© 2011 autodesk topsoil, asphalt, subcut—one road with overlapping corridors as the answer?...

42
© 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design Inc.

Upload: jameson-norrick

Post on 14-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123Bill Neuhauser, P.E.Civil Engineer – Managed Design Inc.

Page 2: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Bill Neuhauser, P.E. C3D I.C.E.

Managed Design Inc. 2005-

Autodesk Reseller since 1988 (Formally Alignex Inc.) Minnesota, Iowa, Wisconsin and the Dakotas

Minnesota Technical and Community College – 2002-2005 Instructor - AAS Civil Techs

Consulting firms 1990-2002 Registered Civil Engineer – P.E. (ND/MN) CADDD Supervisor – LDT, Eagle PT, Geopak CADDD Manager

North Dakota State University – BS Civil Engineering AU Presenter – 4 years

Page 3: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123

Common rural highway design requires the designer to take into account not just the placement of the new road but also all that must be removed, including topsoils, asphalt structures, SubCut (muck), etc. How can we do this? With more than one corridor! Let us think outside the box and see what we can accomplish with multiple corridors overlapping and all working together to get your complex job done. We will calculate removals and placements all at one time using multiple corridors, multiple surfaces, and multiple sample line groups. We will discuss how to account for existing Topsoil, SubCut and proposed Topsoil placement.

Page 4: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

What are we going to cover today?!

Learning Objectives:

Describe SubCut, scarify, topsoil removal and topsoil placement. Create multiple overlapping corridors to show your existing conditions within one

section view. We will describe why multiple datum surfaces are required and why they are not

possible using a standard corridor. Adjust your Quantity Takeoff Criteria so we can also calculate both removal and

placement quantities from these multiple corridors and their multiple surfaces.

Page 5: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Win a Civil 3D Book!!! (And a few other trinkets)

A Practical Guide to AutoCAD Civil 3D 2012

Donated by Rick EllisCadapult Software Solutions

Civil 3D and AutoCAD Map 3D books available at www.cadapult-software.com

Page 6: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

ADVANCED CLASS

This is one of only 5 Advanced Civil 3D classes being offered at AU!

So we are going to assume everyone here knows their…….C3D……

You are here because you want to learn something “ADVANCED!”

Page 7: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

*DISCLAIMER*

What we will NOT cover in this class!

*The Basics*Intermediates

What we will cover!

*Advanced

What we might talk about….THE “PARADIGM SHIFT”If time permits we will talk about this at the end!

Page 8: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

What is SubCut? The ugly stuff from 100 years ago located right below your new and very expensive road bed that needs to be removed if

you want your road to last for more than 5 years!

Page 9: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

What is SubCut? (cont’d)

SubCut is the additional material below our Roadbed that needs to be removed to give us more structure stability.

SubCut is usually paid for as a separate pay item, since this material can’t be used under the Roadway and must be discarded. There are instances where this SubCut material can be used in ditching and other non-structural fill areas.

Sometimes this SubCut material is just scarified and re-compacted by the contractor.

Page 10: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Why is this an issue in Civil 3D?

As of today there is no “Magic” calculate “SubCut” button in Civil 3D

SubCut requires multiple datum's to be defined within our assembly. This is not possible as of today.

Page 11: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

What are we trying to solve today?

**QUANTITIES**

How much is this going to cost?

Page 12: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

HOW?

3 - Assemblies3 - Corridors

3 - Sample Line Groups

Or what I call the 333 plan!

Page 13: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Assemblies:

Subassembly A is the LaneOutsideSuper

Subassembly B is the StrippingTopSoil

Subassembly C is just a Generic called LinkSlopeToSurface

Assembly Number one – Existing Conditions

Page 14: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Assemblies:

Subassembly A is the LaneOutsideSuper

Subassembly B is the Generic called LinkSlopeToSurface

We will change the codes of the daylight point to “Daylight_SubCut” and links to “SubBase”.

Assembly Number Two – SubCut Condition

Page 15: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Assemblies:

Subassembly A is the LaneOutsideSuper

Subassembly B is the ShoulderExtendAll

Assembly Number Three – No-SubCut Condition

Page 16: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Assemblies:

C and D is the Generic LinkSlopeAndVerticalDeflection

E is the Generic subassembly called LinkVertical

Note the Coding of all three links.

Assembly Number Three (Cont) – No-SubCut Condition

Page 17: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Assemblies:

Subassemblies F/G are the Generic LinkWidthAndSlope

Subassemblies H/I are the Generic called LinkSlopeToSurface

Subassemblies J/K are the Generic called LinkOffsetOnSurface, *these are used to label the ROW and any necessary easements

**It needs to be noted that all top Links need to be coded “Top” and bottom Links need to be coded “Datum” and the outer Top Link end pt needs to be coded “Daylight,” while the datum outer end pt is coded “Daylight_Datum”

Assembly Number Three (Cont) – No-SubCut Condition

Page 18: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Properties Parameters Tab

What Assemblies Used Targets Applied

Surface and Boundaries Tab What Surfaces Need to be Created What Boundaries Applied

Page 19: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Parameters Assembly Name:

Corridor 1 – Existing Road

Targets Applied: Surface Targets

1-EG 1 surface targets Width/Offset Targets

LT and RT Pave survey figures LT and RT Outside Ditch survey figures

Slope/Profile Targets LT and RT Asphalt survey figures

Corridor Number One – Existing ConditionsPage one

Page 20: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Surfaces 2-C1 – DATUM – OLD PAVEMENT:

Links Used: Datum Overhang Correction: Bottom Links

3-C1 – DATUM – STRIPPING TPS: Links Used: Stripping Overhang Correction: Bottom Links

Corridor Number One – Existing ConditionsPage two

Page 21: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Surfaces Boundaries 2-C1 – Datum – OLD PAVEMENT:

Boundary Link Used: Daylight-ex-asphalt Type: Outer

3-C1 – DATUM – STRIPPING TPS: Boundary Link Used: Daylight-ex-asphalt Type: Hide Boundary Boundary Used: Daylight_Strip *** or none Type: Outer Boundary

Manually Created Surfaces: 4-C1 – COMP1 – EG WITH PAV TPS DATUM

*This is the Bottom of the Asphalt and TPS pasted on to the Existing Ground.

Corridor Number One – Existing ConditionsPage three

Page 22: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Section Number One

Corridor Number One – Existing ConditionsPage four

Page 23: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Parameters Assembly Name:

SubCut

Targets Applied: Surface Targets

4-C1 – COMP1 – EG WITH PAV TPS Width/Offset Targets

NONE Slope/Profile Targets

NONE

Corridor Number Two– SubCut ConditionPage one

Page 24: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Surfaces 5-C2 – Btm SubBase – Daylight_SubCut:

Links Used: SubBase Overhang Correction: Bottom Links

Corridor Number Two– SubCut ConditionPage two

Page 25: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Surfaces Boundaries 5-C2 – Btm SubBase – Daylight_SubCut

Boundary Link Used: SubCut_Daylight Type: Outer

Corridor Number Two– SubCut ConditionPage three

Manually Created Surfaces: 7-C2 - COMP2 - COMP1 WITH C2 Btm SubCut -

ETW - C3 FILL ABOVE - CUT BELOW *This is the Bottom of the SubCut pasted onto COMP 2

surface created with Corridor One.

Page 26: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Section Number Two

Corridor Number Two– SubCut ConditionPage four

Page 27: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Parameters Assembly Name:

NO_SubCut

Targets Applied: Surface Targets

7-C2 – COMP2 – COMP1 WITH Btm SubC **Except TOP daylight Links

Width/Offset Targets NONE - Project dependent

Slope/Profile Targets NONE - Project dependent

Corridor Number Three– No_SubCut ConditionPage one

Page 28: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Surfaces 8-C3 - FG Datum Above SubBase - C3 FILL BELOW – CUT

ABOVE: Links Used: Datum Overhang Correction: Bottom Links

9-C3 - FG TOP: Links Used: Top

Overhang Correction: Top Links 10-C3 – DATUM FG TPS:

Links Used: Datum Overhang Correction: Top Links

Corridor Number Three– No_SubCut ConditionPage two

Page 29: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Surfaces Boundaries 8-C3 - FG Datum Above SubBase:

Boundary Link Used: Daylight Type: Outer

9-C3 - FG TOP: Boundary Link Used: Daylight Type: Outer

10-C3 – DATUM FG TPS: Boundary Link Used: Daylight_Sub Type: Inner Hide Boundary Link Used: Daylight Type: Outer

Manually Created Surfaces: 11-C3 – COMP3 – COMP1 WITH TOP

*This is the final Top surface from corridor number three pasted onto COMP1 surface.

Corridor Number Three– No_SubCut ConditionPage three

Page 30: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Multiple Corridors:

Corridor Section Number Three

Corridor Number Three– No_SubCut ConditionPage four

Page 31: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Sample Line Groups: Three sample line groups and their corresponding data:

C1 – Existing Conditions C2 – SubCut Only C3 – NO SubCut

Page 32: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Sample Line Groups: Three sample line groups and their corresponding data:

C1 – Existing Conditions C2 – SubCut Only C3 – NO SubCut *** Note the three different types of icons: Surface, Corridor and Earthworks

Page 33: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Earthworks: Topsoil Removal:

Cut: 1-EG1 3-C1 – DATUM – STRIPPING TPS

Asphalt Removal: Cut:

1-EG1 2-C1 – DATUM – OLD PAVEMENT

Page 34: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Earthworks: SubCut Excavation:

Cut: 4-C1 – COMP1 – EG WITH PAV TPS DATUM – C2 SUBCUT BELOW 5-C2 – Btm SubBase – Daylight_SubCut – C2 SUBCUT ABOVE

Common Excavation: Cut:

7-C2 – COMP2 – COMP1 WITH C2 Btm SubCut – ETW – C3 FILL ABOVE – CUT ABOVE

8-C3 – FG Datum Above SubBase – C3 FILL BELOW CUT ABOVE

Fill: 8-C3 – FG Datum Above SubBase – C3 FILL BELOW CUT ABOVE 7-C2 – COMP2 – COMP1 WITH C2 Btm SubCut – ETW – C3 FILL ABOVE – CUT

ABOVE

Page 35: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Earthworks: Topsoil Placement:

Fill: (New corridor 3 surfaces created after full design) 10-C3 – DATUM FG TPS

Inner hide Boundary used is Daylight_sub Outer Boundary is the Daylight_Datum

11-C3 – COMP3 – COMP1 WITH 9-C3

Page 36: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

FINAL Earthworks: All quantities in one are now

included in one material list:

Page 37: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Things to remember! Any surface created in Civil 3D can

be sampled by a sample group and used for quantities, not just corridor surfaces!

There are times when only one Datum line will not be enough!

Corridors are just a tool for creating surfaces!

Multiple surfaces, multiple corridors and multiple sample line groups are your tools to get your job done!

If you really want to shine use conditional subassemblies where possible!

Page 38: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

The Paradigm Shift!

I was notified about this class last week in June

First week in July we had the SHIFT! Subassembly Composer Tool!

Page 39: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

The Paradigm Shift!

Everything in one assembly, in one corridor, in one sample line group!

Topsoil Stripping Asphalt Removal SubCut Removal Topsoil Placement ROW and Easement Labels Shapes for everything above!

Page 40: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Win a Civil 3D Book!!! (And a few other trinkets)

A Practical Guide to AutoCAD Civil 3D 2012 Donated by Rick Ellis

Cadapult Software Solutions Civil 3D and AutoCAD Map 3D books

available at www.cadapult-software.com

Page 41: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123Bill Neuhauser, P.E.Civil Engineer – Managed Design [email protected]

Page 42: © 2011 Autodesk Topsoil, Asphalt, SubCut—One Road with Overlapping Corridors as the Answer? CI3123 Bill Neuhauser, P.E. Civil Engineer – Managed Design

© 2011 Autodesk

Autodesk, AutoCAD* [*if/when mentioned in the pertinent material, followed by an alphabetical list of all other trademarks mentioned in the material] are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the USA and/or other countries. All other brand names, product names, or trademarks belong to their respective holders. Autodesk reserves the right to alter product and services offerings, and specifications and pricing at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. © 2011 Autodesk, Inc. All rights reserved.