Page 1: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanReview Meeting16.04.2015Brussels, BE

16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

Page 2: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Actions undertaken to date

Market situation / prospective / policy framework

Exploitation / Dissemination / Valorisation actions

Technology implementation plan

Topics

16.04.2015Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

Page 3: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Management performed as required (telcos, SC/GA meetings, reports)

Collaboration between beneficiaries

WP1-WP7 ppt of 15.04.2015 current status M1-18

Specification of situation at demo-site (site visits)

Specification of input for tendering

….

Actions undertaken to date

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 4: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Market prospective – Buildings EU-wide

Market situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Source: DoW p. 80BPIE report, 2011, p 8

Page 5: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanMarket situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Market impact: Ownership of non-residential buildings

Source: DoW p.79 BPIE report, 2011, p 41

Page 6: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanMarket situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Source: DoW p. 81BPIE report, 2011, p 51

Energy impact

Page 7: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanMarket situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Source: DoW p. 81BPIE report, 2011, p 52

Energy impact

Page 8: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanMarket situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Source: DoW p. 81BPIE report, 2011, p 52

Energy impact

Page 9: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Market prospective – Buildings within consortium ADU as a public owner of different education buildings and

districts. They own 43 Buildings of different characteristics in Aydin.

GEX being the regional government of the Spanish region of Extremadura owns 944 different buildings

SPB. Being the Liege Province Service of Buildings as a public owner of 370 different education buildings and districts

Further analysis on the market situation will be done on public/private residential buildings with similar characteristics, and commercial buildings such as malls

Further also focus will be set on social housing

Market situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 10: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Market prospective – Technology Further analysis needs to be done during the next period,

this will include: SWOT analysis of technology solutions, Value innovation analysis (value propositions)

Market situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 11: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Policy framework

European Strategic Energy Technology Plan

The EU climate and energy action targets “20-20-20”

The European Initiatives on Smart Cities

EU Directives:

Renewable Energy Directive

Energy Efficiency Directive (2012/27/EU)

Directive on the energy performance of buildings (EPBD)

Directive 2004/8/EC on the promotion of cogeneration based on a useful heat demand in the internal energy market

Public procurement for a better environment

Market situation / prospective / policy framework

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 12: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

SME involvement Greencom, Purinova, Soltigua, RANK

Soltigua is in the SC and representing SME interests

Exploitation potential of SMEs Greencom, Purinova, Soltigua, RANK

by replication in demo-site regions/with demo site partners, in future market uptake projects (H2020/KIC IE), by actities in EU- wide industrial networks

Use of results: plan for the use of foreground, incl. any update Overall concept of exploitation workshops next slide Structure of Exploitation Plan next slide

Exploitation / Dissemination / Valorisation actions

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 13: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanExploitation / Dissemination / Valorisation actions

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Identification of relevant project results // Identification of results with potential for exploitation // IPR Management - Clarification of IP / IPR / Access (Rights) / Exploitation Claims

Market Analysis: description of the market (PEST), description of the solution proposals (SWOT)

Value Innovation Analysis: Characterisation of exploitable results, Analysis on organisation level (interest/ capability/ strategy match)

Business Model Frameworks: financing (business model development), strategic partnerships, technology watch (synergies with Enterprise Europe Network)

Technology Implementation Plan and Roadmapping

Source: Del. 6.17/18_M18

Page 14: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Dissemination Flow

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 15: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Actions by partners include Participation in 48 events Publications : 25 press releases, 18 articles and interviews, 3 broadcasts, 2 e-

Newsletters

Dissemination targets   General public via web site and LinkedIn page – over 17 000 hits Online media: BuildUp portal, Construction21 platform, Ingenieros.es Controlling stakeholders including national, regional and local public

authorities, European and national professional associations and platforms

Resource/ knowledge stakeholders including RTD projects, universities and research centres

Value chain stakeholders including general public via web site, building industry, promotors and investors

Exploitation / Dissemination / Valorisation actions

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 16: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Users and stakeholders from outside consortium Training seminar with students at ULG – Building teaching

opportunities into energy efficiency renovations (see interview on web site)

First Open House at the ULG 25/04/2015 – Interviews with attendees for youris web site

Links to other projects and/or programmes, interactions with Initiatives from FP7, SCC, national programs (web site) Membership in European and national key stakeholder

organisations (web site) Member of the RESSEEPE platform involving 35 representatives

of different EeB projects ENACE (certification body, Spain), promote BRICKER at events,

e.g. SuSoH 12/03/ 2015 Madrid

Exploitation / Dissemination / Valorisation actions

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 17: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Major fairs and events with dedicated BRICKER contributions to

Annual EeB PPP Impact workshops – EeB SCC community ASME – ORC 2015 (RANK, ULG) – Co- and trigeneration

community Dissemination/ exploitation workshop with the cluster partners

end 2015 ECTP conference 2016 – Building industry, RTD community Open House at demo sites during EUSEW 2016 – Citizens Construmat 2017 – Building industry, architects, building

engineers Batimat 2017 - Building industry, architects, building engineers CECODHAS Conference –Social housing community Event dedicated to public building owners,, e.g. Convenant of

Mayor assembly, Energy Cities events, Climate Alliance events Event gathering investors and promotors, e.g EIB Climate

Finance Day

Exploitation / Dissemination / Valorisation actions

Planning events opportunities

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 18: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Presentation of BRICKER results with visual material, brochures, Best Practice book.

Targeting EU institutions and relevant professional associations at European level

Option: Study tour for conference participants to the Liège demo site.

June/ September 2017 in Brussels

Exploitation / Dissemination / Valorisation actions

Planning Final Conference

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 19: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Articles, interviews and press releases about BRICKER progress

Ten articles dedicated to BRICKER results in Scientific publications Technical literature Dedicated journals

…..such as <input from BRICKER partners>

Exploitation / Dissemination / Valorisation actions

Planning publications

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 20: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Map key messages to events audiences and publications

BRICKER brings about greater energy efficiency in public owned buildings through smart retrofit – Citizens, building owners

To achieve energy efficient buildings on a European scale, BRICKER delivers a set of renewable and adaptable solutions – Constructors, architects, building industry

Replicability is key to the widespread and beneficial application of the BRICKER concept – Public Building owners

Latest advances in building technologies and legal and economic knowledge come together in BRICKER to produce a comprehensive and integrated approach to cutting energy demand in public buildings – Designers and planners, promoters and investors

Exploitation / Dissemination / Valorisation actions

Planning – Message mapping

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 21: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Presentation of BRICKER results with visual material, brochures, Best Practice book.

Targeting local/ regional/ public administrations, architects, designers and engineers, research organisations

Madrid, Liège, Izmir

Webinar targeting public building owners

Exploitation / Dissemination / Valorisation actions

Planning workshops including study tours to demo site in 2017

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 22: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Presentation of BRICKER results with visual material, brochures, Best Practice book.

Targeting local/ regional/ public administrations, architects, designers and engineers, research organisations

Warsaw, Rome, Stuttgart, Paris

Webinar for architects, building designers, engineers and research

Exploitation / Dissemination / Valorisation actions

Planning workshops in 2017

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 23: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Approach (Tasks 4.6, 5.5, 6.4), Part B p. 79/82, impact

BRICKER concept <see concept on following pages> and we are going to try to make it work in the 3 demos, so we maybe can make the future plan implement/replicate/valorise

Overview on the tendering processes, on site status at demo-sites related to the status of implementation.

Technology implementation plan

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 24: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Combination/Integration

Zero emissions energy

production technologies

Envelope retrofitting

solutions

The BRICKER Concept

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 25: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Envelope retrofitting solutions for energy demand reduction

The BRICKER Concept

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 26: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Zero emissions energy production technologies

The BRICKER Concept

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 27: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Development of integration and operation for BRICKER technologies : guidance for design, commissioning and maintenance

Implementation in three real building complexes in different countries with different end-uses

Technology integration, guidance for implementation and technolgical transfer to social housing.

The BRICKER Concept

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 28: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation Plan

Impact : scientific/ technical/ commercial/social or environmental impacts/evidence not measurable yet, expected :……

Business Model framework development will support implementation and replication

Structure of Replication Plan see next slide

Technology implementation plan

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Page 29: + Technology Implementation Plan Review Meeting 16.04.2015 Brussels, BE 16/04/2015Review Meeting 1 – Brussels – Juan Ramón de las Cuevas Jiménez, Charlotte

+Technology Implementation PlanReplication plan / Valorisation actions

Review Meeting 1 – Brussels – Juan R. de las Cuevas Jiménez, Charlotte Schlicke, Helga Treiber

16.04.2015

Identification and quantification of suitable building typologies

Suitability Analysis

Impact assessment (Energy and CO2 reductions, RES production and socio-economic gains)

Roadmap for Implementation

Alignment with local planning / regulation framework

Source: Del. 6.17/18_M18