PROJECT EXECUTION MANUAL

JOB PACAKAGES FOR THE FABRICATION AND ERECTION

OF TANKS

CLIENT: ENGRO FOODS SUPPLY LTD

CONTACTOR: FAUZ ENGINEERING

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 1

Page 2: 00 Master Document

PROJECT EXECUTION MANUAL

PROJECT BRIEF:

FAUZ has been awarded with the fabrication and erection of five liquid storage tanks at Integrated Rice Process Complex of Engro Foods Supply Ltd.

FAUZ SCOPE OF WORK:

The Scope of Work of FAUZ includes the following:

Mobilization and de-mobilization. Procurement of all direct materials and consumables. Skilled manpower for the fabrication and installation. Provision of all necessary tools and plants. Erection and installation of storage tanks. Scaffolding. Hydro-testing. Welder qualification. QA/QC documentation. PPE’s as per requirement. Boarding & lodging of workers. Internal rubber lining for treated water tank. Internal epoxy coating for condensate tank. Electrical power supply and water at work location. Radiography 10%. Sandblasting & Painting. Transportation of shop fabricated tanks (02 Nos.) to site.

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 2

Page 3: 00 Master Document

PROJECT EXECUTION MANUAL

However following is excluded from FAUZ Scope of Work

Basic design, detailed design and fabrication drawings. Any type of civil works at site. Arrangement of Third Party Inspection. Any type of E & I work. Water for hydro-test. Area for site office, store and site camp. Area for material storage and workshop.

PROJECT COMPLETION PERIOD

The project is to be completed and delivered to client in the duration of 60 days

PROJECT DETAILS

Following are the details of dimension/weight of tanks to be fabricated and erected by FAUZ ENGINEERING.

SR

CAPACITYUOM

MATERIAL Diameter/M Height/M Weight/KG Tag NoWeight

/Ton1 900 M3 A-283C S235 JR 12.00 10.00 35,000 T-200 352 600 M3 A-283C S235 JR 9.89 8.00 25,000 T-300 253 200 M3 A-283C S235 JR 7.00 6.00 15,000 T-6071 154 100 M3 A-283C S235 JR 5.00 6.00 15,000 - 155 30 M3 A-516 GR-70 3.30 4.00 4,500 T-6072 4.56 20 M3 A-516 GR-70 1.80 5.50 5,483 T-701 5.5

DESCRIPTION

Water Storage TankTreated Water Tank

Diesel TankCondensate TankDiesel Day Tank

Air Receival Vessel

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 3

Page 4: 00 Master Document

PROJECT EXECUTION MANUAL

PROJECT LOCATIONAL LAYOUT

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 4

Page 5: 00 Master Document

PROJECT EXECUTION MANUAL

MANPOWER REQUIRED TO EXECUTE THE JOB

Following is the manpower required to execute the job

Supervisor 1 Nos Rigging Foreman 1 Nos Fabricators 9 Nos Welders 14 Nos Fitters 18 Nos Scaffolders/Riggers 12 Nos Electrician 1 Nos Electrician Helper 1 Nos Helper 20 Nos

FAUZ PROJECT TEAM

Following Management Team has been deployed on the Project Site.

Project Manager: Khalid Nizami Mechanical Supervisor: Mr Saeed Planning Engineer: Mr Nasir Quality Inspector: Mr Adnan HSE Inspector: Mr Khursheed Store Personel: To be Nominated Administrator: Mr Qaiser

The Project will be supported by supporting departments in Head Office, that includes the following

Head Operations: Mr Mutahir Aziz. Administration/HR: Mr Aijaz Chaudry Stores: Mr Nauman Planning : Mr Muhammad Ammar Finance Dept: Mr Khalid Razzaque

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 5

Page 6: 00 Master Document

PROJECT EXECUTION MANUAL

PROJECT RESPONSIBILITY MATRIX

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 6

Page 7: 00 Master Document

PROJECT EXECUTION MANUAL

JOB DESCRIPTIONS AND RESPONSIBILITIES OF MANANGEMENT STAFF DEPLOYED AT PROJECT

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 7

Page 8: 00 Master Document

PROJECT EXECUTION MANUAL

EFSL`S/FAUZ PROJECT REQUIRMENTS

ADEHERENCE TO SCHEDULE AS PER ATTACHED ANNEXURE A

ADHERENCE TO QHSE POLICY AS PER ATTACHED ANNEXURE B

ADEHERENCE TO LIST OF NON TOLERANT ITEMS ANNEXURE C

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 8

Page 9: 00 Master Document

PROJECT EXECUTION MANUAL

ANNEXURE A

LEVEL III SCHEDULE

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 9

Page 10: 00 Master Document

PROJECT EXECUTION MANUAL

ANNEXURE B

QHSE POLICY

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 10

Page 11: 00 Master Document

PROJECT EXECUTION MANUAL

ANNEXURE C

LIST OF NON-TOLERANT ITEMS

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 11

Page 12: 00 Master Document

PROJECT EXECUTION MANUAL

IMPLEMENTATION OF PROJECT PROTOCOLS

Project protocols includes implementation of following documents at site for project execution

Project Manager must ensure that these formats are implemented on site by respective departments

1. Material Indent Form Annexure A12. Document Transmittal Annexure A23. Material Issue Requisition Annexure A34. Quality Inspection plan Annexure A45. Welding Procedure Specifications (WPS) Annexure A56. Radiographic Examination Report Annexure A67. Liquid Penetration Examination Report Annexure A78. Welding Electrode Issuance Annexure A89. Non Conformance Report Annexure A910. Inspection Stickers Annexure A1011. Material Inspection Report Annexure A1112. Calibration Certificates Annexure A1213. Welders Qualification Record Annexure A1314. Dimensional Inspection Report Annexure A1415. Hydro testing Report Annexure A1516. Daily Diary Report Annexure A1617. Weekly Report Annexure A17

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 12

Page 13: 00 Master Document

PROJECT EXECUTION MANUAL

PROJECT EXECUTION METHADOLOGY

1. SITE VISIT

1. Make Site Visit and make sure that space provided for TSF is leveled.2. Make sure that the accesses to the site is clear3. Mark the location of temporary site facility as per TSF Layout below.4. Covered Laydown Area is 40 Ft X 40 Ft5. Uncovered Laydown Area 40ft X 40Ft6. Mark the temporary site facility. Area required 200Ft X 150Ft7. Carries out the site activities as per responsibility mentioned in responsibility matrix.

All Execution to be done as per following work packages

2. EXECUTION STRAGEDY

8. Diesel Day Tank/Condensate Tank/Diesel Storage Tank are going to be assembled at ground and will be lifted to foundation once all assembly is completed

9. Water Storage Tank/Treated Water Tank are going to be assembled on foundations.

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 13

Page 14: 00 Master Document

PROJECT EXECUTION MANUAL

JOB PACKAGE

WATER STORAGE TANK

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 14

Page 15: 00 Master Document

PROJECT EXECUTION MANUAL

DRAWINGS

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 15

Page 16: 00 Master Document

PROJECT EXECUTION MANUAL

SCHEDULE

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 16

Page 17: 00 Master Document

PROJECT EXECUTION MANUAL

QUALITY INSPECTION PLAN

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 17

Page 18: 00 Master Document

PROJECT EXECUTION MANUAL

MANPOWER HISTOGRAM

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 18

Page 19: 00 Master Document

PROJECT EXECUTION MANUAL

JOB PACKAGE

TREATED WATER TANK

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 19

Page 20: 00 Master Document

PROJECT EXECUTION MANUAL

DRAWINGS

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 20

Page 21: 00 Master Document

PROJECT EXECUTION MANUAL

SCHEDULE

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 21

Page 22: 00 Master Document

PROJECT EXECUTION MANUAL

QUALITY INSPECTION PLAN

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 22

Page 23: 00 Master Document

PROJECT EXECUTION MANUAL

MANPOWER HISTOGRAM

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 23

Page 24: 00 Master Document

PROJECT EXECUTION MANUAL

JOB PACKAGE

DIESEL STORAGE TANK

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 24

Page 25: 00 Master Document

PROJECT EXECUTION MANUAL

DRAWINGS

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 25

Page 26: 00 Master Document

PROJECT EXECUTION MANUAL

SCHEDULE

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 26

Page 27: 00 Master Document

PROJECT EXECUTION MANUAL

QUALITY INSPECTION PLAN

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 27

Page 28: 00 Master Document

PROJECT EXECUTION MANUAL

MANPOWER HISTOGRAM

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 28

Page 29: 00 Master Document

PROJECT EXECUTION MANUAL

JOB PACKAGE

CONDENSATE TANK

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 29

Page 30: 00 Master Document

PROJECT EXECUTION MANUAL

DRAWINGS

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 30

Page 31: 00 Master Document

PROJECT EXECUTION MANUAL

SCHEDULE

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 31

Page 32: 00 Master Document

PROJECT EXECUTION MANUAL

QUALITY INSPECTION PLAN

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 32

Page 33: 00 Master Document

PROJECT EXECUTION MANUAL

MANPOWER HISTOGRAM

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 33

Page 34: 00 Master Document

PROJECT EXECUTION MANUAL

JOB PACKAGE

DIESEL DAY TANK

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 34

Page 35: 00 Master Document

PROJECT EXECUTION MANUAL

DRAWINGS

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 35

Page 36: 00 Master Document

PROJECT EXECUTION MANUAL

SCHEDULE

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 36

Page 37: 00 Master Document

PROJECT EXECUTION MANUAL

QUALITY INSPECTION PLAN

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 37

Page 38: 00 Master Document

PROJECT EXECUTION MANUAL

MANPOWER HISTOGRAM

| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 38