© abb - 1 - 1mrs756828-0 microscada pro ortviken upgrade & crimea wind power plant stefan...
TRANSCRIPT
© A
BB
- 1
-1M
RS
7568
28-0
MicroSCADA ProPartners Club 2008
MicroSCADA ProOrtviken upgrade & Crimea Wind Power Plant
Stefan Johansson, Sweden
© A
BB
- 2
-
Upgrade and wind park projects
Ortviken Paper Mill Upgrade of one of Sweden's largest MicroSCADA
installations to the latest MicroSCADA Pro
Crimea Wind Power Plant New Wind Power Plant on the Crimea peninsula
© A
BB
- 3
-
Ortviken Paper Mill
© A
BB
- 4
-
Ortviken 1850-2005
© A
BB
- 5
-
Facts and figures
Ortviken News
375.000 ton/year
Ortviken LWC (Light Weight Coated)
475.000 ton/year
Number of employees
930
Electrical consumption
1,9 TWh
Facts and figures
© A
BB
- 6
-
Orvikens Electrical installation
2 x 130kV lines from EON, normal power 250MW Outdoor 130kV-substation with 7 st breakers 130kV GIS with 25 bays 12 x refiner 5-15 MW with direct start from GIS 1 x counter-pressure turbine with generator 15 MVA 30 x 6kV substations, 260 bays with Safesix total of
453 bays 60 x 6 kV motors 125 x low voltage/motor substations
© A
BB
- 8
-
Connected IED
250 protection units of type SPAM and SPAJ
45 protections/control units of type REF
100 SACO units analog/digital
100 SPOC units
2 RTUs
Fiber loops via RS232 converters
SPOC 110 C
ABBABB SACO 16 D1
SPAC 539 C
© A
BB
- 9
-
The history of MicroSCADA
First system was installed in 1992
The ”last” was installed in 2001
Total 15 SCS with different versions
Terminal server functionality via external software (Exceed)
NCC was using ATA functionality
Communication and data exchange with the process control system via GCOM
© A
BB
- 1
0 -
SPOC 110 C
ABBABB SACO 16 D1
SPAC 539 C
ST1ST2ST3ST3-11/21ST3-31ST4ST4‑11ST4‑21/31ST53-71ST52ST53ST53-41/61ST56ST57/58GIS
ST53‑61ST2-31/41
NCC/Control room SCS 100
Connection to office network
Alarm announciator
Event printer
Hardcopy printer
SCS 100TERMINAL
TERMINAL
GPS
ÅC
LAN
GCOM-SERVER
15”
TCP/IP
Advant Controller
Delivery by ABB
21” 21” DCNT
The original system
© A
BB
- 1
1 -
How to upgrade the system
The system was to be upgraded in three phases Phase 1
Get a fresh backup of the system
Upgrade all databases to lib 4*
Build a new structure from 15 individual SCS to one NCC with 15 frontends
New database build up from individual SCS
New addressing of all individual databases to fit the new structure
© A
BB
- 1
2 -
Upgrade from LIB3 to LIB4
No ready made tool to upgrade the LIB3 to LIB4
We developed special tool that did parts of the job (excel)
Manual ”hands-on” for addresses etc.
Upgraded all special functions by hand to LIB4
Simulated the upgraded database and all connected SPA units by using SPA-SIM
© A
BB
- 1
3 -
How to upgrade the system
The system was to be upgraded in three phases Phase 1
Get a fresh backup of the system
Upgrade all databases to lib 4*
Build a new structure from 15 individual SCS to one NCC with 15 frontends
New database build up from individual SCS
New addressing of all individual databases to fit the new structure
© A
BB
- 1
4 -
Phase 1
SPOC 110 C
ABBABB SACO 16 D1
SPAC 539 C
NCC/Control room SCS 100
Connection to office network
Alarm announciator
Event printer
Hard-Copy printer
SCS 100 TERMINAL
GPS
Delivery by ABB
Advant Controller
Delivery by ABB
21” 21”
LAN
MicroSCADAPRO, Server A
TCP/IP
Industrial PCwith PCNET
LAN
Local workplace
SPA
ST1ST2ST3ST3-11/21ST3-31ST4ST4‑11ST4‑21/31ST53-71ST52ST53ST53-41/61ST56ST57/58GIS
© A
BB
- 1
5 -
How to upgrade the system
The system was to be upgraded in three phases Phase 2
Upgrade the system by system i.e. letting the old system run in parallel with the new one
Move over SCS by SCS to the new structure
© A
BB
- 1
6 -
NCC/Control room SCS 100
Connection to office network
Alarm announciator
Event printer
Hard-Copy printer
SCS 100 TERMINAL
GPS
Delivery by ABB
Advant Controller
Delivery by ABB
21” 21”
LAN
MicroSCADAPRO, Server A
TCP/IP
SPOC 110 C
ABBABB SACO 16 D1
SPAC 539 C
Industrial PCwith PCNET
LAN
Local workplace
SPA
ST1ST2ST3ST3-11/21ST3-31ST4ST4‑11ST4‑21/31ST53-71ST52ST53ST53-41/61ST56ST57/58ST59/60GIS
Phase 2
© A
BB
- 1
7 -
How to upgrade the system
The system was to be upgraded in three phases Phase 3
Install the Hot standby server
Install and upgrade the new HMI to the new Pro Graphics
© A
BB
- 1
8 -
Connection to office network
Delivery by ABB
SPOC 110 C
ABBABB SACO 16 D1
SPAC 539 C
Industrial PCwith PCNET
LAN
Local workplace
SPA
NCC/Control room
BILDSKRIVARE
MicroSCADAPRO, Server A
TCP/IP
MicroSCADAPRO, Server B
HSB
MicroSCADAPRO, Workstation
ST1ST2ST3ST3-11/21ST3-31ST4ST4‑11ST4‑21/31ST53-71ST52ST53ST53-41/61ST56ST57/58ST59/60GIS
Phase 3
Remote desktoptimesyncOPC-connection
© A
BB
- 1
9 -
Crimea Wind Power Plant
Crimea
© A
BB
- 2
0 -
Facts and figures
Customer
Nova-Eco, Kiev Ukraine
Consultant
Krim-Irey.
Ukrenergomerezhproject (Ukrainian power grid design, "Kharkov Institute”)
Project
Turn-Key delivery of two Wind Power Plant of 200MW and 100MW
Partners
Eltel for 330kV or 220 kV transmission lines and communication.
Martifer / Suzlon for 150 x 2 MW Wind Mills.
© A
BB
- 2
1 -
Site location
Eastern Project Area
Western Project Area
© A
BB
- 2
2 -
West WPP
WPP Substation
© A
BB
- 2
3 -
West WP Substation
125 MVA110/33kV 225 MVA
330/110kV
33kV Switchgear
330kV DCB
Control Room33kV Capacitors
110kV DCB
330kV CVT330kV SA
33kV Capacitors
© A
BB
- 2
4 -
East WPP
WPP Substation
© A
BB
- 2
5 -
East WP Substation
125 MVA220/33kV 220kV DCB
33kV Switchgear
33kV Capacitors
Control Room
© A
BB
- 2
6 -
How to connect ?
?
© A
BB
- 2
7 -
General requirements of the control system
The control system is adapted to fit the requirements of the power system and the turbine
Each feeder contains up to 12 windmills
There has to be a special startup sequence (soft start) during normal startup and trip situations
Startup sequences has to be both manually and automatically
Prepared for OPC connection with the WPP SCADA
© A
BB
- 2
8 -
Setting up the system
© A
BB
- 2
9 -
The RMU
Each Windmill has it’s own RMU: Transformer 690V / 33kV Breaker RTU560D
With I/O to connect to the units in the RMU
Communication switch to the substation Communication to the substation via IEC-104 Internal power supply via the local voltage transformer
The windmill Has it’s own control system powered from the 690V side When the Windmill is started up it will automatically connected to
the power grid
© A
BB
- 3
0 -
Setting up the system
IEC-104
IEC-101 to NCC
© A
BB
- 3
1 -
In the substation
RTU 560 Communicates with all the bayhouses via IEC-104
Communicates to the NCC via a IEC-101 line
Has a PLC program that can manually or automatically control each circuit breaker in each RMUs for soft in coupling of the windmill
Exchange information with the local control in the WPP/SS and the IEDs on the 33kV side
© A
BB
- 3
2 -
Setting up the system
61850-8-1
IEC-104
IEC-101 to NCC
© A
BB
- 3
3 -
In the substation
MicroSCADA Pro Local control of the substation
Communicates with the 33kV bays and the transformer units 220/330 kV via IEC61850
Exchanges information with the RTU for local control
Start/stop of all sequences of the 33 kV power grid
Busbar coloring of 100 RMUs
IED and disturbance tools
© A
BB
- 3
4 -
The system solution for WPP West Ethernet TCP/IP
RMU no1
RTU 560D
2*IEC 60870-5-104 Master
RMU no100
WPP S/S
IEC 60870-5-104 SlaveIEC 60870-5-104 Slave
14pc REX 521
Switch Switch
Switch
SPA ZC402
IEC 61850 Client
Ethernet TCP/IP
IEC 61850 Servers
MicroSCADASubstationControl System
IEC 61850
IEC 60870-5-104
IEC 60870-5-101 Slave
SCADA
4pc RET670
GPS time- syncronisation
RTU 560APLC for manual/automatic control
of circuit breakers in WPP/SS and RMUs
Fibre-cable
TP-cable
RTU 560D
110DC PS16pc DI 110VDC2pc DO 110VDC
110DC PS16pc DI 110VDC2pc DO 110VDC
© A
BB
- 3
5 -
The system solution for WPP East Ethernet TCP/IP
RMU no1
RTU 560D
1*IEC 60870-5-104 Master
RMU no50
WPP S/S
IEC 60870-5-104 SlaveIEC 60870-5-104 Slave
7pc REX 521
Switch Switch
Switch
SPA ZC402
IEC 61850 Client
Ethernet TCP/IP
110DC PS16pc DI 110VDC2pc DO 110VDC
IEC 61850 Servers
MicroSCADASubstationControl System
IEC 61850
IEC 60870-5-104
IEC 60870-5-101 Slave
SCADA
2pc RET670
GPS time- syncronisation
RTU 560APLC for manual/automatic control
of circuit breakers in WPP/SS and RMUs
Fibre-cable
TP-cable
RTU 560D
110DC PS16pc DI 110VDC2pc DO 110VDC