wildlife management seriesd2ouvy59p0dg6k.cloudfront.net/downloads/project_planning.pdfthe project...

48
WILDLIFE MANAGEMENT SERIES PROJECT MANUAL PLANNING

Upload: others

Post on 09-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

WILDLIFE MANAGEMENT SERIES

PROJECT

MANUAL

PLANNING

Page 2: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

1

PROJECT

PLANNING

M A N U A L

Page 3: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

2

These guideline booklets are based on field experience and original research reports which are available from the WWF -Southern African Regional Programme Office (SARPO) in Harare. WWF wishes to acknowledge the importantcontribution made by the Rural District Councils (RDCs) and their constituent communities in the development of theseries. The methods presented in the manual have been tested by the Support to CAMPFIRE Project with differentcommunities in several districts.

In addition, WWF wishes to acknowledge the valuable ideas contributed by Thandie Chikomo, Champion Chinhoyi,Brian Child and Hasan Moinuddin.

The Norwegian Agency for Development Co-operation (NORAD) is funding the WWF Resource Management Supportto CAMPFIRE Project which produced this guideline manual. The work undertaken here is part of a collaborativeprogramme with the Department of National Parks and Wild Life Management.

Editing, illustration, design and production: Action

Published in June, 2001 by WWF-Southern Africa Regional Programme Office (SARPO), Harare, Zimbabwe. Anyreproduction in full or in part of this publication must mention the title and credit the above-mentioned publisher as thecopyright owner. © text (2001) WWF. All rights reserved.

This publication was also made possiblethrough support provided by the office ofUSAID Harare under the terms of project613-0241 and grant 690-0251-4-9001-00. The opinions expressed herein arethose of the authors and do not necessarilyreflect the views of USAID. This materialhas been produced by the authority of andfor the use of the CAMPFIRE programme inZimbabwe for information purposes only.

ACTION

Page 4: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

INTRODUCTION

Introduction to the Project Planning Manual........................................................................

CHAPTER 1

Background to project planning.............................................................................................

CHAPTER 2

Identifying projects ..................................................................................................................

CHAPTER 3

Project planning........................................................................................................................

CHAPTER 4

Project implementation and monitoring...............................................................................

CHAPTER 5

Project evaluation.....................................................................................................................

APPENDICES ......................................................................................................................................39

35

29

21

17

13

5

3

CONTENTS

Page 5: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

4

A locally made poster highlighting the importance of CAMPFIRE projects in Masoka Ward, Guruve RDC.

Page 6: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

What is the objective of this manual? Under the Communal Areas Management Programme forIndigenous Resources (CAMPFIRE), rural communitiesparticipate in, and benefit from, the management of theirwildlife and other natural resources. The money from wildlifeis used by wards for CAMPFIRE administration, theimplementation of projects and sometimes the payment ofhousehold dividends. It is through the projects, that mostpeople derive a benefit from CAMPFIRE and their wildlife.

The purpose of this manual is to improve the project planningand project implementation skills of people involved inCAMPFIRE and other natural resource managementprogrammes. The manual breaks project planning andimplementation into a series of simple stages and steps. Themethods are easy to use and can save project implementorsfrom making costly planning mistakes at the district and sub-district levels.

What methods are used by the manual?The manual proposes using a simple project planning matrixand participatory approaches to improve project planning andimplementation.

• The project planning matrix: This is a simpleframework which stresses the major activities of theproject (what), their timing (when), their cost (howmuch) and who is responsible for their implementation(who). The matrix can be changed to suit the exact needsof the planners.

The project planning matrix is a flexible tool and must beused to meet the needs of the planners. The manualshows how the project planning matrix can be used ateach of the following stages of the common project cycle.These are:

• Stage One: Project identification,

• Stage Two: Project planning and review,

• Stage Three: Project implementation andmonitoring,

• Stage Four: Project evaluation.

• Participation in project planning: The manual stressesthe importance of the participation of the project’s keystakeholders during planning. The project plan and itsimplementation will be improved if the planning processinitially involves as many of the key stakeholders aspossible.

5

INTRODUCTION

INTRODUCTION TO THE PROJECT PLANNING MANUAL

Page 7: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

6

Evaluation Planning

The project matrix is used at every stage of the Project Cycle.

Implementationand monitoring

Identification

Page 8: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

This will ensure that everybody involved;

• understands the project,

• contributes to the development of the project plan,

• feels part of a team.

Participation in project planning is improved by;

• inviting people to contribute ideas,

• using visual planning methods.

How were these methods developed?The project planning matrix and the visualisation methods areloosely based on the “Logical Framework Approach” (LFA)used by Governments and Non-governmental Organisations(NGOs) for planning development work. The methodsproposed in the manual were designed and tested by producercommunities and Rural District Councils during the first phaseof the WWF Support to CAMPFIRE Project.

How can greater participation in project planning beachieved?It is important to allow key stakeholders to participate in, andcontribute to, project planning. Visualising the planningimproves participation by different stakeholders. There aremany ways of visualising the project planning process such asthe following:

• Cards and pin-boards - These are the best way ofvisualising the project planning process. Shortstatements are written on cards which are pinned to aboard. This method is extremely flexible - the cards canbe re-written, their position changed and they lendthemselves to the project matrix approach. Cards ofdifferent colours can be used to improve communicationbetween the participants. The disadvantage of cards andpin boards is that they are expensive. Pin boards can beborrowed from GTZ in Harare, for a small fee.

7

Page 9: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

• Flip charts and easel - These are a good way ofvisualising project planning. Their disadvantage is thatthey are not as flexible as cards and pinboards.

• Chalk and blackboard - Schools are a common meetingplace in many communities. Most classrooms in theseschools have blackboards and a supply of colouredchalk. The planning methods described in the manualcan be used on a blackboard but will have to be copiedonto paper as a permanent record.

• Paper and floor - If none of the above materials areavailable, a participatory project planning process canstill be achieved by using pieces of A4 paper laid out onthe floor.

Who are the key stakeholders in a project?The key stakeholders of any project will depend on where theproject is, who the project is being implemented by and whothe intended beneficiaries are.

8

Page 10: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

For natural resource management and CAMPFIRE relatedprojects, the key stakeholders will normally include;

• rural district council executive officers,

• local government officials for departments such ashealth, education, natural resources and agriculture,

• traditional and political leaders,

• special interest groups from within the community,

• locally based NGOs and other aid organisations.

Who should use this manual?Anybody who is involved in planning simple projects in eitherrural or urban areas should find this manual useful. Under CAMPFIRE the manual can be used by;

• district level planners such as executive officers andpolicy makers (councillors),

• sub-district level planners such as ward wildlifecommittees.

This manual assumes that most district and sub-districtprojects are being funded with money earned from wildlife.The manual does not specifically assist with the preparation ofproject plans for donors, although Appendix 3 gives someideas of what should be included in a proposal to a donor.Most donors would be very supportive of proposals whichinclude a project planning matrix.

9

Page 11: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

10

Page 12: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

11

Page 13: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

How should this manual be used? The manual should be used as a guide to project planning andimplementation. Where possible, ideas are presented as stages ofthe project cycle and then as steps within each stage. A samplep roject dealing with human-wildlife conflict in Chilazi RDC isused as an example throughout the manual.

How is this manual organised? This manual has five chapters as follows:

• Chapter One examines some of the background issues top roject planning and why it is so important to plan pro j e c t sp ro p e r l y.

• Chapter Two discusses ways in which wildlife pro d u c e rcommunities and their committees can identify appro p r i a t ep ro j e c t s .

• Chapter Three describes how to develop a simple pro j e c tplanning matrix.

• Chapter Four discusses how the project planning matrixcan be used during project implementation andm o n i t o r i n g .

• Chapter Five describes why project evaluation is importantand how it can be carried out.

The manual has four appendices. Appendix 1 is a glossary of keyw o rds and terms. Appendix 2 describes the principles and stepsinvolved in a simple cost:benefit analysis. Appendix 3 describeswhat a simple project proposal to a donor should contain.Appendix 4 gives some ideas of who might fund small pro j e c t s .

12

Page 14: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Although this manual uses a simple four stage projectplanning cycle, the implementation and management of aproject is an ongoing commitment. Even whenimplementation has been completed, projects still need to bemanaged, the infrastructure maintained and important recordskept.

What is a project? A project is a set of related activities which, when completed,will achieve a defined objective. This objective should beachieved;

• within a given time period,

• within a given budget.

There is no limit to the size of a project. Generally however,bigger projects are more difficult to plan and implement thansmaller projects. If a big project can be broken down intoseveral smaller sub-projects, this will make planning andimplementation easier.

Why is it important to plan a project? There are two reasons why it is important to plan projectsproperly:

• Financial and human resources are always limited. Nocommunity, group or even individuals have all theresources that they require. They must plan to make thebest use of the available resources (financial, human andnatural resources) that they have.

• Poor planning has been shown to be the most importantreason why projects fail to meet their given objectives,exceed their given budget and/or are not completed ontime.

What are the other factors which effect the success of a project?The success of a project will be affected by internal andexternal factors:

• Internal factors, such as the number and skills of peopleneeded to make a project work properly, can becontrolled by the project.

• External factors, such as the economic conditions(market, price) or the ecological conditions (climate,drought), cannot be controlled by the project.

13

CHAPTER 1

BACKGROUND TO PROJECT PLANNING

We have agreed to build an extra classroom block for our school, before

the January 1 for aboutZ$550,000.

Page 15: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Project planners will try and reduce the number of externalfactors that can negatively affect the project. A robust project isone where the project overcomes important changes in theexternal factors. All project planners should aim to developrobust projects which are capable of withstanding majorchanges in their external factors.

What kind of projects are being implemented underCAMPFIRE? A wide range of projects have been planned and implementedunder CAMPFIRE. Most of the projects can be classified asfollows:

14

Type of project

Income generating projects

Social infra-structure projects

Natural resource management projects

Description and objective

The objective of the project is to make a profit.

Example: Sanyati Bridge Lodges in Hurungwe District

The objective of the project is to assist a certain group within the community.

Example: Kanyurira Clinic, Guruve District

The objective of the project is to improve natural resource management.

Example: Repairs to Maitengwe Dam in Bulilamamangwe District

I need moretraining.

This is the third flood in four

years.

Page 16: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

15

What is the relationship between projects and naturalresource management?Under CAMPFIRE, RDCs earn revenue by leasing the rightsover wildlife to commercial safari operators. Between 1989 and1999, the fourteen major wildlife producing districts devolvedapproximately Z$119 million or US$8 million to wards andvillages. This money has been used to;

• pay for the administration costs of CAMPFIRE(meetings, allowances, transport) in the producer wards,

• pay for natural resource management activities such asgame guards, fence monitors and problem animalreporters,

• to pay household dividends in some wards such asKanyurira, Guruve RDC and Mahenye, Chipinge RDC,

• pay for the implement of projects at district, ward andvillage level. It is through these projects that most peoplein CAMPFIRE Districts experience the benefit from theirwildlife.

SummaryBy planning their projects communities, will make better useof their CAMPFIRE revenue. This will strengthen the linkbetween people in the community and the wildlife resource.

Sanyati Bridge Lodges in Hurungwe District

Kanyurira Clinic in Guruve District

Page 17: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

16

0

0.5

1.0

1.5

2.0

2.5

3.0

CommunitiesSport hunting Tourism

Hides & Ivory Other

Management

Levy

‘89 ‘90 ‘91 ‘92 ‘93 ‘94 ‘95 ‘96 ‘97 ‘98 ‘99‘89 ‘90 ‘91 ‘92 ‘93 ‘94 ‘95 ‘96 ‘97 ‘98 ‘99

Other Not Detailed

0

0.5

1.0

1.5

2.0

2.5

3.0

Year Year

CAMPFIRE Income (US$): 1989 - 1999 Allocation of CAMPFIRE Revenue (US$): 1989 - 1999

Page 18: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

The first stage in the project cycle is Project Identification.There are many ways in which a project might be identified,for example;

• a project might be one person’s good idea,

• it might be the result of an analytical (problem analysis)approach as described below.

What is problem analysis? Problem analysis aims to identify the major problems andtheir causes. When the problem analysis is being carried out, itis very important that people agree on the current situation,i.e. they should not imagine or anticipate future problems.

Why is problem analysis important in project planning? In most rural areas of Zimbabwe, people have many problems.Problem analysis is especially important because;

• it makes people think about what their most importantproblems are. This helps to prioritise projects when thereare only limited resources available,

• it ensures that if the right cause of the problem isidentified, then the right solution can be found.

How is problem analysis carried out? There are five steps in a problem analysis, as follows:

Step one - Identifying problems: It is important to getas wide a range of opinions as possible. Different peopleand different groups of people have very different ideasof what their problems are. In a meeting or workshop,participants should write their most serious problem ona card or piece of paper. Each person should only writeone problem.

Example: A problem identification from a projectplanning workshop in Chilazi Ward produced 20problems. Many of these problems were similar, forexample, the school roof is leaking and the school is old,are very similar statements of the same problem.

17

CHAPTER 2CHAPTER 2

IDENTIFYING PROJECTS

Identification

Planning

Implementationand monitoring

Evaluation

No water atschool

Problemanimal control

Transport

Transport istoo

expensive

No clinicPoor soils

School roofleaking

No busserviceThe clinic is

far

There is noirrigation

The school isold

There is nofence

Problemanimals

Buffaloseating

cotton andmaize

Many wildanimals

There aremany

mosquitoesWe have

few cattle Very dry andhot

Fertiliser istoo expensive

Too manyanimals eating

crops

Page 19: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Step two - Prioritising one problem: The second step isto find and agree on the most important problem. If theproblems are written on cards or pieces of paper sort thecards into classes of similar problems. The class with thehighest number of cards often indicates the mostimportant problem. However, this is not always so and itis important to discuss, debate and finally agree as agroup, on one problem.

Example: In Chilazi Ward there were five classes ofproblems. These were, the school, human-wildlifeconflict, transport, health and agriculture. The mostcommon problem identified by the participants washuman-wildlife conflict.

Step three - Finding the causes of the problem: Before aspecific project can be identified, the causes of theproblem must be analysed. These are the factors whichdirectly lead to the problem. Another way of identifyingcauses is to ask the question “why do we have thisproblem?”

Example: In Chilazi, there were five causes of the human-wildlife conflict as follows:

18

School Human -wildlife conflict Transport Health Agriculture

No water atschool

Problem animalcontrol

Transport

No clinic Poor soils

School roofleaking

No busservice

The clinic isfar

There is noirrigation

The schoolis old There is no

fence

Problem animals

Buffalos eatingcotton and

maize

Many wildanimals

There aremany

mosquitoesWe have few

cattle

Very dry andhot

There is nobarrierbetween

people andwildlife

Agricultureis expandinginto wildlife

areas

Buffalo andelephants

prefer cropsto naturalvegetation

The numberof buffalo

andelephants inthe ward isincreasing

There is noproblemanimalcontrolsystem

Humanwildlifeconflicts

Fertiliser istoo expensive

Too manyanimals eating

cropsTransport is

tooexpensive

Page 20: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Step four - Solving the cause of the problem:Participants must suggest direct methods of solving thecauses of the problem. These solutions to the causes ofthe problem are the basis for identifying new projects forimplementation.

Example: In Chilazi Ward, the participants identifiedsolutions to four of the five causes of the problem. Thesewere to construct an electric fence, to limit the expansionof agriculture through land use planning, to increase thequotas and to employ problem animal hunters.

Step five - The options analysis: If the steps given above havebeen followed, there will always be more than one solutionwhich can be turned into a project. The aim of the optionsanalysis is to discuss each of the options in a commonframework. This will help prioritise the options and identify oneviable project to be implemented. The options analysis asks somesimple questions about the proposed projects. The types ofquestions that need to be asked are :

• How much will the project cost? (This is also known as thecapital cost of the pro j e c t )

• How much will the project cost to run? (This is known asthe re c u r rent costs of the pro j e c t )

• How difficult will the project be to implement andm a n a g e ?

• How likely is it that the project will solve the pro b l e m ?

The answers to the questions a re used to rank the options whichhave been analysed. The ranking is simply the selection, in ord e r,of the option which is most likely to solve the problem that wasi d e n t i f i e d .

19

There is noproblemanimalcontrolsystem

Employproblemanimal

hunters toprotectcrops

Increase thesport hunting

quota

?Limit theexpansion ofagriculture

(no newimmigrants)

Construct anelectric

fence aroundthe

agriculturalarea

There is nobarrierbetween

people andwildlife

Agriculture isexpanding

into wildlifeareas

Buffalo andelephants

prefer cropsto naturalvegetation

The numberof buffalo

andelephants inthe ward isincreasing

Humanwildlifeconflicts

Page 21: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

E x a m p l e : The option analysis for Chilazi Wa rd looked at thre eoptions. These were; limiting agriculture, constructing an electricfence and employing problem animal hunters to protect thec rops. The options analysis used four questions, these were :

• What was the capital cost of the pro j e c t ?

• What the re c u r rent costs of the project were ?

• How difficult was the project going to be to implement?

• That was the likelihood or chances that the project optionwould solve the pro b l e m ?

The participants agreed that the best option of the three was theconstruction of the electric fence i.e. it was ranked 1.

What other factors should be considered in the analysis ofoptions? Other factors which might be considered in the optionsanalysis are:

• Who will benefit from the project? It is important toidentify which groups of people will benefit from theproject. As a matter of principle, projects should try andbenefit all the groups within the community.

• Who will lose as a result of the project? There are veryfew projects where there are only winners. It isimportant to consider who might be negatively affectedby the project. If necessary, the project might have to bere-designed to reduce the negative impact of the project.

• What is the impact on the environment? Some projects,especially infra-structure projects, might have a negativeimpact on the environment. These need to be identifiedand ways of reducing the impact might have to beconsidered.

• What is the cost:benefit ratio? Instead of just looking atthe cost of the project, a cost:benefit analysis comparesthe costs to the likely benefits of the project. This is amore rigorous way of examining the options. A simpleoutline of a cost:benefit analysis is given in Appendix 2.

SummaryIf project identification is not properly done, this can result inthe wrong project being implemented. As a result, the project;

• will not solve the problem that people expected it to,

• will not be viable and sustainable.

20

Option Recurrentcost Implementation Likelihood of

meeting objective Rank

Limit the expansionof agriculture (no new

immigrants)Could be high? Very difficult to limit -

new families need land Low 2

1

3

Construct an electricfence around thecultivated areas

Estimate at 10% perannum = Z$130,000

Can be done - a line hasalready been agreed with

all the farmersHigh

Employ problemanimal hunters to

protect crops10 persons x Z$1 000

/month x 6 = Z$60,000

Capital cost

Low capital cost

25km x Z$52 000/km= Z$1.3 million

Low: uniforms,weapons, training etc

PAC only kill animals anddoes not deal with the

problemLow

Page 22: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

This chapter shows how to use the project planning matrix toplan the chosen project. The project planning matrix makes itclear;

• what the objective and the major activities of the project are,

• when each activity will be completed by,

• how much each activity will cost,

• who is responsible for the activity.

Who should be involved in project planning? The most important people to be present at this stage are thosewho are going to implement the project. They must be able toagree that;

• the activities are feasible,

• when the activities are completed they will meet theproject’s objective,

• the activities can be completed within the given time andbudget.

What resources are needed for project planning? Like problem analysis, project planning is improved if it isdone in a participatory way. This means that the planningstage should be visualised so that everyone involved canparticipate. Visualisation can be achieved with;

• pin-boards and cards,

• flip chart and easel,

• blackboard and chalk,

• pieces of paper, laid on the ground.

If there are only a few people involved, then it can be done onpaper with the participants seated around a table.

21

CHAPTER 2CHAPTER 3

PROJECT PLANNING

The objective of the project is to construct anelectric fence around the cultivated areas by thestart of the next rains to stop crop destruction

by elephant and buffalo

1.Activities(What) 2. When 3. Who 4. Cost 5. Other

1. Clear theagreed fence

line of alltrees and

shrubs

start beforeend of May

and finish byend of July

2001

contractlabourers

SupervisorS. Mutake(WWMC)

5 persons per day$30 per person

per day200 m per person

per day labour: 25 days x 5

x 30 = $3,750supervisor:

25 days x 40 = $1,000

Total: $4,750

1. workersto bring

their owntools

Identification

Planning

Implementationand monitoring

Evaluation

Page 23: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

What is the project matrix?The project planning matrix is a framework, which oncompletion, clearly shows;

• the objective of the project (as a heading)

• what each activity consists of (column 1),

• by when each activity should be completed (column 2),

• who is responsible for the activity (column 3)

• the cost of each activity (column 4),

• any other resources that are needed (column 5).

The matrix can be developed and read either in rows orcolumns. The matrix is the main feature of the project plan.

What are the steps involved in developing the projectplanning matrix? There are seven major steps in project matrix. These are:

Step one - Agreeing on the objective: The objective ofthe project should be clearly stated at the beginning ofthe plan. Ideally, it should also include a date by whenthe project will be completed. The objective of the projectshould come from the problem analysis.

Example: The objective of the fence in Chilazi Ward is to“stop crop destruction by elephant and buffalo”

22

Page 24: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

23

Step two - Defining the major activities: The secondstep is to decide on and list the major activities that needto be completed for the project to succeed. Each activitymust be;

• clearly defined so that everybody knows exactlywhat needs to happen,

• manageable either as single activity or severalrelated tasks.

The activities should be listed in the order that they mustbe undertaken. Defining the activities and then listingthem in the right order might take more than oneattempt. This iterative process is an important part ofproject planning.

Example: The construction of the electric fence in ChilaziWard has been broken down into eight activities (seeproject matrix page 27).

Step three - The timing of each activity: The third stepis to decide when each activity will start, how long it willtake to complete and most importantly, by when it willbe finished. There are two ways of doing this. The firstway is to use actual dates, which is better as itestablishes real deadlines and target dates. The secondway, is to allocate a number of days but no fixed dates.This option should only be used when there is nodefinite starting date for the project.

Example: The first activity on the Chilazi Fence Project,is to clear the agreed fence line. This should start beforethe end of May and finish before the end of July.

Step four - The responsibility for each activity: Thefourth step is to identify who is responsible for theactivity. Where possible, a single person should be giventhe responsibility for the activity. If a company is beingcontracted, the name of that company should be used onthe matrix under the column “who”.

Example: In the Chilazi Fence Project, S. Mutake amember of the Ward Wildlife Committee (WWMC), hasagreed to be responsible for clearing the fence line.

Page 25: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Step five - The cost of each activity: The fifth step is toestimate the cost of each activity. For each activity list;

• what materials will be required and what they will cost,

• what time (labour / supervision / meetings /travel and subsistence ) will be required and whatit will cost,

• what transport is required and what it will cost.

For each activity, there should be a sub-total of costs. Thetotal cost of the project can then be calculated by addingup the costs of all the activities. At first, the planningmatrix will only have rough estimates of costs. As theplan is revised and improved, the costs can be mademore accurate.

Example: The cost of clearing the fence line will be:

• labour = $3,750

• supervisor = $1,000

• total = $4,750

It is normal practice to include a factor for priceincreases. This is known as the contingency and isusually calculated as a percentage. The percentage usedto calculate the contingency will depend on;

• the length of the project,

• the rate of inflation.

If the project is going to take six months from start tofinish and the annual rate of inflation 50%, then it wouldbe appropriate to use a figure of between 20% and 25%to calculate the contingency.

Example: The sub-total of the Chilazi Fence Project hasbeen estimated at Z$1,311,730. Using a contingency of25% (0.25 x Z$1,311,730) the actual contingency has beencalculated as Z$262,346. The total project now costsZW$1,574,076.

• sub-total = Z$1,311,730

• contingency = Z$262,346

• total project = Z$1,574,076

24

Contingency percentage = annual rate of inflation x length of project (months)

12 months

Page 26: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Step six - Other comments and notes: The final columnof the matrix can be used for making comments aboutthe activity or noting the need for additional resources.

Example: The WWMC has decided that the workersclearing the fence must bring their own tools.

Step seven - Recording the project planning matrix: Ifthe project planning matrix has been visualised, then itmust be recorded. This step can be given to the secretaryof the WWMC who should copy the project planningmatrix exactly as it has been produced by theparticipants. How the matrix is used will depend onwhether it is;

• a locally funded and implemented project. Thematrix forms the instructions for theimplementation of the project. If possible makecopies for all the committee members and theimportant stakeholders such as the RDC.

• a jointly funded and implemented project. Thematrix forms the instructions for theimplementation of the project. If possible makecopies for all the committee members and thepartner organisation such as the RDC.

• a proposed and unfunded project. The matrixshould be added to the other information that isneeded by the donor (see Appendix 3).

Example: The Chilazi Fence was to be funded out of theWard’s dividend. The project planning matrix was usedas the minutes of the meeting and copied for eachmember of the WWMC and the RDC. Copies were madeto give to the successful contractor and WWF as theNGO responsible for training fence minders.

Reviewing and revising the completed project plan: A project plan is never really finished, it should be constantlyrevised, improved and updated. After the first draft of theproject planning matrix has been completed, it should bereviewed and revised if necessary. Reviewing the project planmeans asking if;

• the main activities have been recorded?

• the project can be completed in the time given?

• the project can be completed within the given budget?

• when completed, will it fulfill its objective?

The review can also be used to ask;

• who will manage the project?

• what impact will the project have on the community,who will gain and who will loose?

• what is the likely impact on the environment?

If the project is found to be weak in any one of the factorshighlighted above or there is new information, then it shouldbe changed.

25

Page 27: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

SummaryThis chapter has outlined the steps to develop the projectplanning matrix. The matrix contains the instructions to theproject implementors and is crucial to the successfulimplementation of the project. It is worth spending time onthis stage and, if necessary, coming back to adapt and improveit as more information becomes available.

26

Thank you for your planning matrix, Miss Moyo,I am sure it will assist your

proposal.

Donors generally insist that project proposals contain a planning matrix.

Page 28: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

27

Page 29: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

28

After floods damaged the electric fence at Masoka, repairs were sub-contracted to a local Resident. The WWC monitored the repairs.

Page 30: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

29

The third stage of the project cycle is project implementation.During project implementation, the project planning matrix isused to;

• to provide the project implementors with a descriptionof the key activities, their order, the time-frame andbudget that they should be completed within,

• as a tool to monitor the progress of the project.

How is the planning matrix used to implement the project? The project planning matrix becomes the set of instructions forthe implementation of the project. The committee or personsresponsible for implementing the project should follow thematrix so that the activities are carried out;

• in the order that they were planned,

• within the time limits that were planned,

• within the budgets that were planned,

• by the people who were responsible for the activity.

How is the planning matrix used to monitor projectimplementation? Project monitoring is the regular review of a project’s progressduring its implementation. Using the project planning matrixto monitor the progress of a project simply means comparingthe planned set of activities with the activities which haveactually taken place. The monitoring should consider whether;

• the activities are being completed within the agreed timeperiod,

• the activities are being completed by the plannedpersons,

• the activities are being completed within the plannedcost.

Monitoring can be carried out very easily by adding a sixthcolumn to the project planning matrix in which the progress ofeach activity is recorded.

CHAPTER 2CHAPTER 4

PROJECT IMPLEMENTATION AND MONITORING

1. Clear the agreed lineof all trees and shrubs

start before endof May and finish

by end of July2001

contract labourers Supervisor S.

Mutake (WWMC)

1.Activities 2. When 3. Who

labour: 25 days x 5 x 30= $3,750

supervisor: 25 days x 40= $1,000

Total: $4,750

4. Cost

workers to bringtheir own tools

5. Other

Completed on 21 July 2001

6. Progress

Identification

Planning

Implementationand monitoring

Evaluation

Page 31: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

Can the plan be changed during project implementation? The project planning matrix is designed to assist withimplementing a given project within certain time and financiallimits. If the project monitoring identifies a problem then theoption of changing the plan might be part of the solution. Thesize of the change will depend on how much the actualimplementation of the project is diverging from the plan.Unexpected conditions might mean that the project has to bechanged significantly, for example;

• a garden project: The boreholes that are drilled for agarden project do not have water. The remainingactivities should not be implemented until a new andequally cost effective source of water is found. If noalternative is found, the project team should cancel theproject.

Other changes in conditions might mean that the projectrequires no modification, for example;

• the Chilazi Fence: Due to a cement shortage it was notpossible for the selected contractor (Shocking Fences) tocomplete the planned fence by the end of November.After a short delay in construction, the fence wascompleted at the end of December 2001.

What are the common problems that are experiencedduring implementation? Problems will always arise during the implementation of aproject. Knowing what problems might occur, and how theymight be solved, will reduce the delays experienced, forexample;

• The project starts exceeding its budget: Due to eithercost increases or poor budgeting the project starts toexceed the budget. The solution depends on what kindof project it is and by how much the project is overbudget. On an infra-structure project (example, anelectric fence) it is sometimes possible to modify thedesign to save money and reduce costs. If it is a socialproject (for example, drought relief food) the activitiesmight have to be reduced to keep within the budget.

30

Unless we findanother source of

water, we agree thatthis project must be

cancelled.

Page 32: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

31

• Money is not available when it is needed by theimplementors: When a project is being implemented bya team which does not directly control the money, theproject is often delayed by the lack of money to makepayments. This can be solved by making sure that thosewho control the money are involved at every stage of theproject cycle so that they know when payments have tobe made.

• People fail in their responsibilities: Communityprojects are often delayed or fail because people neglecttheir responsibilities. This is because they underestimatethe time effort needed to complete these projects.Anybody who has to spend time on the project should bepaid for their effort.

• There are conflicts: Community projects are oftendelayed or fail because there are conflicts betweencommittees or between people within committees. Theseproblems can be avoided by;

• participatory planning which involves as many ofthe important stakeholders,

• setting very clear terms of reference for thecommittee / sub-committee or team responsiblefor the project.

• There are insufficient skills to run the project: Thesuccess of community projects is often limited by theskills of the people who are required to manage them.Most projects should include some training for thosewho have to implement and/or manage the project.

Page 33: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

32

How to avoid implementation problems by usingcontractors? Rural district councils and ward wildlife committeesimplement a very wide range of projects. These range fromsmall social or income generating projects to bigger infra-structure projects. With infra-structure projects some of theproblems listed above can be overcome by using a contractor.A contractor is any person or a company that agrees tocomplete a given set of activities in a given time period, to agiven quality for a given price. A contractor can be a personfrom within the community it does not have to be a companyfrom an urban area.

• The advantages of using contractors: There are severaladvantages to using contractors for implementation ofprojects, especially those which involve building infra-structure:

• They have specialist knowledge or specialistequipment necessary for the project (for examplean electric fencing company or a borehole drillingcompany).

• They are contracted to complete the project in anagreed period and for an agreed price.

• They can often do the work at a very competitiveprice because they buy materials in bulk or atwholesale prices.

• The disadvantages of contractors: There are severaldisadvantages to using contractors:

• They are motivated by profit and sometimes takeshortcuts (for example using insufficient cement inconcrete) and therefore they need to be closelysupervised. Work which is not of an acceptablestandard should not be paid for.

Page 34: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

33

• They often bring labour in from outside the projectarea. Agreements with contractors should specifyhow much “local” labour should be used.

• Choosing a contractor: The principles of selecting acontractor for a project are very similar to those ofselecting a safari operator to use the wildlife resources inthe district or ward (see Marketing Wildlife Leases,WWF WMS Manual Number 3). The important pointsare:

• Information: Always provide as much informationabout the project as possible. This will allow thepotential contractors to make better estimates ofmaterials, labour and the costs of the project.

• Competition: Always get quotes from more thanone contractor, even if they are local residents.

• Openness and transparency: Make sure that thereis no favouritism in the bidding process. Alwaysassess the qualifications and experience of thecontractor together with their price. Contracts donot have to be awarded to the contractor with thelowest price.

• Contract: Always have a written contract with thechosen contractor. The contract must describe thework, indicate when it should be undertaken andfor what price. If possible, use ideas and clausesfrom other similar contracts. Avoid changing thecontract during the project because this will makeit difficult to manage and monitor.

SummaryA project will only generate benefits if it is implemented.Attention to detail and good planning will assist with theproject’s implementation. Monitoring the progress of theproject during implementation should prevent thedevelopment of problems, which might restrict the progress ofthe project.

Page 35: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

34

Annual review of CAMPFIRE projects in Mahenye Ward, Chipinge RDC.

Page 36: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

35

The last stage in the project cycle is “project evaluation”. This stage is usually done when the project has beencompleted.

What is project evaluation? The purpose of the project evaluation is to find out whetherthe project has met its objective and solved the problem orproblems that it was supposed to.

Why is project evaluation an important stage in the project cycle? The evaluation of a project is important because it is anopportunity for the project implementors to learn from theentire project cycle. An evaluation should not only focus onthe aspects of a project that did not follow the plan, it mustalso identify those aspects which went well. This will allow theproject planners and implementors to;

• take the positive lessons that they learned from theproject forward to the next projects,

• change the way that future projects are planned andimplemented.

How is the planning matrix used to evaluate a project? If a project has been planned and implemented using theproject planning matrix, then evaluation can be done bycomparing the project planning matrix to the actual project. At each step the evaluators should try to understand thereasons for any differences between how the project wasplanned and the actual implementation.

CHAPTER 5

PROJECT EVALUATION

Identification

Planning

Implementationand monitoring

Evaluation

Page 37: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

36

Step One - Evaluating the project’s objective:The evaluating team should compare the project’sobjective and how far the project has gone in meetingthat objective.

Step Two - Evaluating the implementation of theproject: The implementation of the project can bedivided into several categories such as;

• the timing of the project implementation - did ittake longer / shorter than planned, if so why wasthis?

• who implemented the project - was the projectimplemented by the people who were indicated inthe project plan. If not why not?

• the cost of implementation - was the projectimplemented within the planned budget or did itgo over the budget and if so, why was this?

• the benefits of the project’s implementation - didthe projects benefits exceed expectation or werethey below expectation. What was the benefit:costratio of the project?

Step Three - Evaluating the social impact of the project:Most projects will affect different interest groupsdifferently. The evaluation should:

• Identify and record the beneficiaries - whobenefited from the project and by how much didthey gain or benefit?

• Identify and record the losers - who lost as a resultof the project and what did they loose?

Step Four - Evaluating the environmental impact of theproject: A wide range of projects are implemented underCAMPFIRE. The impact on the environment will dependon the type of project and the local conditions. Theevaluation should:

• Identify and record the positive environmentalimpacts - the positive environmental impacts of theproject need to be identified, if possible quantifiedand recorded.

• Identify and record the negative environmentalimpacts - the negative environmental impacts ofthe project need to be identified, if possiblequantified and recorded.

Projects implemented under CAMPFIRE should have morepositive than negative environmental impacts.

Page 38: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

37

Who should evaluate the project?Project evaluation is usually done by an independent personor group of people. This approach is not usually possible forprojects which have been funded out of local money such aswith CAMPFIRE. For district and sub-district committeeswhich are involved in planning and implementing projects, thebest time to evaluate projects is before finalising subsequent orfollowing budgets. This means that part of the meeting can bespent reflecting on the performance of the projects that thecommittee has planned and implemented. If sub-committeeshave been formed, then they should use this opportunity andframework to evaluate their work.

Summary Project evaluations are often seen as a threat and a nuisance.They can, however, provide a valuable opportunity for projectimplementors to reflect on the performance of the project andlearn from its success and failures.

Certain groups might bear unexpected costs as a result of aproject. For example, the time taken to collect water because ofa new fence. These kinds of issues should be raised during aproject evaluation.

Page 39: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

38

Page 40: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

39

APPENDICES

Page 41: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

40

Page 42: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

41

Page 43: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

42

Page 44: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

43

Page 45: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

44

Page 46: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

45

Page 47: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

46

notes

Page 48: WILDLIFE MANAGEMENT SERIESd2ouvy59p0dg6k.cloudfront.net/Downloads/Project_planning.pdfThe project planning matrix is a flexible tool and must be used to meet the needs of the planners

This booklet is the ninth in a series of guides on wildlife management and examines various aspects of project planningimplementation. It provides background information and guidance to Rural District Councils and should be read along with the otherbooklets in this series. The WWF Wildlife Management Series provides information and guidance to members of villages, wards andRural District Councils involved in the management of CAMPFIRE. These booklets are linked to training programmes being undertakenby members of the CAMPFIRE Collaborative Group.

Booklets in the Wildlife Management Series include:

1. Problem Animal Reporting2. Electric Fencing Projects3. Marketing Wildlife Leases4. Managing Safari Hunting5. Quota Setting Manual

District Quota Setting Toolbox6. Maintaining Electric Fences7. Counting Wildlife Manual8. Fire Management Manual9. Project Planning Manual

WWF is a member of the CAMPFIRE Collaborative Group supporting CAMPFIRE in Zimbabwe and has provided support and trainingto communities for the establishment of wildlife management systems.

WWF’s mission is to stop the degradation of the planet’s naturalenvironment and to build a future in which humans live in harmonywith nature by:

• conserving the world’s biological diversity• ensuring that the use of renewable natural resources is sustainable• promoting the reduction of pollution and wasteful consumption

WWF - SARPOP.O. Box CY 1409CausewayHarareZimbabwe

Tel: Harare 252533/4