zhjv w i si 0165 0 a1_abutment concrete placing plan

1
PROCEDURE CRANE ARRANGEMENT PLAN CONCRETE PLACING PLAN AT A1 A-A PROJECT DOCUMENT NUMBER: company phase SCALE : FILE NAME: zone document number DRAWING TITLE: A1_ ABUTMENT WORKING DRAWING ENGINEERING CONSULTANT: REV ESTABLISHED CHECKED APPROVED DATE DESCRIPTION STAT. GOVERNMENT OF UGANDA EMPLOYER: ORIENTAL CONSULTANTS CO., LTD. EIGHT-JAPAN ENGINEERING CONSULTANTS INC. UGANDA NATIONAL ROADS AUTHORITY PLOT 11, YUSUF LULE ROAD P O BOX 28487 KAMPALA - UGANDA Email: [email protected] PYUNGHWA ENGINEERING CONSULTANTS LTD ENGINEERING CONTRACTOR: ZENITAKA-HYUNDAI Joint Venture P.O.BOX 7158, Kampala, Uganda BUCKET CONCRETE DIRECTION PUMP CONCRETE DIRECTION 4 VIBRATORS 6 VIBRATORS 65 ton CRANE A A Flexible Hose Stationary Concrete Pump Concrete Bucket (2M3)x2 Total 3 workers Total 1 worker Total 2 workers for pump Old Tyre / Timber Hopper Formwork Checking Total 4 worker

Upload: asaale-gloria

Post on 03-Feb-2016

224 views

Category:

Documents


0 download

DESCRIPTION

ZHJV-W-I-SI-0165-0 A1_ABUTMENT CONCRETE PLACING PLAN.

TRANSCRIPT

Page 1: Zhjv w i Si 0165 0 a1_abutment Concrete Placing Plan

PROCEDURE

CRANE ARRANGEMENT PLAN

CONCRETE PLACING PLAN AT A1

A-A

PROJECT DOCUMENT NUMBER:

companyphase

SCALE :

FILE NAME:

zonedocument number

DRAWING TITLE:

A1_ ABUTMENT

WORKING DRAWING

ENGINEERING CONSULTANT:

REVESTABLISHED CHECKED

APPROVED

DATE DESCRIPTION

STAT.

GOVERNMENT OF UGANDA

EMPLOYER:

ORIENTAL CONSULTANTS CO., LTD.

EIGHT-JAPAN ENGINEERING CONSULTANTS INC.

UGANDA NATIONAL ROADS AUTHORITY

PLOT 11, YUSUF LULE ROAD

P O BOX 28487

KAMPALA - UGANDA

Email: [email protected]

PYUNGHWA ENGINEERING CONSULTANTS LTD

ENGINEERING CONTRACTOR:

ZENITAKA-HYUNDAI Joint Venture

P.O.BOX 7158, Kampala, Uganda

BUCKET CONCRETE DIRECTION

PUMP CONCRETE DIRECTION

4 VIBRATORS

6 VIBRATORS

65 ton CRANE

A

A

Flexible Hose

Stationary C

oncrete

P

um

p

Concrete Bucket (2M3)x2

Total 3 workers

Total 1 worker

Total 2 workers for pump

Old Tyre / Timber

Hopper

Formwork Checking

Total 4 worker