wright s olar park llc project - merced county, california

31
NOT IMP WR P REP Cou Plan 222 Mer Con P REP ICF 630 Sacr Oct TICE OF P PACT REP RIGHT S ARED FOR unty of Merc nning and C 22 M Street rced, CA 953 ntact: James ARED BY : Internation 0 K Street ramento, CA ober 2013 PREPARA PORT SOLAR P : ced ommunity D 340 Holland, Pl nal A 95814 A TION OF P ARK, L Developme anner III F A DRAF LLC PRO nt Departm FT ENVIR OJECT ment RONMENT T AL

Upload: others

Post on 11-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

NOTIMP

WR

P R E PCouPlan222MerCon P R E PICF 630Sacr

Oct

TICE OF PPACT REP

RIGHT S

A R E D F O Runty of Mercnning and C22 M Street rced, CA 953ntact: James A R E D B Y : Internation0 K Street ramento, CAober 2013

PREPARAPORT

SOLAR P

: ced ommunity D340 Holland, Pl

nal A 95814

ATION OF

PARK, L

Developmeanner III

F A DRAF

LLC PRO

nt Departm

FT ENVIR

OJECT

ment

RONMENTTAL

Page 2: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

ICF International. 2013. Notice of Preparation of a Draft Environmental Impact Report, Wright Solar Park, LLC Project. October. (ICF) Sacramento, CA. Prepared for County of Merced, Merced, CA.

Page 3: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project i October 2013

ICF

Contents

List of Tables and Figures ....................................................................................................................... ii List of Acronyms and Abbreviations ...................................................................................................... iii

Page

Introduction .................................................................................................................................... 1 Purpose and Organization of the NOP ................................................................................................... 1 Scope of the EIR ...................................................................................................................................... 1

Project Description .............................................................................................................................. 2 Background Information ........................................................................................................................ 2

Project Title ...................................................................................................................................... 2 Lead Agency Name and Address ...................................................................................................... 2 Lead Agency Contact Person and Phone Number ........................................................................... 2 Project Location ............................................................................................................................... 2 Project Sponsor’s Name and Address .............................................................................................. 2 General Plan Designation ................................................................................................................. 3 Zoning .............................................................................................................................................. 3

Description of the Project ...................................................................................................................... 6 Project Overview .............................................................................................................................. 6 Project Objectives ............................................................................................................................ 9 Proposed On-Site Facilities and Project Operation ......................................................................... 9 Operational Facilities ..................................................................................................................... 16 Wildlife Protection Corridors and Fencing Design ......................................................................... 18 Operation and Maintenance .......................................................................................................... 18 Project Construction ...................................................................................................................... 19

Decommissioning and Site Reclamation Plan ...................................................................................... 23 Removal of Equipment .................................................................................................................. 23 Site Reclamation ............................................................................................................................ 24

Other Permits and Approvals that may be Required ........................................................................... 24 Construction Schedule ......................................................................................................................... 25

Phased Schedule and Workforce Requirements ........................................................................... 25

Page 4: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project ii October 2013

ICF

Tables and Figures

Table Page 1 Associated Parcels and Parcel Size .................................................................................................. 7 2 Temporary and Permanent Project Component Acreage ............................................................... 7 Figure Page 1 Project Vicinity Map ......................................................................................................................... 4 2 Project Site Map ............................................................................................................................... 5 3 Project Facilities ............................................................................................................................... 8 4 Typical Single-Axis Tracking System ............................................................................................... 11 5 Power Gate Plus 1 Megawatt Solar PV Inverter ............................................................................ 13 6 Typical Control Room ..................................................................................................................... 15 7 Access and Haul Route Modifications ............................................................................................ 20

Page 5: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project iii October 2013

ICF

Acronyms and Abbreviations

AC alternating current applicant Wright Solar Park, LLC BESS Battery Energy Storage System BMPs Best Management Practices CCR California Code of Regulations CDFW California Department of Fish and Wildlife CEQA California Environmental Quality Act CUP Conditional Use Permit DC direct current EIR environmental impact report GHG greenhouse gas kV kilovolts LGIA Large Generator Interconnection Agreement MVA Megavolt ampere MVCS Medium Voltage Collection System MVOH Medium Voltage Overhead MVTs medium voltage transformers MW megawatt NEPA National Environmental Policy Act NERC North American Energy Reliability Corporation NOP notice of preparation NOX oxides of nitrogen O&M Operations and Maintenance PCS power conditioning station PG&E Pacific Gas and Electric Company PM10 particulate matter less than or equal to 10 microns in diameter POI Point of Interconnection PRC Public Resources Code Project Wright Solar Park, LLC Project PV photovoltaic RPS Renewables Portfolio Standard SCADA Supervisory Control and Data Acquisition SJVAPCD San Joaquin Valley Air Pollution Control District SR State Route SUTs Step Up Transformers SWPPP Storm Water Pollution Prevention Plan USACE United States Army Corps of Engineers USFWS United States Fish and Wildlife Service USGS U.S. Geological Survey WECC Western Electricity Coordinating Council

Page 6: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 1 October 2013

ICF

Introduction

Purpose and Organization of the NOP Merced County will prepare an environmental impact report (EIR) that addresses the potential impacts of the proposed Wright Solar Park, LLC Project (project). This notice of preparation (NOP) has been prepared pursuant to the California Environmental Quality Act (CEQA) (14 California Code of Regulations [CCR]) and State CEQA Guidelines Sections 15082(a), 15103, and 15375 to inform agencies and the public that the EIR is being prepared and to invite comments and input on the scope and content of the EIR. This NOP presents general background information on the scoping process, the environmental issues to be addressed in the EIR, and the anticipated uses of the EIR. It also describes the proposed project as currently envisioned. The County, as the lead agency under CEQA, must evaluate the environmental impacts of the project prior to considering whether to approve the project. If the lead agency finds substantial evidence that any aspect of the project, either individually or cumulatively, may have a significant impact on the environment—regardless of whether the overall effect of the project is adverse or beneficial—the lead agency is required to prepare an EIR. In reviewing the preliminary information provided for the proposed project, the County has analyzed the potential environmental impacts of the proposed project in this NOP and has determined that preparation of an EIR is required. Scope of the EIR The EIR will contain analysis of both the short- and long-term impacts of the proposed project. The full range of environmental issues will be addressed in the EIR, including:

aesthetics and visual resources, air quality and greenhouse gas emissions, cultural resources, geology and soils; mineral resources, hazards and hazardous materials, hydrology and water quality, land use/planning, noise, population and housing, public services, utilities and recreation, and transportation/traffic. The issues to be addressed will be finalized after comments on the NOP are received.

Page 7: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 2 October 2013

ICF

Project Description

Background Information Project Title Wright Solar Park, LLC Project (project) Lead Agency Name and Address Merced County Community and Economic Development Department 2222 “M” Street Merced, California 95340 Lead Agency Contact Person and Phone Number James Holland, Planner III (209) 385-7654, Ext. 4407 Project Location The project would be located in western Merced County near Santa Nella, California (Figure 1), southwest of the intersection of Interstate 5 and State Route 33/152, west of the California Aqueduct, on the south side of Billy Wright Road (Figure 2). The San Luis Reservoir is located 5 miles to the northwest, and the Los Banos Creek Reservoir is approximately 1 mile from the project’s southernmost boundary. The project area falls within portions of two 7.5-minute U.S. Geological Survey (USGS) topographic quadrangle maps: Volta and Ortigalita Peak NW. The project area comprises all or portions of Township 10 South, Range 9 East, Sections 34 and 35, and Township 11 South, Range 9 East, Sections 1, 2, 3, 11, and 12, Mount Diablo Base and Meridian. Project Sponsor’s Name and Address Wright Solar Park, LLC 1777 Borel Place, Suite #102 San Mateo, California 94402 Contact: Tom Fitzgerald Phone: (650) 539-3380 Mobile: (415) 562-7675 [email protected]

Page 8: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 3 October 2013

ICF

General Plan Designation The project site is designated as Foothill Pasture in the 1990 Merced County General Plan and the Draft 2030 Merced County General Plan. Zoning The Merced County zoning designation for the project area is Exclusive Agriculture (A-2).

Page 9: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California
Page 10: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California
Page 11: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 6 October 2013

ICF

Description of the Project Project Overview Wright Solar Park, LLC (applicant) proposes to develop, own, and operate a 200-megawatt (MW) alternating current (AC) ground-mounted solar photovoltaic (PV) power plant located on leased and purchased agricultural lands in unincorporated Merced County, California. The applicant has filed a Conditional Use Permit (CUP) application with Merced County (CUP Application No. CUP12-017) for the Project to allow for the construction, operation, and maintenance of such facilities for the long-term generation of clean renewable energy from solar power. In addition, the project includes cancellation of the Williamson Act contracts covering portions of the project site. Project Location The project facilities would be located approximately 4.5 miles southeast of the community of Santa Nella, California (Figures 1 and 2). The project area is approximately 2 miles south of the intersection of State Route (SR) 33/152 and Interstate 5, and can be accessed via Billy Wright Road off of SR-33/152. The project site is located approximately 3.5 miles southwest of the city of Los Banos and approximately 26 miles southwest of the city of Merced (the county seat). Site Acreage The project would be developed using portions of multiple parcels of land listed in Table 1. Temporary and permanent disturbance acreages are described in Table 2. As indicated in Table 2, the proposed project would permanently develop 1,392 acres out of 2,732.49 parcel acres, or approximately 50.9 percent of the total parcel acreage (Figure 3). Temporary disturbance outside of the 1,392 acres of permanent disturbance totals to 190.33 acres, to include temporary office staging and laydown of components (Table 1). Total disturbance during construction would be approximately 1,600 acres (1,582.33 exact from Table 1), including both temporary and permanent disturbance.

Page 12: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 7 October 2013

ICF

Table 1. Associated Parcels and Parcel Size

Assessor’s Parcel Number (APN) Parcel Size1 (acres, approximate) 078-200-026 - Betty J. Freeman 194.29 078-200-027 - James O’Banion 118.8 078-200-028 - Victor Zabala 40.0 078-200-030 - McInerney Trust 160.0 078-200-081 - Arotzarena Farms 158.9 078-200-082 - Arotzarena Farms 240.3 078-200-083 - Arotzarena Farms 239.3 088-020-002 - Arotzarena Farms 480.0 088-020-003 - Arotzarena Farms 160.0 088-020-038 - Harold and Marilyn Bogard 160.2 088-020-040 - David Gould 423.7 088-020-041 - David Gould 160.0 088-200-027 - Fai Fh197, LLC 197.0 Total 2,732.49 1 The project would require a land footprint of approximately 1,600 contiguous acres to site the power plant; however, the Conditional Use Permit (CUP) application area encompasses approximately 2,732.49 acres. The parcels or portions not within the final project site boundaries would not be utilized by the project in any manner during the duration of its lifecycle.

Table 2. Temporary and Permanent Project Component Acreage

Item Quantity (acres)

Temporary ground disturbance staging outside final fence 179.64

Temporary office staging 10.69

Permanent disturbance (all lands inside final fence) plus common facilities 1,392.00

Total Site Disturbance 1,582.33

Page 13: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California
Page 14: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 9 October 2013

ICF

Project Objectives The goal of the project is to provide renewable solar energy to be sold to a load serving entity through a power contract, generating electrical power from a clean source that would supplement the energy capacity of the existing power grid, thereby increasing the stability and operability of the transmission system, as well as offsetting supplies from fossil fuel generating sources. The project sponsor is proposing to construct the project to meet the following objectives, thus supporting the following statewide and local objectives:

Support the efforts of Merced County and the State of California to reduce greenhouse gas (GHG) emissions consistent with the timeline established by California Assembly Bill 32, the Global Warming Solutions Act of 2006; Assist the State of California in complying with Executive Order S-21-09 and California utilities in meeting their obligations under California’s Renewables Portfolio Standard (RPS) Program to be fully online by 2016 to help fulfill federal, state, and county renewable energy mandates; Support the energy goals stated in the Merced County General Plan, as well as other policies in the plan designed to protect Merced County’s environment and economy; Provide an investment in California and Merced County that would create jobs and other economic benefits; Develop an economically feasible and commercially financeable project; Maximize the use of existing transmission infrastructure while minimizing the network upgrade costs borne by the California Ratepayer. Minimize the cost on the generator interconnection tie-line by limiting the distance to the point of interconnection to less than 0.25 miles. Ensure that the project can be technologically constructed in a manner that allows electricity to be provided at a competitive price; Locate the facility on land of low agricultural value that is classified as non-prime farmland and has poor soil quality and a limited history of productive agricultural activities; and Develop the facility in a semi-secluded area that is situated outside of established or approved future residential development.

Proposed On-Site Facilities and Project Operation Wright Solar Park, LLC (applicant) proposes to develop, own, and operate a 200-megawatt (MW) alternating current (AC) ground-mounted solar photovoltaic (PV) power plant located on leased and purchased agricultural lands in unincorporated Merced County, California. Project components would include access roads, solar modules, tracker components, direct current (DC) to AC power inverters, medium voltage transformers, a medium voltage collection system, a project substation, and an interconnection switching station as illustrated on Figure 3. In addition, the applicant proposes to construct a battery energy storage system as part of the project to aid in shaping and controlling the timing of energy production for the electrical grid. The applicant has filed a Conditional Use Permit (CUP) application with Merced County (CUP Application No. CUP12-017) for

Page 15: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 10 October 2013

ICF

the project to allow for the construction, operation, and maintenance of such facilities for the long-term generation of clean renewable energy from solar power. The energy generated by the project could be sold to public utilities, municipal utilities, or large private consumers of power. The power generated by the project would be interconnected to existing Pacific Gas and Electric Company (PG&E) power grid infrastructure for delivery to the purchaser of the power. The proposed project would have an operational lifespan of approximately 30-35 years. Mechanical Components within the Solar Field To support the PV panels, the project would utilize a fixed-tilt mounting system or a single-axis tracking system designed to optimize power production of the panels by ensuring proper orientation to the sun throughout the day and seasons. Figure 4 shows a typical installation of a single-axis tracking system. The fixed-tilt mounting and single-axis tracking systems are supported by metal piers driven into the ground by a pile driving machine. These machines are similar to those found on highway construction jobs driving guard rail piers. Pier placement begins with a precise surveyed layout, ensuring proper positioning of remaining tracker assembly parts. Affixed to the top of each pier is a pier cap and bearing assembly that supports and allows proper movement of the torque tube assembly. The toque tube assembly serves two purposes: to provide an attachment point for the panels, and to move through the range of positions needed to optimize panel production. Single-axis tracking systems require a drive system that provides directional force to the torque tube. This can be accomplished with either a mechanical or hydraulic drive arm and tube assembly that “pushes and pulls” the torque arm through its range of motion or by a geared assembly that redirects rotational force to the tubes. Both approaches require a small geared motor or hydraulic system mounted on a pile support or pad strong enough to move the system through its daily range of motions. The panels may be constructed of glass encasing: crystalline silicon, poly crystalline silicon, or amorphous silicon with small quantities of Copper–Indium–Gallium–Selenide, Cadmium–Telluride, or other metal and non-metal materials interposed within the silicon matrix. A plastic binding material and frame provides structural rigidity. The panels would be dark blue or black in color with minimal light reflection. The PV panels would be self-contained durably constructed units designed to withstand exposure to the elements for period of 30 years or greater. The solar modules deployed for use in the project would be certified to comply with all industry standard quality testing. Panels would be electrically connected to the grounding system of the plant in accordance with local and state codes and regulations. The final panel selection would be determined at the detailed project-engineering phase.

Page 16: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of MeDevelopment

Notice of PreWright Solar

Tracka drivThe nas beidesignAs pathrouThis idormchangproduweathMultipwhereeventpanelTrackmaintwouldprelimfeet aassemfeet.1 provioutpu 1 Per the Mcan be exaccess oCaliforni

erced, Planning ant Department

paration of a DrafPark, LLC Project

ker design varvetrain systemnumber of rowing limited byn is also detert of the trackughout the days accomplishant, as the moges in the sunuction periodher event, theple tracker sye the DC prodtual delivery t output relatiker layout is atenance and ed accommodaminary designnd 8.5 feet, anmbly. This desAnother mecde support anut to the PCS. Merced Countyxtended in somn both ends shia Department

nd Community

ft EIR,

Figurries by manufm usually locaws within a try the drive syrmined by thker system, a y and keep thhed by either ootor does notn’s position. Ts, such as thee system wouystems are deduced by the pto the electricive to invertealso constrainemergency peate maintenann specifies thand row lengthsign would acchanical featund containme y Fire Marshal,me situations. Hhould not exceet of Forestry an

re 4 Typicafacturer, but ated in the ceracker block iystem’s abilityhe amount of tcontroller is he panels’ orieoperating thet turn continuhe controllere nightly stowuld move the teployed withipanels is convcal grid. The ner size and dened by the neeersonnel. Thence personneat the distanch would be nccommodate fure of the projent of the DC Merced CountHowever, deaded 300 feet in lnd Fire Protect

11

al Single-Axisgenerally connter of the syis a measure oy to move muthe desired soneeded to prentation as pe motor drivinuously. The cor also is used tw period and ftracker to thein proximity tverted to AC number of trasired output ed to access te project’s trael traveling ince between roo longer that fire equipmenject’s trackerwires used toty Fire Departmd-end rows sholength. Design ion and the Me

s Tracking Sysnsists of a serystem, dividinof desired ouultiple torque olar output torovide the inferpendicularng the systemontroller accoto position thfor maintenane safest positito the power for movemenackers connecfrom the PCSthe interior roackers would n trucks or othows of the tra150 feet on ent access andr system incluo collect the oment hoses areould not exceedof the rows is erced County F

stem ries of trackerng the trackerutput from thetube assembo the inverterformation to tr to the sun’s rm or making tounts for dailhe tracker dunce. In the evion to avoid dconditioningnt to the projected to the PCS. ows of the trabe separatedher maintenaackers would each side of thd a typical hosudes a cable troutput of the e generally 150d 200 feet in lesubject to furthFire Departmen

Project Des

Octob

r panel rows wr into two side tracker as wblies. This rowrs. track the systrays as possibthe motor ly and seasonring off-vent of a seriodamage. g station (PCSect substationCS varies withackers by d by distancesance vehicles.be between 6he drive arm se length of 1ray that woulpanels and m0 feet in lengthength, and rowher review by nt.

scription

ber 2013ICF

with des. well w tem ble. nal ous

S) n and h s that . The 6.5 150 ld move h, but ws with the

Page 17: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 12 October 2013

ICF

Electrical Components in the Solar Field

Direct Current Collection System Direct current electricity is collected from the panels through a DC collection system and sent to the PCS. Panels attached to the tracking system are first grouped into a series circuit. Each tracker consists of a number of circuits determined by optimized individual panel output for total tracker performance. Circuits are collected in parallel through tracker electrical harnesses that travel through the cable trays to combiner boxes. Depending on the manufacturer, there may be a fuse in the linkages of the harness creating the first point of overcurrent protection in the system. The number of combiner boxes varies with final tracker design and can be sized to accommodate electrical design. Combiner boxes combine multiple parallel harnesses through a fused bus system to collect the energy into one set of DC collection cables. The fuses within the combiner boxes create another line of protection from overcurrent. The cables run from the combiner boxes to the PCS skids. While elevated and exposed in the project’s tracker cable tray, the shielded cables would be directly buried where the cables leave the tracker for collection to the PCS. The project’s tracker would supply the positive and negative DC cables from each of its combiner boxes to the PCS, thereby resulting in multiple cables which are a product of the number of combiner boxes in the tracker. These cables would terminate in the DC side of the PCS inverter. Power Conditioning Station (PCS) and Inverters A PCS consists of inverters, a medium voltage transformer, and the auxiliary power system for the trackers. These components are often mounted on a metal platform, referred to as a skid, with or without an enclosure. Each PCS is collecting DC power from the tracker combiner boxes. From the tracker to the PCS, the DC cables would be directly buried to a depth of between 42 inches and 48 inches. At the PCS, the DC power cables originating from the trackers are terminated on the DC side of the power inverter. The inverter converts the DC power from the panels into three-phase AC power for movement across the project site to the high voltage project substation. The inverters consist of a DC side and an AC side, and more than one inverter may reside on the PCS skid (Figure 5). The combined quantity of inverters creates the AC rating for the PCS. The project AC rating for the PCS skids may be 1 to 2.5 MW. This rating, optimized for the site, determines how many PCS skids would be present on site. The project conceptual layout assumes134 PCS skids.

Page 18: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of MeDevelopment

Notice of PreWright Solar

The Pthe trsystemfrom Once the pohave omoveeach oanothMedThe pcablesjunctiparallthat 1lengththe syAlternOverhprojecunderincorpAll cirwouldpowe

erced, Planning ant Department

paration of a DrafPark, LLC Project

PCS skids provracking systemms and can bthe solar panpower has beower (varyingone MVT thatment along thof the three pher level of prium Voltagpower that exs are buried 4ion boxes. Thlel until the q13 to 15 MW oh of the directystem. natively, the phead (MVOH)ct substationrground line cporating potercuits of the Md then be collr side of the e

nd Community

ft EIR,

Figure 5 vide another m. This source fed to the synels. een convertedg the voltage)t would step uhe medium vphases transforotection fromge Collectioits the MVT fr42 inches to 4e MVCS travequantities reaof power woutly buried cabproject would) transmission. A final optimcomponents, ential shadingMVCS would blected into thelectrical bus

Power Gatepoint of powe of auxiliaryystem even wd to AC, it can) through meup the voltagoltage collectormed for them overcurren

on System rom the PCS s48 inches deeels between thched are optiuld be carriedble and what d route appron line (and asmized design or some comg issues from be routed acre substation ts system of th

13

e Plus 1 Megaer routing bay power is critwhen solar irrn be effectiveldium voltagege of the electtion system. Ee Medium Volt. skid travels inep and may behe MVTs founimized for a gd by one circuamount of lin

oximately 1.5 ssociated polewould determmbination of bpole sets andross the projethrough a sere substation.

awatt Solar Pack to the contical to the prradiance is inly moved longe transformertrical power tEach MVT woltage Collectin three-phasee spliced abovnd on each PCgiven MVCS ciuit; however, ne loss wouldmiles of the Mes) within themine whetherboth would bed conductors.ect site to the ries of circuit

PV Inverter ntrol boxes anrimary operatadequate to gger distancesrs (MVTs). Eato 34.5 kilovoould have a fuon System (Me directly burve ground in CS skid, addinircuit. This prthis is highlyd be considereMVCS as a Mee project bour overhead line used in the . project substbreakers and

Project Des

Octob

nd motors thation of the tragenerate pows by transformach PCS skid wlts (kV) for use system forMVCS), offerinried cables. Tclearly markng power in roject assumey dependent oed acceptableedium Voltagndaries to thne componenMVCS tation. The Md into the low

scription

ber 2013ICF

at run acker wer ming would r ng hese ked es on the e for

ge e nts, MVCS w

Page 19: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 14 October 2013

ICF

Electrical Components in the High Voltage Systems

Project Substation The project substation is the portion of the system where project power is transformed to match the specification of the interconnection into the electrical grid. The project substation is characterized as having a low side and a high side, as defined by the point of power transformation from 34.5 kV (low side) stepped up in voltage to match the grid specifications in the transmission system (high side). In the case of the project, the power would be stepped up to 230 kV at the project substation. The footprint of the substation would be approximately 2.1 acres in size. The low side of the substation is composed of the MVCS terminations into a low side bus. This power is fed through automated circuit breakers that can be controlled remotely from a control room or can automatically open the circuit if a phase fault is detected anywhere in the portion of the solar field routed through that circuit breaker. The low side bus is tied directly to the Step Up Transformers (SUTs) where the power goes through the voltage transformation. The project would utilize two or three SUTs in order to provide redundancy and protection in the system, should a failure occur at one of the SUTs. Within the low side and high side of the substation bus work, there are several points where air switches would be installed for the project. By manually operating these switches and locking them out for safety, portions of the substation could be electrically isolated. Substation design related to breakers and switches would comply with all relevant interconnection codes and requirements. Additionally, the project substation would include a control room with an environmental enclosure housing the relay switches and the electrical control gear (Figure 6). The control room would be the base of operations for the entire solar facility, not just the substation, and provides for external communication. The project’s control room would be powered by lower voltage power produced by the project through an installed step down transformer. Project Transmission Line The project includes an electrical transmission line (“gen-tie line”) to connect the project to generation facilities owned and operated by PG&E. The gen-tie line would be composed of a span of three conductors between the project substation dead end structures and the adjacent switching station dead end structures. The line would be less than 500 feet in length, and sizing of the conductor would be relative to the exact length of the span necessary for the project and the avoidance of calculated line losses. The dead end structures on both sides of the facilities would also carry a fiber communications system between the control rooms of the facilities.

Page 20: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of MeDevelopment

Notice of PreWright Solar

SwitcA prothe Loand reprovitransmisolatThe swthe prAt thethe LaperimThereIntercof a loCalifodelive(MVAPoweThe sis toomornfailurbreak

erced, Planning ant Department

paration of a DrafPark, LLC Project

ching Statioject switchinos Banos-Panelated equipmde a point of mission line. te circuits of twitching statroject fence lie conclusion oarge Generatometer of the swe are three 23connection (Poop into the Lornia Indepener the projectA) normal ander Back Feeolar generati low for enering and evenes. Back feed kers and trans

nd Community

ft EIR,

(

on and Poing station wounoche 230-kVment, as requisolation for tAfter the swithe Los Banostion facility wine and wouldof constructioor Interconnewitching stati30-kV transmPOI) would beLos Banos-Panndent System t’s full outputd at 388-MVAed Requiremon facility wogy productionings), mainteis accomplishsformers wor

Figure 6(Photo Courtes

nt of Interculd be locatedV line. The swiuired by the inthe solar genitching stations-Panoche 23would have itsd be directly on, the switchection Agreemion. mission lines the directly on tnoche #1 230Operator (CA. The currentA emergency cments ould require pn from the soenance periodhed directly trk in the oppo

15

Typical Consy of Intermou

connectiond within appritching stationterconnectioeration facilitn is built and 0-kV line. own perimetaccessible byhing station wment (LGIA). hat run directthe property 0-kV line. TheAISO) intercot line capacitycapacity, withpower to opeolar panels. Thds, and occasithrough the hosite direction

ntrol Room untain Electric

roximately 20n would incluon provider. Tty and for thetested, PG&Eter fencing thy the facility owould be ownPG&E would tly through that the switche line has no konnection quey is estimatedh a 46-MVA lo

erate during phis would occional plant ouhigh voltage sn, allowing th

)

00 to 500 feetude breakers,The switchinge two circuitsE would have hat would be operator durined and operacontrol all ache property. Thing station anknown compeeue and has ed at 328-Megaoad on the lin

periods whencur at night (iutages relatedsystem from the appropriat

Project Des

Octob

t of tower #92, switches, meg station wous of the the ability toindependent ng constructiated by PG&Eccess to insideThe Point of nd would conetitors in the enough capaciavolt ampere ne currently.

n solar irradiaincludes earlyd to low side the POI. All te power leve

scription

ber 2013ICF

2 of eters, uld o t from ion. E, per e the nsist ity to

ance y els to

Page 21: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 16 October 2013

ICF

be fed into the system. Back feed power is controlled at the inverters so that solar field components are not damaged beyond the PCS skid. Communications and Metering

Supervisory Control and Data Acquisition A Supervisory Control and Data Acquisition (SCADA) system would be installed to provide plant visibility and control of the solar field and all components of the electrical system to the plant and grid operators. Physically, the system would be installed with a series of fiber communication lines running within the same trenches of the MVCS to each of the PCS skids. This fiber system would connect points (item to be monitored) of the electrical system to the control room of the substation, where it would be terminated at servers of the operating system. Fiber is also run from all the high voltage components that require monitoring, such as the breakers within the substation. This SCADA system is used to remotely operate breakers within the substation, and is integral to the safe operation of the substation. Energy Storage As part of the project, a Battery Energy Storage System (BESS) would be constructed within the solar facility to provide dispatchable energy under various operating conditions. The ability to store energy would improve the project’s operability and enhance the integration of as-available solar-generated energy resources into the transmission network by offering additional ramp rate control and more consistent energy flows. The BESS would be constructed as a single building facility, the footprint of which would be up to 4 acres. The primary storage components would consist of self-contained electro-chemical battery systems using conventional storage technologies with proven safety and performance records such as Lithium Ion, Nickel Cadmium, Zinc Chlorine Redox Flow, or advanced lead acid batteries.

Operational Facilities

Operation and Maintenance Facility The proposed project includes an Operations and Maintenance (O&M) facility that would consist of a pre-engineered 35-foot by 100-foot metal building that would rest on a 10-inch concrete slab. Electricity The O&M facility would receive electrical power from a utility meter though a 120-volt, 100-ampere single-phase panel. Additionally, future maintenance may necessitate the use of equipment that requires three-phase power. Three-phase power would be attained through manipulation of on-site energy from the proposed MCVS or through an agreement with the utility provider. Septic The O&M facility would need a potable water supply to provide minor anticipated needs of the staff. Within the O&M facility would be restroom facilities. Standard break room plumbing would also be needed. An engineered and approved septic system would be installed, and would be gravity fed

Page 22: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 17 October 2013

ICF

from the facilities’ plumbing. Septic system permits would be obtained and strictly adhered to in the installation. Water For operations, an on-site groundwater well would be drilled during construction, and would be primarily utilized for the O&M building’s water system, for panel washing, and for maintenance. Water would be supplied from the well to up to a 50,000-gallon water tank, or several smaller tanks totaling 50,000 gallons, will be installed near the O&M facilities. Irrigation water would be obtained through water allocation from existing landowners’ approved rights to irrigation water from the San Luis Water District.

Security Fencing and Lighting

Site Security The project would be remotely monitored by the applicant or an affiliated company. Site security would consist of an 8-foot-high chain-link fence with three-strand barbed wire installed around the perimeter of solar panel arrays, as illustrated in Figure 3. Manual swing gates would be constructed at the main entrance and in strategic areas, as required for access by property owners and for the convenience of utility companies in accessing and maintaining their facilities. All easements already recorded would be honored. Additional site security measures would include a monitored camera system designed to cover the entire facility. This system would be remotely monitored and security breaches would be reported to emergency responders as well as site operations. An intrusion detection system would be installed along array fences to alert monitors of fence breaches. A camera working in conjunction with the fence intrusion system would decrease the number of false positives reported. Furthermore, the proposed project would comply with North American Energy Reliability Corporation (NERC) and Western Electricity Coordinating Council (WECC) requirements for regulatory control and security systems. Lighting Project lighting would be installed for ongoing maintenance and security purposes. Low-level lighting would be installed at entry and egress gates at strategic locations around the facility. All project lighting would be shielded and directed downward to minimize the potential for glare or spillover onto adjacent ownerships. All lighting would conform to applicable Merced County outdoor lighting codes. Lighting would be used from dusk to dawn. Lighting would be installed at the project’s substation and switching station. Project lighting would conform to NERC requirements and those of the Merced County.

Signage Signs warning of high voltage danger would be posted on the array fences and at all entry points. These signs would also include a “no trespassing” statement. Signs posted along the project substation and switching station would conform to all codes and PG&E requirements for safety. Signage would identify the project operator and owner and provide emergency contact information. All signage would conform to Merced County signage requirements.

Page 23: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 18 October 2013

ICF

Wildlife Protection Corridors and Fencing Design To facilitate wildlife movement, the project design has incorporated multiple wildlife-friendly movement pathways through the project site, as illustrated on Figure 3. Exclusionary fencing, installed around the solar arrays, would preclude the use of the solar array areas by large ungulates, such as elk; however, this fencing is designed to allow virtually unregulated movement within the project site by small rodents and mammals, such as San Joaquin kit fox. The incorporation of the wildlife corridors into the project design is intended to allow for the use of portions of the site and prevent a complete barrier to movement due to the project. Additionally, as illustrated on Figure 3, security fencing planned for the perimeter of the project site and arrays would include design features to allow San Joaquin kit fox and other wildlife movement in and out of the facility. Fence design, such as leaving a 4-inch clearing from bottom of the fence, is intended to allow San Joaquin kit fox and other wildlife to move freely into and out of the project site. Operation and Maintenance

Operational Time Limits Once in operation, the project would generate electricity during daylight hours. Typically, the plant would produce energy from 6:00 a.m. until 6:00 p.m. Personnel The project would be a private facility and, for safety reasons, would not be open to the public. Only authorized personnel would be permitted on site and would generally be limited to the employees monitoring and maintaining the facility. Upon completion of construction, the project would employ up to six employees to service and maintain the arrays. During scheduled maintenance and emergency repairs, the project would require additional crews of two or more technicians. Facility Maintenance Facility maintenance would include the periodic maintenance of buildings, solar panels, and solar components, as well as the internal road network. The level of vehicle activity entering and leaving the site during operation would be limited to scheduled and emergency maintenance visits and infrequent delivery vehicles. Scheduled solar park maintenance would occur in the early evening or early morning hours to avoid interference with the project’s peak hours of generation, no later than 10:00 p.m. and no earlier than 4:00 a.m. Unscheduled emergency maintenance would occur at any time; however daylight maintenance and emergency service would be strongly encouraged to maximize worker safety. Panel Washing Project O&M would require water for washing dust particles from the solar panels; this task would be take place several (up to four) times per year. Approximately 500,000 gallons of water would be used to clean the panels per year. Panel washing would take place during daylight hours. It is anticipated that the O&M well would be sufficient to provide this quantity, as panel washing extends

Page 24: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 19 October 2013

ICF

over several days, thereby giving water supplies time to recharge the 50,000-gallon water tank during nighttime hours. Project Construction

Site Access Construction and Internal Circulation/Parking

Construction Phase Site Access Access to the project site for construction personnel and construction deliveries would be via Billy Wright Road, which intersects with SR-33/152, a divided four-lane, fully surfaced regional transportation route. The access and interior roads would be surfaced with aggregate, be dust free, and would be maintained to facilitate on-site circulation for emergency vehicles during all weather conditions. The internal road network and project site access are illustrated on Figure 3 and Figure 7, respectively. Construction Deliveries All materials for project construction would be delivered by truck. All truck traffic would occur on designated truck routes and major streets. Deliveries may be made from the north and south via Interstate 5, exiting to SR 152/33, and turning south onto Billy Wright Road. Deliveries form the east would travel along SR 152/33 and turn on Billy Wright Road. Vehicles would travel southwest along Billy Wright Road for approximately 2.8 miles and then turn east on an unnamed access road to enter the project site. Additionally, vehicles may access the project site by turning south off of Billy Wright Road onto an unnamed access road approximately 1.1 miles from the SR 152/33 Billy Wright Road exit. Construction traffic exiting the project site would travel northeastward on Billy Wright Road and then west on SR 33/152 to reach Interstate 5, or east on SR 152/33 to access other points in Merced County.

Page 25: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California
Page 26: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 21 October 2013

ICF

Sections of Billy Wright Road would need to be improved to allow for equipment delivery. Some sections of the road would require grading and repaving. These areas are illustrated on Figure 7. Traffic from construction activities would be temporary and would occur along area roadways as workers and materials are transported to and from the project site. Project components (e.g., PV solar panels, support structures, and electrical interconnection equipment), with the exception of pre-assembled components, would be brought to the project site and assembled. Approximately 9,645 truck trips are assumed for project construction-related deliveries (e.g., tracking system, various supplies, and common features). Construction Phase Parking and Traffic Flow During construction, all employees would park within the site boundary. Approximately 10.5 acres of all-weather parking spaces, temporary office facilities, and equipment staging would be temporarily constructed to provide on-site parking for construction staff. This area could be expanded to accommodate increased worker needs. This area and the gravel placed on it would be reclaimed at the end of substantial construction and re-deployed elsewhere on the project site. Figure 3 shows the location of this temporary worker area that includes the parking.

Construction Phase Utilities and Service Systems The project’s construction phase utility and services system requirements are described below. Electricity The temporary office and construction facilities would obtain construction electricity from a temporary drop off line from the local electrical distribution system. There would be need for electricity distributed across the project and until back feed access is made from the inverters. Up to 15 portable electrical generators that meet local and state emission controls would be used throughout the project area during construction and operation. Waste Disposal Portable restroom facilities would be located across the project where work is occurring in quantities that meet all labor code requirements. These facilities would be regularly cleaned and maintained to health and safety codes. A contract would be executed with the local waste hauling company to ensure removal of all landfill material from the site. Efforts would be made to reduce landfill waste by developing an effective waste recycling program. Waste containers would be spread over work areas making it easy for workers to utilize them. Workers would make regular sweeps to ensure the worksite is clean and safe. Water The project is anticipated to require a volume of approximately 351 acre-feet of water during construction. It is anticipated that 351 acre-feet would be used during the construction phase for soil conditioning, dust control, and other uses. Approximately 1.5 acre-feet would be used annually for project O&M, largely used for panel washing. The project proposes to use a combination of delivered water via truck and irrigation canals for construction and on-site groundwater wells for

Page 27: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 22 October 2013

ICF

operation. Irrigation water would be obtained through water allocations attached to the existing landowners’ approved rights. Site Preparation and Grading Activities

Site Disturbance The project has been designed to limit grading activities; however, solar panel site design requires a maximum of 15 percent slopes. Earthwork would focus on cut and engineered fill as necessary to create finished grade slopes suitable for panel installation. Graded areas would be cleared and grubbed with vegetative material stockpiled on site and distributed back onto disturbed surfaces once grading is complete. Grading and Compaction The maximum project footprint would be approximately 1,600 acres, including staging areas and access roads. Approximately 3,111,000 cubic yards of grading are assumed for inverter pads, the switching station, roads, arrays, battery storage, and other improvements. Approximately 82,000 cubic yards of material (mostly gravel for all weather roads) would be imported to the site. Soil compaction, soil strengthening agents, or geo fabric may be used for access and circulation roads. Compaction may also be required for the construction of inverter pads, the switching station, control rooms, and roads. Road construction would require soil conditioning to achieve proper compaction. Roads and other work areas would be periodically sprayed with water to reduce dust. Roads and work areas may also be treated with approved dust-suppression products approved by Merced County. Fire Protection Fire protection improvements would consist of perimeter and evenly dispersed interior access roads with a 20-foot minimum width constructed of all-weather aggregate base, thereby conforming to Merced County and State of California Fire Code standards. In addition, the project would meet the minimum standards set forth by Public Resources Code 4290 (PRC 4290), Title 14, for fire protection and emergency water standards.

Equipment Installation Construction activities would include the installation of civil infrastructure (e.g. roads, utilities, fencing, etc.), mechanical infrastructure (e.g., tracking components, PV panels, etc.), and electrical infrastructure, as listed below: Civil Infrastructure Survey and project layout, including road, panel, switching station, and support buildings; Road construction, including placement of aggregate; Temporary facilities, parking, and staging areas; Installation of the chain-link fence and gates; Watering for dust control and soil compaction; and

Page 28: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 23 October 2013

ICF

Switching station, skid/inverter, and control room pads. Mechanical & Electrical Infrastructure Installation of I-beam foundations and placement of a racking system on top of I-beam/tubular steel foundations; Placement of PV solar modules and DC collection system; Installation of a wire harness, fuses, and wire grounding; Trenching for buried wires; Installation of buried wiring; Inverter/transformer structures; Wiring and interconnection; AC collection system Trenching and overhead installation of MVCS from inverters/transformers to the project switching station; Construction of the project substation; Construction of the project switching station; Construction of the interconnection to the PG&E transmission/distribution system; Telecommunications installation; Installation of meteorological equipment; O&M facility; Battery energy storage system; and Well for operations water.

Decommissioning and Site Reclamation Plan A decommissioning plan would be prepared in accordance with Merced County requirements. The plan would ensure that the project facilities would be decommissioned and removed and that the site would be restored to pre-construction conditions. Soils and impacted areas would be reclaimed to a level that would, at a minimum, support uses for the land consistent with pre-construction activities, which consist of cattle grazing or dry farming. A detailed Decommissioning and Site Reclamation Plan will be reviewed and approved by the County. Removal of Equipment While all project structures would be removed during decommissioning, it may be advantageous to leave some improvements to enhance agricultural operations following removal of the solar generating facility. The final permitted decommissioning plan would explain how some roads and other features may be left in place to accommodate more efficient farming practices. The decommissioning and restoration process would likely involve the removal of aboveground

Page 29: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 24 October 2013

ICF

structures, restoration of topsoil, revegetation, and seeding. Temporary erosion and sedimentation control Best Management Practices (BMPs) would be used during the decommissioning phase of the project. Equipment that would be removed includes electrical wiring, equipment on the inverter pads, the battery storage system, and the interconnection transformer pad and associated equipment. Equipment would be de-energized prior to removal, salvaged (where possible), placed in appropriate shipping containers, and secured in a truck transport trailer for shipment off site. Removal of the solar modules would involve removing the racks to which the solar panels are attached and placing them in secure transport crates, and then into a trailer for storage and ultimate transport to another facility. The bolts and reusable fasteners that attached each solar module to the racks would be removed and saved for reuse. Once the solar modules were removed, the racks would be disassembled and the structures supporting the racks would be removed. All other aboveground site infrastructure, including fences, awnings, and the concrete pads that supported the inverters, transformers, and related equipment, would be removed. The fences and gates would be removed, and all materials would be recycled to the greatest extent possible. All debris would be removed from the area. Site Reclamation All roads and other areas compacted during original construction or by equipment used in the decommissioning process would be tilled to restore the sub-grade material to a density and depth consistent with adjacent properties. An appropriate seed mixture would be broadcast or drilled across the project site. Other Permits and Approvals that may be Required The applicant has submitted an application for a CUP to the Merced County Community and Economic Development Department for the project. The following required permits and approvals have been identified for the project. Additional permits and approvals may also be required:

Merced County, Construction Permit (Building Permit) and Right of Way Encroachment Permit. Merced County authorizes construction activities under a Construction Permit. This permit encompasses grading, building, electrical, mechanical, landscaping, and other activities. Merced County may require multiple building permits due to the size and complexity of the project. The Merced County’s review for ordinance standards is undertaken as part of this process. An encroachment permit from the County Department of Public Works will also be required.

Central Valley Regional Water Quality Control Board, National Pollutant Discharge Permit and Report of Waste Discharge. Construction of the project and alternatives would disturb a surface area greater than 1 acre; therefore, the applicant would be required to obtain a National Pollutant Discharge Elimination System Permit from the Central Valley Regional Water Quality Control Board. As part of this permit, a Storm Water Pollution Prevention Plan (SWPPP) would be developed and implemented. Pursuant to California Water Code, Section 13260, all persons proposing to discharge waste that may affect the quality of waters of the state must submit to

Page 30: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 25 October 2013

ICF

the Central Valley Water Board a Report of Waste Discharge, following which the Board will either prescribe waste discharge requirements or issue a waiver. San Joaquin Valley Air Pollution Control District (SJVAPCD), Indirect Source Review. An Indirect Source Review (District Rule 9510) would be filed with the SJVAPCD to determine potential mitigation, if any, for oxides of nitrogen (NOX) and particulate matter less than or equal to 10 microns in diameter (PM10) emissions. San Joaquin Valley Air Pollution Control District (SJVAPCD), Dust Control Plan. A dust control plan is required to be submitted and approved by the SJVAPCD prior to initiation of ground disturbance activities associated with construction. United States Army Corps of Engineers (USACE), Clean Water Act Section 404 Permit. The applicant has formally consulted with the USACE regarding potential impacts to jurisdictional waters. USACE has chosen not to take jurisdiction of features within the project area. Therefore, a Section 404 permit is not required. Accordingly, Section 401 certification through the Central Valley Regional Water Quality Control Board is not required. United States Fish and Wildlife Service (USFWS), Incidental Take Permit. Under Section 10 of the Endangered Species Act, an Environmental Assessment or an Environmental Impact Statement, pursuant to the National Environmental Policy Act (NEPA), is required for the USFWS to issue a Biological Opinion and an Incidental Take Permit. California Department of Fish and Wildlife (CDFW) Incidental Take Permit and

Streambed Alteration Agreement. The applicant would consult with CDFW to obtain an Incidental Take Permit (if possible) under Section 2081 of the California Endangered Species Act. CDFW also regulates impacts to riparian habitat under Section 1600 of the Fish and Game Code through the streambed alteration agreement process. CAISO, Connection Approval. CAISO is charged with the management of the flow of electricity across high voltage, long-distance power lines under its control in California. CAISO approval is required for connecting to the Los Banos-Panoche #1 230-kV transmission line. State Historic Preservation Office, Native American Heritage Commission, Section 106

Consultation. Consultation for Section 106 of the National Historic Preservation Act is required because the project is pursuing a Habitat Conservation Plan under Section 10 of the Endangered Species Act. Consultation pertains to known cultural resources and the listing of cultural or historic resources in the National Register of Historic Places or California Register of Historical Resources. Construction Schedule Phased Schedule and Workforce Requirements Phased construction is planned to begin in August 2014, after completing California Environmental Quality Act (CEQA) review, receiving all necessary construction permits, and meeting pre-construction CEQA conditions. The applicant anticipates that construction and testing of the project would take a total of 26 months to complete. Therefore, project construction is expected to be completed in October 2016.

Page 31: WRIGHT S OLAR PARK LLC PROJECT - Merced County, California

County of Merced, Planning and Community Development Department Project Description

Notice of Preparation of a Draft EIR, Wright Solar Park, LLC Project 26 October 2013

ICF

The project elements would be completed either in phases or concurrently. Crews typically work six 10-hour days per week. Depending on local permit requirements, Sunday, evening, and night work may also be required due to the scheduling of system outages and construction schedules. Construction would commence following Merced County approval of permits and other entitlements, final engineering, and procurement activities. The peak construction workforce is anticipated to range between 400 to 600 workers, depending on scheduling constraints. All proposed construction activities would be completed within approved working times, as dictated by Merced County Municipal Code Section 18.41.07, and would conform to standard conditions in Planning Commission Resolution No. 97-1. Commissioning and Energizing Before solar field components can be commissioned and tested, they must have back feed power from the high voltage system. The project substation and the switching station must be constructed, tested, and energized back to the SUTs prior to commissioning activities of the solar field and before power can be exported from the site. As a result of the low voltage side of the substation, the solar field can be brought to commercial power in phases, as dictated by the isolation capabilities of the low side breakers. Final construction phasing would be determined during project financing but, for the purposes of CEQA analysis, it is assumed that all construction phases may occur simultaneously.