5~ l?.-'.' l'l -
•
• - - ~ Greyish-brrn·m, loosely cer:ented SAfID-
i:::::;:::: S'Jl'.)NE w/some rocks, VG!:'} dense, T'Dist ... - ::;:::;::
:::;::::: . -
~ 20- 1-: 84 t-b • m::; reo::ivery •
. - 2oring terminated at 20.5 feet. lb groundwater enoountered. - -
• - -- -
. 25..
- -• - -- -- -. -•
Tl~l~l~A Sl~Al~t~H INC. I FlOURE NO. 2 - If)'.; OF ri~.ST BORING
32
•
• LOGGEO BY ~.!B PA TE PRILLEP 12/5/89 BORINC) PIAMETER 6" BORING NO. 2
• ~g -b .:2 ,g 8. 11i -= .!e
~ 'i MISC • .,; 21 ·u;. . ~l:> .8 al Ji ....... ..,. "' - => LAB .&£ SOIL DESCRIPTION .o
~~ -:;; z:. ~ i == .... -... §!? -;; ·a .... ·- -0 .. ' .. z:. C>. ~ .... RESULTS
~ ... - 50: => "' c :::> - "" ... o-8:_ u c
•
:;~-,.~~-
Bl:'"OV.1'J.J Clayey SJ-IND •·7/f.i.lt a..."'1d Gravel - - -~-t-~-
2-' ~.$)· (weathered bedrock) , very dense, '1Dist SW 80 104 9 - - r..: ~"-Z"·
""" ... - ~~·j<
'-f.;i; .,,,, - ··-.:,;l· - -~··'J
~r.
"' 5 - •, -~-
but becanes rredium ~: SP.lnte as atove, - 2-2
,. dense, nnist 23 Bag sariple ... < r.
•
•
•
- - ·;~J ~.ti'." '.(._v:
- - 1-·.I" -!J.-?. -~::.I
- - 1'.\:. - 10 - -·~~~:
2-3 ~:~- 56 102 11 rerrolded
- - ~! Bro,1Jl"l Silty Sk'ID Fjheavv GrE!Vel , SN c>O . 1! fl"'64 degrees - t~' very de-..nse, rroist ·yl (scme Gravel -..H ... - i•--r is rernved) :~~; . . ; .. ... - :i~ib
.,1~1· ... is- I ;<
2-4 l.1 SillOO as above 1 but less dense -:ir.: lH s ·~:1 ~--
~: - - ~I
• ~ ·1·
... - . \i~· f ) ·r11f
... - 'iit! lf?.e
... - ·Vf {1\ eJi Be=ros very dense ... 20- 2-5. ·l;l 102 8
- - Eoring terminated at 20.5 feet. ... tb groundwater encountered. -
• ... -- -- 25-
-• - .
- -- -... -•
TEl~l~A Sl~Al~tH INC. I rJOORE NO. ~ - IDG O:' TI:ST l'Olc'.I!"G J
33 •
Pro1eet tb. (,(,63 18 Dx.ernt>?x 1~8~
• LOGGED BY DR DA TE: DRILLED 12/5/89 BORING DIAMETER 6" BORING NO.
3
• ::::: ~8. ~! §Ii -:£ ~
!!! ~ MISC. ..!!~ i ll~ ...... ...,. .,; ~ '!1j _,
"' LAB 5 SOIL DESCRIPTION ~ ... .o ., .
-:;:; ~ Q. ~ ~-~ -~ o~ ·- --cl ., . .,
~ ... j~ RESULTS ~ ... ..... -~ "' iii 0 ::=> - i:D .....
<.> O'c... 0
• I 13rovm Sandy GRAVEL w/traee of Silt and GW
t- - Clay (i~eathered Sandstone), VP_ry der1se, 3-1 97 115 13
" rrol.st ,_ - .. .:.• - " ;.~{f~Y .
- - Eorl.ng te=inated at 3.5 feet. .. 5 - lb grounC:Viater p_nccuntered.
.. -
• .. -,_ -
- -
" -
• - -- -
- -
- -
• - -- -- -- -
• - -
- -,_ -
,_ .
• . -- .
. -
. -• . .
- -- -- -•
T~•~•~A s•~••~•~n ••c. I FIOURE NO. 4 - LOG OF '"EST !30RD<G
34
•
•
•
•
•
•
•
•
•
•
•
•
!'rOJ8Ct ~Jo. 6063 lH I:ecernber l'!B'!
------- -------------------------------------------, LOGGED BY ,\Y DATE DRILLED 12/5/89 BORING DIAMETER
~8. :d .8 --"' ~~ - [ <>- n .. "' 0
' -ti. - - /.·
4-1 ;. - - ~
- - ~¥
~ - -V;ii - 5 -"''*
4-2 - -
- -
~ - -- -.10 -
'"15 -
~20 -
-
--
" -
- -- -
- -
SOIL DESCRIPTION
Beddish-brown Sandy CLAY wjhce.vy Co:ravel, dense, rrnist
Becomes less rroist
1'annish-brown weathered (fractured) S.l\NLS'IONE w/Si.lt (cuttings are very noist Sandy Clay, very dense, rroist)
~an Silty S.""-"lD w/fractured rocks, very dense, !:'Dist
cuttings are crushed rock
Boring terminated at 23.5 feet. Ko groundwater en=untered.
~~ ~1i ll~ ...... ...,. i= '; -~ - :1: :>- eQ..,
u
CL 50
93
111
6'' BORING NO. 4
-b ... !!! 'i :i MISC. "ih .
"' - "' .o ~ <..?
-.;; i!:' LAB - -"i ·-"" RESULTS i'::'"'" :i _., g.~ 0
112 14
110 13
104 15
TBl~l~A Sl~A·~·~H INC. I FlOURE NO. 5 - LOG OF TEST !'DPJNG
35
•
•
•
•
•
•
•
•
•
•
•
T>ro-ject No. 6063 18 December 1989
~---,--- ----~---------------------..,..,,.--------;:----,
G" BORING NO. S LOGGED BY _c.K DATE DRILLED 12/5/89 BORING DIAMETER
0 = z: i!t .c ~.i!> Ci. ~ "' c tl.,
-
.
- -
--
-10 -
-
--
15 ..
.
--
... 20 -
--
-
... 25 -
-~ -... 30 -
.8 !!. ...,
SOIL DESCRIPTION
Heddish-brown Sandy CLAY w/Gravel, dense, m::iist
Recorres nure ('.ravelly
Dark brown Sandy Clay w/Gravel, dense, TIDist .
Very hard drilling
lbri_ng terrrinate:i at 28 feet. No groundwater encountered •
CH
3"
CL
115 13
lo::'
---
MISC. LAB
RESULTS
Ur51 0 I=28
Tt~•~•~A s1~A•~•~n ••c. I FlOURE NO. 6 - lffi OF TEST BOP.ING
36
ProJect Lb. 6053 18 tecembcr 1989
• I,oc,GED BY Al-( DA TE DRILLED 12/5/89 BORING DIAMETER 6" BORING NO. 6
•
g ~
~-. ., b 0 ~~ -- ~}'. MISC. :::: ~!. _1: .; ~ ·;;;
-=- ~b .8 ~.g ...... ...,. "'-: :::> LAB [ SOIL DESCRIPTION i :::: ....;~
., . .., ~ Q. ~ ;;::: "jjj Q '-! ·-..,. ., .,,
~CL ;i,.. RESULTS Q ~ ... .,, "' .. - Si; :::> "' :::> - lrl ... o-tf (..'> Q
•
•
•
•
~· Brown Sandy CLAY w/fine Gravel, hard - - drilling, da."1j) CL 9Z V; - - '.%. - Ji
at. - -
- 5 - I -
- ~· ~ -l%3 - - Vill
.. 10 - I ~· - -
~ I Very hard drilling - -
- - ~ - - ;~ Dark brown Clayey SAND w/fine Gravel, SD/ ..is - o-1 very dense, damp (REFUSAL) S(~ Jl? llG ~ 0 - -
- - Boring terminated at 16 feet. No qroundwater encountered.
- -• - -
-20 --
- -• --- -- -
• --
- -... -•
TB•~•~• s1~••~•~n IN& I FIOURE NO. 7 - LOG OF 'T'RST BORil'lG
37
•
•
• --
• ---
• -... ... I-
• ----
• ----
• ---
-•
---• -
--•
•
oroject N:::>. 6063 18 December 1989
LOGGED BY_ H'. DATE DRILLED 12/5/89 BORING DIAMETER BORING NO. ~
:~Q~ - ~~:0
~~ - ::~·
•,y.JI.' ;;/!/-
- y· :~-- t 7-1 ~
s- ff.. ~·
- ":jj: ~;t'.
'!-~?:.· . ,:ft .
~ -7-2
I
10 - " ~I - ~ - Xt .1!.1. -
-
is--
----------
--
-
SOIL DESCRIPTION
IX>c:cUsh-brovm Clayey SAl\1D vi/Gravel, rredium dense, noi.st (FILT,) S? I
SC
t:ark greyish-brown Silty CJ..AY w/scrre organics, hard, noist (11ATIVE) CJ,/
B::>ring terminated at 13 feet (refusal) . No groundwater encountered .
CH
18
37
99 15
84 15
MISC. LAB
RESULTS
rerrolded 0"1200 l)Sf
,0=64 degrees (some gravel rerrovo::l J
T•~·~·~A Sl~A·~·~H INC. I FIGURE NO. 8 - LOG OF TEST BOP-.ING
38
•
w \.0
• • • • • • • • • • Project No. 6063 18 December 1989
TYPICAL IJ\NCGLIDE PECDl'lSTPlJCI'IC'.N DETAIL
Existing Ground Surface
Lined Di le h -----.--------------.
Subdroin
Slide Plane
T~l~RA S~Al~CH 111e. FIGURE NO. 9
•
•
•
•
•
•
•
•
•
•
•
/,_. '/,' ,,,., , . " Slide
Project ;Jo. 6063 lR DecS'lber 1989
LANDSLIDE BUT'rRESS DETAIL
40
Minimum 6' bench (see general slope st~bility requirements}
FIGURE NO. 10
•
•
•
•
•
•
•
•
•
•
•
Project Kb. 6063 18 Dec£l'lber .l 98'l
TYPICAL SUBDl<AIN SECTION
As directed by the Soil Engineer
during installation
3' minimum
.. .,
'·
Embankment Material
. .... I::'•' I ' ........ .
•• ·~' 0- ,· • ' -- ~ ... I" ~ . .!! ..... ~ .' .
0 •• • •. ~
. .
.,
Permeable material as specified in the Grading Specifications of this report
6'' perforated pipe with the holes turned down
Note: Bottom of subdrain trench and pipe should be sloped at least 2 percent
TEl~l~A SEAltl~H 111c. F'IGURE NO. 11
41
•
•
•
•
•
•
•
•
•
•
APPENDIX B
Laboratory Investigation
Summary of Laboratory Test Results
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
LABORATORY INVESTIGATION
The laboratory testing program was directed towards provid
ing sufficient information for the determination of the engi
neering characteristics of the site soils so that the recom
mendations outlined in this report could be formulated.
Moisture content and dry unit weight tests were performed on
undisturbed soil samples in order to determine the consist
ency of the soil and moisture variation throughout the ex
plored soil profile and estimate the compressibility of the
underlying soils .
The strength parameters of the foundation soils were deter
mined from direct shear tests performed on selected
undisturbed soil samples .
Field penetration resistance (N) assisted in the determina-
tion of the strength parameters of the soils. The standard
penetration resistances are recorded on the respective "Logs
of Test Borings."
The expansion characteristics of the near-surface soils were
evaluated by means of Atterberg Limits Tests performed in
accordance with ASTM D-423 and D-424 .
A summary of all laboratory test results is presented on
TABLE I of this appendix and on the respective "Logs of Test
Borings", Appendix A .
43
• Project &:>. 6063 18 Decanter 1989
• TllBLE I
• Surrmary of Ial:x:iratpry Test Results
Sample Depth Dry MJisture Atterllero Limits Diiect 511ea;r lib. Dansity content Liquid Plasticity Cohesion Angle of
Limit Index Internal
• Friction ill...l rp.c.f.) (% pzy ~ight) (%) (p.s.f.) (degree)
1-1 2.0 9 1-2 6.0 9 1-3 11.0 7
• 1-4 16.0 124 19
2-1 2.0 104 9 2-3 11.0 102 11 0 64 2-4 16.0 114 9 2-5 20.0 102 8
• 3-1 1.5 115 13
4-1 2.0 112 14 4-2 6.0 110 13 4-3 11.0 104 15
• 5-1 6.0 115 13 51 28 5-2 16.0 102 9
6-1 15.5 116 8
• 7-1 5.0 99 15 1,200 64 7-2 10.0 84 15
•
•
• 44
•
•
•
•
• APPENDIX C
The Grading Specifications
Guide Specifications For Rock Under Floor Slabs
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
THE GRADING SPECIFICATIONS on
SAN LEANDRO ROCK QUARRY 13575 Lake Chabot Road
San Leandro, California
1. General Description
1.1 These specifications have been prepared for the grading
and site development of the subject residential development .
TERRASEARCH, INC., hereinafter described as the Soil Engi
neer, shall be consulted prior to any site work connected
with site development to ensure compliance with these speci
fications .
1.2 The Soil Engineer shall be notified at least two work
ing days prior to any site clearing or grading operations on
the property in order to observe the stripping of surface
contaminated material and to coordinate the work with the
grading contractor in the field.
1. 3 This specification encompasses all clearing or grub
bing, preparation of land to be filled, filling of the land,
spreading, compaction and control of the fill, and all sub
sidiary work necessary to complete the grading of the filled
areas to conform with the lines, grades, and slopes as shown
on the accepted plans. The Soil Engineer is not responsible
for determining line, grade elevations, or slope gradients .
46
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
The property owner, or his Engineer, shall designate the
person or organization who will be responsible for these
items of work.
1. 4 The contents of these specifications shall be inte
grated with the soil report of which they are a part, there
fore, they shall not be used as a self-contained document.
2. Tests
The standard test used to define the maximum densities of
all compaction work shall be the ASTM Test Procedure D1557-
78. All densities shall be expressed as a relative compac
tion in terms of the maximum dry density obtained in the
laboratory by the foregoing standard procedure,
3. Clearing. Grubbing, and Preparing Areas to be Filled
3. 1 All vegetable matter, trees, root systems, shrubs,
debris, and organic topsoil shall be removed from all struc
tural areas and areas to receive fill. The depth of organic
topsoil to be removed will be determined in the field by the
Soil Engineer but, in general, is expected to vary from 4 to
6 inches.
3.2 All soil deemed soft or unsuitable by the Soil Engineer
shall be removed. Any existing debris or excessively wet
soils shall be excavated and removed as required by the Soil
Engineer during grading .
47
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
3. 3 All underground structures shall be removed from the
site such as old foundations, abandoned pipe lines, septic
tanks, and leach fields.
3. 4 The final stripped surface shall be approved by the
Soil Engineer during construction and before further grading
is started.
3.5 After the site has been cleared, stripped, excavated to
the surface designated to receive fill, and scarified, the
native subgrade soils shall be moisture conditioned and com
pacted to the requirements of engineered (structural) fill.
Fill can then be placed to provide the desired finished
grades • The contractor shall obtain the Soil Engineer's
approval of subgrade compaction before any fill is placed.
Final grade within cut areas shall be prepared as above to
provide uniform compaction of disrupted surface soils .
4. Materials
4 .1 All fill material shall be approved by the Soil Engi
neer. The material shall be a soil or soil-rock mixture
which is free from organic matter or other deleterious sub
stances. The fill material shall not contain rocks or lumps
over 6 inches in greatest dimension and not more than 15%
48
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
larger than 2-1/2 inches. Materials from the site below the
stripping depth are suitable for use in fills provided the
above requirements are met.
4. 2 Materials existing on the site are suitable for use as
compacted engineered fill after the removal of all debris
and organic material. All fill soils shall be approved by
the Soil Engineer in the field.
4.3 Should import material be required, it must be approved
by the Soil Engineer prior to transporting it to the project
and must meet the requirements as specified in the report.
5. Placing. Spreading and Compacting Fill Materials
5.1 Before compaction begins, the fill shall be brought to
a water content that will permit proper compaction by either
a) aerating the material if it is too wet, or b) spraying
the material with water if it is too dry. The fill mater
ials shall be placed in uniform lifts of not more than 8
inches in uncompacted thickness. Each layer shall be spread
evenly and shall be thoroughly blade mixed during the spread
ing to obtain uniformity of material in each layer.
5.2 After each layer has been placed, moisture conditioned,
mixed and spread evenly, either import material or native
material shall be compacted to a relative.compaction of not
less than .90% slightly above the optimum moisture content as
determined by ASTM Test Procedure 01557-78 .
49
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
5. 3 Compaction shall be by acceptable compacting rollers .
Rollers of such design that they will be able to compact the
fill to the specified density. Rolling shall be accomp
lished while the fill material is within the specified mois
ture content range. Rolling of each layer shall be continu
ous over its entire area and the roller shall make suffi
cient trips to ensure that the required density has been
obtained and that adjacent areas are overlapped •
5.4 Field density and moisture tests shall be made in each
compacted layer by the Soil Engineer in accordance with ASTM
Test Procedure D1556-64, D2922-81, or D3017-78. When footed
rollers are used for compaction, the moisture and density
tests shall be taken in the compacted material below the
surface disturbed by the roller. When these tests indicate
that the moisture or density of any layer of fill, or por
tion thereof, does not meet the required specifications, the
particular layer, or portion thereof represented by the
test, shall be reworked until the compaction requirements
have been met .
5.5 No soil shall be placed or compacted during periods of
rain nor on ground which contains free water. Soil which
has been soaked and wetted by rain or any other cause shall
not be compacted until completely drained and until the mois-
50
•
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
ture content is within the limits approved by the Soil Engi
neer. Approval by the Soil Engineer shall be obtained prior
to continuing the grading operations.
6. Payement
6 .1 The proposed subgrade under pavement sections, native
soil and/or fill shall be compacted to a minimum relative
compaction of 95% at slightly above optimum moisture content
for a depth of 6 inches .
6 .2 All pavement materials and construction methods used
shall conform to the applicable sections of the latest edi
tion of the Cal-Trans Specifications for Pavements, State of
California, Department of Transportation and/or the City of
San Leandro, Department of Public Works.
6. 3 It is recommended that soils at
level be tested for a pavement design
the proposed subgrade
after the preliminary
grading is completed and the soils at the site design sub
grade levels are known .
7. Subdrains
7.1 Subdrains shall be provided where seepage is discovered
and at any other location where recommended by the Soil
Engineer .
51
•
•
•
•
•
•
•
•
•
•
8. Subdrain Installation
Project No. 6063 18 December 1989
8.1 Provide and install perforated PVC pipes or perforated
metal pipe and filter material for subdrains.
8.2 Use Class II material as specified in Section 68-1.025
of the Standard Specifications of the State of California.
9. Utility Trench Backfill
9.1 The utility trenches extending under concrete slabs-on
grade shall be backfilled with native on-site soils or
approved import materials and compacted to the requirements
pertaining to the adjacent soil. No ponding or jetting will
be permitted.
9. 2 Utility trenches extending under all pavement areas
shall be backfilled with native or approved import material
and properly compacted to meet the requirements set forth by
the City of San Leandro, Department of Public Works.*
NOTE: Requirements of City to be added .
9. 3 Where any opening is made under or through the perim
eter foundations for such items as utility lines and
trenches, the openings must be resealed so that they are
52
•
•
•
•
•
•
•
•
•
•
Project No. 6063 18 December 1989
watertight to prevent the possible entrance of outside irri
gation or rain water into the underneath portion of the
structures.
10. Subsurface r.ine Removal
10.1 The methods of removal shall be designated by the Soil
Engineer in the field depending on the depth and location of
the line. One of the following methods will be used .
10.2 Remove the pipe and fill and compact the soil in the
trench according to the applicable portions of sections
pertaining to compaction and utility backfill .
10.3 The pipe shall be crushed in the trench. The trench
shall then be filled and compacted according to the appli
cable portions of section 5.1 .
10. 4 Cap the ends of the line with concrete to prevent
entrance of water. The length of cap shall not be less than
5 feet. The concrete mix shall have a minimum shrinkage .
11. Unusual Conditions
In the event that any unusual conditions not covered by the
grading specifications are encountered during the grading
operations, the Soil Engineer shall be immediately notified
for additional recommendations •
53
•
•
•
•
•
•
•
•
•
•
•
12. General Requirements
Dust Control
Project No. 6063 18 December 1989
The contractor shall conduct all grading operations in such
a manner as to preclude wind blown dirt and dust and related
damage to neighboring properties. The means of dust control
shall be left to the discretion of the contractor and he
shall assume liability for claims related to wind blown
material .
54
•
•
•
•
•
•
•
•
I
I
•
Project No. 6063 18 December 1989
GUIDE SPECIFICATIONS FOR ROCK UNDER FLOOR SLABS
Definition
Graded gravel or crushed rock for use under slabs-on-grade shall consist of a minimum thickness of mineral aggregate placed in accordance with these specifications and in conformity with the dimensions shown on the plans. The minimum thickness is specified in the accompanying report .
Material
The mineral aggregate shall consist of broken stone, crushed or uncrushed gravel, quarry waste or a combination thereof. The aggregate shall be free from deleterious substances. It shall be of such quality that the absorption of water in a saturated dry condition does not exceed 3% of the oven dry weight of the sample.
Gradation
The mineral aggregate shall be of such size that the percentage composition by dry weight, as determined by laboratory sieves (U.S. Sieves), will conform to the following gradation:
Sieve Size Pe,;:centage Passing
3/4" 90-100 No. 4 25-60 No. 8 18-45 No. 200 0-3
Placing
Subgrade, upon which gravel or crushed rock is to be placed, shall be prepared as outlined in the accompanying soil report.
55