Work Content - Cycle Time Diagram2
![Page 2: Work Content Feb 18 2010](https://reader036.vdocuments.us/reader036/viewer/2022081907/5481c0acb4af9f3b6d8b45f4/html5/thumbnails/2.jpg)
It is the sum of basic tasks performed at each workstation to obtain a complete and good product.
2
2.1. Work Content
Work Content = 30s + 50s + 40s = 120s
Minimum cycle timesfound in time study :
JOB 1 JOB 2 JOB 3
30s 50s 40s
Finishedpart
![Page 3: Work Content Feb 18 2010](https://reader036.vdocuments.us/reader036/viewer/2022081907/5481c0acb4af9f3b6d8b45f4/html5/thumbnails/3.jpg)
It brings out variations between each cycle (variability) and the imbalance among the operators.
3
2.2. Cycle Time Diagram
Time (in s)
0
5
10
15
20
25
30
35
40
45
OP1 OP2 OP3 OP4 OP5
Time (in s)
TAKT TIME TAKT TIME
0
5
10
15
20
25
30
35
40
45
OP1 OP2 OP3 OP4 OP5
![Page 4: Work Content Feb 18 2010](https://reader036.vdocuments.us/reader036/viewer/2022081907/5481c0acb4af9f3b6d8b45f4/html5/thumbnails/4.jpg)
4
2.2. Cycle Time Diagram
![Page 5: Work Content Feb 18 2010](https://reader036.vdocuments.us/reader036/viewer/2022081907/5481c0acb4af9f3b6d8b45f4/html5/thumbnails/5.jpg)
5
Cycle Time Measurement Form
![Page 6: Work Content Feb 18 2010](https://reader036.vdocuments.us/reader036/viewer/2022081907/5481c0acb4af9f3b6d8b45f4/html5/thumbnails/6.jpg)
6
Standardized Work Chart
![Page 7: Work Content Feb 18 2010](https://reader036.vdocuments.us/reader036/viewer/2022081907/5481c0acb4af9f3b6d8b45f4/html5/thumbnails/7.jpg)
7
Standardized Work Combination Table