02 drilling preparation ui 15 sep 2007
TRANSCRIPT
By
R. Harry EddyarsoPT. SARIPARI PERTIWI ABADI
15 September 2006
“KMI Goes to Campus Program”Komunitas Migas Indonesia – Universitas Indonesia
1. Rig Type Including Rig Lay-Out Diagram (for Land Rig & Swamp Barge)
2. Rig Size Calculation
3. Torque & Drag Calculation
4. Casing / Liner Design & Cementing Procedures
5. Wellhead Design & Installation
6. Mud Engineering & Design
7. Directional Drilling Plan & Drill String Design
8. Drilling Hydraulic Optimization
9. Bit Selection
10.Formation Evaluation (Logging, Coring)
11.BOP Stack Diagram & Well Control Procedures
12.Drill Stem Testing Procedures, Well Stimulation and or Well Completion
13.Health, Safety, Environment
14.Emergency Response Plan (ERP)
15. Etc
Closest location between fault and well path at depth –3064’ tvdss
Closest distance from the fault = 95 mtr.Fault position error bar = 30 mtr.Drilling target radius = 50 ft.
Open Hole Logging Package:
1. Resistivity / Sonic
2. Density / Porosity
3. Core Sampling
4. Dipmeter
5. RFT
6. Velocity Survey
Cased Hole Logging Package:
1. CBL/VDL/CET
Net to Gross map
GrossNet
Net
B-29A2 Net to Gross Map