Summary 3
Facility 4
Enrolment, Utilization and Capacity 19
Financial/Operations 23
Policy Criteria Assessment 25
Closing Comments and Recommendation 27
Appendices 29
Appendix A – Facility Information: 2014 Capacity Utilization Order
Appendix B – Instruction and Learning Efficiencies with Amalgamation
3
Summary
The closure of Woodlands Secondary School would reduce the overall secondary capacity by 700 seats, reducing annual operating costs and future capital expenses. The closure of Woodlands would require the movement of students to both Wellington Secondary and Nanaimo District Secondary (NDSS).
In the central Nanaimo secondary school zone, including John Barsby Community School, there was more than 745 empty seats in these four schools combined (See Table 5, Page 19). There is great need for asset consolidation and renewal in this zone.
Woodlands Secondary School has a capacity utilization of 85 percent (see Table 5, Page 19) creating inefficiencies in staffing, class compositions, and difficulty in allocating staff for student support. The Woodland’s catchment also contains a high volume of students who attend other Nanaimo secondary schools. The consolidation of Woodlands into Wellington and NDSS will allow for enhanced programming, greater classroom efficiencies and greater support for students.
Because Woodlands is located in the middle of Wellington and NDSS geographically, catchment areas could be redrawn in such a way as to ensure the least disruption possible for students who reside in that area, while meeting the Ministry of Education’s target of 105-110 percent capacity utilization. Increasing capacity utilization at John Barsby is also imperative to support the application to rebuild at NDSS.
The relocation of Woodlands students to NDSS necessitates a review of central Nanaimo secondary school’s district programs to create equal student distribution. Most of these programs currently occupy NDSS and a number of these programs could be relocated to John Barsby, serving the dual purpose of creating space for Woodlands students at NDSS, as well as filling excess capacity at John Barsby. To accommodate this and to maximize capacity utilization in the central Nanaimo secondary schools, approximately 300 district program students could be moved to John Barsby Community School from NDSS.
While the Enhanced Facilities for Learning Plan identified the closure of Woodlands for June 2017, moving up the closure date to June 2016 would be beneficial as cost savings being realized one year earlier.
4
FACILITY
Site Information
Address 1270 STRATHMORE STREET, NANAIMO, BC
Folio 85023.000
PID 005-574-927
Plan 8604
Size 6 ACRES
Legal Description LOT A, SECTION 1, NANAIMO DISTRICT, PLAN 8604, LAND DISTRICT 32
Zone CS1
COMMUNITY SERVICE ONE
Location 49.18895,-123.9711
Legal Information from the City of Nanaimo www.nanaimo.ca
Facility and Operations
School Size (gross floor area): 9009 m2
Age of Facility: See Figure 3 – Total Building Area, Page 8
Figure 1. Aerial View of Woodlands Secondary Area
5
Figure 2. Woodlands Floor Plan
6
7
8
Figure 3. Woodlands Total Building Area
9
Figure 4. Wellington Floor Plan
10
11
12
Figure 5. Nanaimo District Secondary Floor Plan
13
14
15
Migration of Woodlands Students
Graph 1. Where Woodlands Students Come From
Source: Baragar Geoschool, Sep. 2014 ; BC Ministry of Education1701 Data Collection
This includes 142 academy students and 36 international students.
85 hockey academy (14 out-of-catchment)
23 soccer academy (3 out-of-catchment)
34 beach volleyball academy (1 out-of-catchment)
Graph 2. Where Woodlands Catchment Residents Attend School
Source: Baragar Geoschool, Sep. 2014 ; BC Ministry of Education1701 Data Collection
344 83
54 34
29 7
Where Woodlands Students Come From (In Migration= 207)
Woodlands Wellington NDSS John Barsby Dover Bay LSS
344
42
39 16 11
Where Woodlands Catchment Residents Attend School
(Outward Migration=108)
Woodlands Sec. Nanaimo District Sec. Wellington Sec.
John Barsby Sec. Dover Bay Sec.
16
Figure 7. Current Catchment Areas
17
Figure 8. Proposed Catchment Changes
Wellington Secondary Catchment
Nanaimo District Secondary (NDSS) Catchment
18
Seismic Risk: See Tables 1 and 2 below – Seismic Structural Risk Ratings by Block (updated January 2015) and Seismic
Mitigation Program Risk Ratings. This information was taken from the Ministry of Education Seismic Mitigation
Program, Province of British Columbia http://bit.ly.1Wh0QVh.
Table 1. Seismic Structural Risk Ratings by Block (updated January 2015) SD SD Name Facility # Facility Name Bl
ock #
Block Name Area (m2) 2004 Risk Current Risk
Status School Risk
Comments
68 Nanaimo/ Ladysmith
6868013 WOODLANDS 1 Classrooms 2,040 High Medium Non Structural Upgrade Required
Medium
68 Nanaimo/ Ladysmith
6868013 WOODLANDS 2 Classrooms 3,714 High Medium Non Structural Upgrade Required
68 Nanaimo/ Ladysmith
6868013 WOODLANDS 3 Gymnasium 856 High Medium Non Structural Upgrade Required
68 Nanaimo/ Ladysmith
6868013 WOODLANDS 4 Shop & Cafeteria
1,233 High Medium Non Structural Upgrade Required
Table 2. Seismic Mitigation Program Risk Ratings
Rating Definition
High 1 (H1) Most vulnerable structure; at highest risk of widespread damage or structural failure; not reparable after event. Structural and non-structural seismic upgrades required.
High 2 (H2) Vulnerable structure; at high risk of widespread damage or structural failure; likely not reparable after event. Structural and non-structural seismic upgrades required.
High 3 (H3) Isolated failure to building elements such as walls are expected; building likely not reparable after event. Structural and non-structural seismic upgrades required.
Medium (M) Isolated damage to building elements is expected; non-structural elements (such as bookshelves, lighting) are at risk of failure. Non-structural upgrades required. Building to be upgraded or replaced within the Capital Plan when it has reached the end of its useful life.
Low (L) Least vulnerable structure. Would experience isolated damage and would probably be reparable after an event. Non-structural upgrades may be required.
The government is structurally upgrading schools that have a high risk rating (High 1, High 2 or High 3). The structural upgrade work will also correct any non-structural deficiencies of these high-risk locations.
Seismic structural risk rating by block: Blocks represent areas within a school that are of different construction types and have
different structural characteristics. For example, gymnasiums are usually a different type of structure than classroom blocks.
The following report shows updated risk ratings by block for all schools within the province’s 37 high-risk seismic zones –
upgrade status for each school is also included.
19
ENROLMENT, UTILIZATION AND CATCHMENT
Student Enrolment
Source: Baragar Demographic Dynamics, September 2014; and BC Ministry of Education 1701 Data Collection,
September 2014
Central Nanaimo Secondary School Enrollment and Catchment
Table 5. Central Zone Capacity Utilization
Source: Baragar Demographic Dynamics, September 2014; BC Ministry of Education 1701 Data Collection, September 2014
See Appendix A – Facility Information 2014 Capacity Utilization Order – smallest to largest utilization by zone.
Table 3. Historical Enrolment
Year 1999 2001 2003 2005 2007 2009 2011 2013 2014
Enrolment 803 780 712 790 708 685 636 578 559 Source: BC Ministry of Education 1701 Data Collection
Table 4. Projected Enrolment*
Year 2015 2017 2019 2021 2023 2025 2026
Enrolment 514 570 571 595 623 605 606
Functional Capacity
2014 2016 2021 2026
Enrol Capacity
Utilization
Enrol
Capacity Utilization
Enrol
Capacity Utilization
Enrol
Capacity Utilization
NDSS 1,400 1,092 78% 1,451 104% 1,530 109% 1,606 115%
Woodlands 700 593 85%
Wellington 900 797 89% 992 110% 987 110% 1,083 120%
John Barsby 1,000 769 77% 462 46% 530 53% 529 53%
Total 4,000 3,251 82% 2,905 88% 3,047 92% 3,218 98%
Empty Seats 749 395 253 82
20
Within the four central Nanaimo secondary schools (Woodlands, Wellington, NDSS, and John Barsby)
exists 749 empty student seats. That is, collectively, these four schools are under-enrolled by 749
students which equates to a capacity utilization score far below Ministry of Education expectations.
If Woodlands Secondary School closes, as is the recommendation from staff, 700 seats would be
removed from this calculation thereby greatly improving the capacity utilization of these four secondary
schools and the district as a whole.
For the purpose of accommodating the closure of Woodlands Secondary School, staff recommends the
following:
1) Woodlands Secondary students would relocate to either NDSS or Wellington.
(See Table 7. Woodlands Relocation to Wellington and NDSS)
2) Change the following elementary feeder schools:
Cilaire from Woodlands to Wellington
Brechin and Forest Park from Woodlands to ND
Table 6. Woodlands Relocation to Wellington and NDSS
Students Capacity Total Seats Available
Woodlands 2014 enrolment 593 – 39 ISE* 700
Wellington 2014 enrolment 797 900 103 + 125 seats in five portables currently on site
Wellington September 2016 projected enrolment
992 1,025 33
NDSS 2014 enrolment 1,194** 1,400 206
NDSS September 2016 projected enrolment
1,451 1,400 +51
*International students **Includes 40 International, 13 District Secondary Skills for Life, 98 VAST (ABOUT, RAVENS Lelum, OWL, NCC, House of Learning, 41 Program Cadre and 61 Continuing Education
It is also important to note that while NDSS has a capacity of 1,400 students and shows over capacity for
September 2016, it houses a number of special and Learning Alternatives programs that do not inhabit
the same space as more traditional classrooms. Some of the programs require much more space per
student eg. District Secondary Skills for Life, while others (VAST and Continuing Education) require much
less space per student.
Although Learn@Home 8-12 is housed in the NDSS building, the 353 full-time equivalent students are
not included in the September 2014 enrolment. However, the program requires four classrooms for its
delivery.
21
To accommodate an additional 229 students at NDSS, this would require 10 classrooms.
Staff recommend:
Moving Learn@Home 8-12 4 classrooms
Return Rooms 128 and 130 from secretarial to general instruction 2 classrooms
Convert Meeting Rooms A and B to general instruction 2 classrooms
Timetable Absorption (teachers prepping out of classroom) 8 classrooms
Total 16 classrooms
Woodlands Sport Academies
Historically, the district has allowed individual schools to develop specialty academies through the Board
Policy of 3870, Programs of Choice. Through this policy, schools were able to identify unique focuses of
students and develop these enhanced programs. Often these programs are looked at as attractions for
students that are out-of-catchment and wish to cross boundaries to attend such an academy.
These academies are based on student requests and staff willing to be the focal leader of the
academy. The Department of Learning Services has had discussions with the individual teacher leaders
and are reporting that all academies would prefer to be at NDSS. This concept also fits into the city
concept of a sports corridor on the third street connector and central access to both district and
municipal bus routes.
Woodlands Hockey Academy 8 – 12
The Hockey Academy has been running since September 2004. It is designed to provide additional training for minor hockey aged players by focusing on individual skill development as part of a regular academic program. The program is open to students who wish to improve their individual skills and maximize their potential on and off the ice. The program is connected to Hockey Canada Skills Academy standards and the students are on the ice three times a week with two days of class instruction on areas such as: nutrition, fitness, cross training and mental imagery training.
Hockey Canada supports academies that maximize the arena facility use during weekday hours. Students should also be participating in hockey in the community. Strong academic performance is emphasized throughout the student’s development. New students must submit an application to the academy along with their registration form. Woodlands traditionally considers out-of-district applications from students accepted to the Silvertips team. There are junior classes in the first semester and senior Hockey Academy classes in first and second semesters.
22
Woodlands Soccer Academy 8 – 12
The Soccer Academy has been in operation since September 2003. It is designed for soccer players who have the desire and commitment to develop their soccer skills and knowledge in an educational setting, as part of their regular academic program. Students in the academy must be registered in youth soccer, at the club-level or above. The focus of the course is individual development, rather than inter-school competition.
For many, this developmental program will enhance their opportunity to take their game beyond high school or youth soccer to the college or university level. Strong academic performance is emphasized throughout the student’s development. New students must submit an application to the academy along with their registration form.
Woodlands Beach Volleyball Academy 8 – 12
The Beach Volleyball Academy has operated at Woodlands since September 2013. The focus is on both technical and tactical skill development of individual athletes in the sport of beach volleyball. It is open to students of all ability levels who wish to participate. This is also a great way for all students interested in high performance training in beach volleyball as students will train and compete against students of the same ability level.
This program is fully endorsed by Volleyball BC. The class is in its second semester. Students participate in beach training for a minimum of 80 hours and also in indoor volleyball training, weight lifting and classroom sessions focused on the sport of beach volleyball. Strong academic performance is emphasized throughout the student’s development. Registration must be accompanied by an academy application.
Table 7. Academy Breakdown of Students
Woodlands Soccer
2015-16
Woodlands Hockey
2015-16
Woodlands Beach
Volleyball 2015-16
# of grades offered 8-12 8-12 8-12
# of students by grade
8-14 9-3
10-4 11-5 12-2
8-14 9-27
10-26 11-20 12-4
8-6 9-11 10-6 11-8 12-1
Total # of students in academy
28 91 32
# of in-catchment students
17 32 16
# of out-of-catchment students
11 59 15
Fee’s charged annually
400 800 600
Both the academies teaching staff and district staff support the recommendation that all the academies
relocate to NDSS, further supporting the community sports corridor and access to facilities.
23
FINANCIAL/OPERATIONS
Facility Operational Issues Table 8. Custodial, Maintenance and Utilities Breakdown
School Work Orders
Size (m2) Custodial Maintenance Utilities Total Per m2
Woodlands 495 9,009 $214,669 $242,894 $109,017 $566,580 62.89
John Barsby 696 11,784 $235,726 $317,701 $149,855 $703,282 59.68
NDSS 1,192 14,930 $332,597 $410,435 $167,853 $910,885 61.01
Wellington 553 10,556 $263,046 $189,735 $149,704 $602,486 57.08
Recent Maintenance Work
In the 1988-89 school year, the school was converted from a junior high school (8-10) to a secondary
high school (8-12). As a junior high school, Woodlands was not equipped with a teaching kitchen or a
trade level shop wing. Over the next number of years, major capital improvements included:
HVAC upgrade 2002
Interior renovations 2004-05
o Corridor
o Classrooms and gym entry
o Exterior/interior paint
o Wheelchair access
o Lockers
o Main electrical service
o Internet/cable access to classrooms
o Telephone upgrade
o Upgrade four washrooms
o Replace water fountains
o Renovate for vending machines and eyewash stations
Elevator install 2002
Oil contamination cleanup 2002
Home Economics Lab 2007
Over the past 10 years, maintenance projects have included, lighting upgrades, rear parking
improvements, frontage works, soccer and hockey academy improvements and reroofing.
24
Future Capital Expenses
Anticipating future capital works is slightly more challenging for Woodlands. Plans to close the school
have been included in previous facilities reports for the last 10 years. With this in mind, capital works
have been limited to those that are absolutely necessary i.e. roofing, parking improvements due to City
of Nanaimo road works.
This has created a larger than normal list of capital, program enhancements and functional
improvements.
Estimated future capital expenses include the following repairs and replacements for an approximate
value of $2,052,000:
Roofing
Boiler replacement
Shop wing improvements
Kitchen
Change rooms
Exterior paint
Flooring
Facility Rentals
Table 9. Woodlands Rental Summary Report for 2014
Complex: Woodlands # Bookings Revenue Extra Fee Total
Facility: Bandroom 25 $465 $61 $526
Facility: Cafeteria 1 $56 $25 $82
Facility: Class 107 1 $8 $0 $8
Facility: Drama Room 1 $40 $25 $66
Facility: Gym 74 $1,971 $369 $2,340
Facility: Soccer 1 – Boundary 3 $108 $25 $133
Facility: Soccer 2 – Private Prop 1 $3 $25 $28
Facility: Weight Room 24 $358 $59 $416
Report Totals 130 $3,009 $589 $3,599
25
POLICY CRITERIA ASSESSMENT SCHOOL DISTRICT 68 (NANAIMO-LADYSMITH) PROCEDURE NO. 3605P SCHOOL CLOSURE AND/OR ALTERNATE SCHOOL USE
The following steps shall be taken to ensure that an open, meaningful public consultation will take place over a period of at least 60 days prior to making a final decision on any proposed closure: Make available, in writing, pertinent facts and information considered by the Board with respect to school closure, including, but not limited to:
a. reasons for the proposed school closure b. the specific school that is considered for closure c. how the proposed closure would affect the catchment areas of affected schools d. the general effect on surrounding schools e. the number of students who would be affected, at both the closed school and surrounding
schools f. the effect of the proposed closure on district-provided student transportation g. educational program/course implications for the affected students h. the proposed effective date of the closure i. financial considerations j. impact on the Board’s capital plan, including possible alternate uses
Procedure Action Rationale and Comments
a. reasons for the proposed school closure
Aging facilities Future cost of maintaining
Raising the central Nanaimo capacity utilization
Reducing the number of empty seats
Shifting students to Wellington and NDSS
b. the specific school that is considered for closure
Woodlands Secondary School Aging facility
Declining enrolment
Projected declining enrolment
c. how the proposed closure would affect the catchment areas of affected schools
Students would be moved to Wellington and NDSS secondary schools
Catchment-areas would be enlarged
Both schools would have room for students
Wellington Secondary school has just completed a major renovation and students would be in an almost new building
26
d. the general effect on surrounding schools
Both NDSS and Wellington would reach capacity
NDSS would need to move some district programs to John Barsby
Elementary Cilaire Forest Park Brechin
To Wellington To NDSS To NDSS
e. the number of students who would be affected, at both the closed school and surrounding schools
Currently in 2014 Woodlands 593 Wellington 797 John Barsby 769 NDSS 1,092
Projected in 2016 Closed 992 462 1,451
f. the effect of the proposed closure on district-provided student transportation
None at this time Not at this time
g. educational program/course implications for the affected students
Both Wellington and NDSS will have larger student bodies to allow for more course offering
Larger staff
More speciality areas offered
Access to Skills and Trades program
More flexibility for supporting students and learning
Greater number of full-time staff allowing for more flexible support
Greater opportunities for programs Extra-curriculum opportunities
Larger sports program including football
27
Closing Comments
The closure of Woodlands Secondary School would reduce annual operating costs by approximately
$970,000 annually, and avoid future capital expenses of approximately $2 million. Furthermore,
relocated students will be in a larger school with a more robust learning environment still within the
central Nanaimo community.
An additional financial benefit would be that the Woodlands property would remain school district land
which would revert into the Asset Management Program and have a capital value of between $4 and $6
million.
Should Woodlands Secondary School close, students would:
Have access to the Skills and Trades program
Have access to more electives and senior academic courses
Have more options for alternate learning placements
Have more full-time teachers and staff to support a greater variety of students’ needs
Have greater programming and opportunities for students
There is currently space to accommodate students from Woodlands Secondary at Wellington and NDSS.
Annual Saving 5 Years Capital Total
Learning $404,800
$2,024,000
Operations $566,580
$2,832,900
$971,380 $4,856,900
$4,856,900
Future Capital Costs Avoided $2,052,000
$2,052,000
Long-term Savings on Proposed Closure
$6,908,900
28
Recommendation
Based on the information and data, staff recommends that:
Woodlands Secondary School close June 30, 2016
Consultation begin to determine the most appropriate location for Learn@Home 8-12 and all district programs connected to the NDSS site
The Hockey Academy be relocated to NDSS
The Soccer Academy be relocated to NDSS
The Beach Volleyball Academy be relocated to NDSS This Strategy will:
Reduce annual operating costs by approximately $970,000
Avoid future capital expenses
Contribute to ensuring that the existing school assets are maintained at or better than the FCI provincial average score of 0.43
Feedback
The Board of Education encourages individuals and groups to submit their input through the online
survey process which can be found under the Facilities Plan Update page on the district website
www.sd68.bc.ca, or written comments via email [email protected], fax 250 741-5309; or mail to
the Board of Education, 395 Wakesiah Avenue, Nanaimo, BC V9R 3K6 by Sunday, November 15.
Appendix A
Appendix B
Instruction and Learning Efficiencies with Amalgamation
Woodlands FTE Amount
Principals and Vice-Principals (1.00) 138,700
Education Assistants (0.98) 46,700
Teachers (0.72) 74,500
Support Staff (2.71) 143,200
Other 1,700
Annual Instruction and Learning savings 404,800
NCI/Woodbank FTE Amount
Principals and Vice-Principals (1.00) 122,900
Education Assistants (0.28) 13,700
Teachers (1.60) 164,500
Support Staff (0.57) 30,900
Other 400
Annual Instruction and Learning savings 332,400
Rutherford FTE Amount
Principals and Vice-Principals 1.00 (98,700)
Education Assistants (0.50) 24,500
Teachers (3.80) 393,200
Support Staff (0.57) 30,900
Other 400
Annual Instruction and Learning savings 350,300
Total Savings FTE Amount
Principals and Vice-Principals (1.00) 162,900
Education Assistants (1.76) 84,900
Teachers (6.12) 632,200
Support Staff (3.85) 205,000
Other - 2,500
1,087,500