WINTER HILLS, SECTOR 77, GURGAON
Construction Status UpdateJuly 2017
Winter Hills, 77, Gurgaon – External Development
TOWER 1
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster Completed
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting WIP
UPVC work WIP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 2
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster Completed
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting WIP
UPVC work Completed
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 3
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster Completed
Kota Stone OP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting WIP
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 4
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster Completed
Kota Stone OP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting WIP
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 5
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster WIP
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles OP
MS Railing Completed
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 6
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster WIP
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 7
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster WIP
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 8
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster Completed
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 9
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster WIP
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles WIP
MS Railing Completed
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 10
Particulars Status
Structural Work Completed
External plaster WIP
Internal plaster WIP
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles OP
MS Railing WIP
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 11
Particulars Status
Structural Work Completed
External plaster Completed
Internal plaster WIP
Kota Stone WIP
Italian marble WIP
Indian Marble WIP
Tiles OP
MS Railing WIP
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
TOWER 12
Particulars Status
Structural Work Completed
External plaster WIP
Internal plaster WIP
Kota Stone OP
Italian marble OP
Indian Marble OP
Tiles OP
MS Railing WIP
External painting CAM
UPVC work OP
MEP WIP
Note: WIP – Work in Progress / OP – Order Placed / CAM – Commence after Monsoon
Required efforts are being made to get the project Ready-for-Possession by December 2017