world bank document...2.4.2 inspect the inlet and outlet gates and valves of the structures on tono...
TRANSCRIPT
MINISTRY OF FOOD & AGRICULTURE (MOFA)
GHANA COMMERCIAL AGRICULTURE PROJECT
(GCAP)
FINAL REPORT
FOR
CONSULTING SERVICES SAFETY ASSESSMENT OF TONO DAM
BY
December, 2018
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Table of Contents
Table of Contents
List of Tables
List of Figures
Abbreviations and Acronyms
Executive Summary
0.1 Introduction
0.1.1 Background
0.1.2 Purpose and Scope of the Assessment
0.2 Methodology
0.2.1 Geotechnical/Dam Engineering Services
0.2.2 Hydrological Services
0.2.3 Hydraulic Engineering Services
0.2.4 Mechanical Services
0.2.5 Instrumentation
0.2.6 Dam Operator Training
0.3 Observations & Findings
0.3.1 Geotechnical/Dam Engineering Services
0.3.2 Hydrological Services
0.3.3 Hydraulic Engineering Services
0.3.4 Mechanical Services
0.3.5 Instrumentation
0.3.6 Dam Operator Training
0.4 Conclusions
0.4.1 Geotechnical/Dam Engineering Services
0.4.2 Hydrological Services
0.4.3 Hydraulic Engineering Services
0.4.4 Mechanical Services
0.4.5 Record Keeping
0.4.6 Dam Operator Training
0.5 Recommendations
0.5.1 Geotechnical/Dam Engineering Services
0.5.2 Hydrological Services
0.5.3 Hydraulic Engineering Services
0.5.4 Mechanical Services
0.5.5 Record Keeping
0.5.6 Instrumentation
0.5.7 Dam Operator Training
1 Introduction
1.1 Background
1.1.1 The Project and Consultancy Assignment
1.1.2 Irrigation Projects being rehabilitation under GCAP
1.2 Purpose and Scope of the Assessment
1.2.1 Consultancy Assignment Scope
1.3 Specific Tasks of the Consultancy
2 Methodology and Analysis
2.1 Geotechnical/Dam Engineering Services
2.1.1 Detailed Dam Inspection
2.1.2 Assessment of Foundation Stability
2.1.3 Assessment of Embankment Stability
2.2 Hydrological Services
2.2.1 Electrical Resistivity Test at Tono
2.2.2 Hydrologic Features and Failure Modes of the Tono Dam
2.2.3 Hydrologic loads (Flood Risk) of Tono Dam analyzed
2.2.4 Investigation of the Dam’s downstream conditions for emergency situations
2.3 Hydraulic Engineering Services
2.3.1 Design and construction data of Tono Dam reviewed
2.3.2 Integrity of appurtenant structures examined
2.3.3 Tono Dam channel for flow discharge capability assessed
2.3.4 Tono Dam downstream conditions assessed and need for emergency concept
ascertained
2.3.5 Installations and instrumentations for Hydraulic Failure assessed
2.4 Mechanical Services
2.4.1 Desk review of data and information on all mechanical equipment on the Tono
dam
2.4.2 Inspect the inlet and outlet gates and valves of the structures on Tono dam.
2.4.3 Desk review of all operation and maintenance reports of the gates and valves
2.4.4 Desk review of the maintenance plan of all the mechanical components of the
facilities
2.4.5 Desk review of the manufacturer's instructions and compare to current use
and operation of the components
2.4.6 Examine instrumentation readings for adequacy and analyze for trends as well
as any information that can be deduced from them, propose any additional
instrumentation required
2.5 Review all the dam operator training programs and reports if any
3 Major Findings and Implications
3.1 Geotechnical/Dam Engineering Services
3.1.1 Visual Inspection of Dams
3.1.2 Foundation Stability
3.1.3 Stability of Embankment
3.2 Hydrological Services
3.2.1 Visual Inspections
3.2.2 Results and Implications of the Electrical Resistivity Test at Tono
3.2.3 Flood Water Evacuation of Tono Dam
3.2.4 Hydrologic failure mode of the Tono Dam
3.2.5 Tono Dam upstream and downstream conditions
3.3 Hydraulic Engineering Services
3.3.1 Integrity of appurtenant structures
3.3.2 Hydraulic Failure Modes of the Tono Dam Assessed
3.3.3 Tono Dams downstream conditions
3.4 Mechanical Services
3.4.1 Desk review of data and information on all mechanical equipment
3.4.2 Inspection of the inlet and outlet gates and valves
3.4.3 Operation and Maintenance
3.4.4 Maintenance plan
3.4.5 Manufacturer's Instructions
3.5 Instrumentation
3.6 Dam Operator Training
4 Conclusions
4.1 Geotechnical/Dam Engineering Services
4.1.1 Dam Foundation
4.1.2 Stability of Embankment
4.2 Hydrologist Services
4.2.1 Flood risk of the Tono Dam
4.2.2 Hydrologic Failure Mode of Tono Dams
4.3 Hydraulic Engineering Services
4.3.1 Integrity of the Spillway and Appurtenant Structures
4.3.2 Hydraulic Failure Modes of the Tono Dam
4.3.3 Downstream conditions of Tono Dam
4.4 Mechanical Services
4.4.1 Valves
4.5 Instrumentation
4.5.1 Record Keeping
4.6 Dam Operator Training
5 Recommendations
5.1 Geotechnical/Dam Engineering Services
5.1.1 Visual Inspection
5.1.2 Stability of Embankment
5.1.3 Regular Visual Observations
5.2 Hydrologist Services
5.3 Hydraulic Engineering Services
5.4 Mechanical Services
5.4.1 Off Take Tower
5.4.2 Scour Tower
5.4.3 Operation and Maintenance (O & M)
5.5 Record Keeping
5.6 Instrumentation
5.6.1 Piezometers
5.7 Dam Operator Training
6 Annexes
6.1 Geotechnical Annexes
6.1.1 Trial Pit Records
6.1.2 Grading Curves
6.1.3 Dynamic Cone Penetration Test (DCPT) Results
6.1.4 Soil Test Results
6.2 Terms of Reference
6.3 Work Plan
6.4 Field visits schedule
6.5 List of Stakeholders met during field visits
6.6 Minutes of Meetings
6.7 Data Collection
6.7.1 List of Data Collected
6.7.2 ICOUR Training Needs
7. REFERENCES
List of Tables
Table 1: Key Features and Inventory of Tono Dam
Table 2: Trial Pits and their GPS Locations
Table 3: Peak Daily Flows of Tono Dam
Table 4: Flood risk analysis of Tono Dam
Table 5: Flood inflows and outflows from the spillway considering Reservoir Attenuation
Table 6: Hydrologic Failure Mode of Vea and Tono Dams
Table 7: Hydraulic Failure Mode of Tono Dam
Table 8: Measurements and Instruments for long term Performance Monitoring
List of Figures Figure 1: Geological Map of Upper East Region
Figure 2: Trial Pit and DCPT Locations
Figure 3: Tono dam showing one profile lines for resistivity measurements
Figure 4: Inspection of the Spillway chute of the Tono Dam (GPS Track in Blue)
Figure 5: Cultivation of Pepper on the Upstream Banks of the Tono Dam
Figure 6: Close up of Joint of replaced section of Spillway Wall indicating lateral movement
Figure 7: Joint of replaced section of Spillway Wall indicating lateral movement
Figure 8: Expansion Joint wider than normal
Figure 9: Change in level at column support due to settlement at hinge support
Figure 10: Spalling of concrete in floors of Spillway Channel
Figure 11: Upstream Slope Protection at Tono Dam
Figure 12: Vegetative cover to downstream slope at Tono
Figure 13: Trapezoidal open paved drain
Figure 14: Trapezoidal open paved drain
Figure 15: Cross Section of Tono Dam
Figure 16: Resistivity Image for Profile along Tono Dam
Figure 17: Sketch of an Ogee crested weir spillway
Figure 18: Geometry of the Ogee crest
Figure 19 Graph of discharge coefficient against ratio of crest elevation to upstream head
over crest elevation
Figure 20 Daily Reservoir Water levels of Tono from 2010 to 2018
Figure 21 Historical Annual Rainfall at the Tono Dam
Figure 23 Tono Dam Spillway rating curve
Figure 24: Common failure mechanisms of Dams (Source: Dam Safety Manual of Ghana)
Figure 24: Gullies on the downstream embankment of Tono dam due to Soil Erosion
Figure 24: Outlet Structure
Figure 25: Obstruction of the Spillway at the stilling basin of the Tono Dam from a broken
channel wall.
Figure 26: Scour Pipe Outlet Structure
Figure 27: Scour Pipe Outlet Structure blocked with Clay
Figure 28: Location of the 12 observation wells at the toe of the Tono Dam
Figure 29: Non-functioning observation wells at the Tono Dam
Figure 30: Observation wells at the Tono Dam
Abbreviations and Acronyms
AfDB African Development Bank
CBR California Bearing Ratio
DCPT Dynamic Cone Penetration Tests
EMWA Edward Mensah Wood and Associates
GCAP Ghana Commercial Agriculture Project
GEL Golden Exotics Limited
GIDA Ghana Irrigation Development Authority
GHA Ghana Highways Authority
GWCL Ghana Water Company Limited
Ha Hectares
ICOUR Irrigation Company of Upper Region
IPC International Power Company
KIS Kpong Irrigation Scheme
KLBIP Kpong Left Bank Irrigation Project
M&E Monitoring and Evaluation
PDO Project Development Objective
PPP Public Private Partnership
SADA Savanna Accelerated Development Authority
SOP Standard Operating Procedures
USAID United States Agency for International Development
VRA Volta River Authority
Executive Summary
0.1 Introduction
0.1.1 Background
0.1.1.1 The Project and Consultancy Assignment
The International Power Company has been awarded a contract by the Ghana Commercial
Agriculture Project (GCAP), Ghana’s flagship agricultural project, financed by a credit from the
International Development Association (IDA) and grant from the United States Agency for
International Development (USAID) to undertake Dam Safety Assessment of the Tono and
Vea Dams.
The project, restructured in 2015 with the revised Project Development Objective (PDO) to
improve agricultural productivity and production of both smallholder and nucleus farms in
selected project intervention areas with increased access to reliable water, land, finance, and
agricultural input and output markets consists of the following seven components: (i)
Strengthening investment promotion infrastructure and facilitating secure access to land; (ii)
Securing PPPs and smallholder linkages in the Accra Plains; (iii) Securing PPPs and small-
holder linkages in the SADA Zone; (iv) Project Management including M&E and impact
analysis; (v) Investments in physical rehabilitation and modernization of existing public
irrigation and drainage infrastructure; (vi) restructuring and strengthening of public irrigation
and drainage institutions of the Government of Ghana; and (vii) development of Water Users’
Associations and private scheme management.
0.1.1.2 Irrigation Projects being rehabilitation under GCAP
Under Component 5 of the Project, GCAP will support the design review, rehabilitation and
modernization of the scheme including an assessment of the economic rates of return and
poverty reduction impacts of the under listed Irrigation Schemes:
Tono and Vea Irrigation Projects in the Upper East Region
Kpong Irrigation Scheme (KIS) at Asutsuare in the Eastern Region
Kpong Left Bank Irrigation Project (KLBIP) in the North Tongu District of the Volta
Region
0.1.1.3 Tono
The Tono scheme was established by the Ghana Government to promote the production of
food crops by small scale farmers within an organized and managed irrigation scheme. It is
located at Tono near Navrongo in the Upper East region of Ghana. It has a gross area of
3,860 ha with a potential irrigable area of 2,680 ha of which 2,490 ha has been developed.
The source of water is the Tono River. Construction of the Tono Irrigation scheme started in
1975 and completed in 1985. Some rehabilitation of the gravity scheme was carried out in
2008 by replacing the concrete slabs in the main gravity canal.
The Tono Irrigation Scheme is under the management of Irrigation Company of Upper Region
(ICOUR).
0.1.2 Purpose and Scope of the Assessment
The objective of this assignment is to assess and evaluate the safety of the existing dam at
Tono. In particular, safety inspections will be carried out on all critical sections of the dam that
include but not limited to the following areas:
Dam Crest
Upstream Embankment
Downstream Embankment
Offtake Chamber, Spindle and Valve
Spillway Crest and Channel
Toe Drain
0.2 Methodology
0.2.1 Geotechnical/Dam Engineering Services
A systematic geotechnical evaluation of the dams were carried out which include: performance
of detailed dam inspections; assessment of current foundation stability; assessment of current
embankment stability; assessment of the slopes of the embankment and assessment of
cracking due to differential movements.
0.2.2 Hydrological Services
The Hydrological Investigations conducted on the Tono Dam included; electrical resistivity test
(field and laboratory), assessment of hydrologic features and failure modes, analysis of
hydrologic loads and downstream conditions for emergency situations.
0.2.3 Hydraulic Engineering Services
The hydraulic investigations conducted a review of the hydraulic components of Tono dams
as designed and built. The hydraulic components reviewed include the Outlet canal, Spillway,
Spillway chute, spillway sections and drains.
0.2.4 Mechanical Services
The mechanical services were performed as follows: Data and information on all mechanical
equipment reviewed; the inlet and outlet gates and valves inspected; operation and
maintenance reports of the gates and valves reviewed; maintenance plan of all the mechanical
components reviewed; compared manufacturer's instructions to current use of the valves.
0.2.5 Instrumentation
Instrumentation readings were examined for adequacy and analyzed for trends as well as any
information that can be deduced from them and additional instrumentation proposed required.
0.2.6 Dam Operator Training
ICOUR provided two sheets (see Section 6.7.2) which listed the training courses with names
of staff to undertake them as well as dates for 2016 and 2017.These were studied for the
review.
0.3 Observations & Findings
Below are the observations and findings:
0.3.1 Geotechnical/Dam Engineering Services
Some of the defects identified at this dam site include:
Widened expansion joint resulting from differential settlement of supports on the scour
tower bridge.
The trial pits revealed the geological successions at this site to consist of three distinct
layers: topsoil of Sandy Silt, underlain by lateritic gravel grading to hardpan and residual
soil of micaceous Silty Clay.
The dynamic cone penetration tests (DCPT) results gave very high penetration resistance
values (N-values) that were increasing with increasing depth.
The upstream slope protection is ensured by providing riprap.
The downstream slope protection is ensured by vegetative cover.
Surface drainage. provided on the downstream slope, had residual silt and seemed non-
functional at the time of the safety assessment.
As per the design, the core of the embankment fill is made of clay, capped with sand and
gravel filters in succession. These filters are then capped with the riprap.
0.3.2 Hydrological Services
The laboratory electrical resistivity results of the saturated soil from the Tono dam was
20Ωm.
Low resistivity areas (3.5-30 Ωm) were observed, signifying saturation zones within the
earth dam.
The geophysical investigations revealed that seepage exist in the dam, stretching along
40% of the Tono Dam. Coincidentally, the locations of the seepage areas fall in line with
the areas of the wetlands about 100m downstream of the dam.
Physical investigations on the dam did not observe any cracks or pipes and most
especially at the locations of the low resistivity.
The flood routing of the dam, estimated to determine their impact on the embankment of
the dam, shows the maximum level of flooding on the dam as an inflow of 603.9m3/s and
its likely impact as an outflow of 302m3/s with an assumed attenuation of 50%.
Gullies due to soil erosion were observed on downstream face of the Tono dam.
Shrub was observed in both faces of the dam, with trees growing on the downstream
faces of the dam. The Toe drain of the dam is completely silted.
Surface drains were observed to be non-functional.
No rodent activity observed.
Recession agriculture is practiced seriously along the banks upstream of the reservoir.
0.3.3 Hydraulic Engineering Services
Sections of the Spillway Chute Wall are tilted due lateral earth pressure on the spillway
channel walls.
The tilting of the wall panels have created a gaps where seepage can take place between
the wall joints and therefore has the tendency to affect the channel embankment
An old broken wall section is lying on the baffle blocks within the stilling basin acting as a
blockage to the water flow.
The stilling basin is sound.
No signs of spillway chute wall overtopping were observed.
The spillway basin sweepout is located about 550m downstream of the chute and has
free standing baffle blocks about 20m before the end sill, made up of boulder packs.
A Schmidt Hammer test conducted on the spillway structure revealed a concrete strength
greater than 52.5kN/m2, which is adequate because it is greater than the allowable
strength of 35KN/m2. The result shows adequate strength and it is consistent with the age
of the structure.
The spillway drain was found to be in good shape.
Spalling of concrete within floors of spillway channel.
0.3.4 Mechanical Services
There are two sets of valves, one in the Off-take Tower and other in the Scour Tower.
The Off take Tower is in the middle of the dam wall and houses two valves in series, a
900 mm Gate valve and a 900 mm Butterfly valve.
The Gate valve leaks from the valve body into the Off-take Tower well, housing the valves
The Off-take Tower walls leak into the well.
The valves in the Off-take Tower are constantly under water.
The second set of valves is in the Scour Tower, thirty meters into the reservoir.
The Scour tower houses four valves which are a 1200 mm scour gate valve and three 400
mm water supply gate valves taking water at different elevations into a 400 mm water
supply pipe.
The Scour Tower walls leak into the well.
The Scour pipe is blocked at the discharge end.
The water supply system is unutilised.
0.3.5 Instrumentation
The team counted twelve observation wells at the Toe of the dam, seven of them had
been filled with sand and the remaining had no piezometers installed.
The team counted three Piezometers[1] which are installed on the downstream face of the
dam, there are no data collections available on the piezometer readings and they are
currently not functioning.
There is a staff gauge on the Scour Tower Wall.
0.3.5.1 Record Keeping
The general observation is that record keeping at Tono Dam is non-existent. The information
is not gathered in the first place to be kept.
0.3.6 Dam Operator Training
There is no “in-house” Training for the staff at Tono.
There was no technical training for the operating staff for 2016.
A planned external training for selected ICOUR staff for 2017 (to be funded by GCAP) will
not train the operating personnel in the relevant fields.
0.4 Conclusions
0.4.1 Geotechnical/Dam Engineering Services
The Tono Dam in its current state is safe and sound
The foundation of the dam is very compact and stable.
The slope protective measures at both upstream and downstream faces are adequate
Both longitudinal and transverse cracking which are generally caused by differential
settlements or deformations in the foundation, abutments or adjacent materials within the
embankment, are absent.
0.4.2 Hydrological Services
The Tono dam is safe for flood events of return period up to 1 in a 1000-year event.
The spillway capacity is adequate.
There is seepage in the dam which is manageable and does not require structural
remedies.
There is lack of maintenance on the dam faces.
The massive flood recession agriculture could enhance sediment transport into the
reservoir.
0.4.3 Hydraulic Engineering Services
The integrity of the spillway chute, walls, stilling basin and the channel of the Tono
dam is currently sound.
Stagnation pressure is likely to occur, specifically at the dam chute wall that has tilted.
The concrete strength of the dam is adequate.
0.4.4 Mechanical Services
0.4.4.1 Valves
There is a safety issue of leakage from the gate valve body and the tower walls, leaving
the valves submerged continuously. Apart from the inconvenience of having to work in
water, there is the danger of drowning.
Flushing of silt through the Scour pipe cannot be done as a result of the discharge end of
the pipe from the Scour Tower being blocked.
0.4.5 Record Keeping
The general observation is that record keeping at Tono Dam is nonexistent. The information
is not gathered in the first place to be kept.
0.4.6 Dam Operator Training
The dam operators require technical training as well as training in the importance of record
acquisition and management.
0.5 Recommendations
0.5.1 Geotechnical/Dam Engineering Services
All structural and non-structural defects identified during the visual inspection and
indicated in this report by our team at this dam site should, as a matter of urgency, be
rectified.
The non-functional system of open paved drains (chutes) along the sloping surface for
surface drainage of downstream slope must be re-instated or re-constructed.
Regular visual observations, an essential aspect of a program for monitoring long-term
performance, should be undertaken.
0.5.2 Hydrological Services
Data collection on spillage and all water uses should be prioritized.
The seepage rates of the dam should be monitored by providing instrumentation.
There is the need to prepare flood inundation maps for various flows in case of emergency
situations such as dam breach. The maps will be useful for emergency preparedness
planning.
0.5.3 Hydraulic Engineering Services
The tilted chute wall at Tono spillway should be given special attention.
The broken wall must be removed from the spillway channel.
Walls need weep holes to relieve them of pressure during surcharge.
0.5.4 Mechanical Services
0.5.4.1 Off Take Tower
The area around the valves must be dewatered and kept dry at all times.
The 900 mm gate valve with body leakage must be replaced.
The leakage from the walls of the Off-Take Tower must be stopped.
0.5.4.2 Scour Tower
The well should be dewatered and kept dry at all times.
The water supply valves and pipes should be kept in good condition for future use.
The leakage from thewalls of the scour tower must be stopped
0.5.4.3 Operation and Maintenance (O & M)
A combination of routine and periodic maintenance programs for optimum operation of the
dam and as a means of continuous safety is recommended.
0.5.5 Record Keeping
Monitoring and surveillance results should be recorded and the records kept. The
data/information should be analyzed, evaluated and reported.
0.5.6 Instrumentation
The sand filled observation wells should be reinstated and piezometers installed in some
of them.
Recommended types of additional instrumentation are:
- Leakage Weirs
- Piezometers
- Liquid level gauges
- Staff Gauges
0.5.7 Dam Operator Training
It is recommended that the Management and Technical Staff are attached to a similar facility
to acquire knowledge in good record acquisition and management. Training should cover the
following:
Structural, mechanical and dam instrumentations and data acquisition.
Inspection, Maintenance and repair works procedures.
Record keeping and data management.
Irrigation water management.
GIS and remote sensing applications to catchment area management including
planning and monitoring.
Negotiation, conflict resolution and stakeholder engagement.
Report writing and communication.
1 Introduction
1.1 Background
1.1.1 The Project and Consultancy Assignment
The International Power Company has been awarded a contract by the Ghana Commercial
Agriculture Project (GCAP) to undertake Dam Safety Assessment of the Tono and Vea Dams.
The Ghana Commercial Agriculture Project (GCAP), financed by a US$100 million credit from
the International Development Association (IDA) and grant of US$45 million from the United
States Agency for International Development (USAID), is Ghana’s flagship agricultural
project.
The project was restructured in 2015 with the following revised Project Development Objective
(PDO): to improve agricultural productivity and production of both smallholder and
nucleus farms in selected project intervention areas with increased access to reliable
water, land, finance, and agricultural input and output markets.
The restructured GCAP consists of the following seven components: (i) Strengthening
investment promotion infrastructure and facilitating secure access to land; (ii) Securing PPPs
and smallholder linkages in the Accra Plains; (iii) Securing PPPs and small-holder linkages in
the SADA Zone; (iv) Project Management including M&E and impact analysis; (v) Investments
in physical rehabilitation and modernization of existing public irrigation and drainage
infrastructure; (vi) restructuring and strengthening of public irrigation and drainage institutions
of the Government of Ghana; and (vii) development of Water Users’ Associations and
private scheme management.
1.1.2 Irrigation Projects being rehabilitation under GCAP
Under Component 5 of the Project, GCAP will support the design review, rehabilitation and
modernization of the scheme including an assessment of the economic rates of return and
poverty reduction impacts of the under listed Irrigation Schemes:
Tono and Vea Irrigation Projects in the Upper East Region
Kpong Irrigation Scheme (KIS) at Asutsuare in the Eastern Region
Kpong Left Bank Irrigation Project (KLBIP) in the North Tongu District of the Volta
Region
1.1.2.1 Tono
The Tono scheme was established by the Ghana Government to promote the production of
food crops by small scale farmers within organized and managed irrigation scheme. It is
located at Tono near Navrongo in the Upper East region of Ghana. It has a gross area of
3,860 ha with a potential irrigable area of 2,680 ha of which 2,490 ha has been developed.
The source of water is the Tono River. Construction of the Tono Irrigation scheme with the
dam started in 1975 and completed in 1985. Some rehabilitation of the gravity scheme was
carried out in 2008 by replacing the concrete slabs in the main gravity canal.
The Tono Irrigation Scheme is under the management of Irrigation Company of Upper Region
(ICOUR).
1.2 Purpose and Scope of the Assessment
There are serious consequences in the event of a dam malfunction or failure. Given the huge
financial investments being made on the Tono project, it is prudent to assess and ascertain
the safety of the dam.
The objective of this assignment is therefore to assess and evaluate the safety of the
Tono dam.
After many years of use and lack of maintenance the dam infrastructure needs rehabilitation
to make them more efficient. In particular, safety inspections will be carried out on all critical
sections of the dam that include but not limited to the following areas:
Dam Crest
Upstream Embankment
Downstream Embankment
Offtake Chamber, Spindle and Valve
Spillway Crest and Channel
Toe Drain
Table 1: Key Features and Inventory of Tono Dam
Item Section Description Unit Quantity Remarks/Condition
1. Dam Earth Dam - -
Reservoir
Capacity
Million
cu.m
92.6
Catchment
Area
Sq. km 650
Top Water
Level
MASL 179.22
Design Flood
Level
MASL 181.69
Maximum
Water Depth
m 15.14
Maximum
Height of
Embankment
m 18.59
Lowest
Ground
MASL 163.98
Level in
River Bed
Top of
Embankment
MASL 182.57
Top of Wave
Wall
MASL 183.2
Reservoir
Surface Area
Ha 1860
2.
Dam crest Level MASL 182.57
Width m 5.7 Good condition.
Camber % 6 Camber not maintained
Length km 3.471
Gravel
Surface
- Good condition.
Height m 12
3.
Upstream
embankment
Slope 1:3 Maintained
Rip-rap slope
protection
- Good condition. Tree stumps
observed but controlled and
prevented from growing tall.
4. Downstream
embankment
Slope - 1:2.5 Maintained
Slope
protection
- Gullies observed on the slope. Need
to be filled with earth material and
grassed.
Also, open paved drains along the
sloping surface filled partially with
earth and seem non-functional.
5. Offtake Invert MASL 171.85
Chamber No. 1 Good but filled with water at the
time of visit. Need to drain the
water.
Valve No. 2 One gate and one butterfly.
Spindle No. 1 In good condition.
Outlet No. 1 In good condition.
6. Spillway Crest height m 3 Uncontrolled Ogee type. In good
condition.
Width m 60 Verified.
Crest Level MASL 179.22
Design Flow cu. m/s 496
Channel - - Good. However, some side walls
have tilted thereby creating gaps.
Walls need weep holes to relieve
them of pressure during surcharge.
7. Scour Tower
Valve
Chamber Chamber filled with water. May be
due to leakage from the walls and
valves.
Access
bridge
No. 1 In good condition but signs of
settlement affected hinge support,
noting wider than normal expansion
joint of Scour Tower walkway.
Valve No. 1 Submerged continuously. Not
operated for over 25 years.
Spindle No. 1 In good condition.
Outlet No. 1 Blocked with earth.
8. Provision for
Domestic
Water
Valve No 3 Water is abstracted at three
different elevations into a 400mm
pipe for domestic use. Not yet
utilized.
1.2.1 Consultancy Assignment Scope
The scope of the Consultancy Assignment is:
a) Assessment of the condition of the structure based on visual observations, review and
analysis of data on the design, hydrology, construction, operation, maintenance and
performance of the structure;
b) General assessment of hydrologic and hydraulic conditions including review of design
floods;
c) General assessment of seismic safety of dam based on site specific seismic
parameters;
d) Evaluation of operation, maintenance and inspection procedures;
e) Evaluation of the downstream conditions and the need for emergency concept
f) Evaluation of any other conditions which constitute or could constitute a hazard to the
integrity of the structure; and
g) Evaluation of monitoring instrumentation associated with providing data that aids in
evaluating the safety and operation of the dam (i.e. hydrometric stations, climate
stations, seepage weirs, piezometers, survey points, reference points, inclinometers,
extensometers, foundation baseplates, crack monitoring devices, etc.).
h) Make recommendations for necessary monitoring instrumentation for dams
1.3 Specific Tasks of the Consultancy
The specific tasks to be performed in the dam safety assessment are the following:
Review of existing reports and relevant documents on dam safety of Tono Dam, if any.
Inspection of each dam and appurtenant structures as well as assessment of
conditions including reservoir.
Experience based assessment of flood risk, seismic risk and structural stability
Evaluation of safety condition of the dam.
Recommendation of remedial measures with cost estimation including prioritization.
Proposition of monitoring system (including instrumentation needed) for the dam,
related to dam safety and operation.
2 Methodology and Analysis
2.1 Geotechnical/Dam Engineering Services
In order to accomplish a comprehensive geotechnical assessment of the Safety of these
Dams, a systematic geotechnical evaluation of the dams was carried out which include:
a) performance of detailed dam inspections
b) assessment of current foundation stability
c) assessment of current embankment stability
d) assessment of the safe slopes of the embankment
e) assessment of cracking due to differential movements
2.1.1 Detailed Dam Inspection
Visual inspection was undertaken by the geotechnical team on 27th February, 2017 on the
Tono Dam as part of the reconnaissance survey. This was immediately followed by a desk
study of all available design drawings that were made available to the IPC Team.
The visual inspection involved the examination of:
a. embankment (construction and performance)
b. spillway crest and channel (design and adequacy)
c. geological outcrops in the vicinity relating to foundation design, characteristics and
performance
2.1.2 Assessment of Foundation Stability
The assessment of the dams’ foundation stability was carried out through a review / study of
the general geology of the region, seismicity of the region, as well as relevant fieldwork.
2.1.2.1 General Geology of the Region
The Upper East Region of Ghana is generally underlain by rocks of Sedimentary-basin
Granitoids (also known as Cape Coast type Granites). The lithology of the Sedimentary-Basin
Granitoids comprises granite, biotite and muscovite granite, granodiorite, pegmatite, aplite
with biotite schist pendants. These rocks are of middle Precambrian and are at times well
foliated.
The granites are characterized by the presence of many enclaves of schist and gneisses.
Figure 1: Geological Map of Upper East Region (Bright K Amegashie, Charles Quansah, Wilson A Agyare and Paul L. G. Vle March 2011)
2.1.2.2 Seismicity of the Region
Micro-seismic studies have indicated that Ghana’s seismicity is associated with active faulting,
particularly along the Akwapim fault zone (in the Akwapim range) which trends approximately
NE – SW, 20km to the west of Accra, or along the Coastal Boundary faults which lies some
3.0km off-shore and runs almost parallel to the coastline of Accra. Indeed seismic activities in
the country are concentrated and most felt at areas where these two (2) causative faults
intersect close to Nyanyanu near Kasoa. (Geological Survey Department)
The Upper East Region (project site) is some 845km away from the two causative fault zones.
Also, no major or splinter geological discontinuities such as faults have been mapped within
the region. Therefore, the region can be described as traditionally non-seismic.
2.1.2.3 Fieldwork
The fieldwork involved the sinking of trial pits, sampling, performance of DCPT, and laboratory
testing of soil samples.
2.1.2.3.1 Trial Pits
In order to determine the condition and stratification of the subsurface soil and to facilitate
sampling, trial pits were sunk manually at carefully selected positions at the dam site.
Table 2 below gives the GPS locations of each trial pit and the depth explored.
Table 2: Trial Pits and their GPS Locations
Trial Pit No. Depth
explored (m)
GPS Location
W/N
TCP1 & TP1 1.5 0701582/1201184
TCP2 & TP2 1.3 0701469/1201261
TCP3 & TP3 1.5 0702951/1203289
The difficulty in manual excavation within highly weathered rock material formed the basis of
termination of trial pits. All trial pits were backfilled. The soil profile in each trial pit was carefully
logged.
Soil sampling was done at a frequency which enabled an accurate description and
characterization of the ground to be made and provide enough representative samples for
laboratory testing.
All Samples were sealed in airtight plastics, labelled immediately after taking from the trial pit
and protected from excessive heat and temperature variations.
2.1.2.3.2 In-situ Test
The dynamic cone penetration test (DCPT), an in-situ test that gives a measure of the relative
densities and also determines if there is soft compressible layer at depth, was performed at
some selected points of the dam site. The DCPT points are shown in Figure 2.
DCPT3 & TP3
DCPT2 & TP2
DCPT1 & TP1
Figure 2: Trial Pit and DCPT Locations
The locations of the Trial Pits and DCPT points were chosen bearing in mind that such
activities had the potential of destabilizing the dam; a concern expressed by GCAP/GIDA at
the Contract Negotiation Meeting, (See Annex Error! Reference source not found.). The
locations shown in
Figure 2 were therefore selected.
The DCPT employs various forms of rod with cone which are driven down into the soil by
blows of a drop hammer. The number of blows for a given distance of 0.1m penetration is
recorded.
The results of the DCPT given as penetration resistance, “r” (No. of blows/10cm of penetration)
were recorded for plotting and analyses.
2.1.2.3.3 Laboratory Testing
The samples were sent to the Central Materials Laboratory of Ghana Highway Authority, Accra
for testing. Relevant laboratory tests were performed on 19th April, 2017 on representative soil
samples recovered from the trial pits to determine the physical and engineering characteristics
of the subsoil material.
2.1.3 Assessment of Embankment Stability
The stability of an embankment depends basically on the characteristics of foundation and fill
materials as well as the geometry of the embankment section.
Consequently, the assessment of the embankment stability was undertaken via:
a. the consideration of the upstream and downstream slope under static loading as well
as full supply level, maximum flood level and rapid drawdown cases
b. the type and nature of slope protection
c. type and method of surface drainage
d. determination of the engineering characteristics of the embankment fill materials
e. growth of trees close to or near the embankment
2.2 Hydrological Services
The Hydrological Investigations conducted on the Tono Dam included; electrical resistivity test
(field and laboratory), assessment of hydrologic features and failure modes, analysis of
hydrologic loads and downstream conditions for emergency situations. The details of how
these activities were carried out are described in the following sections.
2.2.1 Electrical Resistivity Test at Tono
The main reason for carrying out the electrical resistivity test was to help identify the flow paths
occurring within the dam. The resistivity test provides an image of the portions of the dam
where there are likely to be some Geophysical weaknesses or areas of water movement for
consideration. The resistivity results are then compared to ground observations such as ponds
of water, intake points and areas of high water levels to draw meaningful conclusions.
2.2.1.1 Field Electrical Resistivity Profiling
The electrical resistivity measurements commenced on the 21st of March 2017 and ended on
the 25th of March 2017. Resistivity profiling measurements was conducted along
predetermined profile lines running along the Tono dam. The measurement layout showing
the profile lines for the resistivity profiling is shown in Figure 3.
Figure 3: Tono dam showing one profile lines for resistivity measurements
The resistivity measurements were conducted using multi-electrode cables and the
SuperSting R1/IP resistivity equipment, utilizing twenty eight electrodes with a spacing of 5
meters. To cover the whole length of profile line along the dam crest, the roll along technique
was used. The dipole-dipole configuration was utilized and the measurement protocol was
programmed for the equipment to take the measurements automatically.
2.2.1.2 Laboratory Electrical Resistivity Tests
Soil samples from the two dam sites were taken to the KNUST Civil Engineering, Geotechnical
Laboratory to determine their electrical resistivity. The samples were saturated with water
samples obtained from the respective reservoirs at the dam sites. The saturated samples were
placed in the soil box and the resistivity determined.
2.2.1.3 Electrical Resistivity Tomography
The electrical resistivity data collected at each of the four profile lines at the two earth
dams was processed using the EarthImager 2-D software to obtain an image of the
subsurface on each of the profile lines. The measured resistivities were inverted using
Quasi Newton method to obtain an inverted or true resistivity section of the subsurface.
2.2.2 Hydrologic Features and Failure Modes of the Tono Dam
The assessment of the hydrologic features of the Tono Dam first commenced with the review
of design information provided by SMEC. The following were carried out on the inspection of
hydrologic features;
Assessment of the spillway capacity of the Dam
Assessment of the structural integrity of the spillway
Investigation of spillway channel to ascertain its current state and presence of
cavitation damage.
Inspection of the Spillway Channel to about 550 m downstream of the Tono spillway
crest (Figure 4)
Inspection of the upstream section of the Dam was also undertaken to help identify,
the activities ongoing upstream of the reservoir and their implications on inflows and
sedimentation of the reservoir (Figure 5).
Assessment of piezometers and observation wells.
Physical investigations to identify possible signs of cracks, seepage and piping,
activities of rodents and reptiles on the dam.
Assessment of the effects of tree stumps and gully erosions on the dam.
Figure 4: Inspection of the Spillway chute of the Tono Dam (GPS Track in Blue)
Figure 5: Cultivation of Pepper on the Upstream Banks of the Tono Dam
2.2.3 Hydrologic loads (Flood Risk) of Tono Dam analyzed
The assessment of the hydrologic loads of the Tono Dam first commenced with the collection
of hydrologic design data, dam water levels, spillage, irrigation water use, dam volume
elevation curves, catchment area of dam, rainfall data and evapotranspiration data. Not all the
information could be obtained, notably were the spillage, irrigation water use and dam
hydrologic design data. Daily Time series information provided by ICOUR and could be used
spanned the period 2000-2014.
Despite the lack of essential data, the team used the water balance approach to estimate the
Inflows into the dam using the Water Evaluation and Planning Model (WEAP).
2.2.4 Investigation of the Dam’s downstream conditions for emergency situations
The downstream conditions for the Tono Dam were also investigated with respect to
emergency situations. The investigation covered the following:
Inspection of areas around the spillway channel and the drains for possible flooding.
Interaction with farmers cultivating along the spillway drains to ascertain flooding
incidents that they have encountered.
Sand winning along the drains which could increase the spread of flooding was also
investigated.
2.3 Hydraulic Engineering Services
2.3.1 Design and construction data of Tono Dam reviewed
The hydraulic investigations conducted a review of the hydraulic components of Tono dam as
designed. The hydraulic components reviewed include the Spillway, Spillway chute, spillway
sections and drains.
2.3.2 Integrity of appurtenant structures examined
The assignment investigated issues of erosion around and along the spillway chute,
overtopping of the spillway, erosion or washout at the downstream of the spillway, obstructions
to spillway and other outlets, conditions of control structures, defects in spillway structures,
design capacities of spillways for extreme events and defective drainage systems. These
investigations included site observations, field measurements, physical inspection and
capacity analysis.
2.3.3 Tono Dam channel for flow discharge capability assessed
In order to preserve the integrity of the Dam against overtopping, spillways are provided to
take care of high flows which are likely to harm the dam structurally. The ability to evacuate
the flows depends on the spillway capacity. Since the spillway is already installed, the study
tried to assess the capacity of the spillway against various flows and its ability to safely
discharge the flows without harm to the dam and neighboring surroundings.
2.3.4 Tono Dam downstream conditions assessed and need for emergency concept
ascertained
The downstream conditions for the Tono Dam were also investigated with respect to
emergency situations for the hydraulics of flood evacuation. The spillway condition and
possibilities of blockage in the spillway were investigated. Furthermore, the extent of flooding,
downstream of the dam for various flood scenarios need to be investigated for the downstream
emergency conditions to be assessed. This however, is recommended for future studies as it
requires resources beyond the capacity of this study.
A physical investigation of the downstream end of the project area up to about 1km was
conducted to ascertain the closeness of infrastructure to the stream. It was observed that
majority of the areas are farmlands which are part of the irrigation scheme. The closest
infrastructure to the stream is within a distance of about 70m which is safe for most flooding
scenarios. However further investigation which requires the acquisition of High Resolution
Digital Elevation Models will be able to help provide flooding extents for various emergency
situations needed for an emergency preparedness plan which happens to be beyond the
scope of this assignment.
2.3.5 Installations and instrumentations for Hydraulic Failure assessed
The study also conducted investigations on the existing installations and instrumentations for
regular assessment of potential hydraulic failures in the dam. A physical review was conducted
on the current state of existing installations and an inventory was made on them. Following
that, literature review of dam installations and instrumentations was conducted to help advise
on the best installation and instrumentations for the dam.
2.4 Mechanical Services
The Mechanical Services were performed as follows:
2.4.1 Desk review of data and information on all mechanical equipment on the Tono
dam
Two (2) drawings, Valve Tower and Offtake Arrangements and General Arrangement, Scour
and Water Supply Valve Tower, on Tono Dam were reviewed.
2.4.2 Inspect the inlet and outlet gates and valves of the structures on Tono dam.
All valves were submerged in water so no detailed inspection could be carried out. However,
the visible parts were observed.
2.4.3 Desk review of all operation and maintenance reports of the gates and valves
No written Operation and Maintenance Reports of the gates and valves were available to be
reviewed. Discussions were held with the staff on the maintenance history of the valves.
2.4.4 Desk review of the maintenance plan of all the mechanical components of the
facilities
There is no maintenance plan of mechanical components. Discussions were held with the
operator of the valves who said the stem of the valves, above water, are lubricated before
operation at the beginning of the irrigation season.
2.4.5 Desk review of the manufacturer's instructions and compare to current use and
operation of the components
There were no manufacturers’ instructions on the valves to be reviewed. Information was
obtained from manufacturers of valves such as Cameron, Asahi, AIL, Smith and Engineering
360 and information pertinent to what is available on Tono was obtained.
2.4.6 Examine instrumentation readings for adequacy and analyze for trends as well
as any information that can be deduced from them, propose any additional
instrumentation required
No instrumentation readings were available to be reviewed.
2.5 Review all the dam operator training programs and reports if any
There were no training programmes and reports. There was a list of “Training Needs” which
listed external courses on offer.
3 Major Findings and Implications
3.1 Geotechnical/Dam Engineering Services
3.1.1 Visual Inspection of Dams
Some of the defects identified at this dam site include:
a. Lateral movement of the spillway wall panel resulting from lateral earth pressure on
the spillway channel walls as depicted in Figure 6 and Figure 7 below
Figure 6: Close up of Joint of replaced section of Spillway Wall indicating lateral movement
Figure 7: Joint of replaced section of Spillway Wall indicating lateral movement
b. Widened expansion joint resulting from differential settlement of supports on the scour
tower bridge as depicted in Figure 8and Figure 9 below.
Figure 8: Expansion Joint wider than normal
Figure 9: Change in level at column support due to settlement at hinge support
c. Spalling of concrete within floors of spillway channel
Figure 10: Spalling of concrete in floors of Spillway Channel
3.1.2 Foundation Stability
3.1.2.1 Subsoil Condition
Within the depths explored, the geological successions at this site as revealed by the trial pits
consist of three distinct layers: topsoil of Sandy Silt, underlain by laterised gravel grading to
hardpan and residual soil of micaceous Silty Clay.
The depths of the trial pits ranged from 1.3m – 1.5m. The trial pit logs are presented as figures.
Geo 1 – Geo 3 in the Annex 6.1.1Trial Pit Records
Typical grading curves of the subsoil materials have been plotted and given in Annex 6.1.4.Soil
Test Results
3.1.2.2 Strength Characteristics
The dynamic cone penetration tests (DCPT) results have been plotted and presented in Annex
6.1.3. These tests performed gave very high penetration resistance values (N-values) that
were increasing with increasing depth.
Beneath 0.5m depth below existing ground level, penetration resistance “r” values ranging
from 21 to 70 blows/10cm were recorded upstream whilst beneath 0.4m depth below existing
ground level, penetration resistance “r” values ranging from 17 to 88 blows/10cm were
recorded downstream.
3.1.2.3 Laboratory Results
Tests performed include determination of natural moisture content, Atterberg’s limits, particle
size distribution, California Bearing Ratio (CBR) and compaction test.
All tests were performed in accordance with BS 1377-1990. Summary of laboratory test results
is as presented in Annex 6.1.4 Soil Test Results.
3.1.3 Stability of Embankment
The stability of the existing embankments has been assessed by the following criteria:
3.1.3.1 Slope Protection
3.1.3.1.1 Upstream
Upstream slopes are exposed to wave action and thereby require extensive treatment for
protection. At the Tono dam site, upstream slope protection is ensured by providing riprap
since it appears riprap is the preferred type of upstream slope protection.
Figure 11: Upstream Slope Protection at Tono Dam
A minimum of 300mm thick riprap was measured to have been provided up to the top of dam.
3.1.3.1.2 Downstream
The downstream slope protection at Tono dam site is ensured by vegetative cover as depicted
in Figure 12 below.
Figure 12: Vegetative cover to downstream slope at Tono
3.1.3.2 Surface Drainage
For surface drainage of downstream slope, a system of open paved drains (chutes) along the
sloping surface terminating in the longitudinal collecting drains at the junction of slope is
provided at approximately 50m centre to centre to drain rain water at Tono dam site, as
depicted in Figure 13 and Figure 14 below.
Figure 13: Trapezoidal open paved drain
Figure 14: Trapezoidal open paved drain
The section of drain is trapezoidal having depth of about 30cm. The open paved drains
(chutes) should ideally terminate in the downstream rock toe or toe drain; however, this was
not exactly so at this dam site. They were freely terminated, allowing water to exit freely and
find its own way and thereby has the tendency to cause erosion at the toe.
These drains seemed non-functional at the time of the safety assessment.
3.1.3.3 Engineering Characteristics of Embankment Fill
The engineering characteristics of the embankment fill materials were obtained by testing of
samples at Ghana Highways Authority (GHA) Materials laboratory. The CBR and compaction
characteristics of the embankment fill materials were tested for analysis. The results of these
tests are presented in Section 6.1.4.
3.1.3.4 Geometry of Embankment Section
The designed geometry of the embankment sections made available to the team assessing
the safety of the dam as indicated below.
Figure 15: Cross Section of Tono Dam
As per the design, the core of the embankment fill is made of clay, capped with sand and
gravel filters in succession. These filters are then capped with the riprap.
3.2 Hydrological Services
This section provides the major findings from the hydrological assessment conducted on the
Tono dam. The hydrological assessment provides findings from the electrical resistivity test,
flood risk analysis, hydrological failure modes, and downstream conditions for emergency
situations and instrumentation for dam safety monitoring.
3.2.1 Visual Inspections
The downstream face of the dam wall and its immediate surroundings showed no sign of
wetness or saturation areas. However, a key observation was that a wetland (covering an area
of about 1,250m2) exists about 100m downstream of the dam wall.
3.2.2 Results and Implications of the Electrical Resistivity Test at Tono
The laboratory electrical resistivity result indicated the electrical resistivity of the saturated soil
from the Tono dam was almost the same with resistivity of about 20Ωm. This information was
used in the interpretation of the results obtained from the field electrical resistivity
measurement.
The continuous resistivity profiling was adopted at the Tono dam and the image showing the
about 1km electrical resistivity section is provided in Figure 16. The lower resistivity sections
observed from the beginning of the profile line to about 500 m can be considered to be possible
saturation or seepage zones. The higher resistivities may be possible weathered rock material.
Figure 16: Resistivity Image for Profile along Tono Dam
Low resistivity areas (3.5-30 Ωm) were observed in Tono, signifying points of saturation or
seepage within the earth dam. Physical inspection revealed the creation of wetlands
downstream of the dam which have direct link with the observed points of saturation or
seepage from the resistivity test results.
The rate of seepage in the Tono dam is evident because of the wetland it has created.
The total area of the wetland which can be considered as being a result of seepage is
about 1250m2. Because of the fact that the wetlands are stable with no flows it can be
assumed that the seepage rate is almost equivalent to the rate of evapotranspiration from
the wetlands created by the seepage. From the Ghana Water Resource management
study (1997), the mean annual Potential Evapotranspiration of the Tono area is 1950mm.
With the wetland having an area of about 1250m2, this translates into an average seepage
rate of about 6.68m3/day. This seepage rate is manageable and does not pose any serious
threat to the dam water storage. The seepage observed in Tono doesn’t require any
structural remedies however there is the need for instrumentation to monitor the seepage.
3.2.2.1 Conclusion
The visual inspection and field resistivity measurements have been able to delineate possible
seepage zones which were observed as low resistivity (2-50 Ωm) zones. It can therefore be
concluded based on the resistivity images that the dam is experiencing some amount of
seepage. This confirms the existence of flow paths which are aiding the observed seepage.
3.2.3 Flood Water Evacuation of Tono Dam
The flood risk of the dam was assessed by first estimating the flood water evacuation capacity
of the spillway. The flows of various flood events were compared to the spillway capacity to
determine the risk of the dam to flooding.
3.2.3.1 Spillway design discharge assessment
During large rainfall events, runoff from the catchment areas increases, leading to a large amount of water flows into the reservoir. The potential is that the reservoir level may rise above the dam crest. Therefore, a spillway provides avenues to evacuate the high flows to avoid overtopping of the dam. Floodwater evacuation through the spillway creates an emergency situation in which the discharge could exceed the design discharge. The analysis of the design spillway capacity is shown as follows:
Figure 17: Sketch of an Ogee crested weir spillway
Figure 18: Geometry of the Ogee crest
The discharge of flow is a function of the spillway design parameters Total Head Line (THL).
The spillway of Tono dam is Ogee type [15]. Per design flow conditions, the flow rate per unit
width is given as,
Where
qdes is the flow rate per unit width in m2/s,
Cdes is the design discharge coefficient in m1/2/s and a function of the Ogee-crest shape
Hdes is the upstream design head, in meters, and
is the crest height, in metres.
To estimate the flow through the spillway, equation (2) provides determination of the design
discharge coefficient by assessing the ratio of crest height to the upstream design head over
the crest height. The design discharge coefficient, Cdes of Ogee crest is presented graphically
in Figure 19
width is given as,
Where
qdes is the flow rate per unit width in m2/s,
Cdes is the design discharge coefficient in m1/2/s and a function of the Ogee-crest shape
Hdes is the upstream design head, in meters, and
is the crest height, in metres.
To estimate the flow through the spillway, equation (2) provides determination of the design
discharge coefficient by assessing the ratio of crest height to the upstream design head over
the crest height. The design discharge coefficient, Cdes of Ogee crest is presented graphically
in Figure 19.
Figure 19 Graph of discharge coefficient against ratio of crest elevation to upstream head over crest
elevation
Now the Design flood level = 181.69 m
Top water level = 179.22 m
Spillway crest height = 3 m
Therefore, spillway ground level/elevation = (179.22 – 3) m = 176.22
Spillway Design Head, Hdes = Design flood level – Spillway ground level
= (181.69 – 176.22) m
= 5.47 m
Therefore,
From Figure 19, 1.2145 corresponds to a design discharge coefficient, Cdes of 2.146 m1/2/s.
Applying equation (2), the design discharge per unit width is given by,
qdes = 2.146 x (5.47 – 3)3/2,
= 2.146 x (2.47) 3/2 = 8.292 m2/s
The total design discharge, Qdes (m3/s) through the spillway is obtained by multiplying the
design areal discharge, qdes (m2/s) by the width of the weir crest, 60m. The total design
discharge is given by,
Qdes = qdes x 60m
= 8.292 x 60
= 497.5 m3/s
Therefore, the total design discharge of the Tono spillway is estimated to be 497.5 m3/s. The
Dam owner provided 496 m3/s as design discharge of spillway. The estimated design
discharge of spillway compares to the figure provided, recognizing the margin of 1.5 m3/s.
Henceforth, the estimated discharge will be used in the discussions following.
3.2.3.2 Historical Flood Analysis
ICOUR provided historical water levels of the reservoir for the years 2010 to 2018 which is
shown in Figure 20. The graph shows that out of the 9 years of record, there has been spillage
5 times with none reaching the design flood level. Meanwhile the flood occurs within one
month to three months. From the chart it is obvious that the 2012 flood event is the most
severe in recent times. It is therefore important to find out on the impact of the 2012 spillage
on the downstream inhabitants of the dam and also to find out on previous and more severe
flooding and their impacts as well. In doing so, the historical rainfall of the area was analysed
to determine the very wet years and interrogate the flooding impact of those periods.
Figure 20 Daily Reservoir Water levels of Tono from 2010 to 2018
Historical rainfall analysis of the area (from 1961-2005), as shown in Figure 21, provides the
major rainfall experienced in the area since the construction of the Dam was in 1991, which
was equivalent to a 50-year return period rainfall. Interacting with management of the dam on
how the 1991 rainfall affected the operations of the dam, they noted that most of them were
not at post at the time and no record to that effect was available. However, on the recent floods
(2009 and 2012), they indicated those events were manageable, noting that those floods did
not create any severe impact on the downstream communities of the dam.
Figure 21 Historical Annual Rainfall at the Tono Dam
Therefore, with the prevailing conditions until today the integrity of the dam is proven, and the
spillway has performed its function as required. It can be noted, however that, the dam is yet
to experience any extreme flood event that threatens the safety of the dam and life and
property of downstream inhabitants. The records of the dam levels show that, the spillage
experienced so far in the dam is not up to the spillway design capacity.
3.2.3.3 Flood Risk Analysis
The flood risk assessment conducted on the dam was able to provide the Peak inflows for the
dam for the 20, 50, 100, 200, 1000 and 10,000 year return periods. The results are shown in
Table 3.
Table 3: Peak Daily Flows of Tono Dam
Return Period (year) Discharge (m3/s)
20 369.2
50 424.7
100 466.4
200 507.8
1000 603.9
10,000 901.4
A graph of the spillway discharge against the elevation of the water level at the spillway (Figure
20) was also plotted to assess the vulnerability of the dam to various flood events. The design
flood discharge of the spillway is about 497.5m3/s which coincides with the design flood level,
at a height of about 2.48 m above the spillway crest. The height of spillway wall above the
crest is about 3.4m, a little below the Top of Embankment of the dam.
Clearly, at a return period of 200 year and beyond, the design flood level will be exceeded and
the spillway capacity will be challenged to pass the floods associated, where reservoir is full.
Figure 23 Tono Dam Spillway rating curve
Beyond the design flood level, any flood wave will pose serious threat to integrity of the dam.
3.2.3.4 Flood Routing
Reservoir flood routing determines the outflow hydrograph from a given inflow hydrograph and
known reservoir characteristics. It is often accomplished by means of hydrologic routing, which
is a method that considers the reservoir as a lumped system and computes the flow as a
function of time at the reservoir outlet. The outflow from the reservoir is computed as a function
of the water level, which is itself a function of the stored volume in the reservoir.
The flood routing hydrograph for the design flood event (1 in 1000 and 1 in 10,000 year) was
routed through the reservoir, based on the standard weir discharge equation and the level-
storage relationship for the reservoir. The reservoir was assumed to be full at the start of the
event.
Table 4: Flood risk analysis of Tono Dam
Reservoir
Peak
Flood (1
in 1000 or
10000)
(m3/s)
Water
level above
spillway
crest (m)
Embankment
Freeboard
from water
level Crest
(m)
Freeboard of
Maximum
flood Level to
Top of Wave
wall (m)
Remarks
Tono
603.9 2.81 0.54 1.17
The design freeboard of
embankment is 0.9m which
will be reduced to about
0.5m at this level of flow. The
spillway channel with height
of about 3.4m is adequate to
pass the flood waters.
Therefore, spillway is
adequate, implying dam is
safe for 1 in 1000 year flood
741.0 3.22 0.13 0.76
The design freeboard of
embankment is 0.9m and
will reduce to about 0.13m
at this level of flow. The
spillway channel with height
of about 3.4m is adequate to
pass the flood waters.
Therefore, flow is expected
not to overtop the spillway,
making it adequate, to pass
the 1 in 10000 year flood.
The flood routing of the dam was estimated to determine its impact on the embankment of the
dam. Table 4 shows the peak inflows and implications for spillway to transport the flood waters
while assessing the likely impacts on the dam. Without considering flood attenuation, it is
observed that even though a 1000-year flood discharge is greater than the design flood
discharge of the spillway, the maximum flood level and wave run-up level in the spillway leaves
a free heard of about 1.17m to the top of wave wall and 0.54m to the embankment. This implies
that, there will be no overflow above the wave wall of the spillway in the case of a 1000-year
flood. Similarly, in the event of 10,000-year flood, the maximum flood level and wave run-up
level without considering flood attenuation leaves a free heard of 0.88m to the top of wave
wall and o.13m to the embankment. This implies that, there will be no overflow above the wave
wall of the spillway in the case of a 10,000-year flood. Therefore, without considering reservoir
flood attenuation in the extreme event of the occurrence of a 10,000- year flood, the Tono dam
is safe.
Table 5: Flood inflows and outflows from the spillway considering Reservoir Attenuation
Reservoir Inflow (m3/s) Outflow (m3/s) Attenuation
Tono 603.9 302 50%
741.2 370.6 50%
In a previous study conducted by Norconsult in association with Mott McDonald Ltd and
Watertech Ltd on the Vea in 2007 a flood attenuation of 50% was used for the reservoir flood
routing of the dam. Applying the flood attenuation to the Tono dam the outflows through the
spillway are reduced by half. The inflow and outflow peaks for the design flood events of 1000-
year and 10,000-year return, together with the degree of attenuation, are shown in the Table
5. Basically, the attenuation is the temporary storage of the inflows before they are released
through the spillway. This storage has the potential to reduce the rate of outflow through the
spillway. Therefore, applying the flood attenuation of 50% to the inflows and comparing to the
spillway characteristics of the makes the Tono dam safe for both a 1000-year and 10-year
extreme flood event, because the spillway is capable of conveying the flows.
3.2.4 Hydrologic failure mode of the Tono Dam
The hydrologic failure modes likely to occur in dams include cavitation damage, boils/piping,
soil/rock erosion, seepage/leakage, spillway chute wall overtopping, stilling basin sweepout,
stagnation pressures, concrete failure, dam slope stability, trees and rodent activity, flooding,
slump and cracks (Figure 24). The existence of the failure modes were determined from the
electrical resistivity test, physical investigations and flood risk analysis conducted. The results
from the flood risk analysis have been discussed in previous section. The study could not rely
on piezometric readings because there were no records.
Figure 24: Common failure mechanisms of Dams (Source: Dam Safety Manual of Ghana)
The major findings on the hydrological failure modes are presented as follows:
3.2.4.1 Seepage/Leakage
The field investigations of the Tono dam observed the presence of wetlands about 100 m
away from the toe of the dam downstream. Further interrogations revealed that, these
wetlands are not as a result of waste water from canals. This is because in the dry season,
one expects a very dry condition in such areas. One of the possible reasons for the wetlands
is the result of seepage or leakage. Further physical investigations did not reveal any seepage
or leakage at the toe of the dam. The electrical resistivity test was conducted to help give
further proof to the presence of seepage in the dams. The geophysical investigations revealed
that seepage exist in the dam, stretching along 40% of the Tono Dam. Coincidentally, the
locations of the seepage areas fall in line with the areas of the wetlands downstream of the
dam. This confirms that there is seepage taking place in the dam. The seepage rate of the
Tono Dam is 6.68m3/day
3.2.4.2 Presence of Pipes/Boils and Cracks
The electrical resistivity revealed portions of low resistivity in the dam, which indicates the
presence of water in those sections of the dam. Physical investigations on the dam did not
observe any cracks or pipes and most especially at the locations of the low resistivity.
The major finding is that there are flow paths in the dam which are contributing to the seepage
observed in the dam.
3.2.4.3 Displacement of Riprap/Soil Erosion
The displacement of the riprap in dams occurs at the upstream end of the dam. This affects
the structural integrity of the dam. The continuous displacement of the riprap at the upstream
face of the dam will expose the clay and laterite materials to the harsh waves of the reservoir
leading to erosion of the dam and subsequent failure. The Tono Dam has no such challenges
and it is in a good condition.
Soil erosion occurs in dams and most especially the downstream face of the embankment
which usually has no riprap. Soil erosion if not taken care of can develop into gullies and
become paths for dam destruction. Gullies due to erosion were observed in the Tono dam
(Figure 24).
Figure 24: Gullies on the downstream embankment of Tono dam due to Soil Erosion
The upstream investigations conducted on the dam indicate that, the Tono reservoir
catchment is highly susceptible to sedimentation due to the heightened recession farming
along the shores of the reservoir. There is little vegetation along the reservoir shore line to
reduce the sediment flows into the dam.
3.2.4.4 Trees and Rodent Activity
The activities of rodents and the penetration of the roots of trees can aid in providing avenues
for piping in dams. Investigations conducted indicate that, trees are controlled on the dam.
Some tree stumps were observed on the dam, but they are prevented from growing tall. Efforts
should be made to remove the tree stumps as the roots can still develop deeper into the dam.
A summary of the findings identified from the investigations conducted on the failure modes is
provided in Table 6.
Table 6: Hydrologic Failure Mode of Vea and Tono Dams
Failure Mode Observations Remarks
Tono
Flood Risk Analysis
The Tono Dam and spillway capacity is capable of handling 1 in 1000 year flood event without any harm to the Dam.
The current Dam condition is safe for the worst case flood scenario for the dam.
Seepage or leakage
Wetlands observed beyond the Toe of the Dam. Seepage zones in the dam were confirmed from the Electrical Resistivity Test.
Piezometers installed in Tono are not being monitored.
Boils, Piping or Cracks
The seepage zones observed in the Dams give indication of flow paths. No pipes, boils or cracks were observed.
There was no physical observation of pipes, boils or cracks.
Displacement of Riprap/ Soil Erosion
The upstream face is safe with no signs of displacement of riprap
Sections of the downstream face of dam experiencing gully erosion. Some are deep and need immediate attention
There is the need for routine checks for the upstream and downstream slopes and regular maintenance schedule.
Trees and Brush Rodent Activity
Shrub observed in both faces of the dam. No big trees growing on the faces of the dam. No rodent activity observed.
Routine Maintenance schedule should take care of trees and rodent activity.
3.2.5 Tono Dam upstream and downstream conditions
From the field investigations conducted, it was observed that, at Tono recession agriculture is
seriously practiced along the banks of the reservoir which has the tendency to increase the
rate of siltation of the dam. Efforts must be made to improve the protection of the upstream
catchment of the Tono dam.
3.3 Hydraulic Engineering Services
This section reports on the findings of the hydraulic components and functions of the dam in
relation to the safety of the Tono Dam. An overview of the integrity of the spillway and
appurtenant structures are provided firstly followed by the assessment of hydraulic failure
modes, downstream conditions and the conditions installations and instrumentations.
3.3.1 Integrity of appurtenant structures
3.3.1.1 Outlet Structure
The outlet structure looks properly constructed and no leakages were observed
Figure 24: Outlet Structure
3.3.1.2 Spillway
The integrity of the spillway chute and walls of the Tono dam is very sound. One observation
made was the tilting of a section of the Spillway Chute Wall which was reconstructed. The tilt
is as a result of earth pressure behind the wall panel. This section requires regular observation
in order to determine when to replace it.
The stilling basin of Tono is also sound and has no defects. However, it was observed that, a
broken section of the spillway wall, is comfortably sitting on the stilling basin acting as a
blockage to the water flow which reduces the spillway capacity at the stilling basin (see Figure
25). The broken wall must be removed from the stilling basin to allow full capacity of the
spillway.
Figure 25: Obstruction of the Spillway at the stilling basin of the Tono Dam from a broken channel wall.
3.3.2 Hydraulic Failure Modes of the Tono Dam Assessed
There are key hydraulic factors that can affect the integrity of the dam and cause failure. These
factors include cavitation damage, spillway chute wall overtopping, stilling basin sweepout,
stagnation pressures and concrete failure. The failure modes have been assessed for the dam
and are described as follows. A summary is also presented in Table 7.
3.3.2.1 Cavitation Damage
Cavitation is the result of critical combination of velocity, pressure, vapor pressure, bumps and
unevenness on the concrete surfaces, which causes a deviation in the water flow lines and
decreases the pressure in some areas. When water flows over a dam spillway, the
irregularities on the spillway surface will cause small areas of flow separation in a high velocity
flow, and, in these regions, the pressure will be lowered. If the velocities are high enough the
pressure may fall to below the local vapor pressure of the water and vapor bubbles will form.
When these are carried downstream into high pressure region the bubble collapses giving rise
to high pressures and possible cavitation damage (Nohani et al., 2013).
No cavitation damage was observed at Tono.
3.3.2.2 Spillway Chute Wall Overtopping
If the spillway chute is subjected to discharges larger than the design discharge or air bulking
or cross waves were not incorporated properly into the design, flow depths in the chute will
increase and the walls may overtop. Overtopping flows will likely initiate erosion in the wall
backfill which has the potential to progress to the point of undermining the spillway chute slab
and failing the invert of the spillway. Once this occurs, headcutting can initiate and progress
upstream, ultimately leading to a breach of the reservoir (Bureau of Reclamation, 2015).
No signs of spillway chute wall overtopping were observed for Tono.
3.3.2.3 Stilling Basin Sweepout
Stilling basins are used to dissipate the energy of water exiting the spillway of a dam. Their
purpose is to prevent scouring that occurs when high-velocity water enters the downstream
reach of the dam. This scouring can damage the foundation of the dam, and also causes
severe erosion downstream. The primary method of dissipating energy is to generate a
hydraulic jump to transition flow from supercritical to subcritical.
The stilling basin of the Tono dam is made up of boulder pack with sizes ranging from 450-
900cm. Because of the low head between the Spillway crest and stilling basin, the velocity
generated is not too high and as such, the boulder pack are able to dissipate the energy safely
without any harm to the dam.
The Tono spillway basin sweepout is located about 550m downstream of the chute and has
free standing baffle blocks about 20m before the end sill constructed with boulder packs.
3.3.2.4 Stagnation Pressures
Stagnation pressure related to spillway failures can occur as a result of water flowing into
cracks and joints during spillway releases. If water entering a joint or a crack reaches the
foundation, failure can result from excessive pressure and/or flow into the foundation. If no
drainage exists, or if the drainage is inadequate, and the slab is insufficiently tied down, the
build-up of hydrodynamic pressure under a concrete slab can cause hydraulic jacking. If
drainage paths are available, but are not adequately filtered, erosion of foundation material is
possible and structural collapse may occur (Bureau of Reclamation, 2015).
The investigations revealed that, there is lateral pressure on a section of the Spillway chute
wall that has tilted. The tilting has created a gap where seepage can take place between the
wall joints and therefore has the tendency to affect the foundation of the wall at that section.
This is what led to the failure of the previous wall. Attention must be given to that portion of
the Spillway chute wall and replaced in the near future.
3.3.2.5 Concrete Failure
Concrete failure can result from cracks, corrosion of reinforcement, bulking, sagging of slabs,
erosion/exposure of foundation and displacement of walls. The physical observation made
showed that, the integrity of the concrete was still intact. Using a Schmidt Hammer test to
investigate the concrete strength of the spillway structure reveals a concrete strength of
52.5kN/m2 which is adequate because it is greater than allowable strength of 35kN/m2. The
result shows adequate strength and it’s consistent with the age of the structure.
A summary of the findings on the hydraulic failure modes is provided in Table 7.
Table 7: Hydraulic Failure Mode of Tono Dam
Failure Mode Observations Remarks
Cavitation Damage
There is no cavitation damage at Tono
The dam is safe from cavitation damage
Spillway Chute Wall Overtopping
No observation on the possibility of chute wall overtopping for Tono
The dam is safe from Spillway Chute wall overtopping
Stilling basin sweepout
The Tono dam is adequately designed to take care of the stilling basin sweepout.
The dam is well designed to take care of hydraulic pressures at the stilling basin.
Stagnation pressures
Lateral pressure observed at the section of the chute wall that has tilted.
Attention should be given to openings in the wall of the spillway chute.
Concrete Failure
The concrete structure is sound. Tono has no challenges with concrete strength.
3.3.3 Tono Dams downstream conditions
Assessing the downstream conditions of the spillways of the dam, it was observed that, the
spillway drain is in good shape and as such can channel flows safely from the dam without
obstructions. There is the need to however, prepare flood inundation maps for various flows
in case of emergency situations such as dam break which will be useful for emergency
preparedness plan.
3.4 Mechanical Services
3.4.1 Desk review of data and information on all mechanical equipment
A study of drawings on Tono indicated two sets of valves. They are in the Off-take Tower and
the Scour Tower.
3.4.2 Inspection of the inlet and outlet gates and valves
3.4.2.1 Off Take Tower
The Off take Tower houses two valves in series, a 900 mm Gate valve and a 900 mm Butterfly
valve. The Gate valve is used for opening and shutting the water supply for irrigation. The
Butterfly valve is used for regulation. The Off-take Tower is in the middle of the dam wall, if
viewed in cross section, 2200 mm from the center line of the dam, upstream.
The Gate valve leaks from the valve body into the Off-take Tower well, housing the valves.
The Tower walls also leak into the well, keeping the valves constantly under water.
3.4.2.2 Scour Tower
The second set of valves is in the Scour Tower, thirty meters into the reservoir. It houses four
valves. One is a 1200 mm gate valve, called Scour Valve. The scour valve is used for flushing
silt from the reservoir. Inspection revealed that the scour pipe has been blocked at the
discharge end. This was done after the dam construction when leakage was found from the
scour valve. It is therefore blocked permanently
The tower also houses three (3) 400 mm valves for water supply for domestic purposes. It
takes water at three different elevations into a 400 mm pipe.
The tower leaks through the walls and therefore the valves are submerged in water.
Figure 26: Scour Pipe Outlet Structure
Figure 27: Scour Pipe Outlet Structure blocked with Clay
3.4.3 Operation and Maintenance
No written Operation and Maintenance Reports of the gates and valves were available to be
reviewed. Discussions held with the staff on the maintenance history of the valves revealed
that the glands are not checked for leakage, and they are permanently submerged in water.
3.4.4 Maintenance plan
There is no maintenance plan of mechanical components. Discussions were held with the
operator of the valves who said the stem of the valves, above water, are lubricated before
operation at the beginning of the irrigation season.
3.4.5 Manufacturer's Instructions
There were no manufacturers’ instructions on the valves to be reviewed. Information was
obtained from manufacturers of valves such as Cameron, Asahi, AIL, Smith and Engineering
360 and information pertinent to what is available on Tono was obtained as follows:
3.4.5.1 Gate Valve Function
Gate valves are primarily designed for on-off services. They are best used in systems which
require infrequent use of the valve. The valves are designed for full-area flow to minimize the
pressure drop. Since most of the flow change occurs near the shutoff, the relatively high fluid
velocity causes disk and seat wear and eventual leakage if the valve is used to regulate flow.
3.4.5.2 Butterfly Valve Function
A butterfly valve is from a family of valves called quarter-turn valves. In operation, the valve
is fully open or closed when the disc is rotated a quarter turn. The "butterfly" is a metal disc
mounted on a rod. When the valve is closed, the disc is turned so that it completely blocks
off the passageway. When the valve is fully open, the disc is rotated a quarter turn so that it
allows an almost unrestricted passage of the fluid. The valve may also be opened
incrementally to throttle flow.
3.5 Instrumentation
The study conducted assessed the installations of monitoring devices for dam safety. At Tono,
we found twelve observation wells at the Toe of the dam (Figure 28), however seven of them
had been filled with sand and the remaining five had no piezometers installed (Figure 29 and
Figure 30). During the field investigations we also came across three Piezometers installed
on the downstream face of the dam. Further investigations revealed that, there are no data
collections available on the piezometer readings and they are currently not functioning.
Figure 28: Location of the 12 observation wells at the toe of the Tono Dam
Figure 29: Non-functioning observation wells at the Tono Dam
Figure 30: Observation wells at the Tono Dam
3.5.1.1 Record Keeping
The general observation is that operating records are not gathered and kept.
3.6 Dam Operator Training
It was observed that ICOUR did not have an “in-house” training programme. There were no
training reports. Two lists of “Training Needs” which listed external courses on offer for 2016
and 2017 were provided as the training for the staff. (See Section 6.7.2)
A review indicated that there was no technical training for 2016. Technical training listed for
2017 were: Irrigation Water Management for Field Officers and Best Agronomic Practices.
These did not have any institution offering them and there were no dates for them.
4 Conclusions
4.1 Geotechnical/Dam Engineering Services
The Tono Dam in its current state can be described as safe and sound.
4.1.1 Dam Foundation
The trial pits and DCPT results have shown that the foundation of the dam at Tono is very
compact, stable and adequate. In particular, no unsuitable soil material was encountered
within the depths explored and the subsoil materials possess sufficient bearing strengths.
4.1.2 Stability of Embankment
The embankment at this dam site may be described as very stable and safe based on the
following criteria:
The adequacy of the slope protective measures at both upstream and downstream
faces,
Absence of both longitudinal and transverse cracking which are generally caused
by differential settlements or deformations in the foundation, abutments or adjacent
materials within the embankment, and
The adequacy of the embankment section and embankment fill materials.
The ability to safely pass flood flows due to the adequacy of spillways which
precludes excessive pore fluid pressure build up under all conditions of
environment and operations.
4.2 Hydrologist Services
4.2.1 Flood risk of the Tono Dam
The hydrological investigation concludes that the Tono dam is safe for flood events up to 1 in
a 1000-year event. The spillway capacity is adequate.
4.2.2 Hydrologic Failure Mode of Tono Dams
The hydrological investigations assessed the various hydrologic failure modes and conclude
as follows on the various failure modes:
4.2.2.1 Seepage/leakage:
There is seepage in the dam. The seepage effects are observed about 100m downstream of
the Toe of the dam where wetlands have been created.
4.2.2.2 Presence of Pipes/Boils and Cracks:
There are no pipes, boils and cracks in the dam although seepage is present, which is normal
with earth dams.
4.2.2.3 Soil/Rock Erosion
There is lack of maintenance on the dam hence the deep gullies present on the downstream
side.
The Tono dam is not experiencing any riprap displacement at the moment.
4.2.2.4 Trees and Rodent Activity
Trees are controlled on both faces of the dam, and prevented from growing tall.
4.2.2.5 Upstream and Downstream conditions of Tono Dam
Siltation is enhanced and will increase in the Tono dam due to the massive flood recession
agriculture taking place at the upstream section of the dam.
4.3 Hydraulic Engineering Services
4.3.1 Integrity of the Spillway and Appurtenant Structures
The following conclusions are drawn from the findings on the spillway and appurtenant
structures at Tono:
The integrity of the spillway chute and walls of the Tono dam are very sound.
The tilted section of the spillway chute wall panel shows signs of lateral displacement
as a result of earth pressure.
The stilling basin of Tono is sound.
The spillway capacity at the section of the baffle blocks at the stilling basin is reduced
due to the broken section of the spillway chute wall which is sitting comfortably on the
blocks
The outlet structure is sound.
4.3.2 Hydraulic Failure Modes of the Tono Dam
4.3.2.1 Cavitation Damage
There is no cavitation damage.
4.3.2.2 Spillway Chute Wall Overtopping
There are no signs of spillway chute wall overtopping.
4.3.2.3 Stilling Basin Sweepout
The stilling basin of the dam is adequately designed and is sound.
4.3.2.4 Stagnation Pressures
No Stagnation pressure was observed at Tono Dam spillway.
4.3.2.5 Concrete Failure
The concrete strength of the dam is adequate.
4.3.3 Downstream conditions of Tono Dam
The spillway channel is in good shape and can direct flows safely from the dam without
obstructions.
4.4 Mechanical Services
4.4.1 Valves
There are two main types of valves at Tono, gate and butterfly valves.
At Tono, the valves are used appropriately as designed. The safety issue is the leakage of the
gate valve as well as tower walls leaving the valves submerged continuously. Apart from the
inconvenience of having to work in water, there is the danger of drowning in some cases.
An issue at Tono is the end of the pipe from the Scour Tower being blocked.
4.5 Instrumentation
There are twelve observation wells at the Toe of the dam, however seven of them have been
filled with sand and the remaining had no piezometers installed.
Three Piezometers are installed on the downstream face of the dam wall. (These are distinct
from the observation wells). There are no data collections available of the piezometer readings
and they are currently not functioning.
4.5.1 Record Keeping
The general observation is that record keeping at the Tono Dam is non-existent. The
information is not gathered in the first place to be kept.
4.6 Dam Operator Training It would be necessary to give the staff technical training as well as training in the importance
of record acquisition and management.
5 Recommendations
5.1 Geotechnical/Dam Engineering Services
The following recommendations have been developed based on the findings of the visual
inspection at the dam sites and results obtained from the field and laboratory tests.
5.1.1 Visual Inspection
All structural and non-structural defects identified during the visual inspection and indicated in
this report by our team at this dam site should, as a matter of urgency, be rectified.
5.1.2 Stability of Embankment
The non-functional system of open paved drains (chutes) along the sloping surface for surface
drainage of downstream slope must be re-instated or re-constructed.
5.1.3 Regular Visual Observations
Regular visual observations are an essential aspect of a program for monitoring long-term
performance. In fact, visual observations by dam staff, trained to look for seeps, boils, shallow
sloughing, cracks or any other signs of distress, to log their observations, and to inform or
contact the responsible engineer when appropriate, is the primary approach to monitoring
long-term performance of the dams. The visual observations should include the spillway and
abutments.
If visual observations indicate a potential problem, it may be necessary to initiate a quantitative
monitoring program to define the problem and assist in selecting a solution.
5.2 Hydrologist Services
Data collection on spillage and all water uses should be prioritized
The seepage of the dam should be monitored
There is the need to prepare flood inundation maps for various flows in case of
emergency situations such as dam breach. The maps will be useful for emergency
preparedness planning.
The dam owner/operator should reinstate the drainage system to ensure the smooth
drainage of the dam and ensure the stability of the dam.
5.3 Hydraulic Engineering Services
The tilted chute wall at Tono spillway should be given special attention and repaired
The old broken wall must be removed from the spillway channel.
The dam operator should keep close monitor the development of the joint and make
necessary treatment when necessary
5.4 Mechanical Services
5.4.1 Off Take Tower
The area around the valves must be dewatered and kept dry at all times.
The 900 mm gate valve with body leakage must be replaced.
The leakage from the walls of the Off-Take Tower should be stopped.
5.4.2 Scour Tower
The well should be dewatered and kept dry at all times
The leakage from the walls of the Scour Tower must be stopped.
The blocked outlet of the Scour pipe should be cleared if found necessary and convenient.
The water supply valves and pipes should be kept in good condition for future use.
5.4.3 Operation and Maintenance (O & M)
We recommend a combination of routine and periodic maintenance programs for optimum
operation of the dams and as a means of continuous safety as follows:
5.4.3.1 Daily Inspections
- Leveling Staff to check markings of scale
- Outlet/control valves to check blockage or restrictions
- Walkway to the Scour Tower
5.4.3.2 Weekly Inspections
- Observation wells to check for seepage or leakage - During filling of the reservoir, downstream slope of the embankment and the
foundation downstream from the embankment should be carefully inspected for
indications of cracks, slides, sloughs, subsidence, impairment of slope protection,
springs seeps, or boggy areas caused by seepage from the reservoir.
- Upstream slope of embankment after periods of sustained high velocity winds and
draw down of reservoir water surface for evidence of cracks, slides, sloughs,
subsidence or damages to the slope protection such as displacement of riprap or other
sighs of serious erosion
- Channel bank or bed erosion and silting
- Condition of riprap areas
- River aggradations or degradations and possible effect on hydraulic operation of
structures involved.
- Abnormal subsidence of backfill of embankment areas.
- Unusual or inadequate operational behaviour.
-
5.4.3.3 Quarterly Inspections
- Dam catchment and reservoir fringes to check river aggradations or degradations.
- Condition of the embankment slopes and the crest.
- Presence and conditions of undergrowth in bottoms and on sides of channels and
estimated effect on tail-water levels
5.4.3.4 Semi-annual inspections
This inspection is expected to be carried out following the rainy season and before onset of
the next rainy season:
- Spillway crest, channel or stilling basin, baffle piers and abutment - Downstream embankment to check for erosion/gullies - Concrete wave wall to check for settlement - Rip Rap for any displacements - During periods of low reservoirs level, the exposed portions of the abutments and the
reservoir floor should be carefully examined for sinks or seepage holes or cracking
5.4.3.5 Maintenance and Operational Schedules (Electrical, Mechanical, Structural
and Dam Instrumentations)
Component Maintenance Activity Frequency
Embankment Vegetation control
Rodent control
Minor earthwork, erosion repair
Erosion protection
Twice per year, minimum
Check once per year, perform as required
Check once per year, perform as required
As required
Spillway Vegetation control
Minor earthwork, erosion repair
Erosion protection
Concrete repair
Twice per year
Check twice per year, perform as required
Check twice per year, perform as required
As required
Intake/Outlet
structures
Trashrack cleaning
Mechanical operation
Internal conduit inspection
Concrete features inspection
After every major storm
Once per year
Once per year
Once per year
Masonry walls Vegetation control
Missing stones
Twice per year
As required
Miscellaneous
Safety
and Access
Features
Vehicle/pedestrian access
route(s) maintenance
Fences, locks, signs inspection
Once per year
Once per year
Valves Routine Maintenance Once per year
Gates Routine Maintenance Once per year
5.5 Record Keeping
Monitoring and surveillance results should be recorded and the records should be kept for
documentation. The data/information should be analyzed, evaluated and reported. The
reports should be also documented. The Dam Operator Training in Section 5.7 below is to
enhance the ability of personnel in record keeping.
5.6 Instrumentation
The filled Tono dam observation wells should be reinstated and piezometers installed
5.6.1 Piezometers
These are used to monitor pore and joint water pressures. Open standpipe piezometers are
generally considered to be more reliable than other types.
A summary of guidance on the selection and use of various types of instrumentation is
presented in Table 8 below.
Table 8: Measurements and Instruments for long term Performance Monitoring
Measurement Type Recommended Instruments
Leakage emerging downstream Leakage Weirs
Performance of relief wells Open standpipe piezometers
Pore Water pressure Open standpipe piezometers
Reservoir Water Levels Staff Gauge
Stage Flow in Spillway Staff
Gauge
5.7 Dam Operator Training It is recommended that the Management and Technical Staff are attached to a similar facility
to acquire knowledge in good record acquisition and management. Training should cover the
following:
Structural, mechanical and dam instrumentations and data acquisition.
Inspection, Maintenance and repair works procedures.
Record keeping and data management.
Irrigation water management.
GIS and remote sensing applications to catchment area management including
planning and monitoring.
Negotiation, conflict resolution and stakeholder engagement.
Report writing and communication.
Monitoring and recording of Dam Seepage
6 Annexes
6.1 Geotechnical Annexes
6.1.1 Trial Pit Records
6.1.2 Grading Curves
6.1.3 Dynamic Cone Penetration Test (DCPT) Results
6.1.4 Soil Test Results
6.2 Terms of Reference
6.3 Work Plan
Schedule for Safety Assessment of Tono and Vea Dams
6.4 Field visits schedule
Schedule of Site Visits
1st Visit 2nd Visit
Designation Date Date Date Date
Mechanical Engineer 26/2/17 29/2/17 27/3/17 30/3/17
Geotechnical Engineer 26/2/17 29/2/17 28/3/17 4/2/17
Hydraulic Engineer 27/2/17 29/2/17 21/3/17 25/3/17
Hydrologist 26/2/17 29/2/17 21/3/17 25/3/17
6.5 List of Stakeholders met during field visits
List of Participants at Meeting Held at ICOUR Headquarters
No, NAME DESIGNATION ORGANIZATION CONTACT Email
1 Sebastian Bagina Ag. Managing
Director
ICOUR Ltd. 0205358328 [email protected]
2 Peter Agao Finance & Admin.
Mgr
ICOUR Ltd. 0244890165 [email protected]
3 Agartha Akurugu HR Officer ICOUR Ltd. 0502523292 [email protected]
4 David Atijana Asst, Irrigation Eng. ICOUR Ltd. 0208815494
5 Peter Wilkens T.L. SMEC SMEC 0554450111
6 Zoogah
Augustine T.
Field Extension
Officer
ICOUR Ltd. 0205989780 [email protected]
7 Agonnor Ben. Technical Officer ICOUR Ltd. 0209478817
8 Atunya Andrew Field Cashier ICOUR Ltd. 0208504392
Contractor met at Vea Dam undertaking Rehabilitation Work
No, NAME DESIGNATION ORGANIZATION CONTACT
1 David Mbema Site Engineer Proteos Limited 0266464055
6.6 Minutes of Meetings
Minutes of Meetings held at ICOUR HQ, Tono in the
Upper East Region on 27 & 28 February 2017
Agenda of the meeting:
- Introduce the Tono and Vea Dams assessment team to Management of the
facilities and matters arising.
- Discuss the staff strength and training needs.
- Take delivery of documentations to facilitate reporting on the assignment.
- Tour the facilities to ascertain the operations and maintenance of the dams and
appurtenant structures.
Participants at the Meeting:
ICOUR Management Team - Ag. Managing Director: Sebastian Bagina; HR
Officer: Agartha Akurugu; F & A Officer: Peter Agao; Asst. Irrigation Engineer:
David Atujona; Field Cashier: Andrew Atuuya; Field extension Officer:
Augustine Zoogah & Technical Officer (Water Bailiff): Ben Agonnor.
SMEC Team Leader: Robert Wilkens
IPC Team: Stephen Doku, Joseph Suwiir, Maxwell Boateng-Gyimah, Eric
Ofosu Antwi (PhD).
Minutes and key action points noted:
1/ ICOUR Management welcomed the Tono and Vea Dams safety assessment team
to the institution premises, noting that they had received news of the visiting team.
They pledged their support for the process.
2/ Ing. Stephen Doku presented the purpose of the Dams safety assessment for which
reason the team was in the area to undertake reconnaissance survey of the
facilities. He noted further that the preliminary study will be conducted in 2 days and
thanked ICOUR management for the support pledged.
3/ Ag. Managing Director explained the inception of the Tono and Vea Dams
management company, ICOUR. Their mandate was spelt out including (i) operation
and maintenance of the dams; (ii) provision of extension and agronomic services to
farmers; (iii) provision of irrigation water to farmers; (iv) provision of credits and
market facilitation services to farmers; and (v) provision of mechanical services to
farmers.
However, with the GCAP intervention, it seeks to rehabilitate and modernize the 2
schemes in order to (i) improve the infrastructure; (ii) restructure the management
for sustainable development; (iii) Establish Water User Associations (WUAs) and
strengthen their capacities to participate actively in the operation and maintenance
of the schemes and (iii) reduce management operations to bring on board private
sector participation, and thus focus on (a) maintenance of the irrigation schemes;
and (b) provision of water services to farmers.
4/ On staffing and their capacity needs, the Ag. Manager noted a resized outfit from
138 to 42 staff, reducing by about 70%. The organogram is attached annex 1.
However, ICOUR is operating currently at a staffing level of 31. He indicated that
the mode of training of field staff was largely on-the-job training. Others included (i)
soil and irrigation water management (ii) maintenance of irrigation systems. The
team shared concerns of their inability to have the required technical training,
especially for their senior staff and would appreciate if those could be addressed.
In the nutshell, there was the need to formalize the training.
5/ SMEC Rep. noted that he received design drawings from GCAP/GIDA without as-
built drawings. He was candid to share with the dams safety assessment team, but
at a fee.
6/ The safety assessment and ICOUR teams took turns to visit the dams for
inspection, beginning with Tono dam.
- At Tono Dam, the areas inspected include:
o Scour Tower; Offtake structure; Dam Crest and Wall; Dam Toe where
Seepage Wells are located; Dam Embankment; and Spillway.
- At Vea Dam, the areas inspected include:
o Left and Right Intake Structures; Spillway; Crest; Embankment; Toe.
In addition, the team interacted with the contractor in charge of rehabilitation of the
Vea Dam on site to ascertain the progress made with the work.
7/ At a debriefing session, ICOUR Management noted the low morale of staff due to
the slow work pace experienced in recent times. The IPC leader thanked ICOUR
team for their availability and willingness to support the study in whatever capacity
necessary.
ORGANOGRAM FOR THE IRRIGATION COMPANY OF THE UPPER REGION
6.7 Data Collection
6.7.1 List of Data Collected
List of Documents Received
A. List of Drawings Received from GIDA
Drawing No. Drawing Title Rev Date Project Title Format
T1P/304/C19B Dam Sections
Sheet 3
B 2-9-76 Tono Irrigation Project PDF
T1P/304/C19B Dam Sections
Sheet 3
B 2-9-76 Tono Irrigation Project TIFF
T1P/304/C28A Plan on Dam A 29-6-76 Tono Irrigation Project PDF
T1P/304/C28A Plan on Dam A 29-6-76 Tono Irrigation Project TIFF
Maximum Section
of Dam; Dam Crest
Details
Ghana Canada Irrigation
Development Project. VEA
MIN/PT/012 Stability Analysis
for Slope of Dam –
Sheet 12 of 14
July
1965
VEA (YARAGATANGA
RIVER) IRRIGATION
PROJECT
TIFF
B. List of Drawings Received from SMEC
Tono Dam
Drawing No. Drawing Title Rev Date Project Title Format
T1P/304/C78 General
Arrangement
Scour & Water
Supply Valve
Tower Slabs
7/9/76 Tono Irrigation Project JPEG
T1P/304/C3B Centreline of Dam B 15/7/75 Tono Irrigation Project JPEG
T1P/304/C27A Profile Along CL of
Dam (As
Constructed)
Tono Irrigation Project JPEG
T1P/304/C67A Tono Dam, Intake
& Outlet Structures
on Scour Pipe
A 19/2/76 Tono Irrigation Project JPEG
T1P/304/C63 Tono Dam,
Piezometer Layout
19/11/75 Tono Irrigation Project JPEG
T1P/304/C66A Tono Dam, Scour
& Water Supply
Valve Tower 1
A 20/1/76 Tono Irrigation Project JPEG
T1P/304/C66A General
Arrangement
Scour & Water
A 27/3/76 Tono Irrigation Project JPEG
Drawing No. Drawing Title Rev Date Project Title Format
Supply Valve
Tower
T1P/304/C17B Dam Sections
Sheet 1
B 19/10/77 Tono Irrigation Project JPEG
T1P/304/C18B Dam Sections
Sheet 2
B 2/9/76 Tono Irrigation Project JPEG
T1P/304/C19B Dam Sections
Sheet 3
B 2/9/76 Tono Irrigation Project JPEG
T1P/304/C22B Dam Sections
Sheet 6
B 2/9/76 Tono Irrigation Project JPEG
T1P/304/C23B Dam Sections
Sheet 7
B 2/9/76 Tono Irrigation Project JPEG
T1P/304/C24B Dam Sections
Sheet 8
B 2/9/76 Tono Irrigation Project JPEG
T1P/304/C25B Dam Sections
Sheet 9
B 19/10/77 Tono Irrigation Project JPEG
T1P/304/C28A Plan on Dam A 29/8/76 Tono Irrigation Project JPEG
T1P/304/C66A General
Arrangement
Scour & Water
Supply Valve
Tower
A 27/3/76 Tono Irrigation Project JPEG
T1P/304/C27A Profile Along CL of
Dam (As
Constructed)
Tono Irrigation Project TIFF
T1P/304/C27C Profile Along CL of
Dam (As
Constructed)
C Tono Irrigation Project TIFF
Vea Dam
Drawing
No.
Drawing Title Rev Date Project Title Format
Maximum Section of
Dam; Dam Crest Details
Ghana Canada
Irrigation
Development
Project. VEA
JPEG
Outlet Works, Plans,
Sections and Details –
Sheet 4 of 12
Oct,
1965
Vea (Yaragatanga
River) Irrigation
Project
JPEG
MIN/PT-
003A
Outlet Works, Sections
and Details of Left
irrigation and Water
Supply Outlets – Sheet 6
of 12
May,
1966
Vea (Yaragatanga
River) Irrigation
Project
JPEG
Revisions to Gatewell and
Access Bridge
4/1/66 Vea (Yaragatanga
River) Irrigation
Project
JPEG
Revisions to Gatewell and
Access Bridge
4/1/66 Vea (Yaragatanga
River) Irrigation
Project
JPEG
General Layout Vea Irrigation
Project
JPEG
General layout sheet 1a Vea Irrigation
Project
JPEG
General layout sheet 1b
(Vea Dam Basin Survey)
Vea Irrigation
Project
JPEG
General layout sheet 1c Vea Irrigation
Project
JPEG
General layout sheet 1d Vea Irrigation
Project
JPEG
MIN/PT-
002
Cross Section along Dam
Axis showing Limits of
Excavation for Cut Off
Trench – Sheet 2 of 12
July,
1965
Vea (Yaragatanga
River) Irrigation
Project
JPEG
MIN/PT-
003
Maximum Section of Dam Sept,
1965
Vea (Yaragatanga
River) Irrigation
Project
JPEG
MIN/PT-
012
Stability Analysis for
Slope of Dam – Sheet 12
of 14
July,
1965
Vea (Yaragatanga
River) Irrigation
Project
P.F.R. A Vea (Yaragatanga
River) Irrigation
Project
Vea Irrigation Project
General Layout – Sheet 1
of 1
Oct,
1965
Vea (Yaragatanga
River) Irrigation
Project
C. Meteorological Data Received from SMEC:
No Title Range
1 Navrongo Monthly WindSpeed (knots) 2010 to 2015
2 Navrongo Monthly SunShine Hrs. 2010 to 2015
3 Navrongo Monthly Min. Temp.(°C) 2010 to 2015
4 Navrongo Monthly Max. Temp.(°C) 2010 to 2015
5 Vea Monthly WindSpeed (knots) 2011 to 2015
6 Vea Monthly SunShine Hrs. 2010 to 2015
7 Vea Monthly Min. Temp.(°C) 2012 to 2015
8 Vea Monthly Max. Temp.(°C) 2010 to 2015
9 Navrongo Monthly Ave. RH (%) 2010 to 2015
10 Element:P.E.T./Unit:mm/Station:Navrongo 2006 to 2013
11 Element:P.E.T./Unit:mm/Station: Vea-Dam. 2006 to 2013
12 Navrongo Daily Rainfall(mm) 1996 to 2015
13 Paga Daily Rainfall(mm) 1996 to 2004
14 Sandema Daily Rainfall(mm) 1996 to 2003
15 Vea Daily Rainfall(mm) 1996 to 2015
16 Zuarungu Daily Rainfall(mm) 1996 to 2015
D. Training Needs Received from ICOUR
a. ICOUR Training Needs 2016
b. ICOUR Training Needs 2017
E. Drawings Received from ICOUR
1. Tono Catchment and laterals
2. Vea Catchment and laterals
3. Reservoir Volume Elevation Curve for Tono,
F. List of Reports Received
a. Vea Dam Engineering Report (for Ghana Water Company Ltd. (GWCL)), by
Nonconsult in Association with Mott MacDonald Ltd. and Watertech Ltd., May
2007. – Received from GCAP
b. Vea Dam Bathymetric Report by Imagen Consulting Ltd, May 2016.-Received
from SMEC
c. Field Visit Report by R Tippins and G. Beavan of Binnie & Partners,1982.-
Received from ICOUR
6.7.2 ICOUR Training Needs
6.7.2.1 ICOUR Training Needs 2016
6.7.2.2 ICOUR Training Needs 2017
7. REFERENCES 1. John Dunnicliff, Gordon E. Green (1968), “Geotechnical Instrumentation for Monitoring
Field Performance”.
2. Junner, N.R, Bates, D.A, Tillotson E., & Deakin, C.S, “The Accra Earthquake of the
22nd June, 1939, Gold Coast Geological Survey” Bulletin No. 13.
3. F.G. Bell – Ground Engineer’s Reference Book, Butterworths and Co. 1987
4. Peck, R.B; Hanson, W.E; and Thornburn T.H.; (1974) - Foundation Engineering, 2nd
edition, Wiley, New York – (1974).
5. Bowles, J.E (1982) – Foundation Analysis and Design, McGraw-Hill International Book
Company – third edition.
6. British Standard (BS. 5930 –1981) – Site Investigations for Civil Engineering Works.
7. Bureau of Reclamation, Stagnation Pressure Failure of Spillway Chutes, Report DSO-
07-07, Technical Service Center, Denver CO, December 2015.
8. Kesse (1985), “Geology Map of Upper East Region – Ghana”.
9. Paulina Ekua Amponsah (2005), “Seismic activity in Ghana: past, present and future”
10. Washington State Department of Ecology (1993), “Dam Safety Guidelines: Part IV,
Dam Design and Construction”.
11. North Carolina Department of Environment and Natural Resources (1985), “Dam
Operation, maintenance, and Inspection Manual”.
12. US Army Corps of engineers (2004), “General Design and Construction
Considerations for Earth and Rock-fill Dams”.
13. A Water Resources Technical Publication (1995), “Safety Evaluation of Existing Dams”
[1] These are not related to the observation wells mentioned above