Tracking the Technical Critical Path: Systems
Engineering Meets Project Management
James R. Armstrong
Stevens Institute of Technology
Castle Point on Hudson
Hoboken, NJ 02070 Copyright © 2009 by James Armstrong. Published and used by APCOSE with permission.
Abstract. The critical path in the project schedule, the path with the least slack, has been a
mainstay of project management for many years. Along with earned value techniques, the project
manager uses this method to track schedule and cost progress. The term Technical Critical Path
appears sporadically as the sequence of activities needed to develop and incorporate critical
technologies that will make the program successful. However, the connection between these
concepts is not clearly defined. At the same time, much has been written about Technical
Performance Measures (TPMs) but it has been confined to the technical management side of
systems engineering. This paper will address how the two worlds of systems engineering and
project management should be integrated to combine the technical, cost, and schedule
performance. Also addressed are the correct implementation of TPMs and several problems
encountered in current usage.
Project Management Focus
The Iron Triangle. The three attributes of cost, schedule, and technical performance have long
been the basis of project management. However, the emphasis in project management has been on
methods to track cost and schedule. As shown in figure 1, the WBS, schedules, and earned value
are structured to address these management concerns.
Figure 1. The Iron Triangle with Management Emphasis
WBSxxxxxx xxxxxxxxxx
xxxxx xxxxxxxxxxxx
xxxxx xxxxxxxxxx
Xxxxx xxxxxxxxxxxx
xxxxx xxxxxxxxxxxxxx xxxxxxxx
xxxxx xxxxx
xxxxx xxxxxxxxxx
xxxxx xxxxxxxx
xxxxx xxxxxxxxxxxxxxxxxx xxxxxxxx
xxxxx xxxxxxxxxxx
xxxxx xxxxxxxxx
xxxxxx xxxxxxxx
xxxxx xxxxxxxxxxxxx xxxxxxxxx
?
Budget Baseline
Management Reserve
Time
$$
EV
Actuals
EAC
CVSV
PM BaselinePlan
JANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDEC
AWD PDR CDR TRR FCA
/PCA
EventSchedule
Milestones
HW Design
HW Fab
HW Test
SW Design
SW Test/Int
HW/SW Integ
System Test
Schedule Technical
Cost
In theory, the WBS tasks should have technical objectives. In practice, this is not often well
defined. In some cases, the specification requirements are referenced, but may not actually be
what is expected at the point in the program where an early design is analyzed or prototype tested.
The use of TPMs can provide a better linkage as will be described in the following paragraphs.
Critical Path
Basic. The path in a network schedule with the least (or most negative) schedule slack is the
critical path. This concept has long been used for managing the highest risk schedule events on a
project. A project may have more than one equally critical path or management may decide to
track more than just the most critical path. Tracking the three most critical paths addresses the risk
that a problem may appear on a path that is close to critical and overtake the original path without
warning. Figure 2 is from a project where the critical path analysis identified multiple parallel
critical paths leading to fixed events. After identification of this situation, action was taken to
address this significant project risk. In this instance, multiple paths had to be monitored
throughout the program.
Figure 2. Critical Path Analysis Example
Technical Critical Path
Limited References. The term was introduced to this paper by Dr. Yeo of the Nanyang
Technological University during discussions about TPMs, February 19, 2009. It can be found in
various references where it addresses the series of technology developments that are necessary for
a development to be successful. One example is a briefing on planning for advancement in solar
energy by the U.S. Department of Energy (2006), Figure 3.
My Integrated Schedule
Q2 1998 Q3 1998 Q4 1998 Q1 1999 Q2 1999 Q3 1999 Q4 1999 Q1 2000 Q2 2000 Q3 2000 Q4 2000 Q1 2001 Q2 2001 Q3 2001 Q4 2001 Q1 2002 Q2 2002 Q3 2002
Acquisition
Design & Produ ction
Test & Evaluatio n
Implemen tation
Human F actors
RRI/ASE Soft ware Delivery
AR INC VDLM2/ATN fo r ATS+ AC ARS
American Airlin es CPD LC Program
American 767 Program
Rockwell CMU/VDR D evelopment ( need ties to cert)
767 Fligh t Deck Integration Activities (need ties t o cert)
FAA Flig ht Stan dards Tasks [Street er, Do n]
FAA Cert ificatio n Tasks (Steve Van Trees, AIR)
Requirements
Development3 90 days
06/29/19910/30/1990 days
Prep./Review of SIR4 5 days
10/26/19910/30/1990 days
SIR Released5 0 days
10/30/19910/30/1990 days
Bid/Prop osal/AwardActivities 6 45 days
11/02/19901/01/1990 days
Contract Award7 0 days
01/15/19901/15/1990 days
Design U sabilit y Stud y4785 days01/04/19904/30/199
0 days
Controller HCI Results48 0 days04/30/19904/30/199
20.4 days
Build 1 H ost/DL AP S/WDevelopment
9 368 days05/05/19909/29/200311 days
FC A/PC A Complete ( HCSSW /ProATN DL AP)
11 0 days09/29/20009/29/200311 days
Internal F AA Ho stInteroperabilit y Testin g &
Debugging25 86 days
10/02/20001/29/200311 days
Host Soft ware Suitabil it y28 22 days
01/30/20002/28/200311 days
PTR fixes, RegressionTesting, f inal H ostSoft ware Uplevel
29 40 days03/01/20004/25/200311 days
Host A5f 1.2 Co de Cut off20 0 days
04/25/20004/25/200311 days
Host Integratio n/keysit e21 159 days
04/26/20012/04/200311 days
National Delivery A5f1.222 0 days
12/04/20012/04/200311 days
Procedures/Training Stud y49 87 days
07/01/19910/30/1991132 days
CMU/Flig ht DeckPreliminary Design (tie toRockwell/Boein g effor ts)
175360 days09/01/19901/17/200323 days
CMU CPDLC/C M APreliminary Design
122129 days01/01/19906/30/199204 days
Aircraft C onfig uration
Review13264 days
01/01/19903/31/1990 days
B767 Deliveries13367 days
02/01/19905/04/1990 days
TSA Complete1340 days
06/11/19906/11/199201 days
Cockpit Display Definition13513 days
06/14/19906/30/199204 days
Development of CockpitDisplay/W iring Updates
136450 days06/14/19903/02/200200 days
Design U sabilit y Stud y51 85 days
01/04/19904/30/1990 days
Pilot HCI Result s52 0 days
04/30/19904/30/199247 days
Architect ure/H MIDefinitio n Finalized
121 0 days06/30/19906/30/199
204 days
Flight Deck HCI Evaluation53 23 days
08/25/19909/24/199
335 days
An alizeR esults54 33 days
09/27/19911/10/199335 days
Commun it y Co nsensu s55 36 days
11/12/19912/31/199334 days
CMU CPDLC/C M ADevelopment
123325 days07/01/19909/27/200
204 days
High Level Certi ficatio nAp plication172 0 days
01/31/19901/31/1990 days
AGC App roval1621 day
04/15/19904/15/1990 days
Public Co mmen t
16345 days04/20/19906/21/199383 days
Commen t Disp osition16430 days
06/22/19908/02/199383 days
AC 20DC Final
165 0 days08/03/19908/03/199383 days
American develops
certification plan andcomplian ce data
173220 days08/03/19906/05/200383 days
AF M Sup plementsDeveloped17490 days
06/06/20010/09/200966 days
CMU/Flig ht Deck
Preliminary Design
Completed1760 days
01/17/20001/17/200323 days
CMU/Flig ht Deck Detai led
Design (tie to
Rockwell/Boein g effor ts)177160 days
01/18/20008/28/200323 days
CMU/Flig ht Deck Detai ledDesign C omplet e
1780 days08/28/20008/28/200323 days
Operatio nal EnvironmentDefinitio n (F AA-Hritz)
158214 days12/07/19909/30/199560 days
Operatio nal Saf et yAssessment (F AA-Hrit z)
159214 days12/07/19909/30/199560 days
Systems Requirement sand Procedures
160167 days05/03/19912/21/199502 days
AC O app roval ofcertification plan, design
data17980 days
08/29/20012/18/200323 days
VDL Mod e 2 Development117295 days
01/11/19902/25/200357 days
Contract Preparation13174 days
06/01/19901/28/200278 days
Contract Award forCPDLC B uild 1
14 0 days01/30/20001/30/200278 days
Pre-CTS Soft ware Delivery60 0 days
02/07/20002/07/200221 days
AT NSI R RI Delivered1180 days
02/07/20002/07/200221 days
AT NSI R RI Integ/Debu g119151 days
02/23/20009/20/200209 days
CPDLC and CM A ASE'sDelivery61 0 days
02/07/20002/07/200223 days
AC I ASE Delivered1240 days
02/07/20002/07/200223 days
Reqts An alysis t oIntegrate ATNSI RRI and
ASEs15 50 days
03/02/20005/10/200255 days
CMU ACI CPDL C/CM AASE Integ/Debu g
125149 days02/15/20009/08/200217 days
CMU/VD R FunctionalTesting12648 days
09/28/20012/04/200204 days
Avionics/Groun d Syst emTesting and Up dates
(Estimated)12760 days
12/05/20002/26/200204 days
R/L CMU Available1280 days
02/26/20002/26/200204 days
Pro ATN DL AP Accept edand Complete10 0 days
05/11/20005/11/200255 days
Design, Implement, TestAT NSI R RI, ASE
16180 days07/24/20003/30/200203 days
Conduct FinalConfiguration
Au dits/In corporateChanges1723 days
04/02/20005/02/200203 days
FC A/PC A Complete(ATNSI D L AP)18 0 days
05/02/20005/02/200203 days
System D elivered to T &E
Site240 days
05/02/20005/02/200203 days
Internal F AA FinalInteroperabilit y Testin g &
Debugging2640 days
05/14/20007/06/200196 days
FAA HMI Cockp it Survey97 4 days
11/09/19911/12/1990 days
Cockpit Integrat ion H MIprogram with T ech Center
98131 days04/01/19909/30/199
1239 days
Sim Hard wareConfiguration 1
99219 days04/01/19902/01/200
336 days
Sim Hard wareConfiguration F inal
10067 days03/01/20006/01/200316 days
Sim Data Link Provision101120 days
07/03/20012/15/200295 days
AT SS/Pilot/Syst emIntegratio n Plan ning
56382 days05/17/19910/31/200870 days
CPDLC IRD/ICD69130 days
05/28/19911/25/199833 days
Interface bet ween ARINC,FAATC
74 60 days08/09/19910/29/199852 days
Implemen t Test bed GSs
75 60 days08/09/19910/29/199852 days
Demo test/prep
76196 days11/26/19908/25/200
833 days
Support Demon stratio n77 170 days
08/28/20004/20/200833 days
Demonst rate
AT SS/Pilot/Syst emIntegratio n57 86 days
12/18/20004/16/200837 days
R/L VDL Mode 2 VDRAvailable1130 days
10/01/19910/01/199571 days
B/L VDL Mode 2 VDRAvailable
1140 days06/30/20006/30/200376 days
AVLC Testing w/RColl ins65100 days
06/30/20011/16/200944 days
Provision Aircraft for RedLabel avionics137140 days
08/01/20002/12/200214 days
VDL-2/C MU/Flig ht DeckIntegratio n13840 days
03/05/20004/27/200200 days
Cockpit integrat ionComplete1390 days
04/27/20004/27/200200 days
Quick Ch ange ECO's ( tieto out of service testin g)
140153 days07/03/20001/31/200890 days
Integrate ATN D isplaysand CMU in Sim10246 days
04/30/20007/02/200200 days
Review and Upd ateHuman F actors
Requirements andGuidance45 304 days
12/01/19901/28/2001153 days
Human F actors Testin gComplete580 days
04/16/20004/16/200837 days
Procedure Refin ement for
PET AL IIe109133 days
06/01/20012/04/200333 days
Installatio n Insp ection(tied to C MU/flight Deck
completion)18123 days
04/30/20005/30/200229 days
Maintenance & MELManuals Complete
107485 days10/26/19909/01/200422 days
Aircraft and Op eratingManuals Complete
106152 days06/01/20012/31/200337 days
Maintenance CrewTraining & Procedures for
PET AL IIe1080 days
12/31/20012/31/200337 days
AA Approved Training
Program104 451 days
01/08/19909/29/200402 days
AA PET AL II Maastrich tFirst Flig ht182 1 day
05/31/20005/31/200229 days
PET AL II
18360 days07/02/20009/21/200208 days
PET AL II Test R esultAn alysis
18410 days09/24/20010/05/200208 days
CMU Up dates and Release12915 wks
10/08/20001/18/20041.6 wks
Planned B/L CM U Availfor Cert
1300 days01/18/20001/18/200208 days
Ad dress PET AL II TestIssues an d Fix
18515 wks10/08/20001/18/20041.6 wks
Provision Aircraft for
Black Lab el CM US14170 days
01/21/20004/26/200208 days
767's Available f or Miami1420 days
04/26/20004/26/200208 days
AF M Sup plementsCompleted1865 days
01/21/20001/25/200632 days
FAA T yp e Desig nAp proval
187 1 day01/28/20001/28/200632 days
Ground Based ( ServiceProvider/F AA) NetMgt
Description/Req s70 87 days
05/28/19909/27/199489 days
Ops Perf & SuccessCriteria
71 175 days05/28/19901/27/200401 days
AR INC, F AATC G/Ginterop @ F AATC
81 40 days04/06/20005/31/20091 days
Begin Int egratio n Test ing(need Flight Deck inpu t,
sho ws sim option)30 0 days
07/06/20007/06/200196 days
Integratio n Test ing
31 55 days07/09/20009/21/200196 days
Acceptab ilit y Testing
32 44 days09/24/20011/22/200196 days
DL AP PT R Fixes &Regression Test ing
33 50 days11/23/20001/31/200196 days
OT&E Co mplete
34 0 days01/31/20001/31/200196 days
Install production Gro undStation f or testing
79 60 days09/08/20011/30/200657 days
A/G interop test ing wit hRockwell, American fo r
P2E80107 days
12/01/20004/30/200657 days
AR INC, F AATC A/Ginterop @ F AATC
82170 days07/06/20002/28/200609 days
OT&E Su pport83170 days
07/06/20002/28/20066 days
Site Prep, HostImplemen tation,
Installatio n & C heckou t,SAT Activities
36133 days08/01/20002/01/200195 days
Delivery t o Key Site37 10 days
02/04/20002/15/200195 days
Field Familiarization38 63 days
02/18/20005/15/200195 days
SAT Testing Co mplete39 0 days
05/15/20005/15/200195 days
VDL Mod e 2/AT NDevelopment64741 days
06/29/19904/30/200119 days
AT S M2/ATN IOC66 0 days
04/30/20004/30/200119 days
Install VD L Mod e 2/AT N inMiami/op s service syst em
86 120 days10/15/20003/29/2000 days
Pre-operations88 130 days
12/03/20005/31/2000 days
Post-operations89140 days
06/03/20012/13/200403 days
Procedure/Train ingDevelopment/R efinement
for Miami110578 days
03/17/19906/01/200443 days
AGC App roval14544 days
04/15/19906/15/199557 days
Public Co mmen t14623 days
06/16/19907/16/199557 days
AF S Team Approval14768 days
07/19/19910/20/199557 days
AC 120.com Fin al1480 days
11/01/19911/01/199550 days
American DevelopsValidatio n Test Plan
151220 days11/01/19909/01/200550 days
POI Checks Ops ApprovalTest Plan15265 days
09/04/20012/01/200550 days
Validatio n Test15323 days
06/05/20007/05/200419 days
American develops an dsubmits operational
approval plan spec150220 days
11/01/19909/01/200638 days
Operatio nal SpecificationSpec/Operation al
Ap proval Issued ( AFS POI)1540 days
11/01/20011/01/200335 days
Initial Op eratingCapabilit y (IOC)
40 0 days05/15/20005/15/200195 days
Prep. For OperationalRediness Demo nstration
(ORD)41 67 days
05/16/20008/16/200488 days
First OR D42 0 days
08/16/20008/16/200488 days
Flight Standard s DataCollectio n durin g live ops
155360 days06/04/20010/20/200182 days
Svc Level Agreementwit h F AA72 60 days
03/12/20006/01/200260 days
Service for Miami liveoperation s90543 days
06/03/20006/30/2000 days
Data Link Implementat ionReview
92156 days06/01/19901/04/1990 days
Retrofit Plan for AmericanFleet
95 43 days02/01/19903/31/199
1370 days
RTC A 172 VDL Mode 2
MOPS (Son Tran)167296 days
04/15/19906/01/200794 days
AIR-100 T SO
168270 days06/02/20006/14/200794 days
AIR-100 T SO process170143 days
04/15/19911/01/1991217 days
FAA- ARINC Co ntract forBld 1
67 0 days05/28/19905/28/1990 days
Critical Airports/EnRo uteIAGS Dep lo yed
85 0 days12/31/19912/31/1990 days
Host/
DLAP
RRI/AS
E
767
Host Cutoff
Miami
Petal II
Path at or near critical
Key Events
Fixed Events
My Integrated ScheduleQ2 1998 Q3 1998 Q4 1998 Q1 1999 Q2 1999 Q3 1999 Q4 1999 Q1 2000 Q2 2000 Q3 2000 Q4 2000 Q1 2001 Q2 2001 Q3 2001 Q4 2001 Q1 2002 Q2 2002 Q3 2002
Acquisition
Design & Produ ction
Test & Evaluatio n
Implemen tation
Human F actors
RRI/ASE Soft ware Delivery
AR INC VDLM2/ATN fo r ATS+ AC ARS
American Airlin es CPD LC Program
American 767 Program
Rockwell CMU/VDR D evelopment ( need ties to cert)
767 Fligh t Deck Integration Activities (need ties t o cert)
FAA Flig ht Stan dards Tasks [Street er, Do n]
FAA Cert ificatio n Tasks (Steve Van Trees, AIR)
Requirements
Development3 90 days
06/29/19910/30/1990 days
Prep./Review of SIR4 5 days
10/26/19910/30/1990 days
SIR Released5 0 days
10/30/19910/30/1990 days
Bid/Prop osal/AwardActivities 6 45 days
11/02/19901/01/1990 days
Contract Award7 0 days
01/15/19901/15/1990 days
Design U sabilit y Stud y4785 days01/04/19904/30/199
0 days
Controller HCI Results48 0 days04/30/19904/30/199
20.4 days
Build 1 H ost/DL AP S/WDevelopment
9 368 days05/05/19909/29/200311 days
FC A/PC A Complete ( HCSSW /ProATN DL AP)
11 0 days09/29/20009/29/200311 days
Internal F AA Ho stInteroperabilit y Testin g &
Debugging25 86 days
10/02/20001/29/200
Requirements
Development3 90 days
06/29/19910/30/1990 days
Prep./Review of SIR4 5 days
10/26/19910/30/1990 days
SIR Released5 0 days
10/30/19910/30/1990 days
Bid/Prop osal/AwardActivities 6 45 days
11/02/19901/01/1990 days
Contract Award7 0 days
01/15/19901/15/1990 days
Design U sabilit y Stud y4785 days01/04/19904/30/199
0 days
Controller HCI Results48 0 days04/30/19904/30/199
20.4 days
Build 1 H ost/DL AP S/WDevelopment
9 368 days05/05/19909/29/200311 days
FC A/PC A Complete ( HCSSW /ProATN DL AP)
11 0 days09/29/20009/29/200311 days
Internal F AA Ho stInteroperabilit y Testin g &
Debugging25 86 days
10/02/20001/29/200311 days
Host Soft ware Suitabil it y28 22 days
01/30/20002/28/200311 days
PTR fixes, RegressionTesting, f inal H ostSoft ware Uplevel
29 40 days03/01/20004/25/200311 days
Host A5f 1.2 Co de Cut off20 0 days
04/25/20004/25/200311 days
Host Integratio n/keysit e21 159 days
04/26/20012/04/200311 days
National Delivery A5f1.222 0 days
12/04/20012/04/200311 days
Procedures/Training Stud y49 87 days
07/01/19910/30/1991132 days
CMU/Flig ht DeckPreliminary Design (tie toRockwell/Boein g effor ts)
175360 days09/01/19901/17/200323 days
CMU CPDLC/C M APreliminary Design
122129 days01/01/19906/30/199204 days
Aircraft C onfig uration
Review13264 days
01/01/19903/31/1990 days
B767 Deliveries13367 days
02/01/19905/04/1990 days
TSA Complete1340 days
06/11/19906/11/199201 days
Cockpit Display Definition13513 days
06/14/19906/30/199204 days
Development of CockpitDisplay/W iring Updates
136450 days06/14/19903/02/200200 days
Design U sabilit y Stud y51 85 days
01/04/19904/30/1990 days
Pilot HCI Result s52 0 days
04/30/19904/30/199247 days
Architect ure/H MIDefinitio n Finalized
121 0 days06/30/19906/30/199
311 days
Host Soft ware Suitabil it y28 22 days
01/30/20002/28/200311 days
PTR fixes, RegressionTesting, f inal H ostSoft ware Uplevel
29 40 days03/01/20004/25/200311 days
Host A5f 1.2 Co de Cut off20 0 days
04/25/20004/25/200311 days
Host Integratio n/keysit e21 159 days
04/26/20012/04/200311 days
National Delivery A5f1.222 0 days
12/04/20012/04/200311 days
Procedures/Training Stud y49 87 days
07/01/19910/30/1991132 days
CMU/Flig ht DeckPreliminary Design (tie toRockwell/Boein g effor ts)
175360 days09/01/19901/17/200323 days
CMU CPDLC/C M APreliminary Design
122129 days01/01/19906/30/199204 days
Aircraft C onfig uration
Review13264 days
01/01/19903/31/1990 days
B767 Deliveries13367 days
02/01/19905/04/1990 days
TSA Complete1340 days
06/11/19906/11/199201 days
Cockpit Display Definition13513 days
06/14/19906/30/199204 days
Development of CockpitDisplay/W iring Updates
136450 days06/14/19903/02/200200 days
Design U sabilit y Stud y51 85 days
01/04/19904/30/1990 days
Pilot HCI Result s52 0 days
04/30/19904/30/199247 days
Architect ure/H MIDefinitio n Finalized
121 0 days06/30/19906/30/199
204 days
Flight Deck HCI Evaluation53 23 days
08/25/19909/24/199
335 days
An alizeR esults54 33 days
09/27/19911/10/199335 days
Commun it y Co nsensu s55 36 days
11/12/19912/31/199334 days
CMU CPDLC/C M ADevelopment
123325 days07/01/19909/27/200
204 days
High Level Certi ficatio nAp plication172 0 days
01/31/19901/31/1990 days
AGC App roval1621 day
04/15/19904/15/1990 days
Public Co mmen t
16345 days04/20/19906/21/199383 days
Commen t Disp osition16430 days
06/22/19908/02/199383 days
AC 20DC Final
165 0 days08/03/19908/03/199383 days
American develops
certification plan andcomplian ce data
173220 days08/03/19906/05/200383 days
AF M Sup plementsDeveloped17490 days
06/06/20010/09/200966 days
CMU/Flig ht Deck
Preliminary Design
Completed1760 days
01/17/20001/17/200323 days
CMU/Flig ht Deck Detai led
Design (tie to
Rockwell/Boein g effor ts)177160 days
01/18/20008/28/200323 days
CMU/Flig ht Deck Detai ledDesign C omplet e
1780 days08/28/20008/28/200323 days
Operatio nal EnvironmentDefinitio n (F AA-Hritz)
158214 days12/07/19909/30/199560 days
Operatio nal Saf et yAssessment (F AA-Hrit z)
159214 days
204 days
Flight Deck HCI Evaluation53 23 days
08/25/19909/24/199
335 days
An alizeR esults54 33 days
09/27/19911/10/199335 days
Commun it y Co nsensu s55 36 days
11/12/19912/31/199334 days
CMU CPDLC/C M ADevelopment
123325 days07/01/19909/27/200
204 days
High Level Certi ficatio nAp plication172 0 days
01/31/19901/31/1990 days
AGC App roval1621 day
04/15/19904/15/1990 days
Public Co mmen t
16345 days04/20/19906/21/199383 days
Commen t Disp osition16430 days
06/22/19908/02/199383 days
AC 20DC Final
165 0 days08/03/19908/03/199383 days
American develops
certification plan andcomplian ce data
173220 days08/03/19906/05/200383 days
AF M Sup plementsDeveloped17490 days
06/06/20010/09/200966 days
CMU/Flig ht Deck
Preliminary Design
Completed1760 days
01/17/20001/17/200323 days
CMU/Flig ht Deck Detai led
Design (tie to
Rockwell/Boein g effor ts)177160 days
01/18/20008/28/200323 days
CMU/Flig ht Deck Detai ledDesign C omplet e
1780 days08/28/20008/28/200323 days
Operatio nal EnvironmentDefinitio n (F AA-Hritz)
158214 days12/07/19909/30/199560 days
Operatio nal Saf et yAssessment (F AA-Hrit z)
159214 days12/07/19909/30/199560 days
Systems Requirement sand Procedures
160167 days05/03/19912/21/199502 days
AC O app roval ofcertification plan, design
data17980 days
08/29/20012/18/200323 days
VDL Mod e 2 Development117295 days
01/11/19902/25/200357 days
Contract Preparation13174 days
06/01/19901/28/200278 days
Contract Award forCPDLC B uild 1
14 0 days01/30/20001/30/200278 days
Pre-CTS Soft ware Delivery60 0 days
02/07/20002/07/200221 days
AT NSI R RI Delivered1180 days
02/07/20002/07/200221 days
AT NSI R RI Integ/Debu g119151 days
02/23/20009/20/200209 days
CPDLC and CM A ASE'sDelivery61 0 days
02/07/20002/07/200223 days
AC I ASE Delivered1240 days
02/07/20002/07/200223 days
Reqts An alysis t oIntegrate ATNSI RRI and
ASEs15 50 days
03/02/20005/10/200255 days
CMU ACI CPDL C/CM AASE Integ/Debu g
125149 days02/15/20009/08/200217 days
CMU/VD R FunctionalTesting12648 days
09/28/20012/04/200204 days
Avionics/Groun d Syst emTesting and Up dates
(Estimated)12760 days
12/05/20002/26/200204 days
R/L CMU Available1280 days
02/26/20002/26/200204 days
Pro ATN DL AP Accept edand Complete
12/07/19909/30/199560 days
Systems Requirement sand Procedures
160167 days05/03/19912/21/199502 days
AC O app roval ofcertification plan, design
data17980 days
08/29/20012/18/200323 days
VDL Mod e 2 Development117295 days
01/11/19902/25/200357 days
Contract Preparation13174 days
06/01/19901/28/200278 days
Contract Award forCPDLC B uild 1
14 0 days01/30/20001/30/200278 days
Pre-CTS Soft ware Delivery60 0 days
02/07/20002/07/200221 days
AT NSI R RI Delivered1180 days
02/07/20002/07/200221 days
AT NSI R RI Integ/Debu g119151 days
02/23/20009/20/200209 days
CPDLC and CM A ASE'sDelivery61 0 days
02/07/20002/07/200223 days
AC I ASE Delivered1240 days
02/07/20002/07/200223 days
Reqts An alysis t oIntegrate ATNSI RRI and
ASEs15 50 days
03/02/20005/10/200255 days
CMU ACI CPDL C/CM AASE Integ/Debu g
125149 days02/15/20009/08/200217 days
CMU/VD R FunctionalTesting12648 days
09/28/20012/04/200204 days
Avionics/Groun d Syst emTesting and Up dates
(Estimated)12760 days
12/05/20002/26/200204 days
R/L CMU Available1280 days
02/26/20002/26/200204 days
Pro ATN DL AP Accept edand Complete10 0 days
05/11/20005/11/200255 days
Design, Implement, TestAT NSI R RI, ASE
16180 days07/24/20003/30/200203 days
Conduct FinalConfiguration
Au dits/In corporateChanges1723 days
04/02/20005/02/200203 days
FC A/PC A Complete(ATNSI D L AP)18 0 days
05/02/20005/02/200203 days
System D elivered to T &E
Site240 days
05/02/20005/02/200203 days
Internal F AA FinalInteroperabilit y Testin g &
Debugging2640 days
05/14/20007/06/200196 days
FAA HMI Cockp it Survey97 4 days
11/09/19911/12/1990 days
Cockpit Integrat ion H MIprogram with T ech Center
98131 days04/01/19909/30/199
1239 days
Sim Hard wareConfiguration 1
99219 days04/01/19902/01/200
336 days
Sim Hard wareConfiguration F inal
10067 days03/01/20006/01/200316 days
Sim Data Link Provision101120 days
07/03/20012/15/200295 days
AT SS/Pilot/Syst emIntegratio n Plan ning
56382 days05/17/19910/31/200870 days
CPDLC IRD/ICD69130 days
05/28/19911/25/199833 days
Interface bet ween ARINC,FAATC
74 60 days08/09/19910/29/199852 days
Implemen t Test bed GSs
75 60 days08/09/19910/29/199852 days
Demo test/prep
76196 days11/26/19908/25/200
10 0 days05/11/20005/11/200255 days
Design, Implement, TestAT NSI R RI, ASE
16180 days07/24/20003/30/200203 days
Conduct FinalConfiguration
Au dits/In corporateChanges1723 days
04/02/20005/02/200203 days
FC A/PC A Complete(ATNSI D L AP)18 0 days
05/02/20005/02/200203 days
System D elivered to T &E
Site240 days
05/02/20005/02/200203 days
Internal F AA FinalInteroperabilit y Testin g &
Debugging2640 days
05/14/20007/06/200196 days
FAA HMI Cockp it Survey97 4 days
11/09/19911/12/1990 days
Cockpit Integrat ion H MIprogram with T ech Center
98131 days04/01/19909/30/199
1239 days
Sim Hard wareConfiguration 1
99219 days04/01/19902/01/200
336 days
Sim Hard wareConfiguration F inal
10067 days03/01/20006/01/200316 days
Sim Data Link Provision101120 days
07/03/20012/15/200295 days
AT SS/Pilot/Syst emIntegratio n Plan ning
56382 days05/17/19910/31/200870 days
CPDLC IRD/ICD69130 days
05/28/19911/25/199833 days
Interface bet ween ARINC,FAATC
74 60 days08/09/19910/29/199852 days
Implemen t Test bed GSs
75 60 days08/09/19910/29/199852 days
Demo test/prep
76196 days11/26/19908/25/200
833 days
Support Demon stratio n77 170 days
08/28/20004/20/200833 days
Demonst rate
AT SS/Pilot/Syst emIntegratio n57 86 days
12/18/20004/16/200837 days
R/L VDL Mode 2 VDRAvailable1130 days
10/01/19910/01/199571 days
B/L VDL Mode 2 VDRAvailable
1140 days06/30/20006/30/200376 days
AVLC Testing w/RColl ins65100 days
06/30/20011/16/200944 days
Provision Aircraft for RedLabel avionics137140 days
08/01/20002/12/200214 days
VDL-2/C MU/Flig ht DeckIntegratio n13840 days
03/05/20004/27/200200 days
Cockpit integrat ionComplete1390 days
04/27/20004/27/200200 days
Quick Ch ange ECO's ( tieto out of service testin g)
140153 days07/03/20001/31/200890 days
Integrate ATN D isplaysand CMU in Sim10246 days
04/30/20007/02/200200 days
Review and Upd ateHuman F actors
Requirements andGuidance45 304 days
12/01/19901/28/2001153 days
Human F actors Testin gComplete580 days
04/16/20004/16/200837 days
Procedure Refin ement for
PET AL IIe109133 days
06/01/20012/04/200333 days
Installatio n Insp ection(tied to C MU/flight Deck
completion)18123 days
04/30/20005/30/200229 days
Maintenance & MELManuals Complete
107485 days10/26/19909/01/200422 days
833 days
Support Demon stratio n77 170 days
08/28/20004/20/200833 days
Demonst rate
AT SS/Pilot/Syst emIntegratio n57 86 days
12/18/20004/16/200837 days
R/L VDL Mode 2 VDRAvailable1130 days
10/01/19910/01/199571 days
B/L VDL Mode 2 VDRAvailable
1140 days06/30/20006/30/200376 days
AVLC Testing w/RColl ins65100 days
06/30/20011/16/200944 days
Provision Aircraft for RedLabel avionics137140 days
08/01/20002/12/200214 days
VDL-2/C MU/Flig ht DeckIntegratio n13840 days
03/05/20004/27/200200 days
Cockpit integrat ionComplete1390 days
04/27/20004/27/200200 days
Quick Ch ange ECO's ( tieto out of service testin g)
140153 days07/03/20001/31/200890 days
Integrate ATN D isplaysand CMU in Sim10246 days
04/30/20007/02/200200 days
Review and Upd ateHuman F actors
Requirements andGuidance45 304 days
12/01/19901/28/2001153 days
Human F actors Testin gComplete580 days
04/16/20004/16/200837 days
Procedure Refin ement for
PET AL IIe109133 days
06/01/20012/04/200333 days
Installatio n Insp ection(tied to C MU/flight Deck
completion)18123 days
04/30/20005/30/200229 days
Maintenance & MELManuals Complete
107485 days10/26/19909/01/200422 days
Aircraft and Op eratingManuals Complete
106152 days06/01/20012/31/200337 days
Maintenance CrewTraining & Procedures for
PET AL IIe1080 days
12/31/20012/31/200337 days
AA Approved Training
Program104 451 days
01/08/19909/29/200402 days
AA PET AL II Maastrich tFirst Flig ht182 1 day
05/31/20005/31/200229 days
PET AL II
18360 days07/02/20009/21/200208 days
PET AL II Test R esultAn alysis
18410 days09/24/20010/05/200208 days
CMU Up dates and Release12915 wks
10/08/20001/18/20041.6 wks
Planned B/L CM U Availfor Cert
1300 days01/18/20001/18/200208 days
Ad dress PET AL II TestIssues an d Fix
18515 wks10/08/20001/18/20041.6 wks
Provision Aircraft for
Black Lab el CM US14170 days
01/21/20004/26/200208 days
767's Available f or Miami1420 days
04/26/20004/26/200208 days
AF M Sup plementsCompleted1865 days
01/21/20001/25/200632 days
FAA T yp e Desig nAp proval
187 1 day01/28/20001/28/200632 days
Ground Based ( ServiceProvider/F AA) NetMgt
Description/Req s70 87 days
05/28/19909/27/199489 days
Ops Perf & SuccessCriteria
71 175 days05/28/19901/27/200401 days
AR INC, F AATC G/Ginterop @ F AATC
81 40 days
Aircraft and Op eratingManuals Complete
106152 days06/01/20012/31/200337 days
Maintenance CrewTraining & Procedures for
PET AL IIe1080 days
12/31/20012/31/200337 days
AA Approved Training
Program104 451 days
01/08/19909/29/200402 days
AA PET AL II Maastrich tFirst Flig ht182 1 day
05/31/20005/31/200229 days
PET AL II
18360 days07/02/20009/21/200208 days
PET AL II Test R esultAn alysis
18410 days09/24/20010/05/200208 days
CMU Up dates and Release12915 wks
10/08/20001/18/20041.6 wks
Planned B/L CM U Availfor Cert
1300 days01/18/20001/18/200208 days
Ad dress PET AL II TestIssues an d Fix
18515 wks10/08/20001/18/20041.6 wks
Provision Aircraft for
Black Lab el CM US14170 days
01/21/20004/26/200208 days
767's Available f or Miami1420 days
04/26/20004/26/200208 days
AF M Sup plementsCompleted1865 days
01/21/20001/25/200632 days
FAA T yp e Desig nAp proval
187 1 day01/28/20001/28/200632 days
Ground Based ( ServiceProvider/F AA) NetMgt
Description/Req s70 87 days
05/28/19909/27/199489 days
Ops Perf & SuccessCriteria
71 175 days05/28/19901/27/200401 days
AR INC, F AATC G/Ginterop @ F AATC
81 40 days04/06/20005/31/20091 days
Begin Int egratio n Test ing(need Flight Deck inpu t,
sho ws sim option)30 0 days
07/06/20007/06/200196 days
Integratio n Test ing
31 55 days07/09/20009/21/200196 days
Acceptab ilit y Testing
32 44 days09/24/20011/22/200196 days
DL AP PT R Fixes &Regression Test ing
33 50 days11/23/20001/31/200196 days
OT&E Co mplete
34 0 days01/31/20001/31/200196 days
Install production Gro undStation f or testing
79 60 days09/08/20011/30/200657 days
A/G interop test ing wit hRockwell, American fo r
P2E80107 days
12/01/20004/30/200657 days
AR INC, F AATC A/Ginterop @ F AATC
82170 days07/06/20002/28/200609 days
OT&E Su pport83170 days
07/06/20002/28/20066 days
Site Prep, HostImplemen tation,
Installatio n & C heckou t,SAT Activities
36133 days08/01/20002/01/200195 days
Delivery t o Key Site37 10 days
02/04/20002/15/200195 days
Field Familiarization38 63 days
02/18/20005/15/200195 days
SAT Testing Co mplete39 0 days
05/15/20005/15/200195 days
VDL Mod e 2/AT NDevelopment64741 days
06/29/19904/30/200119 days
AT S M2/ATN IOC66 0 days
04/30/20004/30/200119 days
Install VD L Mod e 2/AT N inMiami/op s service syst em
86 120 days10/15/20003/29/2000 days
Pre-operations88 130 days
12/03/20005/31/2000 days
Post-operations89140 days
06/03/20012/13/200403 days
Procedure/Train ingDevelopment/R efinement
for Miami110578 days
03/17/19906/01/200443 days
AGC App roval14544 days
04/15/19906/15/199557 days
Public Co mmen t14623 days
06/16/19907/16/199557 days
AF S Team Approval14768 days
07/19/19910/20/199557 days
AC 120.com Fin al1480 days
11/01/19911/01/199550 days
American DevelopsValidatio n Test Plan
151220 days11/01/19909/01/200550 days
POI Checks Ops ApprovalTest Plan15265 days
09/04/20012/01/200550 days
Validatio n Test15323 days
06/05/20007/05/200419 days
American develops an dsubmits operational
approval plan spec150220 days
11/01/19909/01/200638 days
Operatio nal SpecificationSpec/Operation al
Ap proval Issued ( AFS POI)1540 days
11/01/20011/01/200335 days
Initial Op eratingCapabilit y (IOC)
40 0 days05/15/20005/15/200195 days
Prep. For OperationalRediness Demo nstration
(ORD)41 67 days
05/16/20008/16/200488 days
First OR D42 0 days
08/16/20008/16/200488 days
Flight Standard s DataCollectio n durin g live ops
155360 days06/04/20010/20/200182 days
Svc Level Agreementwit h F AA72 60 days
03/12/20006/01/200260 days
Service for Miami liveoperation s90543 days
06/03/20006/30/2000 days
Data Link Implementat ionReview
92156 days06/01/19901/04/1990 days
Retrofit Plan for AmericanFleet
95 43 days02/01/19903/31/199
1370 days
RTC A 172 VDL Mode 2
MOPS (Son Tran)167296 days
04/15/19906/01/200794 days
AIR-100 T SO
168270 days06/02/20006/14/200794 days
AIR-100 T SO process170143 days
04/15/19911/01/1991217 days
FAA- ARINC Co ntract forBld 1
67 0 days05/28/19905/28/1990 days
Critical Airports/EnRo uteIAGS Dep lo yed
85 0 days12/31/19912/31/1990 days
Host/
DLAP
RRI/AS
E
767
Host Cutoff
Miami
Petal II
Path at or near critical
Key Events
Fixed Events
Figure 3. Technical Critical Path Reference
The term can also be found in a Defence Acquisition University briefing on Systems Engineering
Plans. Measuring this overall technology development would appear to be on the scale of
Technology Readiness Levels.
Technology Readiness Levels. NASA identified a nine-level scale to address the maturity of
technologies for application to programs. As can be seen in figure 4 (Mankins, 1995), the levels
can be broadly interpreted. The differences between levels are primarily driven by factors other
than specified performance. For instance, a demonstration can be of a component or a subsystem.
It can be performed in a laboratory environment or the appropriate space or ground environment.
This is appropriate for addressing general progress in a longer term program over several phases.
However, there is an opportunity to tie the levels of technical progress in a specific program to a
more detailed definition of the progress.
Figure 4. Technology Readiness Levels
Actual system “flight proven” through successful
mission operations
Actual system completed and “flight qualified”
through test and demonstration (Ground or Flight)
System prototype demonstration in a space
Environment
System/subsystem model or prototype demonstration
in a relevant environment (Ground or Space)
Component and/or breadboard validation in relevant
Environment
Component and/or breadboard validation in
laboratory environment
Analytical and experimental critical function and/or
characteristic proof-of-concept
Technology concept and/or application formulated
Basic principles observed and reported
Technical Performance Measures
Need for technical input. The primary emphasis of management systems is on cost and schedule.
The Earned Value Measurement System (EVMS) is intended to connect the tracking of dollars
with the actual progress being made. While the descriptions of tasks in a Work Breakdown
Structure (WBS) call for a definition of technical objectives, specific guidance on how to establish
these objectives is not readily available. This leaves the integration of the EV management
techniques and the technical effort to the reader. In practice, the WBS tasks often refer to the
accomplishment of a task or completion of a product without a qualitative description of what the
task or product is intended to achieve. As a result, the EVMS and technical progress tracking are
generally addressed in a disconnected fashion. Properly constructed and implemented TPMs can
provide the technical progress information to address the technical critical path and help the
integration of the technical and management disciplines. However, several common mistakes in
TPM use must be avoided to allow this integration to take effect.
Why more on TPMs. Descriptions of TPMs and
how to use them abound. For instance, the
INCOSE Systems Engineering Handbook
(INCOSE, 2006) has a good description of what
they are and an example, figure 5. They have been
used in programs effectively for decades.
Therefore, it was with surprise that they were
observed in systems engineering training classes as
the one concept that was most frequently
problematic in exercises. Later, as students used
their internal process assets in class to develop
TPMs it was discovered that the processes did not
address the key features of TPMs in their directions
or templates. In another instance, the same was
found to be the case in an appraisal.
What to measure. The first concern is to determine the parameters that should be measured. All
measurement decisions of this kind should begin with determining the question to be answered by
the data. In the case of TPMs, the status of the progress on the most critical design parameters is
what the data should reveal. The determination of which parameters are the most critical is
accomplished through a combination of requirements decomposition and risk management.
Requirements decomposition. There are many terms for the highest level of requirements for a
system. Measure of Effectiveness (MOE) will be used here but other terms with similar meanings
include Key Performance Parameter, Most Important Requirement, and Key System Attributes.
For instance, you might be concerned about cost of ownership for a vehicle. Gas mileage is one
contributor. However, if that is achieved through a very complex control system that is expensive
to build and maintain, the total cost, the MOE, may not be achieved. However, if the mileage is
determined to be the critical component of the MOE and at risk, it would be a very likely
candidate. Further, we would look for a detail parameter in engine design that is both the design
challenge and a driving factor in achieving the desired performance. This trace of MOE to TPM is
shown in figure 6 as described in a PSM and INCOSE report (PSM/INCOSE 2005).
Figure 5. SE Handbook TPM Example
Figure 6. Relationship between MOEs and TPMs
Risk. Of course, the parameter in question
should also show up on the list of technical
risks as one of the higher risks in combined
impact and likelihood of occurring, as shown in
figure 7. TPM tracking then becomes one of
the mitigations as a monitoring technique. It
also provides the trigger for future decisions to
add or cancel specific mitigation activities.
Should the progress not be satisfactory,
additional mitigations may be triggered or
decisions for alternate designs made. Should
progress exceed plans, efforts on back-up
designs might be canceled.
Plan for changes. The next step is to define the
projected change in the monitored parameter
over the life of the development, figure 8. As
we have been discussing it, this would likely be an improvement to meet the desired value.
However, there may be a positive margin at the start of design, e.g., the product looks to be well
under a weight limit, and we want to make sure that the margin does not disappear in the first few
weeks of serious design. In figure 5, that case is represented by the term “limit” rather than
“target” for a performance objective we are trying to achieve. In the case where the product starts
out overweight, the initial prediction would be above the target and the prediction curve would
show the plan for reduction.
Measures of
Effectiveness
(MOEs)
Measures of
Performance
(MOPs)
Technical
Performance
Measures
(TPMs)
Key
Performance
Parameters
(KPPs)Mission
Needs or
Operating
Issues Increasing
Scope of
Technical Solution
Increasing
Technical Resolution
& Periodic Insight
Technical
Insight
(Progress
& Risk)
Technical Measures are Interdependent
Figure 3. Relationship of TPMs and MOEs
5
43
21
Risk #1: Related to selected TPM
Pro
bab
ility
Severity
Figure 7. TPMs and Risk
Figure 8. Prediction of Change
The shape used in this example is a simple exponential form where more rapid progress is
expected early in the development with progress becoming more difficult as the program proceeds.
This is a notional example. Planned progress for a specific program may look considerably
different. For instance, figure 5 shows a TPM where a design margin is monitored and the plan is
to minimize degradation early and expect some larger changes later in the program. Some
examples to avoid are presented later in this paper.
Adding ties to events. The next step is one that is most commonly omitted. This is essential to the
integration or separation of the technical and management processes. In this step, progress on the
plan curve is explicitly tied to specific events in the WBS and schedule, particularly the events on
the Technical Critical Path, as shown in figure 9. One description of tasks says to “identify
physical products, milestones, technical performance goals, or other indicators that will be used to
measure progress.” (NASA) In practice, this means referring an early design tasks or prototype
effort to the final target specification. The results are misleading if the expectation is that the final
number will not be met at that time or that a positive margin will be mostly retained. It is more
realistic to make the technical performance goal for that early event to the predictions in the TPM
plan. If the top highlighted task in the WBS in figure 5 is a prototype development to address the
technical risk relating to the TPM parameter, the technical goal for that task should be the same as
the value on the TPM plan curve at that time in the program. In this case, it appears to be about
half way between the initial estimate and the final target.
Figure 9. Integration of TPM and WBS
Target or Limit
Initial
estimate
Time
Reserve margin
not shown
How will we
close (or
maintain)
this gap?
Expected
change
Target or Limit
Initial
estimate
Predicted
ProgressProject Schedule
Estimate
results at each task
completion
and map to
graph
WBSxxxxxx xxxxxxxxxx
xxxxx xxxxxxxxxxxx
xxxxx xxxxxxxxxx
Xxxxx xxxxxxxxxxxx
xxxxx xxxxxxxxxxxxxx xxxxxxxx
xxxxx xxxxx
xxxxx xxxxxxxxxx
xxxxx xxxxxxxx
xxxxx xxxxxxxxxxxxxxxxxx xxxxxxxx
xxxxx xxxxxxxxxxx
xxxxx xxxxxxxxx
xxxxxx xxxxxxxx
xxxxx xxxxxxxxxxxxx xxxxxxxxx
Measurement method. In conjunction with tying to the WBS, the measurement method for each
critical point in the schedule, figure 10. The method should be integrated into the WBS. It may be
planned that the estimate of weight at the completion of initial design drawings will be by analysis
rather than actual measurement of a prototype. If so, that point needs to be clearly defined at the
outset, not debated at the completion of the design task.
Figure 10. Identifying Measurement Methods
Additional integrations. In some cases, particularly later in the development, the TPM plan
should be tied to the Test and Evaluation Master Plan and other verification plans. A mismatch
between the pass/fail criteria and expected progress at the time of test will certainly be
problematic. Another relationship to maintain is with the entrance and exit criteria for design
reviews. If the plan was to show 90% performance on a challenging parameter at CDR as
demonstrated by a prototype, that is what should be expected at the review. The customer, internal
or external, should not be complaining that it isn’t 95%. Likewise, if the results are only supported
by analysis because the prototype is not completed, the designer should expect a strong response.
In either case, neither side should be caught off guard and have to argue adequacy of method or
results at this point since the plan was agreed to at the start.
Thresholds. There are several approaches to Thresholds. Figure 11 depicts an upper and lower
bound. This is the range in which results are acceptable without further action. If performance
deviates beyond these limits, management action is to be taken. If the performance deviates in the
negative direction, additional resources may be applied or additional mitigation actions may be
triggered. As long as the performance is within the bounds, internal and external customers and
management should not consider it a problem. In another approach, double boundaries are applied
with green, yellow, and red bands around the target. In this method, green is not a problem, yellow
is handled within the program, and red is addressed by higher management outside the program.
Target or Limit
Initialestimate
Defined updates
• Analysis
• Prototype
• Test
• Etc.
Time
Should connect
to TEMP, other
verification
plans, and
design reviews
Figure 11. Addition of Thresholds
Some organizations do not use a “good” side limit and some use the plan as the boundary. Figure
5 is an example of this approach. While the argument is made that there is no value in
investigating good news, there are two reasons why this can be appropriate. One is to verify that
the good news is real. The other is to evaluate the possibility of reallocating resources to more
needy areas. While the good side is not as critical as a negative threshold breach, it is worth more
that casual attention.
Tracking Progress. Of course, the efforts so far are without value if the actual results are not
tracked as the program progresses, figure 12, and corrective action taken as necessary. The
tracking frequency is established in the original plan along with the collection and analysis
methods. Relationships to other risk mitigations are maintained in the risk plans.
Figure 12. Tracking Actuals
Target or Limit
Variance
Thresholds
Time
Target or Limit
Time
ActualPlan
Start
Perf
orm
an
ce
Delivery
Integration
When the complete process is followed, TPMs and risk management combine to add the technical
planning and progress to the overall management process as shown in Figure 13 and real meaning
to tracking the Technical Critical Path.
Figure 13. TPMs integrating SE and PM
EVMS impacts. There are some complications in using this integrated approach. When a task is
completed but the performance is not within the planned value limits, the earned value should not
be taken. As with any incomplete task, the impact on downstream tasks must be specifically
addressed. The complication comes in the case of a prototype, for instance, where the course of
action is not to continue to redo the prototype. Even though the original task, building and testing
the prototype, will end, care must be taken to properly handle whatever the additional work results
from the failure and not just take full earned value and move on.
An easier to accept but still less than straightforward situation exists if the activity exceeds the
limits on the positive side. The concern here is to assess reductions in future tasks that may be
available.
The most complex situation would be where several requirements are in play and some go to the
good side while others go to the bad. In this case, a decision based on overall risk exposure from
the combined factors is a more reasonable way to address the question. A net risk reduction goal
could be identified as the objective rather than individual parameter changes.
TPM Uses
The initial value of TPMs is to proactively forecast the technical progress to be achieved instead
of only reactively responding to technical events. TPMs identify differences between actual
versus planned performance to provide informed management. This enables the technical and
program management to assess and predict progress towards achieving the performance values,
determine the impact of these differences on system effectiveness, and react effectively. TPMs
provide early indicator of risks and problems requiring management attention.
54
3
21 Target
Pro
pe
lle
nt
Time
WBSxxxxxx xxxxxxxxxx
xxxxx xxxxxxxxxxxx
xxxxx xxxxxxxxxx
Xxxxx xxxxxxxxxxxx
xxxxx xxxxxxxxxxxxxx xxxxxxxx
xxxxx xxxxx
xxxxx xxxxxxxxxx
xxxxx xxxxxxxx
xxxxx xxxxxxxxxxxxxxxxxx xxxxxxxx
xxxxx xxxxxxxxxxx
xxxxx xxxxxxxxx
xxxxxx xxxxxxxx
xxxxx xxxxxxxxxxxxx xxxxxxxxx
Budget Baseline
Management Reserve
Time
$$
EV
Actuals
EAC
CVSV
PM BaselinePlan
JANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDEC
AWD PDR CDR TRR FCA
/PCA
EventSchedule
Milestones
HW Design
HW Fab
HW Test
SW Design
SW Test/Int
HW/SW Integ
System Test
Schedule Technical
Cost
Figure 14 shows the use of TPMs in several modes. On the left, the TPMs are monitoring
performance gaps as they are closed. On the right, the TPMs monitor positive margins to assure
that they do not disappear too rapidly. In the center is an alternative that may not be used often, if
ever, but should be considered. If a key parameter is initially on target, but has a history of varying
making it a risk, it would be a candidate to monitor.
Figure 14. TPM Use Examples
In addition to the tracking progress, TPMs also allow the manager to determine where
opportunities exist to make design trades to reduce overall risks. One example of this was
described by Hamman and Mackertich (INCOSE 2007) where the understanding of positive
technical margins enabled a trade of technical performance to reduce cost with significant savings.
TPMs can also be used to monitor performance improvement after delivery as shown in figure 15.
However, this is an additional use and not the main focus of predicting technical progress during
development.
Figure 15. TPM Use After Delivery
Target
Pro
ba
bility o
f
Dete
ctio
nTime
Limit
Ba
nd
wid
th
Use
Time
Target or
Limit MT
BF
Time
Limit
Th
rou
gh
pu
t
Time
Target
Pro
ce
ssin
g
Tim
e
Time
Maintain
Level
Manage Improvement Manage Margin
Extended Target
Re
lia
bility (M
TB
F)
Time
Delivery
Initial Target
Things to Avoid
Driving through the rear view mirror. Some programs and organizational processes have fallen
into the trap of defining TPMs as reporting past results only as in figure 16. In addition to the
obvious issue that the future expectations are not defined, the current state has no target to define
its acceptability. In this case, there is no decision point to determine when corrective action is
needed.
Figure 16. Looking in the Rear View Mirror
Straight line predictions. This mistake, figure 17, is not acceptable in any progress prediction
with extremely rare exceptions. The last few improvements are almost always a bit slower.
However, the practice continues to occur.
Figure 17. Straight Line Prediction
The miracle. One guide that had some good guidance on TPMs seems, unfortunately, to have
fallen victim to the elimination of military standards. While the text was valuable, a different kind
of lesson can be gleaned from the example at the end of the guide, figure 18. In this example,
Target
We
igh
t
Program Schedule Time
Today
Target
We
igh
t
Program Schedule Time
progress on throughput time in information processing software was to be tracked. The time per
message needed to be reduced to meet the requirements. Modest progress was predicted through
the development process. Some degradation was predicted at system test. However, the miracle
predicted was the sudden improvement when the system is to be fielded and live data added. In
reality, it should be expected that things get worse when real world is encountered. One possible
explanation is that the chart meant track throughput and to reflect a positive margin with realistic
expectations of the margin disappearing when fielded.
Figure 18. Predicting a Miracle
Only used after delivery. The use of TPMs after delivery is an acceptable as described above.
However, one error that has occurred frequently in classroom exercises is to believe that TPMs
only start at delivery, figure 19. The key is to predict and track performance throughout
development.
Figure 19. TPMs after delivery
- USAF TPM Guide Example
Target
Pro
ce
ssin
g T
ime
Unit test
System test
Live data test
Program Schedule Time
Extended Target
Re
lia
bility (M
TB
F)
Time
Delivery
Initial Target
Now
Summary
The concept of a Technical Critical Path is evident in some form on most projects that depend on
technological advances. In order to make it work, there needs to be a measurement approach that
will yield actionable information with enough granularity to allow for management response.
Technical Performance Measures are a basic part of technical management that can be applied to
provide a that level of measurement to the Technical Critical path. While the concept of TPMs is
quite simple, the execution has been sporadic in many programs and organizations. Following a
few simple guidelines can produce effective measurement of technical progress and aid the
management processes such as earned value measurement. If done correctly, the TPMs can be a
missing link between the technical and management sides of a development project, provide
tracking of the Technical Critical Path, and increase the likelihood of project success.
References
INCOSE 2006, Systems Engineering Handbook - A Guide for System Life Cycle Processes and
Activities, Version 3, Edited by Cecilia Haskins.
Hamman and Mackertich, Get Smart – Enabling Enterprise Systems Intelligence and Decision
Making Through Critical Parameter Management, INCOSE, 2007
Mankins, J. C. 1995. Technology Readiness Levels. White paper, NASA Office of Space Access
and Technology. http://www.hq.nasa.gov/office/codeq/trl/trl.pdf.
Office of the Deputy Under Secretary of Defense for Acquisition and Technology, Systems and
Software Engineering, Enterprise Development. Systems Engineering Plan Preparation Guide,
Version 2.01. Washington, DC: ODUSD(A&T)SSE/ED, 2008.
Roedler and Jones, Technical Measurement, PSM/INCOSE 2005
Solar America Initiative: Technology Pathway Partnerships (TPP’s), US Department of Energy
presentation for April 18-19, 2006 meeting in Chicago
Systems Engineering Principles, Defense Acquisition University presentation, 22 May, 2008
BIOGRAPHY
Jim Armstrong has practiced systems engineering for 40 years, performing various roles including
configuration management, test, deployment, chief engineer, program manager, and program
element monitor. For the last 20 years, he taught, consulted, and appraised systems engineering in
industry and government. Also, he was on the author teams for most of the systems engineering
standards and models.