wind catcher public service company of oklahoma...

2
The Wind Catcher Energy Connection Project components include: • Acquiring the Wind Catcher Facility from Invenergy, LLC when completed in late 2020. The wind farm features 800 GE 2.5 MW wind turbines located on 300,000 acres in Cimarron and Texas counties. • Building the Wind Catcher Power Line. The approximately 350-mile 765 kV power line is the connection to efficiently deliver the renewable power to SWEPCO and PSO customers. • Constructing two new substations. One will be located at the wind facility and the other near Tulsa. The Wind Catcher Energy Connection Project will provide a cost savings of $7 billion over 25 years and diversify the energy supply for PSO and SWEPCO customers. Additional benefits include approximately 4,000 direct and 4,400 indirect jobs annually during construction and 80 permanent jobs once operational. The project will also contribute approximately $300 million in property taxes over the life of the project. The Wind Catcher Facility is located in parts of Texas and Cimarron counties in western Oklahoma. The proposed 350-mile 765 kV power line will start at the wind facility, cross parts of Oklahoma and end at a new substation near Tulsa. The line route is under development. WHAT PROJECT SCHEDULE WHY WHERE LINE ROUTE DEVELOPMENT PROCESS Summer 2017 FILE REGULATORY APPLICATIONS* Summer 2017 OPEN HOUSE FOR PUBLIC INPUT Fall 2017 RIGHT-OF-WAY (ROW) COMMUNICATIONS BEGIN Early 2018 FINAL ROUTE DETERMINATION Late 2017 ROW ACQUISITION BEGINS Spring 2018 PRELIMINARY ENGINEERING ACTIVITIES Early 2018 ROW CLEARING & PRE-CONSTRUCTION Late 2018 CONSTRUCTION BEGINS Early 2019 PROJECT IN-SERVICE Late 2020 ROW RESTORATION COMPLETE Fall 2021 *Timeline subject to change. *Regulatory applications to be filed in Arkansas, Louisiana, Oklahoma, and Texas. *Timeline subject to change. *Regulatory applications to be filed in Arkansas, Louisiana, Oklahoma, and Texas. 2017 2018 2019 2020 2021 2022 WIND CATCHER ENERGY CONNECTION PROJECT Public Service Company of Oklahoma (PSO) and Southwestern Electric Power Company (SWEPCO) plan to invest approximately $4.5 billion to bring 2,000 megawatts (MW) of new wind energy to customers in Arkansas, Louisiana, Oklahoma and Texas. The Wind Catcher Energy Connection Project is expected to save PSO and SWEPCO customers approximately $7 billion, net of costs, over 25 years. The project includes acquiring a wind farm currently under construction in the Oklahoma Panhandle and building about 350-miles of dedicated extra highvoltage 765 kilovolt (kV) power line to connect two new substations, one located at the wind facility and a second near Tulsa. PSO will own about 30 percent of the project, including 600 MW of wind. SWEPCO will own approximately 70 percent of the overall project, including 1,400 MW of wind. The project is subject to regulatory approvals in Arkansas, Louisiana, Oklahoma and Texas as well as the Federal Energy Regulatory Commission. Development of the line route will begin in the summer of 2017. The overall project is expected to deliver wind energy to customers by the end of 2020.

Upload: lamnguyet

Post on 21-May-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

The Wind Catcher Energy Connection Project components include:• Acquiring the Wind Catcher Facility from Invenergy, LLC when completed in late 2020. The wind farm features 800 GE 2.5 MW wind turbines located on 300,000 acres in Cimarron and Texas counties.• Building the Wind Catcher Power Line. The approximately 350-mile 765 kV power line is the connection to efficiently deliver the renewable power to SWEPCO and PSO customers.• Constructing two new substations. One will be located at the wind facility and the other near Tulsa.

The Wind Catcher Energy Connection Projectwill provide a cost savings of $7 billion over 25years and diversify the energy supply for PSOand SWEPCO customers. Additional benefitsinclude approximately 4,000 direct and 4,400indirect jobs annually during construction and80 permanent jobs once operational. The projectwill also contribute approximately $300 millionin property taxes over the life of the project.

The Wind Catcher Facility is located in partsof Texas and Cimarron counties in westernOklahoma.

The proposed 350-mile 765 kV power line willstart at the wind facility, cross parts ofOklahoma and end at a new substation nearTulsa. The line route is under development.

WHAT

PROJECT SCHEDULE

WHY WHERE

LINE ROUTE DEVELOPMENT PROCESSSummer 2017

FILE REGULATORY APPLICATIONS*Summer 2017OPEN HOUSE FOR PUBLIC INPUTFall 2017

RIGHT-OF-WAY (ROW) COMMUNICATIONS BEGINEarly 2018

FINAL ROUTE DETERMINATIONLate 2017

ROW ACQUISITION BEGINSSpring 2018

PRELIMINARY ENGINEERING ACTIVITIESEarly 2018

ROW CLEARING & PRE-CONSTRUCTIONLate 2018

CONSTRUCTION BEGINSEarly 2019PROJECT IN-SERVICELate 2020ROW RESTORATION COMPLETEFall 2021

*Timeline subject to change. *Regulatory applications to be filed in Arkansas, Louisiana, Oklahoma, and Texas.*Timeline subject to change. *Regulatory applications to be filed in Arkansas, Louisiana, Oklahoma, and Texas.

2017 2018 2019 2020 2021 2022

WIND CATCHERENERGY CONNECTION PROJECT

Public Service Company of Oklahoma (PSO) and Southwestern Electric

Power Company (SWEPCO) plan to invest approximately $4.5 billion to bring

2,000 megawatts (MW) of new wind energy to customers in Arkansas,

Louisiana, Oklahoma and Texas. The Wind Catcher Energy Connection

Project is expected to save PSO and SWEPCO customers approximately $7

billion, net of costs, over 25 years.

The project includes acquiring a wind farm currently under construction in

the Oklahoma Panhandle and building about 350-miles of dedicated extra

highvoltage 765 kilovolt (kV) power line to connect two new substations, one

located at the wind facility and a second near Tulsa.

PSO will own about 30 percent of the project, including 600 MW of wind.

SWEPCO will own approximately 70 percent of the overall project,

including 1,400 MW of wind. The project is subject to regulatory approvals

in Arkansas, Louisiana, Oklahoma and Texas as well as the Federal

Energy Regulatory Commission.

Development of the line route will begin in the summer of 2017. The overall

project is expected to deliver wind energy to customers by the end of 2020.

LAWTON

FAYETTEVILLETULSA

OKLAHOMA

TEXAS

ARKANSAS

MISSOURI

KANSAS

LOUISIANA

CLARENDON

LONGVIEWSHREVEPORT

N

CIMARRONCOUNTY TEXAS

COUNTY

PSO & SWEPCO VALUE YOUR INPUT ABOUT THE PROJECT. PLEASE SEND COMMENTS AND QUESTIONS TO:

Typical Height: Approximately 140 feetTypical Base: Approximately 40 to 50 feet square Typical Right-of-Way Width: 200 feetTypical Distance between Structures: Approximately 1,000 - 1,500 feet (four to five structures/mile)

PSO's and SWEPCO’s parent company, American Electric Power,

owns the nation’s largest electricity transmission system, a more

than 40,000-mile network that includes more 765-kilovolt extrahigh

voltage transmission lines than all other U.S. transmission

systems combined.

PSO and SWEPCO are committed to carefully balancing the

energy needs of customers while protecting the environment and

natural beauty of the region.

Route to be determined for dedicated line to connect the two future substations.

The line route is currently underdevelopment and study segments will bepresented for public input in the fallof 2017.

*Exact structure, height and right-of-way requirements may vary

[email protected]

If you have questions or need more information visit the project website atwww.PSOklahoma.com/Windcatcher

TYPICAL PROPOSED 765 KV STRUCTURE

7/26/20177/26/2017

Wind Catcher Facility

PSO Service Territory

Wind Catcher 765 kV Power Line(actual route to be determined)

SWEPCO Service Territory

Future Substation

PROJECT MAP

LEGEND