| bam goes to the south pole | pioneering in a british ... · bascules are balanced so that lifting...
TRANSCRIPT
| BAM goes to the ... South Pole 4| Pioneering in a British dock 5| Circular construction 8
This will float
Five gravity-based wind turbine
foundations are fast taking
shape in their dock near
Newcastle upon Tyne. BAM
Nuttall, BAM Infra and BAM
Infraconsult are working closely
together on this innovative
project. The caissons are due to
be towed (!) to their submersion
location off the British coast
near Blyth this spring. More
about this project on page 5.
Magazine of Royal BAM Group nv, volume 14, number 1, spring 2017
Danish bio lab
BAM goes to the ... South Pole
Sleek-lined water towers
Luxurious living by the Schelde
Pioneering in a British dock
The unmissable addition to Manchester’s skyline
Major upgrade of the Kiel Canal sea lock
Aloft Hotel Dublin
The Swan opens its wings again
On the Lyngby Campus of the
Technical University of Denmark
in Copenhagen, BAM Danmark
has handed over the biotechnology
research centre for DTU Biosustain
- Novo Nordisk Foundation Centre
for Biosustainability. The six-storey
building has a total floor area
of over 12,000 m² and offers
laboratories, classrooms, offices,
meeting rooms and a canteen.•
Tower BridgePedestrians – some 40,000 every
day – and drivers (21,000) were
recently able to reclaim the
unhindered use of London’s
122-year-old Tower Bridge. For
a period of three months, BAM
Nuttall has been busy repairing
and resurfacing the two moving
sections, including some repairs
on the supporting structure.
The project required intricate
logistics – dividing the work
into sections to retain pedestrian
Aloft Hotel DublinIn Dublin, BAM Ireland is
constructing an Aloft Hotel.
The 20-million-euro project is
for the design and construction
of a 202-bed hotel. This
comprises a seven-storey
in-situ concrete structure
above a two-storey basement
with retail areas on the ground
floor. The façade is a bespoke
unitised glazing system, with
rain screen and natural stone
access – and also a vast amount
of historical and material research
on what types of wood and steel
the bridge was originally
constructed from. ‘We did a lot
of investigations, but ended up
with like for like’, says BAM Nuttall
Senior Agent Agne Smakovaite.
‘The overall weight won’t change.’
This is crucial as the 1,000-tonne
bascules are balanced so that
lifting them requires very little
energy.•
cladding. In addition to
bedrooms and suites, the
hotel has a foyer and reception,
all day restaurant areas, bar
facilities, meeting and
conference spaces,
administration rooms and
a gym area. BAM will hand
over the hotel to client
Pembroke Hospitality Ltd
in April 2018.•
Circular construction
9
11
5
7
10
4
2
12
8
2
From the Board - BAM Construct UK
Stronger collaboration and performanceImplementation of ‘Building the
present, creating the future’ is well
underway in BAM Construct UK.
We made good progress in 2016
and I am pleased that we delivered
the profit for 2016 that we
promised the Group. We improved
our cash position by 111 million
pounds over the year to 258 million
pounds. This year our goal is to
achieve at least two per cent
profit on all of our operations.
‘Building the present, creating
the future’ has helped us to focus
on the market sectors and the
clients we wish to target, while
the stage gate procedure is
helping us to be more selective
about projects. The quality of
our order book is improving.
Having a coherent strategy
enables us to create a resilient
business that can exploit any
benefits or withstand any shocks
that may emerge from Brexit.
It is good to see that the strategy
is leading to increased collaboration
across Royal BAM Group. For
example, we value the input
from colleagues in other operating
companies in peer reviews and are
learning a great deal from reviewing
their projects. There is a vast
reservoir of expertise across Royal
BAM Group and the more we share
it the more we will all succeed.
As well as achieving greater
operational efficiency, the drive
to digitalise our business and
the goal of having a positive
net impact for society from our
work are inspiring objectives for
everyone in the Group.
And while we become a stronger
Group, we must also become
a safer one. Our primary safety
goal this year in BAM Construct UK
is to increase the involvement of
our supply chain in our safety
management. We had ten
accidents involving serious
injuries on our sites last year;
we must reduce that this year.
Graham Cash, Chief Executive
BAM Construct UK
Rijnstraat 8 readyIn January the Poort Centraal
consortium, BAM, ISS and
architect OMA, received the
Availability Certificate for
the Rijnstraat 8 in The Hague.
Originally the seat of VROM,
the Ministry of Housing, Spatial
Planning and the Environment,
the building is now a flexible and
sustainable multi-agency building
– energy label A – suitable for
6,000+ employees of three
Ministries: Foreign Affairs,
Infrastructure and Environment
and Immigration and
Naturalisation Services and
the Dutch Central Agency for
the Reception of Asylum Seekers
(COA). To mark the end of the
construction period, the BAM
band ‘Under Construction’
performed on site.
Project completion takes place
on 10 March 2017 and end users
will move into their new building
in June 2017. BAM PPP will
continue to manage the project
until 2042, with facilities
management provided by
BAM Bouw en Techniek and ISS.
Project Director Fred de Jonge:
‘All who have committed
themselves to this magnificent
building have every reason
to be proud of the result’.•3
Appointment
Walter Swinkels has been appointed as Director
Governance, Risk and Compliance (GRC). Swinkels
was a partner at consultant CPI Risk Finance
Governance and also a lecturer at the University
of Amsterdam. BAM regards governance, risk
and compliance as three interconnected pillars
which are essential to realise the Group’s strategic
objectives and maintain a solid reputation.
BAM has been chosen to partner with British Antarctic Survey (BAS) to modernise UK Antarctic and other research facilities. BAM has teamed up with major European design consultants Sweco to assist with project delivery.
Commissioned by the Natural
Environment Research Council
(NERC), this long-term UK
partnership will last between
seven and ten years and is
estimated at 120 million euro.
The modernisation programme
will enable a world-leading
capability to ensure that Britain
remains at the forefront of climate,
biodiversity and ocean research
in the polar regions.
One of the first projects to
be undertaken by BAM Nuttall
and BAM International is the
redevelopment of the wharf at
the BAS Rothera Research Station
on the Antarctic Peninsula.
This is part of the enhancement
of polar facilities to accommodate
the new state-of-the-art polar
research vessel the RRS Sir
David Attenborough.
In addition to building a new
wharf, storage and living quarters
at Rothera Research Station, other
Antarctic development projects
that will be undertaken include
modernising buildings and
facilities at BAS stations in Signy
(South Orkney Islands), Bird Island
(South Georgia) and at King
Edward Point (South Georgia).
The Antarctic construction
projects will present unique
challenges given the continent
is the highest, driest, coldest
and windiest on Earth, and most
construction work will need to be
completed during the four-month
window of the Antarctic summer.
Construction workers will live and
work alongside science teams in
harsh and remote environments,
sometimes in sub-zero
temperatures.
‘We will be fully isolated on site
and will have no one to rely on but
ourselves. Leaving early won’t be
an option and there are no friendly
neighbourhood shops around the
corner. You have to be up for that,
and of course that is something
we will take into consideration
when assembling our team’, says
Project Manager Gerard Turk.•
Gerard Turk.
BAM goes to the ... South Pole
Hotel in Sphinx porcelain factory
Part of the historic Eiffel building in
Maastricht, once part of the Sphinx
factory complex, is being converted
by BAM Bouw en Techniek into The
Student Hotel. The 378-room hotel
will be opened in the autumn of
2017. The remaining forty per cent
of the monumental building will
be delivered in shell form, ready
for further development for
residential, commercial, retail or
catering purposes. The contract
value is 28 million euro.
4
Innovation
Pioneering in a British dockThings are moving fast in Newcastle! In the construction dock on the banks of the river Tyne, the steel shafts of the wind turbine foundations have already reached a prominent height and will soon rise up another thirty metres.
A group of British and Dutch BAM
companies is building these five
submersible wind turbine
foundations, which will be lowered
onto the North Sea seabed off the
coast of Blyth, Northumberland.
The project, partially financed
with a Dutch sustainability grant,
is EDF Energy Renewables’ way of
demonstrating that, in deeper waters
especially, submersion is an excellent
alternative to jackets placed on the
seabed.
The hybrid construction (concrete
caisson and steel shaft) was designed
by BAM Infraconsult. ‘It is wonderful
to see our contribution to sustainable
energy becoming reality’, said Nhut
Nguyen, who leads the BAM
Infraconsult design team. ‘It shows
that BAM is able to handle the entire
cycle from design to construction
and, finally, submersion.’
The other BAM parties in the project
are BAM Ritchies, BAM Nuttall, BAM
Infra and BAM International, whose
Siewert Dob is currently overseeing
the heavy civil part of the works.
Engineering Manager Richard Bewell
of BAM Nuttall is pleased to see how
all BAM partners unite to meet the
challenges of the complex innovative
project. ‘Among the most
challenging features are the
temporary works required during
fabrication. For the conical roof of
the caisson, for instance, 130-tonne
precast elements are held in place
with extensive steel temporary
works while interconnecting
in-situ concrete is placed and
cured. The steel components are
then removed from the caisson
via a number of openings.’
A key aspect of the project is to
learn from the work with an eye
on further development for mass
production. Sander Overbeeke,
Business Development Consultant
at BAM Infraconsult: ‘We are looking
at options to reduce weight, for
instance, and alternatives for the
use of temporary constructions.
The input from the project team is
of great value to our investigations,
especially with regard to
constructability.’
In the spring the caissons will
receive a final layer of ballast
concrete. Towing and submersion
of the units are scheduled for
May/June 2017.•
Richard Bewell taking his BAM Infraconsult colleagues on a tour of the dock.
5
Tweets
German department for lean construction
Established in mid-2016,
the new department aims to
systematically improve value-
adding activities in design and
construction and eradicate
inefficiency. ‘The success of
the implementation of lean
construction depends on the
commitment of all employees
in all divisions and at all levels
of the company. For it is only
our employees who have the
know-how and the experience
that we need to sustainably
improve and strengthen
internal and external processes’,
says Sebastian Lange, Head of the
Lean Construction Department.
‘Our work starts with our
engagement. Followed by
supporting pilot projects and
providing training to share our
‘Lean Construction’ and tool
utilization know-how.’
Tool: regular meetings
One of those tools involves
meetings that take place on
a regular basis. ‘These meetings
focus on the information
Every business has processes that leave room for further optimisation. At BAM Deutschland, there is now a separate department that is dedicated to developing improvements on the basis of the principles of lean construction.
requirements of the participants
and knowledge sharing. The
objective should at all times be
that meetings have added value
for all participants. Depending
on the size of a group, meetings
should not be longer than fifteen
to twenty minutes’, says Lange.
How often and in which manner
these meetings are held isn’t
decisive – what counts is the fact
that they are held regularly. In
addition to knowledge sharing,
regular meetings have many other
benefits, such as team building,
Across the UK construction
sector there have been a
worrying series of tragic
incidents involving forward
tipping dumpers. Including
the fatality at a BAM Nuttall
project in Scotland.
Chief Operating Officer Erik Bax
recently visited the project
involved together with
Corporate Safety Officer
Geert van der Linde and
Steve Fox, BAM Nuttall Chief
Executive. They visited the
location of the fatal accident
offering support and
condolences to those directly
involved.
Discussions took place with
site employees on how such
incidents could be avoided in
the future. There were also
discussions on the segregation
of construction traffic and
pedestrians. Geert van der Linde
stressed the importance of open
dialogue and engagement with all
employees, so that vital information
can be used to prevent incidents in
the future. It is crucial that lessons
are learnt not just by BAM Nuttall
but by the Group as a whole.•
BAM Nuttall is working with other stakeholders in the UK construction industry on forward tipping dumpers with a view to eradicating their use on construction projects.
Dumpers made safer
The Scottish site.
Safety
The unmissable addition to Manchester’s skyline
BAM and the ‘Big Six’ are realising
the 100-million-plus-euro project
on a commission from Allied
London. ‘This developer plays
a key role in the renovation of
Manchester’s older areas, like
Spinningfields, which over the
past decade has been transformed
into a brand-new business centre.
This office tower is more or less
the final piece in the Spinningfields
puzzle’, said Project Manager
Philip London.
The contract is the first from Allied
London for BAM Construction,
which has already delivered a series
of prestigious projects in the British
industrial city, such as One Angel
Square, the Graphene Institute and
Manchester City Football Academy.
‘Allied London recommended
that we collaborated with six
subcontractors
who had
delivered to full
satisfaction on
the foundations,
concrete and
steel structures,
façades, building
installations and lifts of previous
projects. We’ve nicknamed them
the Big Six. It’s working out very
well and construction is going
according to plan.’
The building, which is designed
to achieve a BREEAM Excellent
sustainability certificate, will
reach completion by mid-2017.
Allied London has praised BAM
for collaboration. ‘BAM has shown
a real understanding of our need
to secure tenants for the building.
With BAM‘s support, we have
produced one of the best
marketing suites ever seen in
a commercial development
in the UK’, said Chris Reay,
a Director of Allied London.•
In Manchester, BAM Construction is working with six major subcontractors on building No. 1 Spinningfields, an office tower reaching 112 metres high, that will offer 24,000 m2 high-end office space.
Philip London.
Lean construction leverages the know-how of the employees.
a better insight into project
progress and current issues, and
a better overall understanding
of processes and related matters.
Long weekly meetings can be
shortened, lengthy protocols can
be simplified. The know-how and
free capacity of employees can
be put to use more efficiently and
to avoid duplication. Eventually,
a direct and personal style of
communication results in crystal-
clear agreements between all
internal and external parties
and disciplines.•
Crane barge IB-Marlin arrived ahead
of schedule at Willemstad, Curaçao,
where she will be deployed at the
Mega Cruise Pier project.
No.1 Spinningfields basking in the sun in January.
The new look of Hoog Catharijne2017 is going to be the year of
Hoog Catharijne, the drastically
renovated shopping mall in
Utrecht’s city centre. This
spring, shopping crowds and
rail users on their way to
Utrecht Central Station will be
able to feast their eyes on the
mall’s brand-spanking new
exterior. Realised by BAM NHC
(a joint venture of BAM Bouw
en Techniek and BAM Infra
Civiel), the buildings comprising
Utrecht’s main shopping
attraction are now a pleasure
to behold on the outside as
well as the inside. One of
them, Poortgebouw (picture),
features colourful and partly
extremely curvy façades.
Its upper levels (third storey
and higher) will eventually be
used as a hotel. Ahead of the
aboveground part, the five-floor
underground car park was
taken into use in mid-2016.•
76
Innovation
Circular construction
ABN AMRO Bank chose BAM Infra
to do the structural work on the
basement of the pavilion in front
of its headquarters, while BAM
Bouw en Techniek and BAM
Advies & Engineering joined the
bank, the architect Architecten Cie.
and other project partners in the
development of a design that
fulfilled ABN AMRO’s wishes with
regard to circular construction.
‘Basically, circular construction
revolves around a chain-wide
effort to maintain or even increase
the value of raw materials. This
requires a mind-reset that lets you
see design and production as
a whole. All elements have to be
suitable for assembly and future
re-assembly’, says Sander Holm,
Sustainability Manager at BAM
Advies & Engineering.
In the run-up to the project, the
partners have reviewed designs
on the basis of criteria such as
sustainability, aesthetics, circularity
and life cycle costs. The criteria for
materials and products included
residual value, recyclability and
maintainability.
The pavilion will contain a
meeting centre and a catering
facility that will seat 200. Above
ground, the building will have
two storeys and a partial third
level. ABN AMRO will be able to
showcase this example of circular
construction later this year.•
In Amsterdam’s ‘Financial Mile’, the Zuidas business district, BAM is leading the way in circular construction. In close collaboration with its client, ABN AMRO Bank, and their mutual project partners, BAM is building a pavilion that consists almost entirely of elements that can be re-used.
The BAM Bouw en Techniek team jumps for joy at the pavilion.
Re-usability was a key factor in choosing materials and products such as fire reels, fronts and doors.
Al Ain stadium completedBAM International has completed
the original scope contract for
the Al Ain stadium mixed use
development in the emirate of Abu
Dhabi. The original scope of work
comprised six residential buildings
with retail units, a 10,000 m2 office
building, a four-star hotel, 650 m2
of food and beverage outlets,
a 1,350 car park building and
infrastructural works. The Aloft
hotel (brand of Starwood) includes
173 rooms and a variety of
facilities, such as a gym, spa,
swimming pool, and restaurants.
The project is situated next to
the earlier by BAM completed
25,000 seats Hazza Bin Zayed
stadium in Al Ain. Earlier last year
BAM was awarded an extension
to the original scope of work:
a 100-unit residential building
which is targeted to be completed
by October 2017.•8
Strategy
The BAM Bouw en Techniek team jumps for joy at the pavilion.
Project management seminar ‘Build, share, explore’
The next morning COO Erik Bax
kicked off the seminar with
a presentation in which he
connected the Group’s new
strategic agenda with personal
leadership and BAM’s four core
values. The latter were put into
practice in an interactive exercise
during which participants shared
knowledge and gained new
expertise. Ahead of the seminar,
participants had been asked to
complete an Insights Discovery
questionnaire so that personal
profiles could be drawn up that
showed their preferences and
Network building, knowledge sharing and an exploration of leadership: these were the three key focus areas of the second international Olympus project management seminar. On the evening before the seminar, the 75 participating project managers got acquainted over dinner, a pub quiz and drinks.
leadership styles. These were
then discussed on the basis
of inspirational interviews.
Afterwards Erik Bax and
two project managers shared
experiences with the audience.
The afternoon programme
revolved around leadership
workshops focusing on personal
leadership and interaction with
others, followed by a discussion
in which Rob van Wingerden
explained how he uses his
preferences in his job as CEO.
‘Evaluations showed that
participants were pleased with
the open atmosphere. They could
freely discuss things like behaviour
and awareness’, said Saskia van der
Meij, Head of Talent Management
and leader of the Olympus project.
‘We will build on these seminars in
the development of our leadership
programme, which we hope to
pilot in early 2017 with a small
group of project managers.
The final programme will then
be rolled out in the course of
2017 and 2018.’•
Sleek-lined water towersFrom B to C: BAM Lux seems
to be taking the strategy
slogan ‘Building the present,
creating the future’ quite
literally. In the Dippach
municipality in Luxembourg,
some ten kilometres west of
the Grand Duchy’s capital,
Galère’s subsidiary is realising
a drinking water station whose
shape very much resembles
the letter C.
Architect Paul Bretz, who
often uses fair-face concrete
in his designs, is the man
who came up with this unusual
shape for the water tower.
The base of the building
contains two water basins of
600 m3 each. Twenty metres
above them are two storage
tanks of 200 m3. ‘In order to
absorb the enormous forces
in the cantilevering construction
we have postensioned the concrete
with tendons in the base as well as
the cantilevering and upright parts
of the tower’, says Project Manager
Denis Franssen. The project has
a contract value of 2.3 million euro
and will be handed over in June
2017.
For a similar contract sum, BAM Lux
is realising a second and similarly
sleek water tower in Bech, some
twenty kilometres northeast of the
capital. This construction, designed
by Beiler & Francois, stands fifty
metres tall. The ‘cut-out’ corners
will be closed off with bronze-
coloured panels. This tower will
also be completed in June.•9
Major upgrade of the Kiel Canal sea lock
It ain’t half big, mum!
With over 30,000 ship movements
per year, the 100-kilometre Kiel
Canal is the world’s busiest
shipping artery. The canal, known
locally as the Nord-Ostsee-Kanal,
connects the North Sea with the
Baltic Sea. At the North Sea end,
ships enter the canal through
the old Brunsbüttel locks.
The 346-million-euro contract
to build the fifth lock chamber
was awarded to the 50/50 Dutch-
German BAM joint venture, with
BAM Infra taking half and the
two German companies each
taking a quarter.
The new lock chamber will
It’s the largest project in the
history of BAM International: the
new container terminal (phase 2A)
near Moín, Costa Rica. While
consortium partner Van Oord is
making excellent progress with the
reclamation and soil improvement
works, BAM is already laying the
foundations for the 650-metre-long
quay wall. When this is complete,
the project team will have driven
888 piles. Meanwhile the
be 360 metres long and 45 metres
wide. Project Manager Dirk Bennje:
‘The objective of the project is to
increase sufficient capacity to allow
an overhaul of the existing lock
chambers without impacting
prefabrication of 16,000 Xblocs
has been completed. The new
terminal will take almost three
years to complete. This year will see
the realisation of several parts of
the project such as the quay wall,
the tug boat port, several buildings
and the pavement of the
30-hectare port area and related
facilities. The project team
currently consists of 750 people,
with 25 different nationalities.•
The new sea lock in Brunsbüttel, Germany, is currently being realised in a joint effort by BAM Infra, Wayss & Freytag Ingenieurbau and Wayss & Freytag Spezialtiefbau. After thorough preparations, the contours of the fifth lock chamber are now taking shape on an island in the middle of the lock complex.
shipping traffic. It’s one of those
amazing, once-in-a-lifetime
projects.’
Bennje and his 45-strong mixed-
nationality team are facing the
challenge of realising a technically
complex project combined with
the logistical challenges of the
island location. To meet the latter,
they now have their own ferry to
transport materials, equipment and
personnel to and from the site.
At this point in time the site is
dominated mainly by the
cranes and installations of W&F
Spezialtiefbau and BAM Speciale
Technieken. Bennje: ‘The
construction pits are gradually
taking shape, while piles are
being assembled and bentonite
trenches are being dug out for
the combi walls.’•
Dirk Bennje.
The combi wall consists of sheet piles and 40-tonne double H beams.
Overview of the lock island between the existing locks.
Team members posing in front of the project’s own ferry.
10
Luxurious living by the Schelde
‘These buildings are built to
the highest quality standards
in ventilation, insulation and
materials’, says Project Manager
Koen de Wit. He is currently
in charge of the construction
of block 5, which contains
16 apartments, 116 assisted
living apartments and communal
facilities. Five other projects are
in the hands of four of his fellow
project managers.
Designed to the energy-efficiency
standard of the ‘passive house’,
the buildings will meet rigorous
demands in airtightness and will
have green roofs and district
heating. Koen De Wit: ‘Each
building is by a different architect
so there is a lot of variety, despite
a sort of recurring theme of white
concrete prefab elements. The
buildings are interspersed with
green zones, which creates a park-
like environment.’
After handing over four buildings
in 2016, Interbuild is now in the
middle of structural work on
block 5 and has recently started
two new projects.•
In Antwerp’s Nieuw Zuid district, along the river Schelde, Interbuild is building a ‘green’ residential area. Developed by Triple Living the project comprises 38 buildings with a total of 2,500 apartments, student housing, offices, schools, shops and other facilities.
Five ‘Nieuw Zuid’ project managers (from left): Christoph Van Dijck, Jeroen De Vlaminck, Massimo Carroccio, Rolf Letens and Koen De Wit.
Under construction: U-shaped block 5. To the right: construction pit for block 9.
Clean air for care
One of the operating theatres realised by Interflow.
Short turn around times and high quality are key features of Interflow’s projects for the care sector. More and more often, the clean-air specialist takes on main-contractor responsibilities regarding the co-ordination of all project parties. So too on this Amsterdam project to convert a former commercial building into a state-of-the-art clinic.
many technical installations.
All plenums and the flex wall,
clean wall and clean ceiling
systems have been chosen
from Interflow’s product lines.’
After a period of commissioning
and validating the technical
systems, Interflow will hand
over the clinic in March 2017.•
Peter Breman, who manages
Interflow’s project office:
‘We are the main contractor,
but the structural knowledge
and experience of BAM Bouw
en Techniek provide substantial
added value. The centre will have
four operating theatres and the
roof will accommodate a great
A striking feature of block 4: the freely suspended balcony rooms. The steel suspension structure is attached to the roof.
11
Follow us on
High Speed Two
BAM Nuttall has been awarded the Central Enabling Works Contract for High Speed Two (HS2) from London to Birmingham as part of a joint venture. The contract will be worth up to a 100 million pounds over a period of four years. The contract includes the early preparatory work needed ahead of the main civil engineering work for the scheme, including archaeology, site clearance and setting up construction compounds. Work is due to begin in spring 2017.
Multi-faith school
BAM Design and BAM Construction have been appointed to design and build the 25 million pounds Nishkam School in West London. The all-through school with a sixth form will provide places for 1,400 pupils and be set over two and three storeys with four wings radiating from a central hub. The school has several interesting environmental aspects: an extensive solar array on the roof, electric charging points in the car park, and the football field will be used for storm attenuation.
Collection Building Museum
The Municipality of Rotterdam has awarded BAM Bouw en Techniek the contract for the construction of the Collection Building for Museum Boijmans Van Beuningen in Rotterdam. The mirror-clad building designed by architectural firm MVRDV will house a public art depot. The contract value is approximately 43 million euro. Completion is expected in 2019.
BAM World is compiled by Monica van Soldt, Royal BAM Group nv, Corporate Communications, P.O. Box 20, 3980 CA Bunnik, The Netherlands, telephone +31 (0)30 659 86 23, e-mail [email protected] De Beeldredaktie, Adam Bradley, Sandy Cordiner, Ossip van Duivenbode, Chris Henderson, Fotografie Jonathan Vos, Walter Saenen, Patrick ZierDesign Boulogne Jonkers Vormgeving, Zoetermeer Printing MediaCenter Rotterdam
The Swan opens its wings againRotterdam’s favourite landmark, Erasmus Bridge a.k.a. The Swan, is functioning smoothly again. Its 20-year-old mechanism was in urgent need of an overhaul and BAM Infra Verkeerstechniek has been working hard to complete the entire operation within an extremely tight time frame.
a key member of the team that
completed the project to fully
replace the operating and
control systems of Erasmus
and six other bridges.
‘During the closure we replaced
all control panels, working 24/7
the first four days to complete the
replacement and hardware testing.
After that, testing the movable
parts and commissioning the
bridge deck and all safety features
were only allowed during the
night’, says Bakker, who has
been pleased to be part of the
experienced team together with
Project Manager Kees den Dulk,
Lead Engineer René Buitelaar and
Site Manager Martijn Limberg.•
Rotterdam’s favourite, The Swan, opens its wings.
Emiel Bakker at one of the control panels.
Celebrating success at BAM FMHannah Greenhalgh, Facilities
Manager at Derbyshire D Division
Police Headquarters, is named
BAM FM’s Outstanding Team
Member of the Year in the UK.
Louise Williamson, Managing
Director BAM FM, presented
Hannah with the highest accolade
at the company’s annual managers’
conference, hosted in Birmingham
in January.
Louise received an email from the
Deputy Police Constable at
Derbyshire Police Constabulary,
who personally thanked Hannah for
making huge strides in improving
the service delivery at the site.
She has overseen a number of
challenging projects, including
relocating 250 police officers
at short notice with minimal
disruption to their day-to-day work.
As well as winning the overall prize,
Hannah took home the Excellence
in Customer Service Delivery
award. She was among eight
winners at the annual event, which
recognises the best of the best
from the winners of the company’s
monthly employee recognition
scheme BAM FM Stars.
The other winners included: Elaine
Lock, in the Health and Safety
category, East Ayrshire Community
Hospital team, winner of the
Sustainability award, Mark Turner,
recognised for Innovation, Liza
Adnams, winner of the Living the
Values award, Sandra Rogers,
praised for Inspiring Others and
Nicu Toma, who was awarded for
Going Above and Beyond.•
Louise Williamson (left) presents Hannah Greenhalgh with the Outstanding Team Member of the Year Award.
After a 10-day closure of the New
Meuse shipping route, it was a
nail-biting moment for all
concerned when the renovated
Erasmus Bridge was due to open
for the first time. Then it was
smiles all around when at 10am
exactly the bells began to ring
and the barriers came down.
The bridge deck was raised and
The Swan opened its wings again.
Design Manager Emiel Bakker was
one of the proud onlookers and
12