Date: 14.10.15.The following List of Works Progress in PHASE-I AURUM we updated and Herewith with attached details kind your perusal.1) Unit Wiring status 173 Nos completed and 4 flats in progress 2) Lobby wiring status S.NOTOWERCOMPLETED IN FLOORSPROGRESS IN FLOORS

1ATERRACE----

2B15TERRACE

3CTERRACE----

4D15TERRACE

3) Power shafts vertical cable tray status S.NOTOWERNO. OF SHAFTS COMPLEATEDNO. SHAFTS PROGRESSREMARKS

1A30COMPLEATED

2B50COMPLEATED

3C40COMPLEATED

4D50COMPLEATED

4) Power shafts vertical cable laying status S.NOTOWERNO. OF SHAFTS COMPLEATEDNO. SHAFTS PROGRESSREMARKS

1A30COMPLEATED

2B50COMPLEATED

3C40COMPLEATED

4D41

WIP

5) Lift Electrical work statusS.NOTOWERWork statusREMARKS

1ACompletedEarthing to be done after earth pit installation

2BCompleted -do -

3CCompleted -do -

4DCompleted-do -

6) Basement horizontal cable tray status: Total 750Nos (750meters)cable tray MS supports installed and cable tray installation work in progress.

7) Floor conduit status.S.NOTOWERTOTAL FLATSWORK COMPLEATEDCLEARENCE REQUIREDREMARKS

1A19015536

2B1801800COMPLEATED

3C1121039NO CLERANCE

4D180180

0

8) CENTRAL PODIUM WORK STATUS (CONDUIT LAYED AS PER REVISED DRAWING COMPLETED)9) TERRACE PEROGOLA WORK STATUS : TOWER A,B,D COMPLETED AND TOWER C INPROGRESS10) EARTHING STATUS: SITE CLEARANCE NOT AVIABLE11) PANEL ROOM STATUS: NOT HANDEDOVER TO US12) EXTERNAL PODIUM AREA: CONDUITS DONE.13) EXTERNAL PODIUM STREET LIGHT WIRING COMPLETED14) EXTERNAL PODIUM STREET LIGHTS : 15 NOS COMPLETED AND REMAINING WIP15) G.F WIRING:TOWER B & D WIRING COMPLETED AND TOWER A WIRING IN PROGRESS16) BASEMENT AREA WIRING: STARTED C.PODIUM AREA (300 FITTINGS INSTALLED),17) LIGHTNING ARRESTER: CLAMPING & CONDUITS WORK DONE, WE NEED EARTHING WORKFRONT.18) MAIN ROAD STREET LIGHT POLES 18 POLES INSTALLED19) STREET LIGHT CABLE LAYING COMPLETED ( MAIN ROAD)20) TREE UP LIGHTS CABLE LAYING COMPLETED FOR 91 LIGHTS AND REMAINING IN PROGRESS21) COMPOUND WALL WIRING COMPLETED