y2k - 26 days
DESCRIPTION
Y2K - 26 days. ST status report. ST groups status. Remaining Tests and upgrades Access control: SPS exp. area access Cooling and Ventilation: No Y2K issues open Electricity distribution: LEP (starting this week) Telephone: Alcatel PABX in process Control System: ANS to be updated. - PowerPoint PPT PresentationTRANSCRIPT
04/19/23 ST/MO/PS 1
Y2K - 26 days
ST status report
04/19/23 ST/MO/PS 2
ST groups status
Remaining Tests and upgrades– Access control: SPS exp. area access– Cooling and Ventilation: No Y2K issues open– Electricity distribution: LEP (starting this
week)– Telephone: Alcatel PABX in process– Control System: ANS to be updated
04/19/23 ST/MO/PS 3
Y2K instructions
Prepared for– Fire and gas detection,– Pollution monitoring– Electricity HV distribution– Cooling and ventilation
PM32, pumping stations, others?
– Control system Front-ends, ECATCR, TDS
04/19/23 ST/MO/PS 4
Y2K staff
TCR Night: V. Camara, C. Mansilla Morning: J-P. Hernandez, E. Lienard Afternoon: U. Norup, A. Alvarez
Piquets ST/AA: SPIE Vives ST/CV: GEMATEC Drevard ST/EL: D.Denuzier, J-C. Gallois ST/MO: U. Epting SL/CO: A. Bland, G. Surback
04/19/23 ST/MO/PS 5
Checklist
TCR checklist being prepared– using Y2K instructions– defines the minimal test set to identify
problems