YVR Capital Plan
BC Construction Roundtable
November 24, 2011
John Lenahan, P.Eng.
Director, Engineering Projects
![Page 2: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/2.jpg)
YVR
• A private, not-for-profit Authority
• Ranked #1 airport in North America for
second year running – Skytrax
• #4 North America-Asia gateway
• 2010: 16.8M passengers
2
![Page 3: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/3.jpg)
YVR
• 228,000 tonnes cargo
• 294,000 aircraft movements
• 70 airlines & over 100 non-stop destinations
• Stable aeronautical fees
3
![Page 4: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/4.jpg)
YVR Passenger Traffic Trends
4
![Page 5: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/5.jpg)
Employees at Airport
5
![Page 6: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/6.jpg)
6
![Page 7: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/7.jpg)
Vancouver Airport: 1929
7
![Page 8: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/8.jpg)
Vancouver Airport: 1931
8
![Page 9: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/9.jpg)
9
![Page 10: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/10.jpg)
Designated Class “A” Airport: 1953
10
![Page 11: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/11.jpg)
Existing Domestic Terminal
11
![Page 12: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/12.jpg)
What we started with: 1992
12
![Page 13: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/13.jpg)
Where we are now
13
![Page 14: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/14.jpg)
Capital Expenditures 2010 – 2020
14
![Page 15: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/15.jpg)
15
Low visibility upgrades
$8M
Ground Run-up Enclosure
$11M
Major Projects 2011
![Page 16: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/16.jpg)
16
N. Service Road upgrade
$3.5M
Land development
$5.5M
Major Projects 2012 - Groundside
![Page 17: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/17.jpg)
17
Airside Operations Building
$5M
Major Projects 2012 - Airside
Infrastructure (pavement, drainage, dykes)
$19M
Runway End
Safety
Areas
$2M
![Page 18: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/18.jpg)
International to Domestic Transfers
18
![Page 19: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/19.jpg)
19
Transborder
International
Domestic
Link
Baggage system upgrade
$20M
Major Projects 2012 – Baggage System
![Page 20: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/20.jpg)
Baggage Video
20
![Page 21: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/21.jpg)
21
Transborder
International
Domestic
Link
Pier A/B upgrade
$60M
DTB Check-in reconfiguration
$13M
Major Projects 2012 - Terminal
![Page 22: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/22.jpg)
Pier A/B Upgrade
22
![Page 23: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/23.jpg)
Future Projects
• International Terminal expansion $250M
• North-south taxiway $200M
• Pier A/B Phase 2 $150M
• Second parkade $50M
• De-icing pads, equipment & operations
centre $60M
• Templeton interchange $40M
23
![Page 24: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/24.jpg)
24
![Page 25: YVR Capital Plan · •294,000 aircraft movements •70 airlines & over 100 non-stop destinations •Stable aeronautical fees 3 . YVR Passenger Traffic Trends 4 . Employees at Airport](https://reader035.vdocuments.us/reader035/viewer/2022062506/5f0312c77e708231d40766f4/html5/thumbnails/25.jpg)
Questions?