Visit Locations
5 and 6 July 2004 Gothenburg, Sweden Tampere, Finland Helsinki, Finland
21 and 22 July 2004 Densitron Ferrograph Factory, Newcastle, UK Newcastle, UK Chorley, Lancashire, UK Manchester Airport, UK
Gothenburg
549 Buses 18 Regional Train lines 204 Trams 26 Ferries Fully integrated system Widespread real-time
information systems provided by GoTiC Project
Gothenburg
Good Fixed information everywhere
Gothenburg
Real Time information at most stops
Gothenburg
At Interchange points colour coded displays
Gothenburg
Rail and Bus station link together seamlessly
Gothenburg
Not everything is right though
Tampere
300 buses Tram/Train plans PARAS system for
communications between smartcard system, traffic signals and PT vehicles
“You never use enough time on specifications”
System designed to operate at -40°C
Tampere
Outdoor signs for a group of stops
Tampere
Customer profiling from Smartcard system
Web and mobile services part of the system
Helsinki - Tikkurilla
Outdoor real time departure sign