yets activities sps-na s. girod & s. evrard on behalf of the sba team, eatm, 16-12-2014
TRANSCRIPT
YETS ACTIVITIES SPS-NAS. Girod & S. Evrard on behalf of the SBA team, EATM, 16-12-2014
Organization
• Coordination meetings:• 2 preparatory meetings: 05/12, 12/12
• 4 follow-up meetings: 09/01, 16/01, 23/01, 30/01
• Indico: https://indico.cern.ch/category/6111/
Main activities: BA80S51:Painting works in TA801 by PresiozoS51,2:PR PA80 maintenanceS3,4,5:Flowmeters T2,T4,T6S3:PR 537 (TCC2) maintenanceS4,S5:H6/H8 alignment campaign (TCC2)S4:Target T2 T4 T6 upgrade (preparation)S5:Target T2 T4 T6 upgradeS5:Water leaks TDC2
• Réparation des fuites et/ou remplacement des vannes si réparations impossible S5 (B. Bannister)
S5:H6 collimator exchange
Main activities: EHN1S51:Light modification H2 zone 152.S51,2:PPE132 shieldingS51:XEMC.516 in PPE 124S51:Open Survey holes H6 et H8S51:H6/H8 alignment campaignS2:Light modification and cabinet relocation H2 zone 142.S2:MNP22 (Ship) to be movedS2&3:Underground gallery cleaningS3:Light modification H2 zone 132.S3:H2: zone 142/134 steel beam installation (with QNL500 removal/reinstallation)S6:Scan EHN1
Main activities: EHN2 and TT’sS51:Repair work of TT84 floor by contractorS2:MCWV+XABS:
ConsignationsService removalPlexiglas protection removalTransport to B. 867
S2,S3:H6/H8 alignment campaign (TT82)S4 S15: repair in B.867S16: reinstallation