01_20_10_chief self issues brief_v2 final 13
TRANSCRIPT
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
1/13
CBP Office of Finance
Facilities Management and Engineering
January 20, 2010Tactical Infrastructure Update
000001
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
2/13
2
San Diego
A-1Additional re-vegetation work will be required post construction for 3-5 years until
disturbed areas are fully stabilized; Planning documents being prepared
Surf Fence/Borderfield State Park Primary Fence ReplacementPRD for planning efforts to be routed for review/approval by next week
BIS Re-vegetation and Erosion Control MeasuresMajor storm events this week in San Diego
Erosion controls inspected last week in anticipation of the storms
Both contractor and Corps personnel closely monitoring project Contractor prepared to make emergency repairs if conditions warrant FM&E visiting project on Jan 21st (A-1 as well)
Re-vegetation going well; erosion controls in-place and well maintained; re-vegenhancements change order issued ( ); on-site progress meeting to be held with
the Corps/Kiewit on Jan 21st
Proactive out reach with external stakeholders continuing (D. Pagan coordinating) Tijuana River Valley Recovery Team site visit-Jan 28th
Tijuana River Valley Recovery Team meeting-Jan 29th
Continuing dialog with EPA and CEQ regarding status of the project
000002
(b) (4)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
3/13
3
Recent BIS Photos (Jan 11th)
South Side-Smugglers Gulch (looking east)
North Side-Smugglers Gulch (looking east)
South Side-Spooners Mesa Irrigation System
North Side-Spooners Mesa (Note drag road created byBP agents that needs to be stabilized)
000003
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
4/13
4
El Paso
Anapras Drainage Study
Scope of work defined; estimated cost
Addresses drainage improvements; fence replacement; and new fencing
PRD for study forthcoming
K-5A
Construction underway
K-1B
Design underway
Crossovers and K-2C Gates
Design underway
Construction expected to start ??
May need to break into two phases due to real estate acquisition requirements
HV-2 & HV-3 Access
Last week decision made to pursue fee simple acquisition of access roads; will requirenon-friendly condemnation
000004
(b)(4); (b)(5)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
5/13
5
Del Rio
Completion of M-2C
RFP issuance currently projected for February 2010 (dependent on real estate
acquisitions); Contract award now anticipated for late March 2010 withconstruction estimated to be completed by July 2010
Meeting with City officials to review 65% design on Nov 18th was productive;We believe we have adequately addressed the Citys concerns with the 95%
design recently issued by the CorpsPRD for the project is being routed for review and approval; PRD reflects a 14
foot high fence and the fence being painted
Painting fence will cost an additional and add 4 months to the
construction duration
000005
(b)(4); (b)(5)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
6/136
O-1 thru O-3
Meeting with Commissioner Ruth on Jan 6th went very well
Ruth agreed no additional modeling is required and to informally discuss the
fence segments with the new Mexican IBWC Commissioner to determine if hewill support
If it appears Mexico will continue to oppose fencing, CBP/DHS and IBWC/DOSto discuss potential unilateral decision to proceed with construction
Earliest construction could occur is 3rd
quarter FY11 due to real estateacquisition requirements
Assumes real estate acquisition process (ROE-S&E and fee simple) by April1, 2010
000006
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
7/137
Hidalgo Segments
All currently approved levee wall constructed
O-4B (0.2 mile):
O-7 ext (500 feet): Fence extension to fill in gap between O-7 levee wall and newDonna POE perimeter fencing;
O-8 ext (200 feet): Fence extension to fill on gap between O-8 levee wall andnew Donna POE perimeter fencing; construction complete
000007
(b) (5)
(b) (5)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
8/138
RGV Gates RFP
Proposed plan moving forward:
e
rf
March
ved in project to
d
m Phase
000008
(b) (5)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
9/139
O-11 thru O-21
Fence construction on segments O-13 thru O-16 and O-18 is complete
Segment O-11: ~850 feet of fence remain adjacent to the Texas Parks and Wildlife
Department tract pending relocation of the Santa Maria Irrigation District #4 irrigation main,
which is underway
Segment O-12: Drainage canal crossing (via a prefabricated bridge) remains; constructioncompletion expected in April 2010
Segment O-17: ~15 feet of fence remain to be installed between transition between in-
ground and jersey wall foundation systems
Segment O-19:
Segment O-20: NTP for construction is on hold pending completion of power polerelocations
Segment O-21: all land now acquired except for the Nature Conservancy and Dawson tract
Corps has prepared 95% level design for the levee wall design in proximity toproperty
RFP to be issued in mid-February; Contract award estimated for late March ( )
000009
(b) (5)
(b)(4); (b)(5)
(b) (6)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
10/1310
PF225/VF300 Drainage Improvements Project (DIP)
Project is proceeding on schedule
Marfa, Yuma, Tucson and San Diego/El Centro RFPs issued
Contractor pre-bid site visits occurring now
Current estimated cost
Current budget is
Scope modifications
HV segments and the TON segments removed from their respective RFPs asno construction access currently exists
Projects can be completed via new contract once construction access isobtained
000010
(b)(4); (b)(5)
(b) (4)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
11/1311
Comprehensive Tactical Infrastructure Maintenance and
Repair (CTIMR)
The TI Program has finalized the development of a Comprehensive Tactical InfrastructureMaintenance and Repair (CTIMR) contract for long-term maintenance and repair of TI assets alongthe Southwest Border
Four contracts are planned:
Significant progress was made over the last several weeks. The RFPs are completed and approved
for release. The first site visits were conducted in Yuma, Tucson, El Paso and Marfa. Next site visit isscheduled for February in El Centro and San Diego.
Dates of note:Blue Review: Completed November 2009Work Area 2 and 3 RFP: Released December 2009
Work Area 1 RFP: Released January 2010Work Area 2 and 3 RFP Closing Date: January 2010Work Area 1 RFP Closing date: February 2010Work Area 4 RFP: February 2010Work Area 4 RFP Closing date: March 2010
Contract Awards: June-August 2010
000011
(b) (5)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
12/1312
Environmental Items
Road Dragging in San Bernardino National Wildlife RefugePMO has been assisting Tucson Sector regarding USFWS concerns that dust from road
dragging is impacting fish in Black Draw
- FWS has no scientific data supporting their concernsUSFWS recently sent letter to Sector requesting formal Section 7 consultationPMO drafting response to FWS and options moving forward
- Try to keep this informal versus formal consultation (with BA and BO)Could have implications across the border
Consider border-wide Section 7 programmatic consultation for BP operations
mitigation for DOI
CBP still negotiating IAA and project list with DOI
Lost time due to DOI liaison turnoverCBP does not have fiscal authority under Economy Act to fund DOI for land acquisition
for purpose of environmental mitigation Need legislation to give CBP this authority
000012
(b) (4)
-
8/8/2019 01_20_10_Chief Self Issues Brief_V2 Final 13
13/1313
MATOC Task Order
20 Interim Contract PackagesThirteen contracts awardedTwo contract packages are ready for award
One package award pending resolution of real estate issueOne package evaluated by the SSEB and in the process of being funded for award(no CN required)Three packages are in the RFP issue/evaluation processExisting Yuma and Tucson Interim M&R contracts recently extended 30 days
Contracts awarded to date total toThe original estimated value of the contracts awarded was
Contracts awarded to date are approximately .
000013
(b) (4)
(b) (4)
(b) (5)