wild river damdata.dnrm.qld.gov.au/eap/wild-river-eap.pdf · 2019-12-04 · safety report...
TRANSCRIPT
DAM ID 1198
VERSION 7 – JULY 2019
Confidential and Proprietary Information This document contains information that is proprietary to Tablelands Regional Council. Transmittal, receipt, or possession of this document does not express license, or imply rights to use, sell, design, manufacture, or to have manufactured, any product, concept, or service from this information. No reproduction, publication, or disclosure of this information, in whole or in part, electronic or otherwise, shall be made without prior written authorization of an officer of Tablelands Regional Council.
Authorised transfer of this document from the custody and control of Tablelands Regional Council constitutes a loan for limited purpose(s), and this document must be returned to Tablelands Regional Council upon request, and in all events, upon completion of the purpose(s) of the loan.
Wild River Dam
EMERGENCY ACTION PLAN
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 i
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 ii
DOCUMENT CONTROL SHEET
CONTROLLED COPY NUMBER: AUTHORISATION:
Approved by: ..... ..................................................................................... (M r Water and Waste Tablelands Regional Council)
Date: 19 / 09 / 2019
Draft: Final: Version: 7
File Ref: Author:
Date Submitted: 18 September 2019 Review Date: July 2019
DOCUMENT REVISION HISTORY
Version Date Officer Name Change Summary
1 September 2013 Re-written with new DNRME requirements
2 October 2014 Outcomes of Failure Impact Assessment and Dam Safety Report undertaken by SKM in December 2013 and March 2014 respectively.
3 November 2014 Amendments made to document as requested by DNRME
4 September 2015
2015 Review & Update (REVA)
5 December 2017 2017 Review & Update – Approval until 1 November 2018
6 July 2018 2018 Review & Update
7 July 2019
2019 Review and Update to address Matters of Concern
7 July 2019 Finalised
7 September 2019
Review comment updates, Local Government Notice to Dam Owner insertion and Manager Water and Waste authorisation to release.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 i
CONTENTS Chapter-Page 1. INTRODUCTION ................................................................................................................... 1-1
1.1 Purpose ..................................................................................................................... 1-1 1.2 Wild River Dam .......................................................................................................... 1-1 1.3 Failure impact assesment .......................................................................................... 1-4
2. CONTROL COPY AND NOTIFICATION LIST ..................................................................... 2-1
3. ROLES AND RESPONSIBILITIES ...................................................................................... 3-1 3.1 TRC Roles ................................................................................................................. 3-1
3.1.1 EAP Officer ................................................................................................................ 3-2 3.1.2 EAP Backup Officer and Maintenance Officers ......................................................... 3-2 3.1.3 Manager Water and Waste ........................................................................................ 3-2 3.1.4 Tablelands Local Disaster Coordinator ..................................................................... 3-3 3.1.5 Dam Safety Consultant .............................................................................................. 3-3
3.2 External Entity ROLES .............................................................................................. 3-3 3.2.1 Local Disaster Management Group ........................................................................... 3-4 3.2.2 District Disaster Management Group ........................................................................ 3-4 3.2.3 State Disaster Coordination Centre ........................................................................... 3-4 3.2.4 Police COMMUNICATIONS CENTRE CAIRNS ........................................................ 3-4 3.2.5 Queensland Police, Herberton .................................................................................. 3-4
3.3 Affected PAR ............................................................................................................. 3-4
4. COMMUNICATIONS ............................................................................................................ 4-1
4.1 Communication Protocols .......................................................................................... 4-1 4.2 Communication Mechanisms .................................................................................... 4-1 4.3 Communication System ............................................................................................. 4-2
5. DAM OVERVIEW .................................................................................................................. 5-1 5.1 Dam Details ............................................................................................................... 5-1 5.2 Critical storage water level triggers ........................................................................... 5-2 5.3 Potential Problem Identification ................................................................................. 5-3
6. PREDICTED FLOOD LEVELS AND FLOOD TRAVEL TIMES ........................................... 6-1
6.1 Predicted Depth of Flooding ...................................................................................... 6-1 6.2 Flood Wave Travel Times .......................................................................................... 6-1
7. EMERGENCY EVENTS AND ACTIONS ............................................................................. 7-1
7.1 Dam Hazards ............................................................................................................. 7-1 7.2 Flooding ..................................................................................................................... 7-1
7.2.1 Preventative actions for Flooding Events: ................................................................. 7-2 7.3 Earthquake .............................................................................................................. 7-10
7.3.1 Preventative actions for an Earthquake Event: ....................................................... 7-10 7.4 Terrorist or high energy impact ................................................................................ 7-14
7.4.1 Preventative actions for Terrorism or High Energy Impact:..................................... 7-14 7.5 Sunny Day Failure ................................................................................................... 7-18
7.5.1 Preventative actions for a Sunny Day Failure Event: .............................................. 7-18 7.6 Reservoir Water Quality (Toxic Spill/ Algal Bloom within Catchment Area) .............. 7-1
8. WARNINGS AND NOTIFICATIONS .................................................................................... 8-2
8.1 Warning and notification mechanisms ....................................................................... 8-2 8.2 Warning and notification Processes .......................................................................... 8-2 8.3 Pre-prepared messages ............................................................................................ 8-3
8.3.1 Sunny Day Failure – Prepare to Evacuate ................................................................ 8-3 8.3.2 Sunny Day Failure – Evacuate Now .......................................................................... 8-3 8.3.3 Flood Events – Prepare to Evacuate ......................................................................... 8-3 8.3.4 Flood Events – Evacuate Now .................................................................................. 8-4
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 ii
8.3.5 Flood Events – Loss of Radio Signal - Evacuate Now .............................................. 8-4 8.4 Individual Evacuation Plans ....................................................................................... 8-4 8.5 End of Event .............................................................................................................. 8-4
9. EVENT REPORTING ............................................................................................................ 9-1
9.1 Storage Data Book .................................................................................................... 9-1 9.2 Emergency Event report ............................................................................................ 9-1
10. REVISION OF EVACUATION PLANS ............................................................................... 10-1
11. REFERENCES .................................................................................................................... 11-1
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 iii
APPENDICES
APPENDIX A – DATA COLLECTION
APPENDIX B – CATCHMENT BOUNDARY
APPENDIX C – POTENIAL PROBLEM IDENTIFICATION
APPENDIX D – INNUNDATION MAPS, POPULATION AT RISK CONTACT DETAILS AND EVACUATION PLANS
APPENDIX E – WILD RIVER DAM STORAGE CURVE & STORAGE SPILLWAY DISCHARGE CURVE
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 iv
LIST OF ABBREVIATIONS USED IN THIS TEXT AEP Annual Exceedance Probability AHD Australian Height Datum AMTD Adopted Middle Thread Distance ARI Average Recurrence Interval BoM Bureau of Meteorology CEO Chief Executive Officer DCL Dam Crest Level DDMG District Disaster Management Group DDS Director Dam Safety DEHP Department of Environment and Heritage Protection DNRME Department of Energy and Water Supply DICL Ductile Iron Concrete Lined (in reference to water pipe) DN Diameter Nominal DSR Dam Safety Review EA Emergency Alert EAP Emergency Action Plan EER Emergency Event Report EWN Early Warning Network FIA Failure Impact Assessment FSL Full supply level is the level of the water surface of the dam when the water storage
is at maximum operating level when not affected by flood GMIS General Manager Infrastructure Services HICB Hazardous Industries & Chemical Branch WH&S Qld IROL Interim Resource Operations Licence LDC Local Disaster Coordinator LDCC Local Disaster Coordination Centre LDMG Local Disaster Management Group LiDAR Laser Interferometry Detection and Ranging (remote sensing for survey) MWW Manager Water and Waste PAR Population at Risk PAR1 Population at Risk with a travel time for a failure wave from the dam of less than 10
minutes. PAR2 Population at Risk with a travel time for a failure wave from the dam of greater than
10 minutes. PMF Probable Maximum Flood PMP Probable Maximum Precipitation PMPDF Probable Maximum Precipitation Design Flood PMPDFNF Probable Maximum Precipitation Design Flood No Dam Failure PMPDFF Probable Maximum Precipitation Design Flood Dam Failure QPS Queensland Police Service SCADA Supervisory Control and Data Acquisition RE Relevant Entities SDCC State Disaster Coordination Centre SDF Sunny Day Failure SES State Emergency Service SOP Standard Operating Procedure TRC Tablelands Regional Council
EMERGENCY ACTION PLAN
Wild River Dam
Version 7 31/07/2019 v
TERMS AND DEFINITIONS USED IN THIS TEXT The meaning of terms used in this Emergency Action Plan are set out in Section 352A of the Water Supply (Safety and Reliability) Act 2008 (Qld) – Amended 3 July 2017.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 1-1
1. INTRODUCTION
1.1 PURPOSE
Tablelands Regional Council (TRC) has prepared this EAP for Wild River Dam in accordance with the requirements of the Queensland Water Supply (Safety and Reliability) Act 2008 (the Act) that the owner of a referable dam must have an approved Emergency Action Plan (EAP) for the dam. The purpose of an EAP under the Act is to “minimise the risk of harm to persons or property if a dam hazard event or emergency event for the dam happens”. This EAP outlines procedures to be followed to manage the consequences of a dam hazard or emergency event at the dam. It includes the roles, responsibilities and procedures for TRC as the dam owner and local government, as well as those for the Local, District and State Disaster Management Groups, emergency agencies and affected persons. 1.2 WILD RIVER DAM
Wild River Dam is owned and operated by Tablelands Regional Council. Construction of the new Wild River Dam (Figure 1) was completed in 1994. The dam is located at the headwaters of the Wild River (AMTD 335.4 km) approximately 5 km East North East of Herberton at the end of Moomin Road (17o 21’ 22” S and 145o 25’ 55.94” E.). The dam consists of a compacted earth and rock fill embankment with central clay core, vertical filter zone, upstream riprap and a grassed downstream embankment. It is located approximately 790 m upstream of the original mass concrete dam (Figure 1) known as ‘Old Wild River Dam’ (Figure 3) which was the only town water supply storage for Herberton prior to 1994. Wild River Dam has a gravity feed outlet that releases into the Wild River by means of a Floating gravity syphon Intake, Outlet Conduit and Outlet Valve (Figure 4). An intake pipe for the gravity feed pipeline to Herberton is located in the base of a Town Water Supply Weir (Figure 5) immediately downstream of the Old Wild River Dam. The purpose of these dams and weir is to supply water to Herberton.
Figure 1 Wild River Dam
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 1-2
Figure 2 Wild River Dam Location Map
Figure 3 Old Wild River Dam
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 1-3
Figure 4 Herberton Town Water Supply
Figure 5 Schematic Diagram of Dams
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 1-4
1.3 FAILURE IMPACT ASSESMENT
Sinclair Knight Merz Pty Ltd (now Jacobs Group (Australia) Pty Ltd) were engaged by Tablelands Regional Council in 2013 to undertake a Failure Impact Assessment (FIA) study and Dam Safety Review (DSR) report. The FIA study was finalised in December 2013, and the DSR was completed in March 2014. The Population at Risk (PAR) was calculated in accordance with the QLD Government Guidelines for Failure Impact Assessment of Water Dams (2012). The FIA undertaken by Sinclair Knight Merz Pty Ltd (Jacobs Group (Australia) Pty Ltd) identified 26 people at risk in a Sunny Day Failure (SDF) event and 81 people at risk due to a Probable Maximum Flood (PMF) event in either a dam failure or no dam failure scenario. It is noted that all PAR affected in a PMF dam failure scenario are also affected by flooding in a PMF event without dam failure. The PAR identified for the SDF event, is associated with 9 houses. The PAR identified for the PMF events is associated with 20 houses, 1 unit block and 9 terraced/row houses. Further analysis in 2019, assessed the potential consequences in the event of the failure of Wild River Dam causing a cascade failure of Old Wild River dam downstream. Given the small volume and close proximity of the Old Wild River Dam to the Wild River Dam, the effects with and without cascade failure are very similar. This analysis identified no additional buildings affected under cascade failure in the SDF event. One additional building was identified as impacted in a cascade failure during the PMFF event, with an associated additional 2.9 incremental PAR. Lower lying parts of the lot associated with this building are affected by the PMFF event without cascade failure so no additional properties are required to be notified during an event. Evacuation maps prepared for each affected lot have been updated to show impacted areas with and without cascade failure. The PAR for the flooding in a PMF event has been broken into 2 groups, PAR1 for Population at Risk with a travel time for a failure wave from the dam of less than 10 minutes and PAR2 for Population at Risk with a travel time for a failure wave from the dam of greater than 10 minutes. 2 houses are associated with PAR1 and 18 houses, 1 unit block and 9 terraced/row houses are associated with PAR2.
Section 2 has been redacted
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 3-1
3. ROLES AND RESPONSIBILITIES
As the owner of the dam, TRC has responsibility for implementation of the Wild River Dam EAP. TRC has identified a team to undertake this responsibility. The roles and responsibilities within this team are outlined within Section 3.1. Outside TRC, other entities also have roles and responsibilities under this EAP. These are outlined in Section 3.1.5. Affected persons, or Population at Risk (PAR), identified within this EAP also have a role in the effective implementation of this plan to minimise the consequences of a dam hazard or emergency event. This role is outlined in Section 3.3. 3.1 TRC ROLES
The EAP is implemented within TRC by a team which comprises four key roles: EAP Officer
EAP Backup Officers and Maintenance Personnel
Manager Water and Waste
GMIS
CEO
Tablelands Local Disaster Coordinator Figure 6: TRC Roles The responsibilities of each of these officers are outlined in the following sections. Key actions for each role are outlined within the flowcharts and tables for each emergency event. Contact details for the TRC officers with these roles and responsibilities are included in Section 2. Each officer is to undergo initial EAP training when identified for one of these roles and participated in continuing refresher training and annual Scenario Event exercises. EAP Training exercises consist of understanding triggers for when EAP is to be enacted, roles and responsibilities of each person, communication / notification protocols and preventative and remediation actions under different EAP events.
LDC Coordinator
Manager Water and
Waster
EAP
Officer
Backup EAP Officers and
Maintenance Officers
Dam Safety Consultant
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 3-2
3.1.1 EAP Officer
The EAP Officer shall: Keep the Emergency Action Plan in a clean, secure facility.
In the event that the EAP Officer is unable to fulfil these duties advise MWW.
Notify MWW of names and contact details of personnel undertaking and/or relieving the role of Backup EAP Officer and Maintenance personnel.
Monitor the storage water level of the dam.
If possible, monitor Bureau of Meteorology website for forecasted extreme weather events.
Immediately notify the EAP Backup officers when the Emergency Action Plan is being initiated.
Follow the Emergency Action Plan in time of emergency.
During an emergency event, report to and receive instructions from the MWW or if he cannot be contacted, the GMIS, or if he cannot be contacted, the CEO TRC.
In an emergency event, take steps to ensure personal safety and the safety of other EAP Officers and the public.
Provide regular reports to the MWW for evaluation during the emergency or the person who will undertake that role during the emergency event.
If contacted by media during an emergency event the EAP Officer should refer the media to the TRC Strategic Communications Advisor and record time, date and action taken.
On the Log of Events/Actions Sheet (refer to Appendix A) and the Record of Communications Sheet (refer to Appendix A) keep a daily running record of all actions/events and telephone calls to and from the MWW, EAP Backup Officers and other personnel (in relation to the event) for the duration of the emergency event.
- Record: to and from - who requested actions; what actions were requested and carried out; and the time and the date they were carried out. Record any rainfall at the dam during the event using the Record of Rainfall form (Appendix A).
After the event compile an Emergency Event Report and forward unedited copies to the MWW.
Transfer the Record of Events/Actions, Communications and Rainfall to the Storage Data Book after the Event.
Actively participate in the refresher training and annual Event Scenario exercises as directed.
Actively contribute to the review of the Emergency Action Plan. 3.1.2 EAP Backup Officer and Maintenance Officers
EAP Backup Officer and Maintenance Officers shall: Assist the EAP Officer in times of emergency.
Follow the Emergency Action Plan during emergency events.
During adverse weather conditions, EAP Backup Officer and Maintenance Officers shall attempt to contact the EAP Officer.
Actively participate in the refresher training and annual Event Scenario exercises as directed.
If the EAP Officer is unavailable, they shall undertake the responsibilities of the EAP Officer. 3.1.3 Manager Water and Waste
Manager Water and Waste shall:
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 3-3
Review the Emergency Action Plan in consultation with LDMG, DDMG and TRC by 1st August each year (to enable submission to DDMG and LDMG for 30 business days if an amendment is required) and provide notice to DNRME Dam Safety by 1 October each year.
Ensure the Emergency Action Plan is distributed according to the Distribution List and that the police and disaster management organisations are conversant with the plan.
Ensure this Emergency Action Plan is implemented.
Approve the person undertaking and/or relieving in the role of EAP Officer and EAP Backup Officers.
Ensure the EAP Officer and Backup Officers are conversant with the Emergency Action Plan.
Ensure that the PAR in Herberton and Wondecla are contacted annually and informed about the EAP and the expectations of them in dam safety emergency events.
Ensure that the PAR contact details are checked and updated annually.
Ensure that the PAR in Herberton and Wondecla are warned of dam safety emergency events (in collaboration with the LDC).
Notify the CEO and GMIS of any emergency event.
Monitor all emergency events.
Provide regular updates during emergency events to the CEO and LDC.
Evaluate reports from EAP Officers and provide directions where required in this plan.
Undertake verification of / inspection of deficiencies identified by the EAP Officer and provide directions where required in this plan.
Coordinate with external dam safety consultants (RPEQ) where additional expertise is required.
Within thirty (30) days of an event, present an Emergency Event Report to Director Dam Safety.
Ensure that EAP training including initial training, annual refresher training and annual Event Scenario exercises are undertaken in coordination with the LDC
3.1.4 Tablelands Local Disaster Coordinator
The Local Disaster Coordinator shall on behalf of the Tablelands LDMG (excerpt taken from Disaster Management Act 2003):
(a) coordinate disaster operations for the local group;
(b) report regularly to the local group about disaster operations;
(c) ensure, as far as practicable, that any strategic decisions of the local group about disaster operations are implemented; and
Issue Early Warning Network (EWN) and Emergency Alert (EA) messages to the PAR on behalf of the dam owner as required. 3.1.5 Dam Safety Consultant
For the purposes of the Wild River EAP, the responsibility of the Dam Safety Consultant is to provide advice to TRC as requested by the Manager Water and Waste. The Dam Safety Consultant is to be a Registered Professional Engineer of Queensland (RPEQ) with appropriate expertise relevant to the issue to be considered. 3.2 EXTERNAL ENTITY ROLES
External entities with responsibilities under this EAP include the Local Disaster Management Group, District Disaster Management Group, State Disaster Coordination Centre, Queensland Police Service, and Dam Safety Regulator, DNRME.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 3-4
This section outlines the responsibilities of each of these entities. Contact details for the external entities with these roles and responsibilities are included in Section 2. 3.2.1 Local Disaster Management Group
For the purposes of the Wild River EAP, the responsibilities of the Local Disaster Management Group are undertaken by the Local Disaster Coordinator (TRC officer) in collaboration with the Local Disaster Management Group. See Section 1. 3.2.2 District Disaster Management Group
The role of the District Disaster Management Group in relation to this EAP is to support the disaster response by providing support to the LDMG where capacity and capability to respond is exceeded. 3.2.3 State Disaster Coordination Centre
The role of the State Disaster Coordination Centre in relation to this EAP is to store and test emergency alert polygons and messages, and issue when requested by the LDC. 3.2.4 Police Communications Centre Cairns
The role of the Police Communications Centre Cairns in relation to this EAP is to:
Contact Herberton Police and advise them to activate their Station Instruction to provide QPS response for evacuation of the PAR.
Contact the QPS District Duty Officer to ensure adequate Police response to an evacuation of the PAR.
3.2.5 Queensland Police, Herberton
Queensland Police Herberton, will:-
Activate the Station Instruction to provide QPS response actions for the evacuation of the PAR when notified of the relevant Dam EAP activation.
3.3 AFFECTED PAR
Persons likely to be affected in a dam hazard or emergency event have been identified through failure impact assessment for a range of potential events as outlined in Section 1.3. The details of each affected PAR including contact details are identified in Appendix D. Evacuation maps for each PAR are also included in Appendix D. Communication protocols for providing notifications and warnings to PAR are identified in Section 8. The responsibility of the affected PAR under this EAP are to: Provide updated contact details annually when contacted by TRC officers to allow subscription
to the EWN service used for dissemination of warnings by TRC.
Prepare for an emergency event by reviewing the evacuation plans and EAP information provided.
Follow the instructions of warnings and notifications.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 4-1
4. COMMUNICATIONS
4.1 COMMUNICATION PROTOCOLS
Figure 7 identifies the lines of communication during an event. All media queries should be referred to the TRC media coordinator. Notification and warning of affected PAR is the responsibility of the MWW in liaison with the LDC. All other external communications are the responsibility of the MWW.
Figure 7 Communications Protocols 4.2 COMMUNICATION MECHANISMS
The primary means of communications between the EAP Officer and parties external to Herberton and Wondecla shall be by mobile telephone or Council radio. Messages are to be confirmed as being received, leaving a voicemail and assuming it has been received is not sufficient. It is noted that effective communication and warning within this plan is heavily reliant on the mobile telephone network. Following cyclone events, the loss of power and mobile reception is likely. If an emergency event were to occur during the aftermath of a cyclone, implementation of the EAP may be compromised due to loss of communications and difficulty accessing the dam. The following back-up procedures are currently in place: Solar power back up for telemetry at dam site;
Redundancy of monitoring at dam via CCTV on 3G/4G link;
Generator back up at Council depots (not all have automatic fail over) and availability of Council radio; and
EAP Officer
MWW
LDC GMIS
CEO
Media Coordinator
Mayor
Affected PAR
Councillor Police Communications, Cairns
DNRME
Media 000 National Security Hotline
QPS Counter Terrorism Liaison
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 4-2
Potential for relay of warnings to PAR via SES and Police communications e.g. door knocking, radio systems.
4.3 COMMUNICATION SYSTEM
TRC has its own licenses to operate radio communication equipment under the Australian Communications and Media Authority (the AMCA), which are renewed annually. TRC currently has two (2) licenses under the AMCA, details are as follows: Table 1: Details of TRC's licenses to operate radio communications equipment License No. Site/Area Callsign Service /
Subservice Expiry Date
103090/2 Austek Site, 1.5km NE of Cnr Kennedy Hwy and Longlands Gap Rd
VL4QI Land Mobile / Land Mobile System - > 30MHz
14/06/2020
103113/1 VMQ692 Land Mobile / Ambulatory System
14/06/2020
The primary repeaters for the TRC radio network are located at Longlands Gap. This includes the previous Southern and Central zone radios that are now linked and interoperable. The base stations for the radio systems are located in the Local Disaster Coordination Centre (LDCC). Some TRC vehicles are fitted with a UHF radio, in particular the EAP Officer, Backup EAP Officer and Coordinator Water and Wastewater Reticulation vehicles. The Tablelands Local Disaster Management Group has a Resilient Communications Sub Plan under the disaster management plan under the following: http://www.trc.qld.gov.au/disaster-management/local-disaster-management-plan/ TRC promotes the use of UHF CB 10 as a community solution. UHF-CB radio is primarily for members of a community to communicate with each other during and after a disaster so that they can assist one another. Emergency aid may not be available to some people whether or not they have a radio. They may be isolated due to impassable conditions, flooding, down power lines, fire, fallen structures, blocked roads, or there may not be public safety or other resources to assist them. It should be noted that possession and use of a two-way radio does not guarantee an instant and reliable or an immediate and effective response to an individual’s call for help – calling out on a two-way radio does NOT guarantee a response. Whilst it cannot be guaranteed, having a two-way radio may enable community members and appropriate officials to communicate with persons affected by disaster.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 5-1
5. DAM OVERVIEW
5.1 DAM DETAILS
Name and location Name of Dam Wild River Dam Other Names None Location Latitude 17°21'59.56"S
Longitude 145°25'52.20"E DERM Region North Shire Tablelands Regional Council Nearest Town Herberton and Wondecla Stream and AMTD Wild River 335.4 km Licence No No ‘Interim Resource Operations Licence (IROL) Development Permit Development Permit Dam Safety Conditions for Wild River
Dam issued by DNRW in February 2006 Current Owner Tablelands Regional Council Designer & Date Gutteridge Haskins and Davey Pty Ltd, July 1993 Construction Contractor Beckhaus Civil Pty Ltd, 1994 Safety review dates 2004 (SunWater) and 2013 (SKM, now Jacobs Group
(Australia)) Storage characteristics Full supply level (FSL) 1046.6 m AHD Storage capacity 290 ML Surface area 6.2 Ha at FSL Length of shoreline Unknown Catchment area 530 Ha Catchment description Steep hills covered in thick vegetation Dam Crest Level EL 1050.15 m AHD (3550 mm above the spillway) Population at Risk 81 Description of dam wall Wall Type-Main Wall Compacted earth and rockfill embankment with central clay
core, vertical filter zone and upstream riprap protection. Wall Height (max. D/S toe) 16 m Dam Crest Elevation EL 1050.15 m AHD (3550 mm above the spillway) Embankment Length 230 m
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 5-2
Description of spillway Spillway Description Broad-crested weir Spillway Elevation EL 1046.6 m AHD Crest Width 45 m Spillway outflow Capacity (at DCL)
approximately 456 m³/s
Design Flood Estimates SKM (2013, 2014), SunWater(2004) Spillway capacity (AEP) Approximately 1 in 1,700,000 AEP Auxiliary spillway N/A Description of outlet works Intake Works Floating intake raft River Release Conduit Description Concrete encased DN 200 mm DICL Outlet Pipe
Outlet Valve Arrangement Outlet conduit terminates at an Outlet Valve Box containing a 200 mm diameter sluice valve, a 200 mm diameter to 150 mm DICL reducer and a 150 mm diameter Bermad (constant) flow control valve.
5.2 CRITICAL STORAGE WATER LEVEL TRIGGERS
Figure 8 identifies the critical water level triggers within the reservoir for the escalation of activation levels within the EAP. Access to the dam and nearby properties is cut by the Wild River in even minor flood events, thus observation of the dam during flooding events is wholly reliant on remote monitoring. Reservoir water levels are monitored in multiple ways to provide communication link redundancy in the EAP. 1. A pressure sensor was installed in November 2013 to measure the reservoir water level with
the data relayed to the Council dept via a SCADA/Telemetry system. 2. In late 2018, a series of additional monitoring systems including a bubbler water level sensor
were installed at the dam with images and data transmitted to the Council depot via 3/4G signal.
3. Additional redundancy within the system was included via the installation of a CCTV camera. The camera can be operated remotely allowing the operators to zoom in on the spillway. A reflector-style gauge is installed on a centre-post to allow accurate visual assessment of the depth of flow over the spillway. The camera functions including the ability to pan, enabling view of the seepage control structure and the dam wall alignment. The system captures fixed images of the spillway, seepage structure and dam wall alignment every 15 minutes under normal operations.
The EAP officer on duty monitors the reservoir level primarily using the SCADA system with automated alarms set at EAP trigger levels to allow rapid escalation of EAP activation levels as required. An alarm is also triggered if there is an outage of the SCADA system. In the case of an outage, the EAP officer on duty will continually monitor the reservoir level using the backup information from the bubbler system and CCTV camera. While the systems utilise different communication protocols and infrastructure, and are isolated in case of a lightning strike, there is a possibility of loss of both systems in a cyclone event. For this reason, loss of communications warning messages and evacuation procedures are included within this EAP.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 5-3
Figure 8: Dam Embankment Cross Section with Critical Storage Water Level Triggers 5.3 POTENTIAL PROBLEM IDENTIFICATION
Potential problem identification through routine inspections is the key trigger for activation of and escalation of activation levels within the EAP. TRC may become aware of an Earthquake (by way of community reports, employee advice or alerts via GeoScience Australia) which may trigger the Local Disaster Management Group and may trigger EAP activation. Officers inspect the dam weekly and complete an inspection checklist. The weekly inspection checklists are sent to Manager Water and Waste who will check and evaluate these reports. The monitoring equipment installed in late 2018 also allows remote monitoring of conditions at the dam where access to the dam is not possible such as during an earthquake, significant rainfall event, or in the event of a terrorist threat/ attack. This allows the following to be undertaken remotely: Visual inspection of the dam wall, spillway, walkway access and tailwater conditions. Visual inspection of deformities in the dam wall Visual inspection of the v-notch weir in the seepage monitoring station to provide an indication
of seepage flow. It is important that the dam is inspected during an emergency event or shortly thereafter by the EAP officer, providing it is safe to do so. Potential problems that can be identified during these inspections are discussed within Appendix C. Any abnormalities shall be immediately brought to the attention of Manager Water and Waste, and General Manager Infrastructure Services. In the event of an identified issue or potential deficiency, inspection by an RPEQ should be undertaken. In the first instance, this would be undertaken by the Manager Water and Waste. However, if deemed necessary by the Manager Water and Waste, inspection by a dam safety consultant may also be undertaken.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 6-1
6. PREDICTED FLOOD LEVELS AND FLOOD TRAVEL TIMES
6.1 PREDICTED DEPTH OF FLOODING
Hydraulic modelling was undertaken by SKM (Jacobs Group (Australia)) as part of the Failure Impact Assessment in 2013 using the MIKEFLOOD computer package. Further analysis was undertaken in 2019 to identify any additional impacts in a cascade failure scenario should Old Wild River Dam fail due to failure of the upstream Wild River Dam. This analysis concluded there was very little difference in the impacted area in a cascade failure event. Predicted flood depths in the Wild River have been extracted for specific locations and are listed in the table below:
Location Depth (m) Incremental
difference of PMPDFNF – PMPDFF (m)
SDF PMPDFNF PMPDFF
D/S of Wild River Dam
2.8 4.1 4.4 0.3
D/S of Old Concrete Dam
3.3 6.0 6.0 0.0
Railway Bridge 2.1 5.1 5.2 0.1 Herberton Bridge 1.1 5.1 5.2 0.1 Wondecla 4.9 9.9 9.9 0.0 End of model 4.1 19.0 19.0 0.0 6.2 FLOOD WAVE TRAVEL TIMES
The ability of PAR to evacuate is heavily dependent on whether they receive warning before the dam failure wave flood wave arrives at their property. In general, warning of at least 60 minutes is required to be considered best endeavours. Warning time is dependent on: Time for breach formation (and whether breach formation is identified early);
Travel time for flood wave; and
Time to deliver warning. SKM (Jacobs Group (Australia)) (2013) identified breach formation parameters including the likely breach formation time based on the Guidelines for Failure Impact Assessment of Water Dams (DNRME, 2012). The adopted breach parameters are presented the Table below: Event Volume of
water discharged at time of breach (ML)
Volume of material removed from breach (m³)
Breach Initiation Level (mAHD)
Breach Level Final (mAHD)
Final Breach Base Width (m)
Breach Slope (degrees)
Breach Develop’t. Time (minutes)
Sunny Day 290 2460 1050.15 1034 1.7 10 38
PMPDF 600 4760 1050.15 1034 5.1 10 48
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 6-2
The failure wave travel time (time for the failure wave to travel from the dam to each PAR) increases with distance downstream of the dam. It ranges from less than 10 minutes for the closest PAR (2 properties) to 1-1.5 hours for PAR in Herberton and 2-2.5 hours for PAR in Wondecla. The minimum time to send out Emergency Messaging using the Early Warning Network system is approximately 20 minutes, while the minimum time to send out an Emergency Alert using the State-wide system is approximately 40 minutes. It is clear that providing adequate warning of more than 60 minutes will not be possible for the 2 properties immediately downstream of the dam and will be difficult for PAR located further downstream, if warning does not occur until the dam begins to fail. Due to the isolated nature of the dam, early identification of breach initiation is also unlikely. The following are therefore critical: early identification and management of potential failure events;
early and effective warning to PAR occurs; and
effective prior communication with PAR to understand what to do if they receive a warning.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-1
7. EMERGENCY EVENTS AND ACTIONS
7.1 DAM HAZARDS
The following events are defined as emergency events for the Wild River Dam: Flooding Event
Earthquake event
Terrorist or high energy impact
Sunny Day Failure (SDF) events (all other events that may lead to SDF)
Any water quality contamination events at Wild River Dam are managed under Tablelands Regional Council’s Drinking Water Quality Management Plan which includes the Herberton Water Supply Scheme.
Structural failure of the dam can occur when the storage level is at or below FSL, and when the dam is spilling. Structural issues can however become more likely during a flood event due to higher hydrostatic pressures on the structure and foundations.
A “Sunny Day” failure is defined as failure of the dam and the release of water downstream, when there is low or no inflow to the dam from rainfall events. This type of dam failure is unexpected and can occur with little or no warning.
A “Sunny Day” failure may be as a result of any or a combination of the following: Embankment stability issues: increased seepage, new visible signs of seepage and particularly
evidence of sediment transport (i.e. cloudy flow) as this can be an indication of piping.
Signs of distress in embankment such as cracking and/or deformation and/or evidence of material having slid off embankment.
Appearance of sinkholes, soft spots and ‘boggy areas’
abnormal instrument readings (piezometers indicating higher hydrostatic pressures)
differential movement or settlement
increasing rates of seepage or development of new seepage paths
piping of the embankment
Earthquakes and Landslides.
Terrorist or high energy impact (non-natural events), including deliberate, accidental or vandalism actions against the dam structure.
In many of these cases there will be no warning and hence no Alert or Lean Forward level. This has been addressed by the recent installation of remote monitoring equipment at the dam including CCTV camera which allows visual inspection of the dam, spillway and v-notch weir.
7.2 FLOODING
Flooding from significant rainfall has been identified as a dam hazard for Wild River Dam with the potential to cause a dam emergency event. The following sections identify the actions to be undertaken in a flooding event.
The EAP will be activated when the reservoir level reaches EL 1047.1 m AHD (500 mm over the spillway) and heavy rainfall is continuing in the catchment. This corresponds to Alert Level 2. Trigger levels for movement between the different levels are outlined in the Flooding flowchart.
The EAP officer is responsible for monitoring reservoir levels via the SCADA/Telemetry system and
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-2
CCTV system and identifying when activation of the EAP or escalation of the EAP activation level is required.
Failure Impact Assessment undertaken by SKM and Jacobs identified a maximum number of 31 flood-affected properties in a PMF event with and without dam failure or cascade failure of Old Wild River Dam.
The maximum recorded flood depth flowing over the spillway was 108mm (1046.71 m AHD) on Thursday 24 January 2013. This minor flood event resulted in the access road to the dam becoming inaccessible where the road crosses the river near the old railway bridge. It is noted that anecdotally the dam has often experienced larger overflow events prior to installation of gauging in November 2013. SunWater identified the critical duration storm for the catchment as 1.5 hours, with peak dam levels occurring approximately 1.3 hours after the start of the storm. This means that with very intense rainfall, the time period from activation of “Alert” status to “Stand-up” could be less than 30 mins. As access to the dam and nearby properties is cut by the Wild River in even minor flood events, it is noted that: Observation of the dam during flood events is wholly reliant on the remote monitoring systems,
although there is redundancy built into the system; and
At least 2 properties comprising PAR are likely to be isolated prior to activation of the EAP.
There is no public access to the Wild River reach between the Wild River Dam and the Old Wild River Dam and the access road to these dams has locked security gate so it is unlikely to cause hazard to the public when the river outlet of the Wild River Dam is operated.
7.2.1 Preventative actions for Flooding Events:
Monitor BoM weather radar and storage water level.
Initial EAP training and continuing refresher training and annual Scenario Event exercises organised by MWW. Details of the training is as follows:
- EAP Training will be held prior to the start of the wet season.
- EAP Officer, Backup EAP Officers, MWW and LDC are to attend and participate in the training.
- EAP Training exercises to consist of understanding triggers for when EAP is to be enacted, roles and responsibilities of each person, communication / notification protocols and preventative and remediation actions under different EAP events.
Issue individual Evacuation Plans to PAR affected by a PMF event, and in particular to each house visited explain:
- What to do.
- Where to go.
- When.
Ensure that all identified PAR are aware of the implications of large floods with or without dam failure, how they may be affected, where they (as individual groups) are to go and what they have to do at short notice if notified to evacuate.
Contact details in the EAP confirmed, and if necessary updated, each year by 1 September for all PAR affected by a PMF event.
Ensure all identified PAR are signed-up to the Early Warning Network service with TRC which provides voice, SMS and email messaging.
If updated, the relevant section(s) of the EAP sent to each holder of a controlled copy of this EAP.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-3
Review Emergency Alert polygon and template, and check that is properly lodged with the SDCC.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-4
Figure 9: Flood Emergency Flowchart
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-5
Table 2: Flooding Event – Emergency Action Table
Activation Status Alert 1 Alert 2 Lean Forward Stand Up 1 Stand Up 2 Stand Up 3 Stand Down Activation Trigger Cyclone forecast for the
Herberton region with torrential rain and subsequent flooding likely.
Spillway discharging, storage water level at 1047.1 m AHD (500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1047.3 m AHD (700 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1048.1 m AHD (1500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1049.1 m AHD (2500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level approaching 1050.15 m AHD (3550 mm over the spillway); imminent risk of failure or overtopping.
Storage water level dropping to below 1046.9 m AHD (300 mm over the spillway).
Actions: by whom & what
EAP Officer: 1. Notify MWW that EAP
has been enacted and maintain communications.
2. Record all instructions (from whom to whom, where, when & what), telephone conversations, etc. including time and date on the record of communication.
3. Monitor and record storage water level and rainfall via SCADA/Telemetry and/or CCTV system as access road will be impassable.
4. Continue to notify MWW at intervals of four (4) hours.
EAP Officer: 1. Notify MWW that EAP
has been enacted and maintain communications.
2. Record all instructions (from whom to whom, where, when & what), telephone conversations, etc. including time and date on the record of communication.
3. Monitor and record storage water level and rainfall via SCADA/Telemetry and/or CCTV system as access road will be impassable.
4. Continue to notify MWW at intervals of one (1) hour.
EAP Officer: 1. Notify MWW of change
of EAP activation status and maintain communications.
2. Mobilise Backup EAP Officer and Maintenance Officers.
3. Continue monitoring and recording storage water level and rainfall via SCADA/Telemetry and/or CCTV system at intervals of thirty (30) minutes.
4. Provide report to MWW, then at increments of 500 mm or as directed.
EAP Officer: 1. Notify MWW of change
of EAP activation status as water storage level has exceeded 1048.1 m AHD (1500 mm over the spillway).
2. Continue monitoring and recording storage water level and rainfall to MWW at intervals of thirty (30) minutes.
EAP Officer: 1. Notify MWW water
storage level has exceeded 1049.1 m AHD (2500 mm over the spillway), and maintain communication.
2. Continue monitoring and recording storage water level and rainfall to MWW at intervals of fifteen (15) minutes or as directed by MWW.
EAP Officer: 1. Notify MWW that dam
failure may occur at any time.
2. Continue monitoring and recording storage water level and rainfall to MWW at intervals of fifteen (15) minutes or as directed by MWW.
3. Monitor telemetry for signs of failure
EAP Officer: 1. Providing road to dam
is trafficable, request Backup EAP Officers are to inspect dam as soon as possible.
2. Notify MWW water level has dropped below 1046.9 m AHD (300 mm over the spillway) and change of activation status.
3. Prepare report on event for MWW.
4. On the Log of Events / Actions Sheet and the Record of communications Sheet keep a daily running record of all actions / events and telephone calls to and from the MWW, Backup EAP Officers and other personnel.
5. After the event compile an Emergency Event Report and forward unedited copies to the MWW.
6. After the event transfer all data from the event to the Storage Data Book.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-6
Activation Status Alert 1 Alert 2 Lean Forward Stand Up 1 Stand Up 2 Stand Up 3 Stand Down Activation Trigger Cyclone forecast for the
Herberton region with torrential rain and subsequent flooding likely.
Spillway discharging, storage water level at 1047.1 m AHD (500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1047.3 m AHD (700 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1048.1 m AHD (1500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1049.1 m AHD (2500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level approaching 1050.15 m AHD (3550 mm over the spillway); imminent risk of failure or overtopping.
Storage water level dropping to below 1046.9 m AHD (300 mm over the spillway).
Actions: by whom & what
MWW: 1. Notify LDC, GMIS, CEO,
Councillor for division, Police Communication Centre Cairns, DDS (DNRME).
2. Maintain communications with the EAP Officer and LDC.
3. Obtain rainfall forecast from BoM, track progress and effects of flood and inform the EAP Officer of the flood forecast.
4. Should loss of radio signal (Telemetry) occur and high risk of increasing level over spillway notify LDC to issue communicate warning notification.
MWW: 1. Notify LDC, GMIS, CEO,
Councillor for division, Police Communication Centre Cairns, DDS (DNRME).
2. Maintain communications with the EAP Officer and LDC.
3. Obtain rainfall forecast from BoM, track progress and effects of flood and inform the EAP Officer of the flood forecast.
4. Should loss of radio signal (Telemetry) occur and high risk of increasing level over spillway notify LDC to issue communicate warning notification.
MWW: 1. Review EAP Officer
reports. 2. Notify LDC, GMIS,
CEO, Councillor for division, Police Communication Centre Cairns, DDS (DNRME).
3. Maintain communications with the EAP Officer and LDC and provide updates at intervals of one (1) hour.
4. Obtain rainfall forecast from BoM, track progress and effects of flood and inform the EAP Officer of the flood forecast.
5. Should loss of radio signal (Telemetry) occur and high risk of increasing level over spillway notify LDC to issue communicate warning notification.
MWW: 1. Review EAP Officer
reports. 2. Notify LDC and advise
to prepare for evacuation and provide updates at intervals of thirty (30) minutes.
3. Notify GMIS, CEO, Councillor for division, Police Communication Centre Cairns, DDS (DNRME).
4. Maintain communications with the EAP Officer and LDC.
5. Obtain rainfall forecast from BoM, track progress and effects of flood and inform the EAP Officer of the flood forecast.
6. Should loss of radio signal (Telemetry) occur and high risk of increasing level over spillway notify LDC to issue communicate warning notification.
MWW: 1. Review EAP Officer
reports. 2. Notify LDC and advise
evacuation is required and provide updates at intervals of fifteen (15) minutes.
3. Notify GMIS, CEO, Councillor for division, Police Communication Centre Cairns, DDS (DNRME).
4. Maintain communications with the EAP Officer and LDC.
5. Obtain rainfall forecast from BoM, track progress and effects of flood and inform the EAP Officer of the flood forecast.
6. Should loss of radio signal (Telemetry) occur and high risk of increasing level over spillway notify LDC to issue communicate warning notification.
MWW: 1. Review EAP Officer
reports. 2. Notify LDC, GMIS,
CEO, Councillor for division, Police Communication Centre Cairns, DDS (DNRME).
3. Maintain communications with the EAP Officer and LDC and provide updates at intervals of fifteen (15 minutes).
MWW: 1. Notify LDC and advise
that the EAP is deactivated and authorise notification of residents that event is over.
2. Notify GMIS, CEO, Councillor for division, Police Communication Centre Cairns, DDS (DNRME).Prepare EER.
3. Remedial works undertaken to mitigate risk.
LDC: 1. Coordinate the response
and implement the disaster management plans as required.
2. Notify PAR1
LDC: 1. Coordinate the response
and implement the disaster management plans as required.
LDC: 1. Coordinate the
response and implement the disaster management plans as required.
LDC: 1. Coordinate the
response and implement the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the
response and implement the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the
response and implement the disaster management plans as required.
2. Notify PAR
LDC:
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-7
Activation Status Alert 1 Alert 2 Lean Forward Stand Up 1 Stand Up 2 Stand Up 3 Stand Down Activation Trigger Cyclone forecast for the
Herberton region with torrential rain and subsequent flooding likely.
Spillway discharging, storage water level at 1047.1 m AHD (500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1047.3 m AHD (700 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1048.1 m AHD (1500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level at 1049.1 m AHD (2500 mm over the spillway), heavy rain falling and storage continuing to rise.
Storage water level approaching 1050.15 m AHD (3550 mm over the spillway); imminent risk of failure or overtopping.
Storage water level dropping to below 1046.9 m AHD (300 mm over the spillway).
Notifications: by whom & to whom
EAP Officer: 1. MWW
EAP Officer: 1. MWW
EAP Officer: 1. MWW 2. Backup EAP Officer
EAP Officer: 1. MWW 2. Backup EAP Officer
EAP Officer: 1. MWW 2. Backup EAP Officer
EAP Officer: 1. MWW 2. Backup EAP Officer
EAP Officer: 1. MWW 2. Backup EAP Officer
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication
Centre, Cairns 6. DDS (DNRME)
LDC: 1. PAR1
LDC:
LDC:
LDC: 1. PAR
LDC: 1. PAR
LDC: 1. PAR
LDC: 1. PAR
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
Note: - Actions are numbered in order of priority.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-8
Table 3: Flood Event – Communication Table Activation Status Trigger for Communications / Notifications Contact Groups (in
Priority Order) Method Message Code Message Text
Alert 1 Cyclone forecast for the Herberton region with torrential rain and subsequent flooding likely.
Population At Risk (PAR1)
Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• Direct telephone call
Tablelands Regional Council wish to inform you that a cyclone is forecast to affect the Herberton region in the coming days. Torrential rain is likely and Tablelands Regional Council advises you to consider evacuating your property to higher ground or risk access to your property being cut off. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Cyclone forecast to affect Herberton region in coming days. Consider evacuation or risk access to your property being cut off. More info: local radio, TRC 1300 362 242
Alert 2 Loss of remote monitoring communications PAR (all) Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• Direct telephone call
This is a Flash Flood Watch and Act message from Tablelands Regional Council. Radio signal to monitoring equipment at the Wild River Dam has been lost. Heavy rainfall may have led to rises in the Wild River Dam. If you experience rapidly rising water levels, collect your evacuation kit and move to a place of safety on higher ground. For more information tune into local radio or call Council on 1300 362 242
Lean Forward Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Stand Up 1 Storage water level above 1048.1 m AHD (1500
mm over the spillway). PAR (all) Phone (Voice Message) via:
• Early Warning Network system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. Heavy rainfall has led to rapid rises in the Wild River Dam. Water height has now exceeded 1048.1 metres AHD. The critical height for the Wild River Dam is 1050.15 metres AHD (Crest Level). Please prepare for evacuation and await further instruction. For more information tune into local radio or call TRC on 1300 362 242. Heavy rain has led to rapid rises in Wild River Dam. Water is now 2m below crest. Be prepared to evacuate. More info: local radio, TRC 1300 362 242.
Stand Up 2 Storage water level above 1049.1 m AHD (2500 mm over the spillway).
PAR (all) Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. Heavy rainfall has led to rapid rises in the Wild River Dam. Water height has now exceeded 1049.1 metres AHD. The critical height for the Wild River Dam is 1050.15 metres AHD (Crest level). Please collect your evacuation kit and move to a place of safety on higher ground. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Heavy rain has led to rapid rises in Wild River Dam. Water is now 1m below crest. Evacuate to higher ground NOW. More info: local radio, TRC 1300 362 242.
Stand Up 3 No communications or notifications required at this trigger as evacuation should have already been undertaken.
Stand Down Storage water level dropping to below 1046.9 m AHD (300 mm over the spillway).
PAR (each of the evacuated groups)
EAP Officer to contact via phone following consultation with MWW and LDC.
We would like to advise the evacuated groups that the emergency has ended and thank you for your cooperation.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-9
Table 3: Flood Event – Communication Table Activation Status Trigger for Communications / Notifications Contact Groups (in
Priority Order) Method Message Code Message Text
MWW LDC
EAP Officer to contact via phone.
I am advising you that each of the evacuated group has been contacted and advised that the emergency has ended.
Loss of Radio Signal (Telemetry)
Loss of communications and high risk of increasing level over spillway.
MWW Emergency Emergency this is an important message from Tablelands Regional Council. Radio signal to monitoring equipment at the Wild River Dam has been lost. Heavy rainfall has led to rapid rises in the Wild River Dam. Assume worst case scenario as a precaution. Please collect your evacuation kit and move to a place of safety on higher ground. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Radio signal to monitoring equipment at Wild River Dam lost. Heavy rain has led to rapid rises in Wild River Dam. Assume worst as a precaution. Evacuate to higher ground NOW. More info: local radio, TRC 1300 362 242.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-10
7.3 EARTHQUAKE
An earthquake may result in damage to the dam including but not limited to: deformation of the spillway
deformation of the embankment
landslide into the dam. An earthquake-induced failure of the dam can occur when the storage level is at or below FSL, and when the dam is spilling. In many cases there will be no warning and hence no Alert or Lean Forward level. The recently installed CCTV camera at the dam allows remote monitoring of the dam and appropriate escalation of the EAP activation.
In the situation where an earth tremor may cause a deformation of the spillway and/or embankment and/or a landslide into the dam there is no automated early warning system. The only immediate method of detection (other than being within the zone of tremor and feeling it) at present would be if the SCADA or CCTV system was being monitored during the event or if personnel were on site at that time. Travel time of the failure wave from the dam to the first PAR is less than 10 minutes. Earthquake alerts when received by the LDC and passed on to the EAP Officer. If an earthquake is felt in the region, a visual check of the dam is to be undertaken immediately via the CCTV camera. The dam is to be inspected by the EAP Officer at the earliest possible time. Should this inspection identify any changes to the dam or signs of potential failure, further inspection is to be undertaken by the Manager Water and Waste and/or a Dam Safety Consultant. 7.3.1 Preventative actions for an Earthquake Event:
Routine inspections of the dam to identify any indications that there is an increased likelihood of failure following an earthquake.
Public awareness of the evacuation plan.
Initial EAP training and continuing annual EAP refresher training and annual Scenario Event exercises organised by MWW.
Issue individual Evacuation Plans to PAR affected by a Sunny Day Failure, and in particular to each house visited explain:
- What to do.
- Where to go.
- When.
Ensure that all identified PAR are aware of the implications of a Sunny Day Failure event, how they may be affected, where they (as individual groups) are to go and what they have to do at short notice if notified to evacuate.
If updated, the relevant section(s) of the EAP sent to each holder of a controlled copy of this EAP.
Contact details in the EAP confirmed, and if necessary updated, each year by 1 September for all PAR affected by a Sunny Day Failure.
Ensure all identified PAR are signed-up for the Early Warning Network service with TRC which provides voice, SMS and email messaging.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-11
Figure 10: Earthquake Flowchart
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-12
Table 4: Earthquake Event – Emergency Action Table
Activation Status Alert Lean Forward Stand Up Stand Down Activation Trigger Earthquake reported or felt in area.
Intensity less then 5MMI And No changes detected during surveillance inspection
Earthquake reported or felt in area. Intensity greater than or equal to 5MMI And Changes detected during surveillance inspection
Earthquake reported or felt in the area And Failure in progress or likely, increased seepage
Risk assessment has determined that failure risk has reduced
Actions: by whom & what
EAP Officer: 1. Notify MWW 2. Visual Check of CCTV 3. Inspect the dam, spillway and
embankment, assess, monitor and inform MWW.
4. Report to MWW 5. Record data and log book entry 6.
EAP Officer: 1. As per previous activation status 2. Notify MWW of change of EAP activation
status. 3. Inspect, assess, monitor and maintain
communication with MWW. 4. Continue / start remedial action and / or
load reduction if directed.
EAP Officer: 1. As per previous activation status 2. Relocate to safe ground, continue
observing situation and relaying information to MWW.
EAP Officer: 1. Forward event report to MWW 2. Return to scheduled inspection regime 3. After the event transfer all data from the
event to the Storage Data Book.
MWW: 1. Notify LDC
MWW: 1. As per previous activation status 2. Activate EAP 3. Inspect, assess and determine available
timeframe for potential / continuing remedial works and/or load reduction, if practical.
4. Notify LDC evacuation may be required, and direct to Notify the PAR
5. Notify GMIS and CEO that emergency situation has developed.
MWW: 1. As per previous activation status 2. Notify 000 that evacuation is required. 3. Notify LDC evacuation is required. 4. Notify GMIS and CEO that emergency
situation has further developed.
MWW: 1. Authorise notification of residents that
event is over and deactivate the EAP. 2. Prepare EER. 3. Remedial works undertaken to significantly
mitigate risk.
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
Notifications: by whom & to whom
EAP Officer: 1. MWW
EAP Officer: 1. MWW
EAP Officer: 1. Emergency services (000) 2. MWW
EAP Officer: 2. MWW 3. PAR
MWW: 1. LDC
MWW: 1. Police Communication Centre, Cairns 2. LDC 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
MWW: 1. Police Communication Centre, Cairns 2. Emergency Services (000) 3. LDC 4. GMIS 5. CEO 6. Councillor for division 7. DDS (DNRME)
MWW: 1. Police Communication Centre, Cairns 2. LDC 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
LDC: LDC: 1. PAR
LDC: 1. PAR
LDC:
CEO: CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
Note: - Actions are numbered in order of priority.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-13
Table 5: Earthquake Event - Communication Table
Activation Status Trigger for Communications / Notifications Contact Groups (in Priority Order)
Method Message Code Message Text
Alert Earthquake reported or felt in area. Intensity less then 5MMI And No changes detected during surveillance inspection
Not Applicable Not Applicable Not Applicable Not Applicable
Lean Forward Earthquake reported or felt in area. Intensity greater than or equal to 5MMI OR Changes detected during surveillance inspection
PAR Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. Stability issues have been identified at Wild River Dam which may result in failure and rapid flooding. Please prepare your evacuation kit and identify a place of safety on higher ground. Be prepared to evacuate at short notice. For more information tune into local radio or call TRC on 1300 362 242. Stability issues at Wild River Dam. May lead to dam failure and rapid flooding. Be prepared to evacuate. More info on local radio or TRC on 1300 362 242.
Stand Up Earthquake reported or felt in the area And Failure in progress or likely, increased seepage
PAR Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. The Wild River dam has suffered an extreme failure. Rapid flooding is imminent. Please collect your evacuation kit and move to a place of safety on higher ground immediately. This situation poses a significant threat to life and property. Your safety is in jeopardy if you do not act now. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Wild River Dam has FAILED. Rapid flooding is imminent. Significant threat to life. EVACUATE to high ground NOW. More info: local radio, TRC 1300 362 242.
Stand Down Risk assessment has determined that failure risk has reduced
PAR (each of the evacuated groups)
EAP Officer to contact via phone
We would like to advise the evacuated groups that the emergency has ended and thank you for your cooperation.
MWW LDC
EAP Officer to contact via phone.
I am advising you that each of the evacuated group has been contacted and advised that the emergency has ended.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-14
7.4 TERRORIST OR HIGH ENERGY IMPACT
A terrorist threat, or activity, could increase the likelihood of dam failure through a high energy impact (non-natural events), or deliberate, accidental or vandalism actions against the dam structure.
The approach of this plan is to monitor any threat or damage remotely until the threat is abated and it is safe to inspect the dam to identify any potential damage. Travel time of the failure wave from the dam to the first PAR is less than 10 minutes. Therefore, evacuation is advised should any damage be suspected. The recent installation of remote monitoring equipment at the dam provides a significant improvement in the ability to monitor the dam for potential damage without accessing the dam itself. The available remote monitoring equipment includes a CCTV camera that can be remotely operated to zoom into the dam embankment, spillway, v-notch weir, and dam access. Additionally, dam water levels are now monitored via three separate mechanisms with data transmitted via the SCADA system and via the 3G/4G network. 7.4.1 Preventative actions for Terrorism or High Energy Impact:
Public awareness of the evacuation plan.
Initial EAP training and continuing annual EAP refresher training and annual Scenario Event exercises organised by MWW.
Issue individual Evacuation Plans to PAR affected by a Sunny Day Failure, and in particular to each house visited explain:
- What to do.
- Where to go.
- When.
Ensure that all identified PAR are aware of the implications of a Sunny Day Failure event, how they may be affected, where they (as individual groups) are to go and what they have to do at short notice if notified to evacuate.
If updated, the relevant section(s) of the EAP sent to each holder of a controlled copy of this EAP.
Contact details in the EAP confirmed, and if necessary updated, each year by 1 September for all PAR affected by a Sunny Day Failure.
Ensure all identified PAR are signed-up for the Early Warning Network service with TRC which provides voice, SMS and email messaging.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-15
Figure 11: Terrorism or High Energy Impact Flowchart
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-16
Table 8: Terrorist or high energy impact – Emergency Action Table Activation Status Alert Lean Forward Stand Up Stand Down Activation Trigger Not Applicable Possible terrorist activity observed or threat
received Explosion, terrorist action or high energy impact observed at dam
Risk assessment performed and risk deemed to be removed
Actions: by whom & what
Not Applicable. EAP Officer: 1. Notify Police on 000 2. Notify QPS Counter Terrorism Liaison
Officer 3. Notify National Security Hotline 4. Notify MWW 5. Monitor situation remotely via CCTV 6. When deemed safe by Police, inspect dam
under Police escort. 7. Photo record 8. Log book record
EAP Officer: 1. As per previous activation level 2. Notify Police on 000 that evacuation is
required
EAP Officer: 1. Prepare event report and supporting data
to MWW
MWW: 1. Notify GMIS and CEO that emergency
situation has developed. 2. Notify LDC
MWW: 1. Notify GMIS and CEO that emergency
situation has further developed. 2. Notify LDC
MWW: 1. Authorise notification of residents that
event is over and deactivate the EAP. 2. Prepare EER. 3. Remediation works undertaken to
significantly mitigate risk.
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
2. Notify PAR Notifications: by whom & to whom
EAP Officer: 1. Emergency services (000) 2. QPS Counter Terrorism Liaison Officer 3. National security hotline on 1800 123 400 4. MWW
EAP Officer: 1. Emergency services (000) 2. QPS Counter Terrorism Liaison Officer 3. National security hotline on 1800 123 400 4. MWW
EAP Officer: 1. MWW
MWW: 1. LDC 2. Police Communication Centre, Cairns 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
MWW: 1. LDC 2. Police Communication Centre, Cairns 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
MWW: 1. Police Communication Centre, Cairns 2. LDC 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
LDC: 1. PAR
LDC: 1. PAR
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-17
Table 9: Terrorist or high energy impact - Communication Table
Activation Status Trigger for Communications / Notifications Contact Groups (in Priority Order)
Method Message Code Message Text
Alert Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable
Lean Forward Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable
Stand Up Explosion, terrorist action or high energy impact observed at dam
PAR Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. The Wild River dam has suffered an extreme failure. Rapid flooding is imminent. Please collect your evacuation kit and move to a place of safety on higher ground immediately. This situation poses a significant threat to life and property. Your safety is in jeopardy if you do not act now. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Wild River Dam has FAILED. Rapid flooding is imminent. Significant threat to life. EVACUATE to high ground NOW. More info: local radio, TRC 1300 362 242.
Stand Down Remedial works completed and risk of failure drops significantly.
PAR (each of the evacuated groups)
EAP Officer to contact via phone
We would like to advise the evacuated groups that the emergency has ended and thank you for your cooperation.
MWW LDC
EAP Officer to contact via phone.
I am advising you that each of the evacuated group has been contacted and advised that the emergency has ended.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-18
7.5 SUNNY DAY FAILURE
A “Sunny Day” failure is defined as failure of the dam and the release of water downstream, when there is low or no inflow to the dam from rainfall events. This type of dam failure is unexpected and can occur with little or no warning. A “Sunny Day” failure may be as a result of any or a combination of the following: Embankment stability issues: increased seepage, new visible signs of seepage and particularly
evidence of sediment transport (i.e. cloudy flow) as this can be an indication of piping.
Signs of distress in embankment such as cracking and/or deformation and/or evidence of material having slid off embankment.
Appearance of sinkholes, soft spots and ‘boggy areas’
abnormal instrument readings (piezometers indicating higher hydrostatic pressures)
differential movement or settlement
increasing rates of seepage or development of new seepage paths
piping of the embankment
Earthquakes and Landslides.
Terrorist or high energy impact (non-natural events), including deliberate, accidental or vandalism actions against the dam structure.
Actions for earthquake events and terrorism are outlined in Sections 7.3 and 7.4. This section outlines actions and communications for all other potential Sunny Day Failure events. The recent installation of remote monitoring equipment at the dam including a CCTV camera allowing remote visual inspection of the condition of the dam and the seepage flow over the v-notch weir seeks to improve the EAP activation and escalation process. However, in many of these cases there will be no warning and hence no Alert or Lean Forward level, with immediate escalation to Stand Up with associated warnings and evacuations. This is particularly important as travel time of the failure wave from the dam to the first PAR is less than 10 minutes. The dam is inspected weekly for signs of structural defects and increased seepage. The likelihood of this type of failure is lessened with good management practices. However if during an inspection increased seepage/changes in turbidity of seepage was observed and verified then the procedures detailed in the following tables would be followed including inspection by an RPEQ. 7.5.1 Preventative actions for a Sunny Day Failure Event:
Routine inspections of the dam to identify any indications that there is an increased likelihood of failure.
Public awareness of the evacuation plan.
Initial EAP training and continuing annual EAP refresher training and annual Scenario Event exercises organised by MWW.
Issue individual Evacuation Plans to PAR affected by a Sunny Day Failure, and in particular to each house visited explain:
- What to do.
- Where to go.
- When.
Ensure that all identified PAR are aware of the implications of a Sunny Day Failure event, how they may be affected, where they (as individual groups) are to go and what they have to do at short notice if notified to evacuate.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-19
If updated, the relevant section(s) of the EAP sent to each holder of a controlled copy of this EAP.
Contact details in the EAP confirmed, and if necessary updated, each year by 1 September for all PAR affected by a Sunny Day Failure.
Ensure all identified PAR are signed-up for the Early Warning Network service with TRC which provides voice, SMS and email messaging.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-20
Figure 12: Sunny Day Failure Flowchart
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-21
Table 6: Sunny Day Failure Event – Emergency Action Table Activation Status Alert Lean Forward Stand Up Stand Down Activation Trigger Identification during routine inspection of initial
signs of embankment distress such as cracks. OR Abnormal seepage increases / changes in turbidity of seepage: around the outlet works and potentially via pathways through dam wall.
Cracking becoming significant to the point where stability may be starting to be impaired. OR Seepage rate begins to further increase / or further increases in turbidity of seepage.
Loads on embankment increasing or cracking / deformation or seepage is increasing to a state where the safety of the dam is significantly impaired.
Remedial works completed and risk of failure drops significantly.
Actions: by whom & what
EAP Officer: 1. Notify MWW that EAP has been enacted
and maintain communications. 2. Inspect, assess, monitor and inform MWW. 3. Undertake or supervise remedial action if
directed.
EAP Officer: 1. Notify MWW of change of EAP activation
status and maintain communications. 2. Inspect, assess, monitor and maintain
communication with MWW. 3. Continue / start remedial action and / or
load reduction if directed.
EAP Officer: 1. Notify MWW of change of EAP activation
status. 2. Relocate to safe ground, continue
observing situation and relaying information to MWW.
EAP Officer: 1. Notify MWW that remedial works have
been completed and risk of failure has dropped significantly.
2. On the Log of Events / Actions Sheet and the Record of communications Sheet keep a daily running record of all actions / events and telephone calls to and from the MWW, Backup EAP Officers and other personnel.
3. After the event compile an Emergency Event Report and forward unedited copies to the MWW.
4. After the event transfer all data from the event to the Storage Data Book.
MWW: 1. Inspect and determine level of risk of failure
(storage level, inflow, seepage, etc.) 2. Determine available timeframe for potential
remedial works, if practical. 3. Determine if load reduction is required and /
or possible. 4. Notify LDC, GMIS and CEO if deemed
necessary
MWW: 1. Inspect, assess and determine available
timeframe for potential / continuing remedial works and/or load reduction, if practical.
2. Notify LDC evacuation may be required. 3. Notify GMIS and CEO that emergency
situation has developed.
MWW: 1. Notify 000 that evacuation is required. 2. Notify LDC evacuation is required. 3. Notify GMIS and CEO that emergency
situation has further developed.
MWW: 1. Authorise notification of residents that
event is over and deactivate the EAP. 2. Prepare EER. 3. Remedial works undertaken to significantly
mitigate risk.
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
2. Notify PAR
LDC: 1. Coordinate the response and implement
the disaster management plans as required.
Notifications: by whom & to whom
EAP Officer: 1. MWW
EAP Officer: 1. MWW
EAP Officer: 1. MWW
EAP Officer: 1. MWW 2. PAR
MWW: 1. LDC 2. GMIS 3. CEO 4. Councillor for division 5. Police Communication Centre, Cairns 6. DDS (DNRME)
MWW: 1. Police Communication Centre, Cairns 2. LDC 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
MWW: 1. Police Communication Centre, Cairns 2. Emergency Services (000) 3. LDC 4. GMIS 5. CEO 6. Councillor for division 7. DDS (DNRME)
MWW: 1. Police Communication Centre, Cairns 2. LDC 3. GMIS 4. CEO 5. Councillor for division 6. DDS (DNRME)
LDC: LDC: 1. PAR
LDC: 1. PAR
LDC:
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
CEO: 1. Mayor
Note: - Actions are numbered in order of priority.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-22
Table 7: Sunny Day Failure - Communication Table
Activation Status Trigger for Communications / Notifications Contact Groups (in Priority Order)
Method Message Code Message Text
Alert Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Lean Forward Cracking becoming significant to the point
where stability may be starting to be impaired. OR Seepage rate begins to further increase / or further increases in turbidity of seepage.
PAR Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. Stability issues have been identified at Wild River Dam which may result in failure and rapid flooding. Please prepare your evacuation kit and identify a place of safety on higher ground. Be prepared to evacuate at short notice. For more information tune into local radio or call TRC on 1300 362 242. Stability issues at Wild River Dam. May lead to dam failure and rapid flooding. Be prepared to evacuate. More info on local radio or TRC on 1300 362 242.
Stand Up Loads on embankment increasing or cracking / deformation or seepage is increasing to a state where the safety of the dam is significantly impaired.
PAR Phone (Voice Message) via: • Early Warning Network
system subscribed to by TRC;
• State-wide EA system
Emergency Emergency this is an important message from Tablelands Regional Council. The Wild River dam has suffered an extreme failure. Rapid flooding is imminent. Please collect your evacuation kit and move to a place of safety on higher ground immediately. This situation poses a significant threat to life and property. Your safety is in jeopardy if you do not act now. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Wild River Dam has FAILED. Rapid flooding is imminent. Significant threat to life. EVACUATE to high ground NOW. More info: local radio, TRC 1300 362 242.
Stand Down Remedial works completed and risk of failure drops significantly.
PAR (each of the evacuated groups)
EAP Officer to contact via phone
We would like to advise the evacuated groups that the emergency has ended and thank you for your cooperation.
MWW LDC
EAP Officer to contact via phone.
I am advising you that each of the evacuated group has been contacted and advised that the emergency has ended.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 7-1
7.6 RESERVOIR WATER QUALITY (TOXIC SPILL/ ALGAL BLOOM WITHIN CATCHMENT
AREA)
Any water quality contamination events are covered under Tablelands Regional Council’s Drinking Water Quality Management Plan which includes the Herberton Water Supply Scheme. As the Dam is not open to the public for recreational use, there is no need to include a water quality contamination event as part of this document.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 8-2
8. WARNINGS AND NOTIFICATIONS
8.1 WARNING AND NOTIFICATION MECHANISMS
The owner of the dam is responsible for issuing emergency warnings to the Population at Risk (PAR). Locally this is undertaken in collaboration with the Local Disaster Coordinator (LDC) who will issue the notification and warning messages to the affected PAR. Four (4) key options are available for notification and warning of the PAR: An alert via the Early Warning Network system subscribed to by TRC;
An alert via the State-wide Emergency Alert (EA) system;
Media releases / public announcements; or
Direct contact i.e. door-knocking (if possible). The Early Warning Network (EWN) is an opt-in system. This means that residents can sign up to be included in the system to be added to a Wild River Dam PAR group within TRC’s system. However, as the intended use of contact information is to protect public safety, TRC have opted to include the PAR contacts in an additional distribution system, updated by TRC regardless of whether the individuals have ‘opted in’. Prior to 1 September each year, pre-wet season communications is provided to all affected PAR. A warning using this system can be sent directly by the LDC and generally takes around 20 minutes to set up. The State-wide EA system alerts all landline and mobiles located within a spatial polygon at a point in time. A warning using this system generally takes around 10 minutes for the LDC to organise and then it has a lead time of approximately 30 minutes before the warning is delivered as the message has to be approved and sent by the State. This has to be factored into the available evacuation time. Direct contact (i.e. door knocking) may be quicker in some instances, if police or SES are located near the PAR. However, in utilising these warning systems, it is important to note that these warning mechanisms may not provide effective warning to all PAR as: the access to the first 2 properties with PAR will be cut during event minor flood events;
the travel time for a failure wave from the dam to the first 2 properties with PAR is less than 10 minutes; and
the travel time for a failure wave from the dam to Herberton and Wondecla is in the order of 1-1.5 hours and 2-2.5 hours, respectively.
8.2 WARNING AND NOTIFICATION PROCESSES
If a notification or warning is required to be sent to affected PAR, the process is to contact the LDC and make the request. Both the Early Warning Network and the State-wide EA system will be used to send out one of the pre-prepared messages in the following sections. A pre-created EA polygon map and the text of these messages have been pre-lodged with the SDCC watch desk and will be activated by the LDC. In late 2018, TRC installed a series of remote monitoring equipment at the dam. This allows remote electronic dam water level monitoring, rain gauge monitoring and seepage monitoring. TRC continues to investigate the feasibility of utilising this equipment to trigger an automated alarm at a pre-set sequence of events should the Wild River dam should show signs of a pending failure or overtopping. However, at present an automated warning system is not available for Wild River Dam.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 8-3
8.3 PRE-PREPARED MESSAGES
Pre-prepared messages have been developed for SDF and Flood Events, and also in the event of loss of radio signal during either event, to advise PAR to “prepare for evacuation” or to “evacuate immediately”. VOICE, TEXT messages have been prepared for the state-wide Emergency Alert system whilst VOICE, TEXT and EMAIL messages have been prepared for the EWN. 8.3.1 Sunny Day Failure – Prepare to Evacuate
Dam Failure Possible – Prepare to Evacuate (VOICE) Emergency Emergency this is an important message from Tablelands Regional Council. Stability issues have been identified at Wild River Dam which may result in failure and rapid flooding. Please prepare your evacuation kit and identify a place of safety on higher ground. Be prepared to evacuate at short notice. For more information tune into local radio or call TRC on 1300 362 242. Dam Failure Possible – Prepare to Evacuate (TEXT) Stability issues at Wild River Dam. May lead to dam failure and rapid flooding. Be prepared to evacuate. More info on local radio or TRC on 1300 362 242. 8.3.2 Sunny Day Failure – Evacuate Now
Dam Failure – Evacuate Now (VOICE) Emergency Emergency this is an important message from Tablelands Regional Council. The Wild River dam has suffered an extreme failure. Rapid flooding is imminent. Please collect your evacuation kit and move to a place of safety on higher ground immediately. This situation poses a significant threat to life and property. Your safety is in jeopardy if you do not act now. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Dam Failure – Evacuate Now (TEXT) Wild River Dam has FAILED. Rapid flooding is imminent. Significant threat to life. EVACUATE to high ground NOW. More info: local radio, TRC 1300 362 242. 8.3.3 Flood Events – Prepare to Evacuate
Dam – Rainfall (Cyclone) Events – Prepare to Evacuate (VOICE) Tablelands Regional Council wish to inform you that a cyclone is forecast to affect the Herberton region in the coming days. Torrential rain is likely and Tablelands Regional Council advise you to consider evacuating your property to higher ground or risk access to your property being cut off. Dam - Rainfall (Cyclone) Events – Prepare to Evacuate (TEXT) Cyclone forecast to affect Herberton region in coming days. Consider evacuation or risk access to your property being cut off. More info: local radio, TRC 1300 362 242 Dam - Rainfall Events – Prepare to Evacuate (VOICE) Emergency Emergency this is an important message from Tablelands Regional Council. Heavy rainfall has led to rapid rises in the Wild River Dam. Water height has now exceeded 1048.1 metres AHD. The critical height for the Wild River Dam is 1050.15 metres AHD (Crest Level). Please prepare for evacuation and await further instruction. For more information tune into local radio or call TRC on 1300 362 242.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 8-4
Dam - Rainfall Events – Prepare to Evacuate (TEXT) Heavy rain has led to rapid rises in Wild River Dam. Water is now 2m below crest. Be prepared to evacuate. More info: local radio, TRC 1300 362 242. 8.3.4 Flood Events – Evacuate Now
Dam - Rainfall Events – Evacuate Now (VOICE) Emergency Emergency this is an important message from Tablelands Regional Council. Heavy rainfall has led to rapid rises in the Wild River Dam. Water height has now exceeded 1049.1 metres AHD. The critical height for the Wild River Dam is 1050.15 metres AHD (Crest level). Please collect your evacuation kit and move to a place of safety on higher ground. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Dam - Rainfall Events – Evacuate Now (TEXT) Heavy rain has led to rapid rises in Wild River Dam. Water is now 1m below crest. Evacuate to higher ground NOW. More info: local radio, TRC 1300 362 242. 8.3.5 Flood Events – Loss of Radio Signal - Evacuate Now
Dam - Rainfall Events Loss of Radio Signal – Evacuate Now (VOICE) Emergency Emergency this is an important message from Tablelands Regional Council. Radio signal to monitoring equipment at the Wild River Dam has been lost. Heavy rainfall has led to rapid rises in the Wild River Dam. Assume worst case scenario as a precaution. Please collect your evacuation kit and move to a place of safety on higher ground. For more information tune into local radio or call Tablelands Regional Council on 1300 362 242. Dam - Rainfall Events – Evacuate Now (TEXT) Radio signal to monitoring equipment at Wild River Dam lost. Heavy rain has led to rapid rises in Wild River Dam. Assume worst as a precaution. Evacuate to higher ground NOW. More info: local radio, TRC 1300 362 242. 8.4 INDIVIDUAL EVACUATION PLANS
Individual Evacuation Plans (Appendix D) have been prepared and reviewed for distribution to residents at risk. They will be advised to implement their Evacuation Plan if they are provided warnings or become aware of or suspect that an emergency event has occurred. An annual education program that may include community meetings, door knocking and writing to the PAR will be undertaken to ensure that residents at risk at kept aware of their risks and their plan and are updated on any changes to the EAP. As part of this process, residents will be signed up to Council’s Early Warning Network to receive faster information alerts and warning to evacuate. 8.5 END OF EVENT
The EAP Officer must (after receiving advice from the LDC): Contact each of the evacuated groups and advise them that the emergency has ended, and
thank them for their cooperation.
Advise MWW and LDC that each evacuated group has been contacted and advised that the emergency has ended and await further instructions.
Provide information on support available to affected residents and signposting to recovery services if required.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 8-5
Debriefing and identifying lessons to improve future response operations.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 9-1
9. EVENT REPORTING
9.1 STORAGE DATA BOOK
EAP Officer shall ensure that events and appropriate data are recorded in the Storage Data Book. All new entries are to be copied and forwarded to General Manager Infrastructure Services monthly. Entries shall be a record of water levels, weather observations, inspections, actions that are carried out, telephone conversations that are related to the emergency event, and comments identifying problems and unusual events. All entries shall be written legibly, unedited and signed by the person making the entry. Errors made shall be struck out and initialled. The Storage Data Book shall be kept permanently in the EAP Officer work residence. It must be available on request and its location known to, EAP Backup Officers, Manager Water & Waste and General Manager Infrastructure Services. 9.2 EMERGENCY EVENT REPORT
The EAP Officer shall prepare an Emergency Event Report after each emergency event and forward it to the Manager Water and Waste within 15 days of the event. The report shall contain (at least):
(a) A description of the event summarised from the Storage Data Book.
(b) Description of any observed damage or other consequences.
(c) Photographs.
(d) A summary of data recorded during the event and the times of these recordings such as,
- rainfall,
- water level within the storage, and
- seepage flows and observations (if applicable).
(e) Details of communication which took place during the emergency.
(f) Comment on the adequacy of the Emergency Action Plan.
(g) Any recommendations or suggested changes to the Emergency Action Plan.
(h) Any further comments considered necessary. The Manager Water and Waste shall provide a report on the event to the Director, Dam Safety within 30 days of the event.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 10-1
10. REVISION OF EVACUATION PLANS
Each year before the end of August the Manager Water and Waste shall contact each property owner at risk of inundation to verify contact details and revise the evacuation plan in consultation with the EAP Officer and LDC. The revised plan shall be forwarded to General Manager Infrastructure Services.
The revised plan shall be forwarded to the CEO of TRC for review and acceptance. If substantive changes have been made, a formal review process in accordance with Section 352H of the Water Supply (Safety and Reliability) Act 2008 is required.
The CEO is to approve the evacuation plans. Once approved, the General Manager Infrastructure Services shall authorise postage of revised plans to each resident, or alternatively the revised plans can be hand delivered as part of the annual consultation process to alert residents.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019 Chapter-Page 11-1
11. REFERENCES
Disaster Management Act 2003
Disaster Management Regulation 2014
Emergency Action Planning for Referable Dams (DNRME, 2013)
Guidelines for Failure Impact Assessment of Water Dams (DNRME, 2012)
Queensland Dam Safety Management Guidelines (DNRM, 2002)
Tablelands Local Disaster Management Plan V5.3 (TRC, 2018)
Water Supply (Safety and Reliability) Act 2008
Wild River Dam Failure Impact Assessment Report (SunWater, 2004)
Wild River Dam Failure Impact Assessment Report (Sinclair Knight Merz, 2013)
Wild River Dam Safety Report (Sinclair Knight Merz, 2014)Wild River Dam - Operations and Maintenance Manual
Wild River Dam Seismic Hazard Assessment (Seismology Research Centre – August 2018)
Wild River Dam - Standard Operating Procedures
Wild River Dam - Storage Data Book
Workplace Health and Safety Act 2011
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
APPENDIX A
DATA COLLECTION
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
REPORT FORMAT NATURE OF THE EVENT
Describe the event (e.g. spillway discharge, earthquake, chemical spill, etc)
COMMENCED DATE _____ / _____ / __________ TIME ___________
FINISHED DATE _____ / _____ / __________ TIME ___________
DESCRIPTION OF THE EVENT
Describe in your own words the lead up to and progress of the event (e.g. a spillway discharge)
Include such information as listed below: • Weather conditions and rainfall in the catchment • The rate of rise of the storage • When the spillway was overtopped • Date and time of highest level • Briefly describe any immediate downstream damage caused by the discharge • Include any other information considered relevant
STATISTICS
Total inflow ___________ Megalitres Total discharge ___________ Megalitres Capacity of storage prior to inflow ___________ % Volume prior to inflow ___________ Megalitres Maximum inflow ___________ Megalitres per day Maximum discharge ___________ Megalitres per day
EVENT PROGRESS
Briefly describe the daily rate of storage rise, time to peak level, and weather conditions.
Attach copies of the Spillway Level Versus Time Graph, the Communications Record Sheet, and the Log of Events / Actions Sheet.
GENERAL COMMENTS
Include in this section any observations or comments regarding the event, such as equipment malfunctions, safety issues or any suggestions which may improve monitoring and reporting of the event.
DAMAGE REPORT
Detail any tail water damage to the embankment or stream bank in the immediate area of the dam. Attach photos.
ATTACHMENTS
• Photos / video of the event • Spillway Level versus Time Graph • Communications Record Sheet • Log of Events / Action Sheet
Signed: _________________________ Designation: __________________________
Date: _____ / _____ / __________
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
Table A - 1 Record of Rainfall During a Flood
Date Time Rainfall (mm)
Daily Total (mm) Comments
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
Table A - 2 Storage Level Versus Time
Stor
age L
evel
(m A
HD)
1056.00
1054.00
1052.00
1050.00
1048.00
1046.00
1044.00
1042.00
1040.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time in Hours
Full Supply Level
EL 1046.6 m
Dam Crest Level EL 1050.15 m
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
Table A - 3 Log of Actions/Events
Date Time Event Description/Action carried out Record entered by
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
Table A - 4 Record of Communication
Date Time Phone No Contact Person Event Description/Action carried out Record entered by
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
APPENDIX B
CATCHMENT BOUNDARY
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
APPENDIX C
POTENTIAL PROBLEM IDENTIFICATION
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
TYPE OF DEFICIENCY LOOK FOR
SEEPAGE A water flow or sand boil on the lower portion of the downstream slope or toe area, especially at the groins.
Quantity/quality of drain outflows, seepage and its source(s).
Location, type and extent of deteriorated concrete.
Extent of moist, wet or saturated areas.
Wet areas or areas where the vegetation appears greener or lusher in the toe area.
An increase in the amount of water being released from toe drains or through the v-notch weirs. (Remember to take into account changes in the reservoir level.)
Turbidity or cloudiness of the seepage.
Any change in conditions.
CRACKING/MOVEMENT Location, length, displacement and depth of cracks.
Desiccation Cracking: A random honeycomb pattern of cracks usually found on the crest and the downstream slope.
Transverse Cracking: Cracks that are perpendicular to the length of the dam usually found on the crest.
Longitudinal Cracking: Cracks that are parallel to the length of the dam. Longitudinal cracks may be associated with stability problems in the slopes.
Cracking concrete deterioration.
Disintegration.
Spalling.
Efflorescence.
Drummy concrete.
Popouts.
Pitting.
Scaling.
Surface defects.
Misalignment.
Differential movement in cracks.
Conditions of joints.
INSTABILITY Slides on the upstream or downstream slopes.
Bulging, especially at the toe of the dam.
DEPRESSIONS Misalignment in the crest and embankment slopes found by sighting along fixed points.
Sinkholes found by checking and probing each depression.
Remember, sinkholes have steep, bucket like sides while minor depressions have gently sloping, bowl like sides.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
TYPE OF DEFICIENCY LOOK FOR
MAINTENANCE CONCERNS
Inadequate Slope Protection: Check for bald areas or areas where the protection is sparse or damaged.
Surface Runoff Erosion: Check for gullies or other signs of erosion. Make sure to check the low points along the upstream and downstream shoulders and groins since surface runoff can collect in these areas.
Inappropriate Vegetative Growth: Check for excessive and deep rooted vegetative growth.
Debris: Check for debris on and around the dam, especially near outlet works or spillway inlets.
Animal Burrows: Check for damage caused by burrowing animals.
Note: This tabulation adapted from Queensland Dam Safety Management Guidelines-February 2002. WHEN TO GET FURTHER ASSISTANCE Several of the deficiencies covered above are very serious. If you observe any of the issues listed below, you should advise the Manager Water and Waste immediately:
• Sand boils or turbid seepage. • Seepage that has increased since the last inspection (taking the reservoir level into
consideration). • Cracking that extends below the reservoir level or potential reservoir level. • Transverse and longitudinal cracking. • Deep seated slides or bulging associated with slides. • Sinkholes or other large depressions. • Deep rooted vegetation that might need to be removed.
If you are unsure whether or not a condition poses a threat to the safety of the dam, you should discuss your findings with the Manager Water and Waste.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
APPENDIX D
INUNDATION MAPS, POPULATION AT RISK CONTACT DETAILS & EVACUATION PLANS
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
Evacuation Plans -
Moomin SidingRd
Moomin Rd Deba
ndga
ryRd
1AP19246
217CWL342
179NPW922
63SP113985
290CWL35171SP265020
2SP265020
160CWL366
211CWL358
1RP733446
2RP733446
Wild River Dam Evacuation AdviceSunny Day Failure Flood Extent - Map 5
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Moomin Rd
Atherton-Herberton Rd
217CWL342
10M2973
202M2971
63SP113985
9M2973
197AP1009
72SP113986
290CWL3517
201M2971
12M2973
102M2971101M2971
103M2971
1AP19246
203M2971
11M2973
211CWL358
Wild River Dam Evacuation AdviceSunny Day Failure Flood Extent - Map 6
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 60
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.Evacuate to clearing at intersection of Moomin Rd and
Atherton-Herberton Rd.
Atherton-Herberton Rd
194FTY1870
252CWL3185
290CWL3517
197AP1009
201M2971
43H25337
1AP19246
174CWL3185
72SP113986
211CWL358
1MPH24923
Wild River Dam Evacuation AdviceSunny Day Failure Flood Extent - Map 7
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Rose
L
Morris Rd
Todd
St
Rose
St
Emma
St
Florence St
2MPH34194
1MPH24690
2RP738091
28H25326
ASP227808
61H25320
3RP7004002RP700400
CSP120065
ARP736790
14MPH3273273H25320
255CWL3295
10SP292867
1MPH2653
304CWL3609
1RP700399
89SP113988
DSP179216
91SP113989
ASP179216
1MPH34194
254CWL3271
1MPH2485
1RP700409
BSP227808
2RP700398
1RP738091
1SP292867
1RP700402
1RP700400
1RP700398
3RP700402
2RP700402
92SP11398993SP113989
2RP700404
1RP700405
3RP700399
277CP898468
71H25320
20RP838246
2RP845206
72H25320
21RP838246
2RP700410
1MPH31436
5RP7004021RP700404
2RP700399
2RP700406
1MPH2452
3RP845206
63USL39287
27H25326
22H25326
1MPH24714
1MPH2461
1RP7004032RP700403
3RP7004012RP700401
Wild River Dam Evacuation AdviceSunny Day Failure Flood Extent - Map 19
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 60
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
James Rd
Rolley Rd
Longlands Gap-Herberton Rd
104SP113990
1SP202300
1MPH24710
3224CWL839136
2RP700365
211RP860904
208H25327
1MPH2454
1MPH2486
2MPH24788
103SP113991
2MPH2643
210RP860904
2RP700369
2RP700370
1RP700370
275SP106052
102SP113991
207H25327
1RP700369
6H25328
1MPH2457
3RP7003651MPH2643
105SP113990
1MPH247181RP818026
1MPH24788
2RP818026
2RP700366
212H25327
7H25347206AP23116
1MPH30075
4179CP862888
1MPH24752
2RP700367
1RP700367
211H25327
1MPH2458
3MPH2486
2MPH33500
2SP202300
1MPH33500
3RP818026
206H25327
1RP700365
1RP700366
Wild River Dam Evacuation AdviceSunny Day Failure Flood Extent - Map 23
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 75
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.Evacuate along James Rd and Longlands Gap-Herberton Rd
to assemble at the end of No Name Rd.
MoominSiding Rd
Moomin Rd
Deba
ndga
ryRd
Athe
rton-H
erbert
on Rd
2SP265020
1SP265020
12SP181651
217CWL342
290CWL3517
63SP113985
197AP1009
160CWL366
1AP19246
1RP733446
211CWL358
179NPW922
2RP733446
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 5
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Atherton-Herberton Rd
23MPH32725
194FTY1870
238CWL2104
78CWL331572SP113986
CSP301528
251CWL3315
21MPH32725
3MPH32462
80CWL3317
77RP887716
1MPH32462
178CWL3315
4137CP862884
4235CP862883
22MPH32725
2MPH32462
197AP1009
81CWL3316
26MPH32725
24MPH32725
153CWL2611
25MPH32725
80USL39293
27MPH32725
20MPH32725
79CWL3317
43H25337
290CWL3517
65USL39293
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 8
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Grant St
Holdcro
ft Dr
Empress Av
Smith Av
Servi
ceRd
Adco
ckCl
Broa
dway
Atherto
n-Herb
erton Rd
167RP902755
13MPH40334
294CWL3523
36MPH33673
238CWL2104
CSP301528
BSP301528
2AP21279
41MPH40823262CWL3451
2MPH2313
3RP883886
44MPH40823
1MPH31633
6RP895432
166RP902755
197AP1009
42MPH40823
2MPH30644
52CWL835581
ARP851417
762SP252379
1CWL804081
5RP895432
8MPH40334
45MPH40823
153CWL2611
2MPH32304
97SP113987
39MPH40823
15RP851417
AMPH40843
77CWL3479
51MPH40843
4RP895432
50CWL835581
43MPH40823
14RP851417
1MPH24775
72SP113986
5CWL835413
302CWL3579
1MPH24773
37MPH40823
38MPH40823
40MPH40823
296CWL3582
1MPH2313
65USL39293
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 10
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 60
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Herbert St
Grant St
Newe
ll St
Serv
ice R
d
Athert
on-He
rberto
n Rd
Broa
dway
167RP902755
150USL39283
4RP884808
4SP217232
9SP237039
BSP301528
2AP4547
2MPH23136CWL3589
248CP895988
6RP912863
761SP252379
1MPH31633
7CWL3606
166RP902755
2MPH24775
1MPH2416 6CWL3539
1MPH2626
2RP880957
10SP174189
ARP851417
11SP174189
762SP252379
4CWL3662
2CWL3662
97SP113987
10SP237039
1CWL3662
15RP851417
4046CP862881
5RP884808
14RP851417
3CWL3662
7RP912863
1MPH24775
72SP113986
5CWL835413
8MPH35605
1MPH2313
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 12
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 50
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
ElwynPhillip
s Memorial Dr
Herbert St
Grant St
Newe
ll St
Forrester Rd
Empress Av
Servi
ceRd
Mary
St
Adco
ckCl
Athert
on-He
rberto
n Rd
Broa
dway
762SP252379
13CP860924
167RP902755
131H25324
21CWL808403
13MPH40334
294CWL3523
150USL39283
1CWL3663
2SP195716
183SP208318
36MPH33673
8RP836149
4RP884808
4048SP137929
4SP217232
9SP237039
2AP21279
7RP851424
2AP4547
51USL39301
2MPH23136CWL3589
BSP137285
9SP206969
8SP206969
248CP895988
71SP250045
4RP749612
14CP860924
47MPH40843
8RP851424
44MPH40823
20CP860925
2MPH2383103CWL3663
3RP880957
6RP912863
4047SP137929
ASP137285761SP252379
1MPH31633
11CP860924
7CWL3606
6CP860924
166RP902755
197AP1009
1CP860925
181SP208318
2MPH30644
21CP860925
2MPH24775
1RP867121
3MPH32702
5MPH32702
1MPH2416
52CWL835581
6CWL3539
1MPH2626
2RP880957
10SP174189
ARP851417
11SP174189
72SP250045
5CP860924
5RP8954329CP860924
8MPH40334
45MPH4082346MPH40843
17CP860925
15CP860924
4CWL3662
182SP208318
2CWL3662
5MPH40308
1MPH40308
2RP867121
2CP8354464MPH32702
10SP237039
1CWL3662
22CP860924
10CP860924
7CP860924
48MPH4084349MPH40843
39MPH40823
15RP851417
AMPH40843
1MPH2383
6MPH40308
94CP865093 4046CP862881
5RP884808
51MPH40843
BSP298402
12CP860924
4RP895432
50CWL835581
8CP860924
6RP851424
43MPH40823
16CP860924
14RP851417
3CWL3662
4CP860925
7RP9128631MPH24775
22CP881025
3RP867121
10CP835446
5CWL835413
8MPH35605
9RP851424
37MPH40823
38MPH40823
296CWL35823SP195716
1MPH2313
9RP836149
1MPH401852MPH33387
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 14
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 75
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Morris Rd
Todd
St
John St
Ellie St
Florence St
River Tce
Per kins St
6H25332
11SP273698
3RP700401
12H2536
2RP700386
1RP7004001RP700399
1RP700385
1RP700384
3RP749311
27H25326
93SP113989
11SP2207523RP700377
1RP700401
3RP7003992RP700399
11H2536
3RP700382
21H25325
14MPH32732
CSP120065
2RP700381
2RP700395
5RP700402
14H2536
23H2536
2RP845206
89SP113988
1MPH2461
2MPH2461
1SP200263
2RP700384
8H2533224H25325
71H2532073H25320
7H25332
63USL39287
17H2536
3RP7004002RP700400
7RP745690
24H2536
61H25320
1MPH2485
DSP179216
412H2531411H2531
ASP179216
409H2531
2RP700402
1RP702088
1RP700380
1RP700409
408H2531
277CP898468
410H2531
1MPH24690
ASP227808
12SP2207522RP700378
1RP700403
15H25362RP700385
1RP700386
1RP700398
21H2536
3RP700381
33SP190315
23H25325
72H25320
1MPH34194
3RP700402
3RP700378
1RP700402
16H25362RP700391
2RP7004042RP700403
2RP700401
88SP113988
1RP700405
5CWL3313
4RP749311
4RP700383
22H25325
304CWL3609
2MPH34194
ARP736790
2RP700380
2RP700398
3RP845206
92SP113989
13H2536
1RP700404
1RP735215
3RP700383 2RP700382
32H25325
413H2531
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 18
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 50
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Morris Rd
Todd
St
Florence St
Rose St
Emma
St
91SP113989
3RP700399
255CWL3295
14MPH32732
CSP120065 2RP845206
89SP113988
1MPH31436
71H2532073H25320
63USL39287
3RP700400
254CWL3271
1MPH2452
10SP292867
1MPH2485
DSP179216
ASP179216
1RP700409
2RP700410
277CP898468
1MPH24690
72H25320
304CWL3609
1MPH34194
1RP700405
1SP292867
2MPH34194
ARP736790
92SP113989
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 19
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 50
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
James Rd
Broadley Rd
Dei Rossi Rd
Rolley Rd
Long
lands
Gap-H
erbe
rton R
d
2SP202300
206H25327
1RP700367
102SP113991206AP23116
1SP202300
503H25327
207H25327
1MPH2454
210RP860904
1RP700366
104SP113990
1MPH2643
1MPH24718
1MPH30075
351SP177994
2RP700369
1MPH2458
6H25328
2RP700365
3RP700365
1RP700369
1MPH33500
303H25327
7H25347
1MPH24788
208H25327
2RP700370
2RP818026
3MPH24788
211RP860904
3224CWL8391361MPH24572MPH24788
2RP700366
275SP106052
3RP818026
103SP113991
1MPH24752
1H25328
2MPH2643
212H25327
1RP818026
215SP179203
2MPH33500
1RP700370
2RP700367
211H25327
1RP700365
105SP113990
1MPH247104179CP862888
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 23
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
!
Harding Rd
James Rd
Rolley Rd
J.A.
Daws
onRd
Gollogly Rd
Bajem
a Rd
Tepo
n Rd
Reynolds Rd
Tepon Road Ac cessRd
Long
la nd s
Gap-H
erbe
r ton R
d
2SP202300
2MPH2486
601H25327206H25327
3MPH2542
1MPH24800
214H25327
4MPH14281
2AP3435
102SP113991
206AP23116 305H25327
1SP202300
225N25373
503H25327
207H25327
1MPH30876
210RP860904
1MPH14281
67USL39300
402H25327
2MPH24563MPH2456
2RP700369
1MPH24691
3MPH24800
2MPH24753
215H25327
5MPH14281
2MPH2331
1RP700369
3MPH2486
1RP706565
303H25327
7H25347
208H25327
2RP700370
504H25327
1MPH2571
2MPH247521MPH2456
4SP111956
1MPH24795
211RP860904
2MPH14281
110SP113992
1RL6410
ASP250037
4CP866935
1MPH2642
275SP106052
3RP818026
1MPH2486
213H25327
13MPH14281
103SP113991
1MPH24752
2RP706565
306H25327
2SP1119562MPH24691
212H25327
1AP3435
111SP113992
1MPH2542
304H25327
1RP700370
2MPH2542
211H25327
1MPH2303
1MPH2331
1MPH24710
4179CP862888
2MPH24795
Wondecla
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 24
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Gollogly Rd
Cleg
horn
Rd
Rolley Rd
Reynolds Rd
7CAR12432
601H25327
2MPH24878
214H25327
2AP3435
305H25327
1RP723404
12CAR1243213CAR12432
402H25327
AAP17361
AAP2143
1MPH24691
1MPH24878
215H25327
403H253271RP706565
144USL39299303H25327
7H25347
608H25327
701H25327504H25327
1MPH2629
1MPH24613
1MPH2304
276H25327
4SP111956
702H25327
505H25327
404H25327
ASP250037
605H25327
213H25327
2RP706565
306H25327
2SP111956
AAP12201
603H25327602H25327
8CAR12432
1AP3435
406H25327
405H25327
304H25327
ASP107799
704H25327
6CAR12432
604H25327
1MPH2303
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 25
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
Harding Rd
Adams Rd
Cassell Rd
Bajema
Rd
5SP219782
9MPH14281
3MPH2542
4MPH14281
AMPH34484
2MPH250241MPH9375
3MPH14281
1MPH14281
67USL39300
1MPH25024
5MPH14281
2MPH2331
1MPH2603
2SP257022
2MPH40072
14CWL836167
41SP265018
1MPH2593
183OL443
1MPH2641
121SP113993
2MPH14281
1MPH34890
1MPH24803
13MPH14281
1SP257022
1MPH40072
111SP113992
1AP12209
7MPH14281
30AP20151
Wild River Dam Evacuation AdviceProbable Maximum Cascade Failure Flood Extent - Map 29
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 2/08/2019
:
Evacuate away from flood extent upon notification.
MoominSiding Rd
Moomin Rd
Deba
ndga
ryRd
Athe
rton-H
erbert
on Rd
1AP19246
217CWL342
179NPW922
12SP181651
63SP113985
197AP1009
290CWL3517
1SP265020
2SP265020
160CWL366
211CWL358
1RP733446
2RP733446
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 5
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Atherton-Herberton Rd
25MPH32725
77RP887716
3MPH32462
194FTY1870
238CWL2104
20MPH32725
1MPH32462
81CWL3316
290CWL3517
26MPH32725
4137CP862884
251CWL3315
27MPH32725
197AP1009
22MPH32725
65USL39293
4235CP862883
CSP301528
23MPH32725
80CWL3317
43H25337
80USL39293
153CWL261121MPH32725
2MPH32462 24MPH32725
72SP113986
178CWL3315
78CWL3315
79CWL3317
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 8
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Grant St
Holdcro
ft Dr
Empress Av
Smith Av
Servi
ceRd
Adco
ckCl
Broa
dway
Atherto
n-Herb
erton Rd
6RP895432
166RP902755
167RP902755
238CWL2104
15RP851417
1MPH24775
3RP883886
4RP89543238MPH40823
42MPH40823
50CWL835581
2AP21279
36MPH33673
1MPH31633
2MPH2313
302CWL3579
51MPH40843
1CWL804081
294CWL3523
41MPH40823
762SP252379
97SP113987
8MPH40334
197AP1009
AMPH40843
77CWL3479
65USL39293
CSP301528
BSP301528
44MPH40823 5RP895432 1MPH24773
72SP113986
14RP851417ARP851417
1MPH2313
5CWL835413
13MPH40334
37MPH40823
40MPH40823
52CWL835581
43MPH40823
296CWL3582
153CWL2611
45MPH4082339MPH40823
2MPH32304
262CWL3451
2MPH30644
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 10
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 60
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Herbert St
Grant St
Newe
ll St
Serv
ice R
d
Athert
on-He
rberto
n Rd
Broa
dway
2MPH24775
4SP217232
6CWL3589
166RP902755167RP902755
15RP851417
1MPH24775
10SP237039
1MPH31633
761SP252379
11SP174189
9SP237039
1CWL3662
2MPH2313
4046CP862881
2RP880957
762SP252379
97SP113987
3CWL3662
1MPH2626
248CP895988
4RP884808
5RP884808
BSP301528
150USL39283
6RP912863
6CWL3539
10SP174189
72SP113986
14RP851417ARP851417
4CWL3662
8MPH35605
7CWL3606
1MPH2313
1MPH2416
5CWL8354132AP4547
7RP912863
2CWL3662
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 12
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 50
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
ElwynPhillip
s Memorial Dr
Herbert St
Grant St
Newe
ll St
Forrester Rd
Empress Av
Servi
ceRd
Mary
St
Adco
ckCl
Athert
on-He
rberto
n Rd
Broa
dway
72SP250045
762SP252379
2MPH24775
4047SP137929
4SP217232
6CWL3589
5MPH40308
14CP860924
9CP860924
166RP902755
167RP902755
7CP860924
21CP860925
3RP880957
15RP851417
1MPH24775
4048SP137929
4RP749612
10SP237039
4RP89543238MPH40823
50CWL835581
2AP21279
36MPH33673
183SP208318
6CP860924
4CP860925
1MPH31633
761SP252379
2RP8671213RP867121
11SP174189
9SP237039
1CWL3662
2MPH2313
4046CP862881
21CWL808403
103CWL3663 2MPH2383
2RP880957
11CP860924
51MPH40843
294CWL3523
10CP860924
2CP835446
1RP867121ASP137285BSP137285
3CWL3662
6RP851424
1MPH2626
4MPH32702
8MPH40334
197AP1009
AMPH40843
20CP860925 17CP860925
94CP865093
248CP895988
BSP298402
8RP836149
4RP884808
5RP884808
9SP206969
7RP851424
9RP851424
12CP860924
16CP860924
10CP835446
150USL39283
9RP8361496RP912863
131H25324
6MPH40308
6CWL3539
10SP174189
44MPH40823
13CP860924
5RP895432
15CP860924
3SP195716
1CP860925
51USL39301
22CP881025
14RP851417
ARP851417
4CWL3662
1CWL3663
8SP206969
8MPH35605
7CWL3606
1MPH2313
8RP851424
1MPH2383
1MPH2416
3MPH32702
47MPH4084348MPH40843
5CWL835413
13MPH40334
37MPH40823
52CWL835581
43MPH40823
296CWL3582
182SP208318
181SP208318 2AP4547
8CP86092422CP860924
71SP250045
7RP912863
2CWL3662
1MPH40308
1MPH401852MPH33387
5MPH32702
45MPH4082346MPH40843
49MPH40843
39MPH40823
2MPH30644
5CP860924
2SP195716
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 14
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 75
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Morris Rd
Todd
St
John St
Ellie St
Florence St
River Tce
Per kins St
2MPH34194
1MPH24690
21H25325
4RP700383
ASP227808
61H25320
21H2536
3RP700377
14H2536
3RP7004002RP700400
1SP200263
12H2536
408H2531
CSP120065
ARP736790
14MPH32732
8H25332
73H25320
2RP700382
1RP700399
2MPH2461
5CWL3313
409H2531
15H2536
89SP113988
DSP179216
17H2536
13H2536
1RP735215
ASP179216
1MPH34194
411H2531
23H25325
32H25325
1MPH2485
2RP7003951RP702088
6H25332
7H25332
1RP700409
11SP273698
1RP700401
2RP700381
2RP700378
1RP700386
2RP700398
11H2536
24H25325
304CWL3609
11SP220752
3RP700382
2RP700384
1RP700402
1RP700400
1RP700398
3RP700402
2RP700402
16H2536
92SP113989
93SP113989
24H2536
2RP700404
1RP700380
1RP700405
3RP700399
277CP898468
71H25320
412H2531
410H2531
22H25325
2RP845206
2RP700380413H2531
2RP700391
72H25320
7RP745690
5RP700402
3RP700378 4RP749311
1RP700404
2RP700399
33SP190315
3RP845206
63USL39287
3RP7003811RP700385
1RP700384
23H2536
3RP749311
27H25326
12SP220752
3RP7003832RP700385
2RP700386
1MPH2461
1RP7004032RP700403
3RP7004012RP700401
88SP113988
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 18
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 50
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Morris Rd
Todd
St
Florence St
Rose St
Emma
St
2MPH34194
1MPH24690
3RP700400
CSP120065
ARP736790
14MPH32732
73H25320
255CWL3295
10SP292867
304CWL3609
89SP113988
DSP179216
91SP113989
ASP179216
1MPH34194
254CWL3271
1MPH2485
1RP700409
1SP292867
92SP113989
1RP700405
3RP700399
277CP898468
71H25320
2RP845206
72H25320
2RP700410
1MPH31436
1MPH2452
63USL39287
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 19
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 50
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
James Rd
Broadley Rd
Dei Rossi Rd
Rolley Rd
Long
lands
Gap-H
erbe
rton R
d
104SP113990
1SP202300
1MPH24710
3224CWL839136
2RP700365
211RP860904
208H25327
351SP177994
1MPH24542MPH24788
103SP113991
2MPH2643
210RP860904
2RP700369
2RP700370
215SP179203
1RP700370
275SP106052
102SP113991
207H25327
1RP700369
503H25327
6H25328
1MPH2457
3MPH24788
3RP7003651MPH2643
105SP113990
1MPH247181RP818026
1MPH24788
2RP818026
2RP700366
212H25327
303H25327
7H25347
206AP23116
1MPH30075
4179CP862888
1MPH24752
2RP700367
1RP700367211H25327
1MPH24581H25328
2MPH33500
2SP202300
1MPH33500
3RP818026
206H25327
1RP700365
1RP700366
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 23
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
!
Harding Rd
James Rd
Rolley Rd
J.A.
Daws
onRd
Gollogly Rd
Bajem
a Rd
Tepo
n Rd
Reynolds Rd
Tepon Road Ac cessRd
Long
la nd s
Gap-H
erbe
r ton R
d
3MPH2542
2MPH2486
1SP2023002RP706565
1MPH24710
1MPH308761MPH2571
211RP860904
1RL6410
2SP111956
1AP3435
306H25327
208H25327 215H25327
3MPH2456
2MPH2542
1MPH2486
1MPH2456
4SP111956
1RP706565
103SP113991
1MPH24691
2MPH24691
3MPH24800
2MPH24753
1MPH14281
504H25327
210RP860904
2RP700369
2RP700370214H253271RP700370
275SP106052
2AP3435
601H25327
102SP113991
4MPH14281
1MPH24800
2MPH2331
13MPH14281
5MPH14281
207H25327
1RP700369
213H25327
503H25327
305H25327
2MPH24752
110SP113992
111SP113992
1MPH2642
4CP866935
1MPH2303
2MPH14281
67USL39300
1MPH24795
1MPH2331
212H25327
2MPH2456
303H25327
7H25347206AP23116
4179CP862888
2MPH24795
402H25327
1MPH24752
211H25327
3MPH2486
225N25373
304H253272SP202300
3RP818026
206H25327
1MPH2542
ASP250037
Wondecla
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 24
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Gollogly Rd
Cleg
horn
Rd
Rolley Rd
Reynolds Rd
1RP723404
2RP706565
704H25327
1MPH24613
2MPH24878
2SP111956
1AP3435
604H25327
306H25327
1MPH2304
215H25327
505H25327
13CAR12432
ASP107799
144USL39299
4SP111956
403H253271RP706565
702H25327
1MPH24878
1MPH24691
504H25327
214H25327
AAP17361
AAP12201
2AP3435
601H25327
213H25327
6CAR12432
305H25327
276H25327
405H25327
1MPH2303
7CAR12432
404H25327
701H25327
1MPH2629
303H25327
7H25347
605H25327
603H25327602H25327
406H25327
402H25327
AAP2143
304H25327
608H25327
8CAR12432
12CAR12432
ASP250037
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 25
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Harding Rd
Adams Rd
Cassell Rd
Bajema
Rd
121SP113993
3MPH2542
30AP20151
1MPH34890
1MPH14281
7MPH14281
9MPH14281
1SP2570224MPH14281
2MPH233113MPH14281
5MPH14281
1MPH25024
1MPH2593
14CWL836167
1AP12209
111SP113992
5SP219782
2MPH14281
3MPH14281
2MPH40072
1MPH2641
2MPH25024
67USL39300
AMPH34484
1MPH24803
1MPH9375
1MPH2603
2SP257022
41SP265018
183OL443
1MPH40072
Wild River Dam Evacuation AdviceProbable Maximum Flood Extent - Map 29
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Moomin SidingRd
Moomin Rd Deba
ndga
ryRd
1AP19246
217CWL342
179NPW922
63SP113985
290CWL35171SP265020
2SP265020
160CWL366
211CWL358
1RP733446
2RP733446
Wild River Dam Evacuation AdviceSunny Day Cascade Failure Flood Extent - Map 5
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Moomin Rd
Atherton-Herberton Rd
217CWL342
10M2973
202M2971
63SP113985
9M2973
197AP1009
72SP113986
290CWL3517
201M2971
12M2973
102M2971101M2971
103M2971
1AP19246
203M2971
11M2973
211CWL358
Wild River Dam Evacuation AdviceSunny Day Cascade Failure Flood Extent - Map 6
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 60
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.Evacuate to clearing at intersection of Moomin Rd and
Atherton-Herberton Rd.
Atherton-Herberton Rd
194FTY1870
252CWL3185
290CWL3517
197AP1009
201M2971
43H25337
1AP19246
174CWL3185
72SP113986
211CWL358
1MPH24923
Wild River Dam Evacuation AdviceSunny Day Cascade Failure Flood Extent - Map 7
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 100
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
Rose
L
Morris Rd
Todd
St
Rose
St
Emma
St
Florence St
2MPH34194
1MPH24690
2RP738091
28H25326
ASP227808
61H25320
3RP7004002RP700400
CSP120065
ARP736790
14MPH3273273H25320
255CWL3295
10SP292867
1MPH2653
304CWL3609
1RP700399
89SP113988
DSP179216
91SP113989
ASP179216
1MPH34194
254CWL3271
1MPH2485
1RP700409
BSP227808
2RP700398
1RP738091
1SP292867
1RP700402
1RP700400
1RP700398
3RP700402
2RP700402
92SP11398993SP113989
2RP700404
1RP700405
3RP700399
277CP898468
71H25320
20RP838246
2RP845206
72H25320
21RP838246
2RP700410
1MPH31436
5RP7004021RP700404
2RP700399
2RP700406
1MPH2452
3RP845206
63USL39287
27H25326
22H25326
1MPH24714
1MPH2461
1RP7004032RP700403
3RP7004012RP700401
Wild River Dam Evacuation AdviceSunny Day Cascade Failure Flood Extent - Map 19
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 60
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.
James Rd
Rolley Rd
Longlands Gap-Herberton Rd
104SP113990
1SP202300
1MPH24710
3224CWL839136
2RP700365
211RP860904
208H25327
1MPH2454
1MPH2486
2MPH24788
103SP113991
2MPH2643
210RP860904
2RP700369
2RP700370
1RP700370
275SP106052
102SP113991
207H25327
1RP700369
6H25328
1MPH2457
3RP7003651MPH2643
105SP113990
1MPH247181RP818026
1MPH24788
2RP818026
2RP700366
212H25327
7H25347206AP23116
1MPH30075
4179CP862888
1MPH24752
2RP700367
1RP700367
211H25327
1MPH2458
3MPH2486
2MPH33500
2SP202300
1MPH33500
3RP818026
206H25327
1RP700365
1RP700366
Wild River Dam Evacuation AdviceSunny Day Cascade Failure Flood Extent - Map 23
©2019 Tablelands Regional Council (TRC). Based on or contains data provided by TRC;the State of Queensland (Department of Natural Resources and Mines) [2019]; and the Commonwealth of Australia (CSIRO; and Department of Sustainability, Environment, Water, Population & Communities). In consideration of these agencies permitting use of this data you acknowledge and agree that these agencies give no warranty in relation to the data (including accuracy, reliability, completeness, currency or suitability) and accept no liability including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the data. Data must not be used for direct marketing or be used in breach of the privacy laws.
0 75
MetresCoordinate System: GDA 1994 MGA Zone 55
Projection: Transverse MercatorDatum: GDA 1994
Project: 2019-057Page Size: A4Date: 4/07/2019
:
Evacuate away from flood extent upon notification.Evacuate along James Rd and Longlands Gap-Herberton Rd
to assemble at the end of No Name Rd.
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019
APPENDIX E
WILD RIVER DAM STORAGE CURVE & STORAGE SPILLWAY DISCHARGE CURVE
EMERGENCY ACTION PLAN
Wild River Dam
Version 7: 31/07/2019