workbook lesson 8: applying the activity sequencing process · ultimate pmp exam prep ©2005 true...
TRANSCRIPT
Workbook Lesson 8: Applying the Activity Sequencing Process
ULTIMATE PMP Exam Prep ©2005 True Solutions, Inc. (TSI) All Rights Reserved PMI, PMP and PMBOK are registered trademarks of the Project Management Institute, Inc.
The ULTIMATE PMP Exam Preparation Course
®
SPECIAL NOTE: To create the look and feel of the ULTIMATE PMP Exam Prep Workbook, try printing your sample lesson double-sided,
then assemble the pages in a report binder.
Best of Success!
ULTIMATE PMP Exam Prep ©2005 True Solutions, Inc. (TSI) All Rights Reserved. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form, or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written consent of TSI, Inc. Contact: TSI (True Solutions, Inc.) 5001 LBJ Freeway, Suite 125-B Dallas, Texas 75244 (972) 770-0900 (972) 770-0922 (fax) www.true-solution.com PMI, PMP and PMBOK are registered trademarks of the Project Management Institute, Inc.
Workbook Lesson 8: Applying the Activity Sequencing Process
ULTIMATE PMP Exam Prep ©2005 True Solutions, Inc. (TSI) All Rights Reserved PMI, PMP and PMBOK are registered trademarks of the Project Management Institute, Inc.
The ULTIMATE PMP Exam Preparation Course
®
visit us at www.true-solution.com
Welcome ...
Learn all about the course that’s revolutionizing the way Certification Candidates prepare to pass their PMP Exam.
All the details ...
Your Print Brochure Your Video Brochure
PMP Exam Preparation Course
®
PMP, PMI and PMBOK are registered trademarks of the Project Management Institute, Inc.
And more ...
Complimentary Sample Workbook Lesson Your Complete Course Package Only $295
Part III
Planning the Project
“Every moment spent planning saves three or four in
execution.”
- Crawford Greenwalt
Planning the Project
Here is what you will encounter on your PMP Exam ... √ As a PMP planning the project (or project phase), you should be prepared to refine project requirements,
assumptions and constraints through communication with stakeholders and by reviewing project documents to baseline the scope of work and enable development of the execution plan. 8 questions will appear on the PMP Exam to test your understanding of this statement.
√ As a PMP planning the project (or project phase), you should be prepared to create the Work
Breakdown Structure (WBS) using the scope of work, other project documents and decomposition techniques to facilitate detailed project planning and the executing, controlling and closing processes. 7 questions will appear on the PMP Exam to test your understanding of this statement.
√ As a PMP planning the project (or project phase), you should be prepared to develop the resource
management plan (Human Resources, Procurement, etc.) by identifying resource requirements and obtaining commitments from internal, external and procured sources to complete all project activities. 6 questions will appear on the PMP Exam to test your understanding of this statement.
√ As a PMP planning the project (or project phase), you should be prepared to refine project time and cost
estimates by applying estimating tools and techniques to all WBS tasks in order to determine and define project baseline, schedule and budget. 6 questions will appear on the PMP Exam to test your understanding of this statement.
√ As a PMP planning the project (or project phase), you should be prepared to establish project controls
by defining the required correct processes, measures and controls to manage project change, communications, procurement, risk, quality and human resources to facilitate project executing and controlling processes, and to ensure compliance with generally accepted industry standards. 6 questions will appear on the PMP Exam to test your understanding of this statement.
√ As a PMP planning the project (or project phase), you should be prepared to develop a formal and
comprehensive project plan by integrating and documenting project deliverables, acceptance criteria, processes, procedures, risks and tasks to facilitate project executing, controlling and closing processes. 7 questions will appear on the PMP Exam to test your understanding of this statement.
√ As a PMP planning the project (or project phase), you should be prepared to obtain project plan
approval by reviewing the plan with the client and other required stakeholders to confirm project baselines prior to proceeding with project executing processes. 7 questions will appear on the PMP Exam to test your understanding of this statement.
Planning the Project
Here are the PMP knowledge specifics you will find referenced on your PMP Exam ...
As a PMP applying Planning processes in real-world projects, you may be expected to possess in-depth knowledge in several project-specific areas, as well as a broad knowledge of project management in general. The PMP Exam will test your understanding of these ‘knowledge specifics.’ By developing a familiarity with these Planning knowledge specifics, you will better understand the context of many PMP Exam questions. Review this list, and as you read, spend a few moments giving some thought to each item as it relates to your own experience with past projects, current projects or anticipated upcoming projects. New terms that are unfamiliar at this point, will be discussed in subsequent lessons. As a PMP applying Planning processes, you may be expected to have knowledge of ...
√ Accepted/required control processes, measures and thresholds
√ Analysis techniques √ Approving authorities √ Assumption identification techniques √ Authorization procedures √ Business writing techniques √ Communication management concepts, tools
and techniques √ Constraint identification methods √ Decision-making techniques √ Effective communication techniques √ Existing project documents √ Facilitation techniques √ Gantt, PERT, CPM and PDM methods √ Gathering, assessing and integrating
information √ Human resource management techniques √ Industry standards √ Integrating and sequencing activities and tasks √ Interviewing techniques √ Negotiation techniques √ Negotiations √ Procurement guidelines and regulations
√ Procurement management concepts, tools and techniques
√ Quality control and sampling techniques √ Quality management concepts, tools and
techniques √ Required reviewers √ Requirement analysis methods √ Resource estimating techniques √ Resource selection criteria and techniques √ Resource sources and availability √ Resource-leveling techniques √ Risk analysis techniques √ Risk management concepts, tools and
techniques √ Schedule preparation methods √ Scope and change management concepts √ Stakeholder identification techniques √ Stakeholders √ Statistical analysis and forecasting techniques √ Team-building methods and techniques √ Time and cost estimation techniques √ WBS development and decomposition
techniques √ Workload balancing techniques
Planning the Project Here are the PMP performance competencies you will find referenced on your PMP Exam ...
As a PMP applying Planning processes in real-world projects, there are many specific project management performance competencies (skills) you may be expected to exercise. By developing a familiarity with these Planning skills, you will better understand the context of many PMP Exam questions. Review this list, and as you read, spend a few moments giving some thought to each item as it relates to your own experience with past projects, current projects or anticipated upcoming projects. New terms that are unfamiliar at this point, will be discussed in subsequent lessons. As a PMP applying Planning processes, you may be expected to exercise skill in ...
√ Analyzing and measuring statistically √ Budgeting √ Building and motivating teams √ Communicating effectively √ Decision-making while considering legal,
organizational and stakeholder issues √ Developing a chart of accounts √ Developing a communications management
plan √ Developing a comprehensive project plan √ Developing a cost baseline √ Developing a cost management plan √ Developing a decision tree analysis √ Developing a list of resource requirements √ Developing a metrics plan √ Developing a network diagram √ Developing a probability impact matrix √ Developing a procurement management plan √ Developing a procurement statement of work √ Developing a project directory √ Developing a project management plan √ Developing a project schedule … baseline √ Developing a quality checklist √ Developing a quality management plan √ Developing a risk assessment matrix √ Developing a risk management plan √ Developing a risk response plan √ Developing a schedule management plan √ Developing a scope management plan √ Developing a scope statement √ Developing a sensitivity analysis
√ Developing a staffing management plan √ Developing a stakeholder management plan √ Developing a WBS √ Developing an activity list with duration
estimates √ Developing an organization chart √ Developing contingency plans √ Developing contractual agreements √ Developing cost estimates √ Developing mechanisms for obtaining
feedback from stakeholders √ Developing project files √ Estimating, forecasting and managing
uncertainty √ Gathering, assessing and breaking down
information into work elements √ Gathering, assessing and integrating
information √ Making decisions √ Managing change √ Managing procurement √ Managing quality √ Managing risk √ Managing, developing and motivating human
resources √ Negotiating √ Planning projects √ Presenting and explaining information √ Scheduling √ Writing formally
Lesson 8
Applying the Activity Sequencing Process
Lesson 8 Learning Objectives
⇒ Understand the intent of applying the Activity Sequencing process, along with its primary objectives. ⇒ Understand where in the project life cycle to apply the Activity Sequencing process. ⇒ Become familiar with the knowledge and performance competencies you may be expected to demonstrate as a PMP
applying the Activity Sequencing process. ⇒ Understand the major deliverables (Outputs) created by the Activity Sequencing process. ⇒ Become familiar with the generally-accepted methodologies (Tools & Techniques) used to produce Activity Sequencing
process deliverables, along with the prerequisite Inputs necessary to apply the methodologies. ⇒ Become familiar with the generally-accepted vocabulary (key terms) and critical concepts associated with the Activity
Sequencing process. ⇒ Know how the PMP Exam will test your understanding of the Activity Sequencing process.
Activity Sequencing Activity Sequencing is the process of identifying the interrelationships between individual project activities, then documenting them using, what is generically termed, a Network Logic Diagram. This is an essential step that must be performed accurately prior to the development of a realistic and achievable schedule. Project Network Logic Diagrams are often (but not correctly) referred to as PERT Charts. Intuitive sense tells us that certain project activities must be completed before others may start. In many cases, certain activities may be performed in parallel. In some cases, certain activities must start before others can finish. As you will learn shortly, there are four possible interactivity relationships. These relationships must be identified and documented in some form of Network Logic Diagram. This is what Activity Sequencing is all about. As you might imagine, in a project with hundreds or thousands of identified activities, Activity Sequencing can be a very complex process. In real-world project planning, most PMPs rely on the use of project management software to automate and expedite the process. However, to pass the PMP Exam, we must develop the ability to manually create and analyze simple network diagrams. To accomplish this, we must first learn the fundamentals of Network Logic Diagramming, then spend some time with hands-on practice. Because there is so much important information to cover in Activity Sequencing (compared to other processes), expect to devote a little more time here with Lesson 8.
Part III Planning the Project
The Fundamentals of Network Logic Diagrams To master all there is to know about Network Logic Diagramming, we could spend a graduate-level semester dedicated just to this one subject. It can be quite complex, with many specific techniques and technique-variations to consider. To prepare for the PMP Exam, however, we need to master only the fundamentals. Here they are.
There are three generally-accepted methods used to create and document Network Logic Diagrams:
Arrow Diagramming Method (ADM)
Precedence Diagramming Method (PDM)
Conditional Diagramming Methods
Arrow Diagramming Method (ADM) ADM is used with increasingly less frequency in modern times (PDM is in more widespread use today). ADM constructs the project network diagram using arrows to represent project activities and connects them at nodes to illustrate their interdependencies. Here is a simple network diagram, drawn using ADM: In this simplified example, the project consists of six activities, A - F, represented by arrows. We see that activities A and B have no predecessor constraints and can start right away. We see that A must finish before activity C can start. We see that C must finish before E can start. And so on, through to project finish.
ADM Networks are also called Activity-on-Arrow (AOA) Diagrams (Activity information is identified on the arrows) ADM Networks have certain shortfalls:
• In some cases, it is impossible to complete the network logic using only arrows and nodes. In these cases, it is necessary to include dummy activities, ‘dummies.’ In the above illustration, a dummy is included (dotted arrow) to indicate that Activity C is preceded by both Activities A and B. This means Activities A and B must be finished before Activity C can start. Dummies are artificial activities. They represent no real work, resources or time.
• In ADM Networks, only Finish-to-Start (F-S) interdependencies can be illustrated. In PDM Networks, all four possible interdependencies may be illustrated F-S, S-F, S-S and F-F.
Start Finish
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
Page 105
Lesson 8 Applying the Activity Sequencing Process
Precedence Diagramming Method (PDM) This is the method used by most modern project management software programs. It constructs the project network diagram using boxes (called nodes) to represent project activities, and connects them with arrows which illustrate their interdependencies. Here is a simple network diagram, drawn using PDM:
In this simplified example, the project consists of seven activities, A - G. We see that activities A and B have no predecessor constraints and can start right away. We see that A and B must finish before activity C can start. We see that C must finish before D can start. D must finish before E or G can start. E must finish before F can start. Finally, F and G must finish before the project can finish.
Precedence Diagrams are also called Activity-on-Node (AON) Diagrams (Activity information is identified directly on the node) Precedence Diagrams can illustrate four types of interdependencies
A
C
D
E
F
B
G
Start Finish
• Finish-to-Start (F-S) Activity A must Finish before Activity B may Start. F-S is the most common type of interdependency.
• Start-to-Finish (S-F)
Activity A must Start before Activity B may Finish. S-F is the least common type of interdependency.
• Start-to-Start (S-S)
Activity A must Start before Activity B may Start. S-S is a less common type of interdependency.
• Finish-to-Finish (F-F)
Activity A must Finish before Activity B may Finish. F-F is a less common type of interdependency.
B
A
B
A
B
A
B
A
Part III Planning the Project
Conditional Diagramming Methods In some projects, it may necessary to perform multiple tests (loops), then proceed along some conditional branch, based upon the outcome of testing. In these type projects, there may be more than one acceptable end result, again based upon the outcome of testing. Neither ADMs or PDMs allow us to illustrate these types of non-sequential activity relationships (loops) or alternate paths (conditional branching). In projects where it is essential to illustrate looping, branching and/or multiple end results, then some Conditional Diagramming Method is needed. There are two types generally recognized:
GERT (Graphical Evaluation and Review Technique). Although GERT is recognized as an accepted Conditional Diagramming Method, it is difficult to find in field use. At present, it appears that reliable GERT programs remain ‘in the lab.’ System Dynamics models. Some commercial project management software tools allow for looping, branching and multiple end results by incorporating various System Dynamics algorithms.
Critical Path Network Diagrams illustrate all of the project’s activities and their interrelationships/dependencies, from project start to project finish. They also annotate, at minimum, an identification for each activity and the estimated time duration of each activity. A typical PMP Exam Network Diagram is very simple and may look something like this:
• In this simple example, the project is comprised of six activities, A-F. • All predecessor/successor relationships are Finish-to-Start (F-S). • Activity A is estimated to require 3 days for completion, Activity B 12 days, Activity C 10 days, and so on. • There are three possible paths through this Network from start-to-finish; Path 1) Start-A-B-D-F-Finish , Path 2) Start-
A-C-E-Finish and Path 3) Start-A-C-D-F-Finish. • Add the associated Activity time estimates to find that Path 1 is 22 days long, Path 2 is 28 days long and Path 3 is
20 days long. • Path 2 is the longest path through the Network Diagram (28 days), and is therefore identified as the Critical Path.
The Critical Path is the longest path through a Network Diagram. The Critical Path also defines the shortest period of time in which the project may be completed (in this example, 28 days).
• The Critical Path is typically indicated with a heavier arrowed line.
Page 106
A
B
C
D F
E
Start Finish
Activity A 3 Days
Activity B 12 Days
Activity C 10 Days
Activity D 6 Days
Activity E 15 Days
Activity F 1 Day
Page 107
Lesson 8 Applying the Activity Sequencing Process
ADM & PDM Conventions
When properly constructed and annotated, Network Diagrams can communicate an enormous amount of essential information. During planning, this helps the project team in creating the project schedule, obtaining resources and in identifying risks. Here is the way information is typically annotated in ADM Networks (Activity-on-Arrow AOA) and PDM Networks (Activity-on-Node AON). The numbers indicated in this example are work units. Typically, work units are hours, shifts, days, weeks, etc.
Once the Network is constructed and work units for each activity are estimated, we can then determine the following for each activity:
• Earliest Start Time (ES) and Earliest Finishing Time (EF). We can determine ES and EF by making a forward pass (left-to-right) through the Network. The earliest starting time (ES) of a successor activity is the latest of the early finish times of its predecessors. The earliest finishing time (EF) is the total of the earliest starting time and the activity duration.
• Latest Starting Time (LS) and Latest Finish Time (LF). We can determine LS and LF by making a backward pass (right-to-left) through the Network. The latest finishing time (LF) for an activity entering a node is the same as smallest value latest starting time (LS) of the activities exiting the node. The latest starting time (LS) of an activity is the latest finishing time (LF) minus the activity duration.
• Slack (also referred to as float, reserve, total float, path float). We can determine Slack in an activity by subtracting its ES from its LS. Many non-critical project activities may have Slack time, allowing greater flexibility in scheduling and resource allocation. Activities on the network’s Critical Path typically have zero Slack.
A (4,6)
2 (11,13)
Activity Identification
Activity Time Duration Estimate
Earliest Possible Start Time (ES)
Earliest Possible Finish Time (EF)
Latest Possible Start Time (LS)
Latest Possible Finish Time (LF)
ADM
4 2 6
A 7 $35K
11 6103 13
PDM
Activity Identification
Activity Time Duration Estimate ES EF
LS LF
Accounting Center
Cost Estimate
Slack
Page 108
Part III Planning the Project
PMP Activity Sequencing Tasks As a PMP applying the Activity Sequencing process in real-world projects, there are many specific tasks you may be expected to perform. By developing a broad familiarity with these tasks, you will better understand the context of PMP Exam questions that address Activity Sequencing. Here is a typical Activity Sequencing
Think About It ...
Refer to your PM PROCESSES Poster 1. See where the Activity Sequencing process is applied in the project life cycle. Review the Activity Sequencing process illustration below. Note the Input, Tool/Technique and Output elements. Read the condensed descriptions of each. As you read, envision how the Inputs might feed the Tools/Techniques, which then work to create the intended process deliverables (Outputs). Refer to your PM PROCESSES Poster 4. See where the Activity Sequencing process aligns with respect to the nine project management Knowledge Areas.
Think About It ...
• Precedence diagramming method (PDM) • Arrow diagramming method (ADM) • Network templates • Conditional diagramming methods
⇒ Project network
diagrams ⇒ Activity list updates
⇒ Discretionary dependencies ⇒ External dependencies ⇒ Activity list ⇒ Product description ⇒ Mandatory dependencies ⇒ Milestones
Time Management ○ Core Planning Process
ACTIVITY SEQUENCING identifies and documents interactivity dependencies. Discretionary dependencies. Those activity dependencies that can be defined by the project team. External dependencies. Dependencies between project activities and non-project activities. Activity list. The list and description of each project activity, organized as an extension of the WBS. Product description. Documented characteristics of the product (or service) that the project is undertaken to create. Mandatory dependencies. ‘Hard logic’ activity relationships. i.e. Prototype must be built before it can be tested. Milestones. Significant events (typically planned) in the project. Example: Completion of a major deliverable. Precedence diagramming method (PDM). Activity-on-Node (AON) project network diagramming technique. Arrow diagramming method (ADM). Activity-on-Arrow (AOA) method for constructing a project network diagram. Network templates. Standardized networks used to expedite preparation of the project’s network diagram. Conditional diagramming methods. Network diagramming techniques that allow for loops and branching. GERT. Project network diagrams. Schematic displays of the project’s activities and their logical relationships. Activity list updates. ‘Progressive elaboration refinements’ to the activity list.
Page 109
Lesson 8 Applying the Activity Sequencing Process
task list. Activity Sequencing Tasks:
√ Determine your interactivity dependencies. √ Identify the relationships between your project activities for activity sequencing. √ Identify and document the types of interactivity dependencies within your project. √ Construct your project network diagram. √ Identify appropriate diagramming techniques. √ Determine inputs to your activity sequencing process. √ Complete your activity list and WBS updates, as well as updates of related supporting
documentation. √ Define missing activities or activities requiring clarification in your activity list during the development
of your project network diagram.
Review the PMP Activity Sequencing Tasks above. As you review, envision how these tasks might be applied to a familiar project from your past experience, from current experience or on an upcoming project.
Think About It ...
Page 110
Part III Planning the Project
Triple-R Exercises
1. REVIEW Cutout your Lesson 8 ReviewSheets (pages 108-110). Briefly review the contents of each sheet.
2. WRITE Directly on Lesson 8 ReviewSheet 1, fill-in the blanks, as directed, by physically writing-in the appropriate information. A fine-point pencil or pen works best. You can find the appropriate ‘write-in’ information here in Lesson 8 on page 105. Simply copy the information word-for-word.
3. RECITE Once you have completed your WRITE exercise, read aloud each of the statements as directed on ReviewSheets 1, 2 & 3. Verbally reciting the material quietly in an undisturbed setting works best. Reading through each statement one time will be sufficient.
PMBOK Guide Reading Assignment Read PMBOK Guide section 6.2 ACTIVITY SEQUENCING (2-1/2 pages). Take notes as you read, using your Lesson 8 Cutout Notes page.
•__
____
____
____
____
____
____
__
•__
____
____
____
____
____
____
__
•__
____
____
____
____
____
____
__
•__
____
____
____
____
____
____
__
⇒__
____
____
____
____
____
____
____
____
____
⇒
____
____
____
____
____
____
____
____
____
__
⇒__
____
____
____
____
____
____
____
__
⇒__
____
____
____
____
____
____
___
⇒__
____
____
____
____
____
____
___
⇒__
____
____
____
____
____
____
___
⇒__
____
____
____
____
____
____
____
_ ⇒
____
____
____
____
____
____
____
___
__
____
____
____
____
____
____
__ ○
____
____
____
____
____
____
____
____
____
__
“A
CTIV
ITY
SEQU
ENCI
NG __
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
.”
“The
re ar
e six
defin
ed In
puts
to the
Acti
vity S
eque
ncing
pro
cess
…
1) D
iscre
tiona
ry de
pend
encie
s. Th
ese a
re th
e acti
vity d
epen
denc
ies th
at ha
ve so
me de
gree
of fle
xibilit
y and
can b
e defi
ned b
y the
proje
ct tea
m.
2) E
xtern
al de
pend
encie
s. Th
ese a
re th
e dep
ende
ncies
betw
een p
rojec
t acti
vities
(inter
nal) a
nd no
n-pr
oject
activ
ities (
exter
nal).
3)
Acti
vity l
ist. T
his is
the p
rimar
y Acti
vity D
efinit
ion de
liver
able
(Out
put).
It is
the l
ist/de
scrip
tion o
f all p
rojec
t acti
vities
, typic
ally o
rgan
ized a
s an e
xtens
ion of
the W
BS.
4)
Pro
duct
desc
riptio
n. Th
is is
the ‘d
ocum
ent’ t
hat c
hara
cteriz
es th
e pro
duct
(or s
ervic
e) th
at the
proje
ct is
unde
rtake
n to c
reate
. 5)
Man
dator
y dep
ende
ncies
. The
se ar
e ‘ha
rd lo
gic’ a
ctivit
y rela
tions
hips.
An e
xamp
le co
uld be
; a pr
ototyp
e mus
t be b
uilt b
efore
it ca
n be t
ested
. 6)
Mile
stone
s. Mi
leston
es ar
e sign
ifican
t eve
nts (t
ypica
lly pl
anne
d) in
the p
rojec
t. Th
e com
pletio
n of a
majo
r deli
vera
ble is
man
y tim
es m
arke
d as a
mile
stone
.”
Le
ss
on
8
Ap
ply
ing
th
e A
cti
vit
y S
eq
ue
nc
ing
Pro
ce
ss
R
ev
iew
She
et
1
of
3
1. Co
mplet
e the
WR
ITE
por
tion o
f you
r Trip
le-R
Exer
cises
by fil
ling-
in the
blan
ks ab
ove.
You
will
find t
he co
rrect
infor
matio
n to w
rite-in
on pa
ge 10
5 of y
our W
orkb
ook.
2. On
ce yo
u hav
e fille
d-in
the bl
anks
, com
plete
the R
EC
ITE
por
tion o
f you
r Trip
le-R
Exer
cises
by re
ading
alou
d all
of th
e abo
ve m
ateria
l that
appe
ars i
n “qu
otatio
n mar
ks.”
Verb
ally r
ecite
the
mater
ial on
ce-th
roug
h, qu
ietly.
An u
ndist
urbe
d sett
ing w
orks
best.
Cont
inued
on
Revie
wShe
et 2
…
“T
here
are f
our d
efine
d Too
ls &
Tech
nique
s in t
he A
ctivit
y Seq
uenc
ing pr
oces
s ...
1) P
rece
denc
e diag
ramm
ing m
ethod
(PDM
). Th
is is
also t
erme
d, the
Acti
vity-o
n-No
de (A
ON) p
rojec
t netw
ork d
iagra
mming
tech
nique
. Acti
vity i
nform
ation
is ill
ustra
ted on
the
‘nod
es’ in
the n
etwor
k diag
ram.
2)
Arro
w dia
gram
ming
meth
od (A
DM).
This
is als
o ter
med,
the A
ctivit
y-on-
Arro
w (A
OA) m
ethod
for c
onstr
uctin
g a pr
oject
netw
ork d
iagra
m. A
ctivit
y info
rmati
on is
illu
strate
d dire
ctly o
n the
‘arro
ws’ in
the n
etwor
k diag
ram.
3)
Netw
ork t
empla
tes. S
tanda
rdize
d netw
orks
used
to ex
pedit
e pre
para
tion o
f the
proje
ct’s n
etwor
k diag
ram.
4)
Con
dition
al dia
gram
ming
meth
ods.
Thes
es ar
e netw
ork d
iagra
mming
tech
nique
s tha
t allo
w for
loop
s and
bran
ching
. GER
T is
a (ra
re) c
ondit
ional
diagr
ammi
ng
metho
d.”
“T
here
are t
wo de
fined
Out
puts
(or d
elive
rable
s) fro
m the
Acti
vity S
eque
ncing
proc
ess …
1)
Pro
ject n
etwor
k diag
rams
. The
se ar
e the
sche
matic
disp
lays o
f the p
rojec
t’s ac
tivitie
s and
their
logic
al re
lation
ships
, from
proje
ct sta
rt to
proje
ct en
d.
2) A
ctivit
y list
upda
tes. T
hese
are ‘
prog
ress
ive el
abor
ation
refin
emen
ts’ to
the a
ctivit
y list
, iden
tified
durin
g Acti
vity S
eque
ncing
.”
Le
ss
on
8
Ap
ply
ing
th
e A
cti
vit
y S
eq
ue
nc
ing
Pro
ce
ss
Re
vie
wS
he
et
2
of
3
Conti
nue t
he R
EC
ITE
por
tion o
f you
r Trip
le-R
Exer
cises
by re
ading
alou
d all
of th
e abo
ve m
ateria
l that
appe
ars i
n “qu
otatio
n mar
ks.”
Cont
inued
on
Revie
wShe
et 3
…
Mu
st
Kn
ow
Ac
tiv
ity
Se
qu
en
cin
g C
on
ce
pts
1.“T
he A
ctivit
y Seq
uenc
ing pr
oces
s is i
ntend
ed to
iden
tify an
d doc
umen
t inter
activ
ity
logica
l relat
ionsh
ips.”
2.“A
ctivit
y Seq
uenc
ing is
a co
re P
lannin
g Pro
cess
, one
of tw
enty-
one (
21) p
roce
sses
in
the P
lannin
g Pro
cess
es G
roup
. Ac
tivity
Seq
uenc
ing is
also
one o
f five
(5)
proc
esse
s in t
he P
rojec
t Tim
e Man
agem
ent K
nowl
edge
Are
a .
3.“T
he pr
imar
y deli
vera
ble (O
utpu
t) of
the A
ctivit
y Seq
uenc
ing pr
oces
s is t
he pr
oject
netw
ork d
iagra
m.”
4.“T
he pr
oject
netw
ork d
iagra
m be
come
s the
prim
ary i
nput
to de
velop
the p
rojec
t sc
hedu
le.”
5.“T
he pr
oject
netw
ork d
iagra
m illu
strate
s all p
rojec
t acti
vities
and t
heir p
rede
cess
or/
succ
esso
r rela
tions
hips/i
nterd
epen
denc
ies.
It also
iden
tifies
the p
rojec
t’s C
ritica
l Pa
th an
d all o
f the a
ctivit
ies on
the C
ritica
l Path
.”
6.“T
he C
ritica
l Path
is th
e lon
gest
path
throu
gh a
netw
ork d
iagra
m. It
defin
es th
e sh
ortes
t per
iod of
time i
n whic
h the
proje
ct ma
y be c
omple
ted.”
7.“N
etwor
k Diag
rams
are o
ften r
eferre
d to a
s PER
T Ch
arts
(inac
cura
tely).
A P
ERT
Char
t is a
partic
ular t
ype o
f ADM
Netw
ork w
idely
used
in pa
st ye
ars.”
8.“N
etwor
k Diag
rams
are t
ypica
lly cr
eated
and d
ocum
ented
using
Arro
w Di
agra
mming
Meth
od (A
DM) t
echn
iques
, Pre
cede
nce D
iagra
mming
Meth
od (P
DM)
Tech
nique
s or C
ondit
ional
Diag
ramm
ing M
ethod
s (GE
RT or
Sys
tem D
ynam
ics
mode
ls).”
9.“A
DM is
also
refer
red t
o as A
ctivit
y-on-
Arro
w (A
OA).
In AO
A dia
gram
s, ac
tivitie
s
are r
epre
sente
d by a
rrowe
d line
s whic
h are
conn
ected
at no
des t
o illu
strate
their
int
erde
pend
encie
s.”
10.
“PDM
is al
so re
ferre
d to a
s Acti
vity-o
n-No
de (A
ON).
In AO
N dia
gram
s, ac
tivitie
s ar
e rep
rese
nted b
y nod
es w
hich a
re co
nnec
ted by
arro
wed l
ines t
o illu
strate
their
int
erde
pend
encie
s.”
11.
“AOA
diag
rams
can s
how
only
one t
ype o
f inter
depe
nden
cy, F
inish
-to-S
tart (
F-S)
. AO
A dia
gram
s som
etime
s nee
d to i
nclud
e dum
my ac
tivitie
s to c
omple
te the
ne
twor
k log
ic.”
12.
“AON
diag
rams
can s
how
four t
ypes
of in
terde
pend
encie
s (F-
S), (
S-F)
, (F-
F) an
d (S
-S).
Dumm
ies ar
e not
need
ed to
illus
trate
netw
ork l
ogic
in AO
N dia
gram
s.”
13.
“A F
orwa
rd P
ass (
left-r
ight th
roug
h the
netw
ork)
may b
e per
forme
d to d
eterm
ine
Earlie
st St
artin
g tim
es (E
S) an
d Ear
liest
Finish
times
(EF)
for e
ach p
rojec
t acti
vity.”
14.
“A B
ackw
ard P
ass (
right-
left th
roug
h the
netw
ork)
may b
e per
forme
d to d
eterm
ine
Lates
t Star
ting t
imes
(LS)
and L
atest
Finish
times
(LF)
for e
ach p
rojec
t acti
vity.”
15.
“Slac
k (als
o refe
rred t
o as f
loat,
rese
rve,
path
float
or t
otal fl
oat)
for an
y give
n ac
tivity
may
be de
termi
ned b
y sub
tracti
ng E
S fro
m LS
. Acti
vities
on th
e Criti
cal
Path
typica
lly ha
ve ze
ro sl
ack.”
16.
“Sub
net (
or fr
agne
t or s
ubpr
oject)
is a
subd
ivisio
n of a
netw
ork d
iagra
m. H
ammo
ck
is gr
oup o
f rela
ted ac
tivitie
s illu
strate
d as a
sing
le su
mmar
y acti
vity.”
17.
“My P
MP E
xam
will i
nclud
e 47 q
uesti
ons c
over
ing P
lannin
g Pro
cess
es.”
Comp
lete t
he R
EC
ITE
portio
n of y
our T
riple-
R Ex
ercis
es by
read
ing a
loud
each
of th
e 17 ‘
Must
Know
’ stat
emen
ts ab
ove.
Le
ss
on
8
Ap
ply
ing
th
e A
cti
vit
y S
eq
ue
nc
ing
Pro
ce
ss
R
ev
iew
She
et
3
of
3
Lesson 8 Applying the Activity Sequencing Process
Page 115
Lesson 8 Applying the Activity Sequencing Process
Lesson 8 Quiz
Here are 14 questions to help reinforce your Lesson 8 learning material. Complete this quiz from memory to the best of your ability. For each question, circle or check your selected answer. When complete, check your performance by comparing your answers to the correct answers, provided in Appendix A. 1. The longest path through a project network diagram is termed, ______________________
A. path float. B. latest finish time (LF). C. latest start time (LS). D. critical path.
2. Which of the following statements is most true?
A. A project network diagram my identify more than one critical path. B. A project network diagram can illustrate only one critical path. If more than one critical path is identified, a
mistake has been made somewhere in construction of the network logic. C. A project network diagram should be unique to the project, constructed using the best individual elements
of ADM, PDM and Conditional Diagramming Methods. D. A project network diagram is essentially the same as a project WBS. They are interchangeable.
3. Activity Sequencing inputs include all of the following except:
A. Discretionary dependencies (also referred to as soft logic, preferred logic, or preferential logic). B. External dependencies. C. Mandatory dependencies (also referred to as hard logic). D. The Project Network Diagram (typically in ADM form, PDM form or Conditional Diagramming form).
4. In this simplified network diagram, how many paths exist, from project start to project finish?
A. 6 B. 1 C. 5 D. 3
A
B
C
D
E
3 days
6 days
9 days
2 days
12 days
Start Finish
5. Referring to the project network diagram in question 4, identify the critical path.
A. Start-A-C-D-Finish B. Start-A-C-D-E-Finish C. Start-A-B-C-D-E-Finish D. Start-A-B-D-E-Finish
6. Referring to the project network diagram in question 4, identify the shortest period of time in which this project
may be completed.
A. 14 days B. 20 days C. 26 days D. 32 days
7. From the given information, determine how many paths exist through this project’s network diagram.
A. 1 B. 2 C. 3 D. 4
8. Referring to the information given in question 7, identify the project’s critical path.
A. Start-A-C-E-F-G-Finish B. Start-B-D-E-F-G-Finish C. Start-B-C-E-F-G-Finish D. Start-A-C-E-F-Finish
9. Referring to the information given in question 7, identify the shortest period of time in which this project may be completed.
A. 25 weeks B. 31 weeks C. 38 weeks D. Insufficient information
Page 116
Part III Planning the Project
Activity Activity Duration Predecessors
A 1 week none
B 7 weeks none
C 5 weeks A and B
D 12 weeks B
E 10 weeks C and D
F 6 weeks E
G 3 weeks F
Lesson 8 Applying the Activity Sequencing Process
10. While reviewing your project network diagram, you note that an activity has an Early Start time of 3 days and a Late Start time of 12 days. How much float does this activity have?
A. Zero, because activities on the critical path have zero slack. B. + 9 days C. - 9 days D. 75%
11. A forward pass _________________________________________________________.
A. is performed by moving left-to-right through the network diagram to determine the Early Start (ES) and
Early Finish (EF) times for each activity B. is performed by moving right-to-left through the network diagram to determine the Late Start (LS) and
Late Finish (LF) times for each activity C. is performed by moving left-to-right through the network diagram to identify the critical path D. is performed by moving right-to-left through the network diagram to determine the shortest period of time
in which the project may be completed
12. Which of the following is least true?
A. With the Precedence Diagramming Method (PDM), network diagrams are constructed with activities
represented by nodes connected by arrowed lines to complete the network logic. B. With the Arrow Diagramming Method Diagramming Method (ADM), network diagrams are constructed
with activities represented by arrowed lines connected at nodes to complete the network logic. C. Conditional Diagramming Methods, such as GERT and System Dynamics models, are used when
looping, branching and multiple project results must be included in the project network logic. D. Both ADM and PDM, as well as Conditional Diagramming Methods, use dummies and can illustrate all
four possible activity relationships, F-S-, S-F, S-S and F-F.
13. Which of the following is most true?
A. The Precedence Diagramming Method (PDM) constructs project networks by representing activities with nodes, also referred to as Activity-on-Node (AON) network diagrams.
B. The Precedence Diagramming Method (PDM) constructs project networks by representing activities with arrowed lines connected by nodes, also referred to as Activity-on-Arrow (AOA) network diagrams.
C. The Graphical Evaluation and Review Technique (GERT) constructs project networks by representing activities with nodes, also referred to as Activity-on-Node (AON) network diagrams.
D. The Program Evaluation and Review Technique (PERT) constructs project networks by representing activities with nodes, also referred to as Activity-on-Node (AON) network diagrams.
14. The Activity Sequencing process is applied to __________________________________________.
A. identify all of the deliverables-oriented work within the scope of the project B. further subdivide work packages into clearly defined activities C. create the project network diagram D. schedule all of the project’s defined activities
Page 117
Lesson 8 Applying the Activity Sequencing Process
Lesson 8 Applying the Activity Sequencing Process
- Lesson 8 Cutout Notes -
Lesson 8 Applying the Activity Sequencing Process 1. D ‘Critical path’ is one of the most important terms used by PMPs. It is important to know and understand its
definition: the longest path through a network diagram. It is also important to know that the critical path defines the shortest period of time in which a project may be completed.
2. A Although, this was not directly discussed in Lesson 8, it is very possible for a project to have more than one
critical path through its network. When more than one critical path exists, it typically increases project risk. It is usually advisable for the project team to brainstorm some solution to avoid multiple critical paths. B is not true, by default. C is not true, (good judgment should dictate that it is not conventional to attempt the creation of hybrid network diagramming methods). D is not true; the WBS identifies all of the deliverables-oriented work within project scope, the network diagram illustrates all ’activities’ and their logical interdependencies, from project start to project finish.
3. D Review the Activity Sequencing process illustration on page 105. Project Network Diagrams represents an
Output, not an Input. 4. C There are five possible paths; 1) Start-A-B-D-E-Finish, 2) Start-A-C-E-Finish, 3) Start-A-B-C-E-Finish, 4)
Start-A-B-C-D-E-Finish, 5) Start-A-C-D-E-Finish. 5. C The critical path is the longest path through a network diagram. Option A cannot be correct, because Start-
A-C-D-Finish is not a complete path through the network. Option B does represent one of the five possible complete paths through the network and, when durations are added, requires 26 days, start to finish. Option C represents a complete path and, when added, requires 32 days. Option D is a complete path and requires 30 days. When all five paths are analyzed for total time duration, the longest path through the network is Start-A-B-C-D-E-Finish (32 days). Therefore C is the correct answer. HINT: Remember, critical path is typically identified with a heavier arrowed line. If you noticed, the illustration already identified the critical path for you. Don’t be surprised to find such ‘clues’ on your actual PMP Exam.
6. D The critical path defines the shortest period of time in which a project may be completed. All four options
represent actual path times through this network diagram. The longest path is Start-A-B-C-D-E-Finish and therefore defines both the critical path and the shortest time to complete the project. If you identified the wrong path as being the critical path, then one of the other answer options may have appeared correct. On your PMP Exam, you will encounter wrong answers options that appear correct when a calculation error is made.
7. C To answer this question, you must first construct a network diagram from the given information. Be
prepared to do the same during your actual PMP Exam. The proper network diagram appears at the top of the following page. There are three possible paths through this network from start to finish; 1) Start-A-C-E-F-G-Finish, 2) Start-B-D-E-F-G-Finish and 3) Start-B-C-E-F-G-Finish.
Appendix A
Lesson Quiz Solutions
A
B
C
D
E
3 weeks
1 week
12 weeks
6 weeks
7 weeks
Start Finish F G
10 weeks 5 weeks
8. B To answer this question, you must a) construct a network diagram from the given information, b) identify
each path from start to finish c) determine which path is the longest. Remember, the longest path is the critical path. We find three possible paths; 1) Start-A-C-E-F-G-Finish (25 weeks), 2) Start-B-D-E-F-G-Finish (38 weeks) and 3) Start-B-C-E-F-G-Finish (31 weeks). Path 2 is the longest, and therefore the correct answer.
9. C Once again, to answer this question, you must first construct a network diagram from the given information.
Then you must identify all possible paths through the network and determine which path is longest. The longest path is the critical path, which defines the shortest period of time in which the project may be completed. In this example, Start-B-D-E-F-G-Finish represents the critical path, and the shortest time to complete … 38 weeks.
10. B Slack (also referred to as float, total float, path float, reserve) is determined by subtracting Early Start (ES)
from Late Start (LS). The result will be in work units (in this example, days), either positive or negative. While negative slack is unusual, it is possible in some cases. Option A is partially true, in that activities on the critical path typically have zero slack. However, nowhere in this question does it say this activity is on the critical path. Option C could appear correct if the factors are reversed doing the calculation. Option D is wrong, in that it is expressed in percentage, not work units.
11. A The correct answer is taken directly from your Lesson 8 ‘Must Know’ ReviewSheet. Option B
defines a backward pass. Options C and D are simply incorrect definitions. 12. D Options A, B and C are all correct statements. Option D is incorrect, and therefore the least true. Only
PDM can illustrate all four possible activity relationships, F-S, S-F, S-S and F-F. Only ADM uses dummy activities.
13. A Option A is the only correct statement, and therefore the most true. PDM produces Activity-on-Node (AON)
diagrams. Option B is not true because Activity-on-Arrow (AOA) diagrams are produced by ADM. Option C is not completely true because GERT is mostly concerned with looping, conditional branching and multiple project results. Option D in not true because PERT (when it was in widespread use) produced AOA-type network illustrations.
14. C Activity Sequencing is applied primarily to create the project network diagram. Option A generally describes
the Scope Definition process, not Activity Sequencing. Option B generally describes the Activity Definition process. Option D generally describes the Schedule Development process.
visit us at www.true-solution.com
Welcome ...
Learn all about the course that’s revolutionizing the way Certification Candidates prepare to pass their PMP Exam.
All the details ...
Your Print Brochure Your Video Brochure
PMP Exam Preparation Course
®
PMP, PMI and PMBOK are registered trademarks of the Project Management Institute, Inc.
And more ...
Complimentary Sample Workbook Lesson Your Complete Course Package Only $295
True Solutions, Inc. (TSI)
5001 LBJ Freeway, Suite 125-B Dallas, Texas 75244
(972) 770-0900 (972) 770-0922 (fax)
www.true-solution.com
The ULTIMATE PMP Exam Preparation Course
®
The ULTIMATE PMP Exam Prep self-paced, on-demand course package is only $295 USD. Order now, conveniently online, or by phone.
Interested in the ULTIMATE PMP Exam Prep live classroom experience? Check our schedule, then enroll to reserve your seat. Interested in a custom, value-priced, onsite delivery of ULTIMATE PMP Exam Prep for your organization? We welcome your phone call, fax or email inquiry.
www.true-solution.com voice US (972) 770-0900 fax US (972) 770-0922