8:30 am lpvex science overview and aircraft operations 8:50 am radar scanning strategy 9:10 am...

14
8:30 am LPVEx Science Overview and Aircraft Operations 8:50 am Radar Scanning Strategy 9:10 am Site Instrument Manifest and Installation Schedule 9:40 am Personnel and Schedules 10:00 am Post-IOP Consolidation to Emasalo 10:15 am Opportunities to Augment Core Observations 10:30 am Break 10:45 am Data Product Inventory, Responsibilities, and Policies 11:15 am Supporting Datasets 11:30 am Data Archival and Experiment Webite 12:00 pm Post-experiment Activities 12:30 pm Adjourn

Post on 21-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

8:30 am LPVEx Science Overview and Aircraft Operations 8:50 am Radar Scanning Strategy 9:10 am Site Instrument Manifest and Installation

Schedule 9:40 am Personnel and Schedules 10:00 am Post-IOP Consolidation to Emasalo 10:15 am Opportunities to Augment Core Observations 10:30 am Break 10:45 am Data Product Inventory, Responsibilities, and

Policies 11:15 am Supporting Datasets 11:30 am Data Archival and Experiment Webite 12:00 pm Post-experiment Activities 12:30 pm Adjourn

Page 2: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

1. Characterize the relative abilities of space-based W, Ku-, and Ka-band radars and microwave imagers and sounders to detect light.

What are the detection limits of each instrument? Can rainfall probabilities be assigned to Z and TB signatures?

2. Evaluate retrievals of rainfall intensity in shallow freezing level environments.

How does the ratio of cloud-rain impact PIA and PMW TBs? How does the vertical structure of precipitation impact

emission/attenuation-based algorithms? What are the impacts of other algorithm assumptions including

DSD and melting layer properties on rainrate estimates? How do well are FOV-dependent factors such as beamfilling and

multiple-scattering represented?

3. Determine the properties of the local environment that influence the characteristics of precipitation in this region.

Page 3: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Harmaja

Maximum Extent of Flight Operations

Region of Likely Flight Operations

Green = FMI Wx Stn = Enhanced Obs. = Vaisala WxTs (inc. rain)Gray circles = 20 km radar range rings

Kerava

RV Aranda Ops.

Emasalo

Turku Järvenpää

Kalbadaglund

= Spiral

= Stacked flight tracks

KumpulaFerry

Ferry

Kumpula SW Gulf Stack

Spiral S1

Kumpula SE

Ker

ava

NE

Ker

ava

NW

Kerava SW

Page 4: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Wyoming King Air W-band cloud radar Water content: DMT, Gerber, Nevzorov Microphysics: 2D-P, CIP, CDP (FSSP/2D-C) Aerosol: PCASP-100X Environment: RH, T, altitude, wind speed

Departing Wyoming ~Sept. 1 (5 days in transit) 3-5 days installation + 4 hours of test flights

(Sept. 8-14) Research flights:

Begin Sept. 15, 2010 Based in Turku – 30 minute transit to Helsinki 50 total research flight hours budgeted (~13-14 flights) End no later than Oct. 20, 2010

Page 5: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Radar quicklooks will be ready within 24 hours of all research flights.

First cut versions of many probe datasets (eg. DSDs, water contents) will also be turned around in 24 hours and stored along with radar data in a netCDF file for each flight segment.

Z

DSD/PSD

RH and LWP

T and z

Page 6: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule
Page 7: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Leg FIR0-FIR15 Plan to fly this path at different altitudes:

FIR0 at 500’ MSL FIR1 at 1000’ MSL FIR2 at 2000’ MSL Similar up to FIR15 at FL150

The FIR Leg will be repeated five times. Either: FIR0, FIR3, FIR5, FIR7, FIR15 

*OR*  FIR1, FIR4, FIR9, FIR15, FIR4.

Page 8: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Pt. 4

Kumpula Radar

Kerava

Radar

FIR Leg: FIR0-FIR15

Pt. 3

Pt. 1

FIR Leg: FIR0-FIR15

Pt. 2

Page 9: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Along axis of ground research radars 4 legs at different altitudes that depending

on weather conditions. The lowest altitude will be 1000 ft. above highest terrain/obstacle as dictated by controlling authority.

~60 Kilometer Tracks: Jarvenpaa, Mansala, and Porvoo (with KER RHIs)

~30 – 40 Kilometer Tracks: Kumpula and Emasalo (with KUM RHIs)

Page 10: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Pt. 1

Track: Kumpula 0-15

Pt. 6

Pt. 5

Track: Emasalo 0-15

Track: Porvoo 2-15

Track: Mansala 2-15

Track: Jarvenpaa 2-15

Kumpula Radar

Kerava Radar

Track: Kumpula 0-15

Pt: 4Pt: 3

Pt. 6

Pt. 8

Pt. 9

Pt. 10 Pt. 11

Pt. 12

Pt. 14

Pt. 15

Pt. 13

Page 11: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Spiral descent: 500 fpm descent rate 1 minute legs standard rate turns from FL 150 to 1000’ AGL (500’ over

water) Option: can do small race-tracks or

continuous descents

Page 12: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

Spiral: S1

Pt. 1

Pt. 2 Spiral:

S4

Spiral: S3

Spiral: S5

Spiral: S2

Kumpula

Radar

Kerava

Radar

Pt. 4Pt. 3

Pt. 7

Pt. 8b

Pt. 16

Page 13: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

5:00 pm Weather briefing/initial decision regarding operations the following day

7:30 am Updated weather/Baltic radar analysis for definition of potential flight tracks

8:00 am Report to ATC with planned tracks and approx. take-off time

TO-1 hour Final check of radar; go/no-go decision TO-0.5 hour Pre-flight briefing with aircraft team (Turku airport) L+0.5 hour Post-flight briefing with aircraft team (Turku airport) L+1 hour Flight/ground-operations tag-up (small group) L+6 hours Daily operations summary posted on website

(weather summary, instrument notes, flight specifics, data quicklooks, etc.)

Three bases of operation: Kumpula campus, Turku airport hangar, and office at Hotel Centro (Turku)

Page 14: 8:30 am LPVEx Science Overview and Aircraft Operations  8:50 am Radar Scanning Strategy  9:10 am Site Instrument Manifest and Installation Schedule

In-flight communications – 2-way radio (source TBD) Initially restricted to pre-defined flight tracks but may

have more flexibility as experiment progresses

Aircraft Tracking: REVEAL box will transmit lat/lon and altitude that can be ingested and plotted with radar software in real-time Ingest being tested now

To keep briefings running smoothly, group discussions should be held in each location independently and relayed to other group via a small number of group leads via Skype/web-meeting