WWTP Upgrade and Expansion Project Potential Temporary Staging Areas
Park and Recreation CommissionNovember 1, 2017
AgendaAgenda
2
Clean Water Program OverviewWastewater Treatment Plant (WWTP) Project OverviewProposed Temporary Staging Areas—Background—Proposed Temporary Uses—Post Construction Restoration Considerations
Anticipated Staging Area Use ScheduleObtain Feedback
Wastewater Treatment Plant (WWTP) Project Overview
4
LEGENDNew Facility
Existing Facility to be Replaced/Rehabbed
CONCEPTUAL RENDERINGS
CONCEPTUAL LAYOUT
Proposed Temporary Staging AreasProposed Temporary Staging Areas
5
Area 1: Dale Ave Undeveloped Open Space
Area 2: Anchor RdPassive Open Space
Area 3: Portion of Anchor Rd Parking Lot
E. 3rd Ave
Seal Slough
SF Bay
Detroit D
r
Existing WWTP
Future WWTP Site(Detroit Dr Parcel)
Joinville Park
Shoreview Ave
Area 1: Dale Ave Undeveloped Open SpaceArea 1: Dale Ave Undeveloped Open Space
6
1
2
Dale AveExisting WWTP
Meadow View Pl
3
Future WWTP Site(Detroit Dr Parcel)
Area 1: Dale Ave Undeveloped Open SpaceProposed Temporary Uses
Area 1: Dale Ave Undeveloped Open SpaceProposed Temporary Uses
7
Temporary Uses:—Construction trailers/offices—Construction management parking (~50 parking spots)
Preparation for Use:—Grade site to level (sufficient for trailers)—Install safety/security lights & screening/fencing—Close pedestrian/bike path—Provide alternative ped/bike route(s)
Access to/from Staging Area:—From East: Through existing WWTP—From West: Access gate from Dale Ave and
Shoreview Ave for emergency purposes only
Conceptual Alternative Ped/Bike Routes
LEGENDExisting RoutesPotential Alternative Routes*
Shoreview Ave
*Other potential routes to be analyzed as design progresses
Area 1: Dale Ave Undeveloped Open SpacePost Construction Restoration ConsiderationsArea 1: Dale Ave Undeveloped Open Space
Post Construction Restoration Considerations
8
Minimum Restoration Identified:—Restore site to former condition—Remove lighting and screening/fencing—Re‐open pedestrian/bike path
Potential Restoration Considerations discussed between P&R & PW Staff:—Future master planning —Weed control—Lighting improvements—Pedestrian/bike path improvements—Coordinate any improvements with “Area 2: Anchor Rd Passive Space” improvements
Future WWTP Site(Detroit Dr Parcel)
Area 2: Anchor Road Passive Open SpaceArea 2: Anchor Road Passive Open Space
9
`
4
E. 3rd Ave
Seal Slough
SF Bay
Existing WWTP
`
Future WWTP Site(Detroit Dr Parcel)
Area 2: Anchor Road Passive Open SpaceProposed Temporary Uses
Area 2: Anchor Road Passive Open SpaceProposed Temporary Uses
10
Temporary Uses:—Construction worker parking (~100 parking spots)—Equipment laydown
Preparation for Use:—Lightly grade site—Place decomposed granite (DG) surface—Install safety/security screening/fencing (around equipment only)
—Maintain & accommodate ped/bike path & boat ramp uses
Access to/from Staging Area:—From East: From 3rd Ave to Anchor Rd—Potentially From West: Path from Detroit Dr, along the front of dog park, and across bridge over Seal Slough
Decomposed Granite Parking Example
Chain Link Fence w/ Mesh Screen
w/ Slats
Area 2: Anchor Road Passive Open SpacePost Construction Restoration ConsiderationsArea 2: Anchor Road Passive Open Space
Post Construction Restoration Considerations
11
Minimum Restoration Identified:—Remove DG surfacing—Restore grade—Replace top soil
Potential Restoration Considerations discussed between P&R & PW Staff:—Pedestrian/bike path improvements—Lighting improvements—Community Garden—Coordinate any improvements with “Area 1: Dale Ave Undeveloped Open Space” future improvements
Area 3: Portion of Anchor Road Parking LotArea 3: Portion of Anchor Road Parking Lot
12
Further coordination for lot portioning required to maintain some public parking & access during staging area usage
65
SF Bay
Bay Trail
Parking Lot
Area 3: Portion of Anchor Road Parking LotProposed Temporary Uses
Area 3: Portion of Anchor Road Parking LotProposed Temporary Uses
13
Temporary Uses:—Worker parking —Equipment laydown
Preparation for Use:—No modification required—Accommodate vehicle parking and access—If additional parking is needed:
• Lightly grade non‐paved areas• Clear & grub non‐paved areas• Tree trimming & potential removal• Place DG surface
Access to/from Staging Area:—3rd Ave & Anchor Rd intersection
Parking Lot
3rd Ave
Area 3: Portion of Anchor Road Parking LotPost Construction Restoration ConsiderationsArea 3: Portion of Anchor Road Parking LotPost Construction Restoration Considerations
14
Minimum Restoration Identified:—Fix excessive wear or damage by patching, seal‐coating, and/or striping
—If additional parking is needed: remove DG surfacing, restore grade, re‐landscape
Potential Restoration Considerations discussed between P&R & PW Staff:—Lighting improvements—Landscape improvements—Potential relocation of Recology sourced compost piling
Current Recology Compost Piling Location
Future WWTP Site(Detroit Dr Parcel)
Temporary Staging Area Use ScheduleTemporary Staging Area Use Schedule
15
Area Start Use* End Use*
1: Dale Ave Undeveloped Open Space Summer/Fall 2018 Nov 2023
2: Anchor Rd Passive Open Space Summer/Fall 2018 Nov 2023
3: Anchor Road Parking Lot Summer/Fall 2018 Aug 2023
* Dates are based on current schedule and are subject to change
Questions & FeedbackQuestions & Feedback
16
Area 1: Dale Ave Undeveloped Open Space
Area 2: Anchor RdPassive Open Space