why not jessup? - site selection – new hs #13jessuphs.tacobird.com/03 08 2018 hs13 site...
TRANSCRIPT
1
Site Selection – New HS #13
Anissa Brown Dennis, Chief Operating OfficerBruce Gist, Executive Director, Capital Planning and OperationsScott Washington, Director, School ConstructionRenee M. Kamen, Manager, School PlanningDan Lubeley, Manager, Design and Preconstruction ServicesMarch 8, 2018
New HS #13 Site Selection– Sites Under Consideration
2
Mission Road Troy Park• Approximately 77 acres• Existing use: Vacant• Owner: Chase Land LLC• Proposed Use: Recreation & Park, Water Tower &
Future Site of ES and HS
• Approximately 100 acres (existing park)• Existing use: Active Park & Open Space• Owner: Howard County Government• Proposed Use: Active Park & Open Space, Future site of
HS
33
Proposed School
Proposed Fields
Proposed Parking
Mission Ro
ad Proposed Access
New HS #13 Site Selection– Sites Under Consideration
Proposed Fence
Mission Road Base Grading PlanNote‐ drawing was prepared for rough grading . A continuous barrier fence to run the entire boundary between the potential school site and Savage Quarry properties.Final design, including building layout and access to be determined.
44
Proposed School
Proposed Fields
Proposed Parking
Troy Park Illustrative Plan(Illustrative only. No engineering has been completed, and likely this diagram will change as more information becomes available.)
US 1/Washington Blvd
MD 100
I‐95
New HS #13 Site Selection– Sites Under Consideration
5
New HS #13 Site Selection– Troy Park Considerations
52.33 ac16 ac1.33 ac
10 ac+1.3 ac80.96 ac
G. LAND USE CONVERSIONS Land acquired or developed with POS grant assistance may not be used for any purpose other than public recreation or public open space and will be restricted to such uses by covenants in the deed to the property. Prior approval from the Secretaries of the Departments of Natural Resources, Budget and Management, and State Planning is required before any acquisition or development sites may be converted to any other use. The local governing body of a county or municipal corporation responsible for a proposed conversion of use must immediately contact POS when a conversion is proposed [POS Law, Section 5-906 (e) 7]. DNR shall coordinate the review of all conversion requests following guidelines and procedures found in the chapter on Conversions.
Source: Maryland Department of Natural Resources, http://dnr.maryland.gov/land/Documents/POS/localposmanual_2006.pdf
Source: Howard County Recreation and Parks
6
New HS #13 Site Selection– Site Considerations – Distance and Time Traveled
2017-2018 Route Time*
*Actual average bus route time.All HS trips are for all 12 attendance areas.
Either Troy Park or Mission Road is a shorter distance from the furthest point that currently attend Howard HS (Furnace Ave & Race Rd)
• Troy Park approx. 3.6 mi (apprx. 12 min by car)
• Mission Rd approx. 7.6 mi (apprx. 26 min by car)
• Howard approx. 8.3 mi (apprx.20 min by car)
AVG TimeHoward HS 27Hammond HS 27Long Reach HS 24Oakland Mills HS 18All HS Trip 30
7
New HS #13 Site Selection– Site Considerations – Hypothetical Redistricting
Mission Road Site• All TVMS boundary• Portion of ELMS
Troy Park Site• All ELMS• Portion of TVMS
The following criteria to develop the potential redistricting scenarios:• Target Utilization (90% - 110%), per Policy 6010;• HS #13 with 1,615 seats; and• Proposed HaHS addition (+200 seats).
DOES NOT INCLUDE CAPACITIES FURTHER WEST!Should not be considered a redistricting “plan.” Answers only the question raised “can either site be filled.”
New HS #13 Site Selection– Sequence of Construction
8
Timeline of Project/Site (begin 3/9/18) w/o White Property w/White Property** w/Eminent Domain***
SRC/Policy 6000 Complete Complete Complete Complete
Complete Phase I: Env Assessment CompleteBoard Action Required3/2018 ‐ 5/2018
Board Action Requiredand Condition of Sale
Board Action Required9/2020 ‐ 11/2020
Submit A/E ‐ CM Fee to Board for Approval 3/22/2018Proposals Needed followed by Board Action
Approval of Propsoals Prior to Design
Approval of Propsoals Prior to Design
State Review Process 1. MDP Site Visit ‐ Simultaneous w/Clearinghouse 2. Clearinghouse Review ‐ 60 Days 3. IAC Approval ‐ 60 Days
1. Complete2. Complete3. Action Required
5/2018 ‐ 11/2018 12/2018 ‐ 6/2019 11/2020 ‐ 5/2021
Complete Schematic Desgin (SD) Planning Phase 3/2018 ‐ 7/2018 11/2018 ‐ 3/2019 3/2019 ‐ 7/2019 5/2021 ‐ 9/2021
Public Hearing/Work Session on Site Acquisition Action Required Acquired Required Action Required Action Required
Complete Design Development (DD) phase 7/2018 ‐ 12/2018 3/2019 ‐ 8/2019 7/2019 ‐ 12/2019 9/2021 ‐ 2/2022
Complete Construction Design (CD) phase 12/2018 ‐ 6/2019 8/2019 ‐ 2/2020 12/2019 ‐ 6/2020 2/2022 ‐ 8/2022
Contract Bidding & Award 6/2019 ‐ 12/2019 2/2020 ‐ 8/2020 6/2020 ‐ 12/2020 8/2022 ‐ 2/2023
Construction Period 12/2019 ‐ 3/2023 8/2020 ‐ 8/2023 12/2020 ‐ 3/2024 2/2023 ‐ 2/2026
Complete Project Closeout & Commissioning 3/2023 ‐ 8/2023 8/2023 ‐ 1/2024 3/2024 ‐ 8/2024 2/2026 ‐ 8/2026
Open HS #13 9/2023 1/2024* 9/2024 9/2026
*Mid‐year resdricting and assumes that building fits on non‐POS property
**Pending purchase and placement of school on White property (preferred).
***Pending six‐month negotion period to purchase and two‐year litigation process.
Troy ParkMission Road
Estimated Timeline HS #13
New HS #13 Site Selection– Timeline
• Board Report: February 8, 2018
• Public Hearing: February 22, 2018
• Board Site Selection (action): March 8, 2018
9
New HS #13 Site Selection– Staff Recommendation/Board Action Request
• Direct staff to complete the acquisition of Mission Road for the purposes of constructing New HS #13.
• Direct staff to continue the steps to land bank portions of Troy Park for use of a future school.
10