Page 1: White Paper Operational Acceptance Testing En

White Paper

Operational Acceptance TestingBusiness continuity assurance

December 2012

Dirk Dach, Dr. Kai-Uwe Gawlik, Marc Mevert

SQS Software Quality Systems

Page 2: White Paper Operational Acceptance Testing En

Page 2SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Contents

1. Management Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

2. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

3. Market – Current Status and Outlook . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

4. Scope of Operational Acceptance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6

5. Types of Operational Acceptance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

5.1. Operational Documentation Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8

5.2. Code Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

5.3. Dress Rehearsal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

5.4. Installation Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

5.5. Central Component Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

5.6. End-to-End (E2E) Test Environment Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

5.7. SLA / OLA Monitoring Test. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

5.8. Load and Performance (L&P) Test Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

5.9. OAT Security Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

5.10. Backup and Restore Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

5.11. Failover Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

5.12. Recovery Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

6. Acceptance Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

7. Conclusion and Outlook . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

8. Bibliographical References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

Page 3: White Paper Operational Acceptance Testing En

Page 3SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

1. Management Summary

Operational Acceptance is the last line of defence between a software development project and the productive use of the

software. If anything goes wrong after the handover of the finished project to the application owner and the IT operation

team, the customer’s business will immediately be affected by any negative consequences. In order to minimise the risk of

going live, operational acceptance testing is the instrument of choice. The ISTQB defines Operational Acceptance Testing (OAT)

as follows:

Operational testing in the acceptance test phase, typically performed in a (simulated) operational environment by

operations and / or systems administration staff focusing on operational aspects, e.g. recoverability, resource-behaviour,

installability and technical compliance.

Definition 1: Operational acceptance testing (International Software Testing Qualifications Board, 2010)

This definition points out the growing importance of activities connected with OAT in times of increasing cloud computing

which poses additional risks for business continuity. The present whitepaper will give a complete overview of OAT with respect

to all relevant quality aspects. It will show that OAT is not only restricted to a final acceptance phase but can be implemented

systematically following best practices so as to minimise the risks for day one and beyond.

2. Introduction

When the project teams have completed the development of the software, it is released and handed over to the operation

team and the application owner. It immediately becomes part of the business processes as it is launched into the production

environments. Consequently, known and unknown defects of the software will directly impact business continuity

and potentially cause damage to a greater or lesser extent. In addition, responsibility typically is transferred from the

development units to two stakeholders:

— Application Owner: The single point of contact for business units concerning the operation of dedicated applications.

These units are the internal part of the line organisation managing the maintenance, and constitute the interface to the

operation team.

— Operation Team: An internal or external team deploying and operating software following well-defined processes, e.g.

tailored by ITIL (APM Group Limited, 2012). These units are equipped with system and application utilities for managing

the operation, and they will contact the application owners if bigger changes should be necessary to guarantee business

continuity.

Page 4: White Paper Operational Acceptance Testing En

Page 4SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

OAT subsumes all test activities performed by application owners and operation teams to arrive at the acceptance decision

with respect to their capability to operate the software under agreed Service Level Agreements and Operation Level

Agreements (SLAs / OLAs). These agreements provide measurable criteria which – if they are fulfilled – implicitly ensure

business continuity. Operation capability covers three groups of tasks:

— Transition: This designates the successful deployment of software into the production environment using existing system

management functionality. The production environment could be a single server or thousands of workstations in agencies.

Software deployment includes software, database updates, and reorganisation but also fallback mechanisms in case of

failures. The operation team has to be trained and equipped with the respective tools.

— Standard Operation: This designates successful business execution and monitoring on both the system and the

application level. It includes user support (helpdesk for user authorisation and incident management) and operation in case

of non-critical faults, e.g. switching to a mirror system in case of failure analysis on the main system.

— Crisis Operation: System instability causes failures and downtimes. Operation teams must be able to reset the system and

its components into defined states and continue stable standard operation. Downtimes have to be as short as possible, and

reset must be achievable without data or transaction loss and / or damage.

Operational activities are divided between the application owner and the operation team, depending on the individual

organisation, and due to compliance requirements they must be traceable. Division of work has to be taken into account for

OAT.

For many years now, functional testing has been performed systematically, and its methods can directly be applied to OAT:

— Risk-based approach: Test effort is spent on components involving the most probable and greatest possible damage. This

is done in order to achieve the highest quality on a given budget.

— Early error detection: Test activities are executed as soon as possible in the software development life cycle because

the earlier any defects are found the less will be the cost of correction. OAT activities are allocated to all phases of the

software development and coupled with quality gates to follow the cost-saving principle (see Figure 1).

The present paper gives an overview of how to use ISO 25000 (ISO/IEC JTC 1/SC 7 Software and Systems Engineering, 2010)

to scope out OAT systematically, how to adjust activities along the software life cycle, and how to apply test methods

successfully by having application owners and operation teams involve other stakeholders like architects, developers, or

infrastructure.

Page 5: White Paper Operational Acceptance Testing En

Page 5SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Business

Figure 1: Main activities and stakeholders of OAT

3. Market – Current Status and Outlook

Apart from the general requirements outlined above, companies will also be influenced by the implementation models used by

cloud service providers. Gartner recommends that enterprises should apply the concepts of cloud computing to future data

centre and infrastructure investments in order to increase agility and efficiency. This, of course, affects operational models,

and OAT will have to support business continuity in this growing market. Forrester estimates that cloud revenue will grow from

$ 41 billion in 2011 to $ 241 billion in 2020 (Valentino-DeVries, 2011).

Today, OAT is already being executed by a variety of stakeholders. Target groups are specialists like application owners or

operation units in large organisations, as well as individuals in the private sector. Internal departments and / or vendors

need to be addressed to establish sustainable processes. SQS currently has many interfaces with the above-mentioned

stakeholders through projects regarding test environment and test data management. As the leader in this field, SQS notices

a strong demand on the clients’ side to move OAT from an unsystematic to a systematic approach by applying methods

adapted from functional testing. Said demand arises independently in different business sectors as customers increasingly

feel the need to use outsourcing, offshoring, and cloud processing but do not yet fully understand what these require from

the point of view of capability and methodology.

Analysis Design Functional TestingImplementation

Quality Gates

Operation

Operational Acceptance Testing

Operation Teams

Transition Standard Operation

CrisisOperation

Application Owners

Page 6: White Paper Operational Acceptance Testing En

Page 6SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

From a tester’s perspective, many companies neglect the definition of requirements for operating software systems. Quite

often, not just defects but also gaps in mandatory functionality are only identified shortly before release. These features

will not only be missing in production, they already cause delays when executing E2E tests. For this reason, the functional

and non-functional requirements of operation teams have to be systematically managed, implemented, and tested, just like

business functions.

In times of cloud computing and operation outsourcing, it is of great importance to support business continuity and ensure

trust by verifying operation under agreed SLAs / OLAs. Especially monitoring is crucial to achieve transparency and obtain

early indicators in order to avoid incidents. OAT should follow a systematic approach so as to mitigate the risks of cloud

providers and outsourcing partners, because companies which offer services using these types of sourcing will not notice any

incidents but their impact will be felt directly by the clients.

4. Scope of Operational Acceptance Testing

ISO 25010 addresses the quality attributes of software products. One of these attributes – operability – is directly aimed

at stakeholders of operation. But considering operability as a mere subattribute of usability is not enough. Software

development does not produce functionality for business purposes only – dedicated functionality or process definition for

operating purposes also forms part of the final software products. These artefacts are evaluated in terms of the quality

attributes of ISO 25010, and the respective OAT activities are performed close to the artefacts’ creation time along the

software life cycle.

The various stakeholders can shape an OAT environment according to their own focus and determine questions that take their

specific requirements into account, e.g.:

— Application Owner: Is it possible to perform changes to the system with a low risk of side effects (maintainability), thus

ensuring time to market and a minimum of test effort?

— Operation Team (general): Is it possible to operate the system using given manuals (operability)? Is the operation team

equipped with adequate logging functions (functional completeness) and trained in terms of how to obtain and interpret

information from different application trace levels (analysability)?

— Third Party Vendor (external operation): Is it possible to operate my cloud service / software as agreed in the contracts

in view of the needs of customers in my cloud environment?

The relevance of the different types of OAT is derived from the individual artefacts and their quality attributes. The major test

types are allocated, and decisions about test execution follow from the risk evaluation – the scope of OAT is ultimately defined

by selecting columns from the table shown in Figure 2.

Page 7: White Paper Operational Acceptance Testing En

Page 7SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Figure 2: Example of the evaluation

of quality attributes

Oper

atio

nal D

ocum

enta

tion

Revi

ew

Code

Ana

lysi

s

Dres

s Re

hear

sal T

rans

ition

Mod

e

Inst

alla

tion

Test

ing

Dres

s Re

hear

sal S

tand

ard

Mod

e

Cent

ral C

ompo

nent

Tes

ting

E2E

Test

Env

ironm

ent O

pera

tion

SLA/

OLA

Mon

itorin

g Te

st

L&P

Test

Ope

ratio

n

Secu

rity

Tes

ting

Dres

s Re

hear

sal C

risis

Mod

e

Back

up a

nd R

esto

re T

estin

g

Failo

ver T

estin

g

Reco

very

Tes

ting

Transition x x x x x x

Standard x x x x x x

Crisis x x x x x x x x x

Functional suitability

Functional completeness x x x x x x x x x x x x x

Functional correctness x x x x x x x x x x x x x

Functional appropriateness x x x x x x x x x x x x

Performance efficiency

Time behaviour x x x x x x

Resource utilisation x x x x x

Capacity x x x x

Compatibility

Coexistence x x x

Interoperability x x

Usability

Appropriateness recognisability

Learnability x

Operability x x x x x x x

User error protection x x x x

User interface aesthetics

Accessibility x x x x x

Reliability

Maturity x x x x x x

Availability x x x x x x

Fault tolerance x x x x x

Recoverability x x x x x

Security

Confidentiality x x

Integrity x

Non-reputation x x x

Accountability x x x

Authenticity x

Maintainability

Modularity

Reusability

Analysability x x x x x x x x x

Modifiability x

Testability x x

Portability

Adaptability x x x x

Installability x x x x

Replaceability x x x x

Page 8: White Paper Operational Acceptance Testing En

Page 8SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Test activities can be allocated according to their main focus on the transition, standard or crisis mode, respectively. However,

L&P testing for instance addresses standard operation as well as the crisis mode, the latter including the case of system load

entering the stress region with the objective of crashing the system. Consequently, there is a certain overlap as to which

mode is addressed. Test preparation and execution is performed all along the software life cycle so that defects are detected

as early as possible. At the end of the design phase, architecture analysis applying ATAM (Software Engineering Institute, 2012)

or FMEA (Wikipedia contributors, 2012) based on use cases will guarantee fulfilment of all recovery requirements. But not only

that: these use cases can be re-employed as test cases for execution during the test phase.

5. Types of Operational Acceptance Testing

As outlined in Section 3, in the following we shall present the various test types in detail with a short profile in terms

of definition, objective, parties involved, point in time (of the SDLC), its inputs and outputs, the test approach, the test

environment, and the risk incurred if the respective test type is not executed.

5.1. Operational Documentation Review

Definition: All the documents that are necessary to operate the system (e.g. architecture overviews, operational

documentation) are identified, and it is checked that they are available in the final version and accessible to the relevant

people. In the documents, transition, standard, and crisis mode are addressed.

Objective: The aim is to achieve correctness, completeness, and consistency of the operation handbooks and manuals. The

operation team shall be committed to ensure that a given system is operable using released documentation.

Parties Involved: The application owners are generally responsible for providing the necessary documentation, while

analysis may also be performed by an independent tester or testing team. It is necessary to include the operation team in the

discussions.

Time: Operational documentation review should start as early as possible in the development process. In any case, it must be

completed before going live, but only reviewing the required documents after deployment and before going live is too risky.

Page 9: White Paper Operational Acceptance Testing En

Page 9SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Input: A checklist showing the relevant documents and (if possible) the documents under review should be available.

Depending on the system, the documents included in the checklist may vary, such as:

— Blueprints (including hardware and software)

— Implementation plan (Go-live Plan, i.e. the activities required to go live mapped onto a timeline)

— Operational documentation (providing guidance on how to operate the system in the transition, standard/daily and crisis

modes)

— Architectural overviews (technical models of the system to support impact analysis and customisation to specific target

environments)

— Data structure explanations (data dictionaries)

— Disaster recovery plans

— Business continuity plans

Test Approach: The task of the OAT tester is to ensure that these documents are available finalised and in sufficient quality

to enable smooth operation. The documents must be handed over and accepted by the teams handling the production

support, helpdesk, disaster recovery, and business continuity. The handover must be documented. Operation teams must be

included as early as possible to obtain their valuable input about the documentation required for operating the system. This

way, transparency about the completeness of documents is achieved early on in the development process, and there will be

sufficient time left for countermeasures if documents are missing or lacking in quality.

Output: A protocol is to record the handover to the operation team including any missing documents and open issues in the

documentation that still need to be sorted before going live.

OAT Test Environment: In order to review the documents, no special test environment is required. It is, however, essential for

document management to trace the right versions and record the review process.

Risk of Not Executing: If the operational documentation review is omitted or performed too late, testing will start without

the final documentation available which reduces the effectiveness of the tests. As a result, an increased number of issues may

be raised, causing delays in the timeline. For operation teams, not having the correct documentation can affect their ability to

maintain, support, and recover the systems.

Page 10: White Paper Operational Acceptance Testing En

Page 10SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

5.2. Code Analysis

Definition: Code analysis is a tool-based automated and / or manual analysis of source code with respect to dedicated

metrics and quality indicators. The results of this analysis form part of the acceptance process during transition because low

code quality has an impact on the standard (maintenance) and crisis modes (stability).

Objective: This type of test is to ensure transparency about the maintainability and stability of software systems. Applying

correction and refactoring increases manageability of incidents and problems needing hot fixes with a low risk of side effects

and as little effort in terms of regression testing as possible.

Parties Involved: The application owners are generally responsible for fixing issues and use the results of the code analysis

as acceptance criteria. Analysis can be performed in the context of projects or systematically integrated into the maintenance

process.

Time: Code analysis can take place at dedicated project milestones or be consistently integrated into the implementation

phase, e.g. as part of the daily build. The time for corrections has to be planned.

Input: Code analysis is performed on the basis of the source code of an implemented software system – external libraries or

generated code are not considered here. The coding and architecture guidelines are required to perform the analysis.

Test Approach:

— Creating a quality model derived from best practice, coding and architectural guidelines (a quality model maps code

metrics to quality attributes, and allows decisions based on quality and corrections at code level)

— Selecting the relevant code and tool set-up

— Executing code analysis

— Assessing results and thresholds concerning quality attributes

— Analysing trends with respect to former analysis

— Performing benchmarking with respect to standards

— Deciding on acceptance or rejection

Output: This way, a quality model is created which is reusable for all systems implemented in the same programming

language. The code quality is made transparent by meeting the requirements of different thresholds, and any defects are

pointed out at code level.

Page 11: White Paper Operational Acceptance Testing En

Page 11SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

OAT Test Environment: Depending on the programming language and tool code, analysis is directly performed inside an IDE

or on a separate platform using extracted code.

Risk of Not Executing: During incidents or in problem cases, there is a high risk of side effects. Moreover, problems can only

be fixed with delays due to the great effort involved in regression testing.

5.3. Dress Rehearsal

Definition: While functional testing integrates business functions, OAT integrates all functions and stakeholders of a

production system. A dress rehearsal is necessary for bigger changes in production environments, especially when they

concern many stakeholders. This final phase is performed by the people involved in the change scenario. Typical scenarios

comprise the following:

— Transition mode – e.g. big software changes or data migrations with points of no return. In these cases, fallback scenarios

also form part of OAT.

— Standard mode – e.g. the first operation after change operation control or the release of a completely new software

— Crisis mode – e.g. failover and recovery after bigger changes in standard procedures or emergency plans. Dress rehearsals

in the crisis mode form part of the regular training in order to reduce risks caused by ignorance or routine, raising the

awareness of all stakeholders and reminding them of critical processes.

Objective: Bigger changes or fallbacks of software systems involve many different stakeholders, in particular operation

teams, and a great number of manual changes and monitoring activities have to be performed. Through a dress rehearsal,

risks of failures in the process chain and longer system downtimes shall be minimised or avoided.

Parties Involved: They comprise all participants in the transition, standard or crisis modes of operation, including the

application owners and operation teams.

Time: In order to plan a dress rehearsal, operational models are defined for each of the above modes. Fallback scenarios

and emergency plans are defined, and the software is tested completely so that its maturity for production (business) and

operation is ensured. Consequently, performing a dress rehearsal is the last step before going live.

Input: Operational models and handbooks, scenarios, fully tested software, and completed training of stakeholders in their

roles all provide the basis for the dress rehearsal.

Page 12: White Paper Operational Acceptance Testing En

Page 12SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Test Approach:

— Deriving principal scenarios from operational models

— Refining scenarios to sequence planning with respect to each role

— Preparing and executing the test with the operation teams

— Deciding on acceptance or rejection

Output: Software or process changes are carried out in order to correct defects. Those that cannot be corrected but are not

critical are collected and communicated to the helpdesk, business units and users.

OAT Test Environment: A dress rehearsal requires a production-like E2E test environment. Alternatively, a future operation

system not yet in use can be employed for dress rehearsal purposes. Activities in the crisis mode, however, may tear down

complete environments so that they will need to be refreshed extensively. There should be dedicated environments set up for

crisis mode tests in order to avoid delays of parallel functional testing.

Risk of Not Executing: Initially, processing will be performed by insufficiently skilled staff. Therefore, it is highly probable

that incidents may go unnoticed and data may be irreversibly corrupted. There is a high risk of running into disaster after

passing the point of no return.

5.4. Installation Testing

Definition: This test activity ensures that the application installs and de-installs correctly on all intended platforms and

configurations. This includes installation over an old version and constitutes the crucial part of transition acceptance.

Objective: Installation testing is to ensure correctness, completeness, and successful integration into system management

functionality for the following:

— Installation

— De-installation

— Fallback

— Upgrade

— Patch

Page 13: White Paper Operational Acceptance Testing En

Page 13SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Parties Involved: Since the installer is part of the software, it is provided by the projects. Application owner, development

and operation team should collaborate closely when creating and testing the installer, while analysis may also be performed

by an independent tester or testing team. In the early stages, the focus is on the installer. Later on, the integration into

system management functions (e.g. automated deployment to 60,000 workstations) is addressed using tested installers.

Time: Irrespective of performing installation tests when the application is ready to be deployed, the required resources

(registry entries, libraries) should be discussed as early as possible with operation teams in order to recognise and avoid

potential conflicts (e.g. with other applications, security policies). Installation testing in different test environments can be a

systematic part of the software’s way from development to production.

Input: What is required are target systems with different configurations (e.g. created from a base image), as well as the

specification of changes to the operating system (e.g. registry entries), and a list of additional packages that need to be

installed. Additional input is provided by a checklist of necessary test steps (see Test Approach), as well as installation

instructions listing prerequisites and run-time dependencies as a basis for the creation of test scenarios.

Test Approach:

The following aspects must be checked to ensure correct installation and de-installation:

— The specified registry entries and number of files available need to be verified after the installation is finished. Registry

entries and installed files should be removed completely using the de-installation routine. This will ensure that the software

can be removed quickly (returning the system to its previous state) in case any problems arise after the installation. The

same applies to additional software that may be installed with the application (e.g. language packs or frameworks).

— The application must use disk space as specified in the documentation in order to avoid problems with insufficient space

on the hard disk.

— If applicable, the installation over old(er) version(s) must be tested as well – the installer must correctly detect and remove

or update old resources.

— The occurrence of installation breaks has to be tested in each installer step, as well as breaks due to other system events

(e.g. network failure, insufficient resources). The application and the operating system must be in a defined and consistent

state after every installation break possible.

— Handling shared resources is another issue. Shared resources may have to be installed or updated during installation, and

while these processes are performed, conflicts with other applications must be avoided. In terms of deinstallation, the

system should be cleaned from shared resources that are not used any more. This will result in higher performance and

increased security for the whole system.

— Since the installation routine is an integral part of the application and a potentially complicated software process, it is

subject to the regulations of ISO 25010.

Page 14: White Paper Operational Acceptance Testing En

Page 14SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

— The main steps of installation testing are:

— Identification of required platforms

— Identification of scenarios to be executed

— Environment set-up

— Deployment and installation

— Static check of the target environment

— Dynamic check of the environment by executing installed software (smoke test)

— Test evaluation and defect reporting

Output: A protocol records all the checked potential installation problems (see Test Approach) and issues that have been

found. It also includes suggestions for resolving these issues.

OAT Test Environment: Ideally, the deployment should be tested in an environment that is a replica of the live environment.

Moreover, a visual review of existing specifications can be carried out. Before testing the installer, the number and the relative

importance of the configurations must be checked with the operation teams. Every possible configuration should receive

an appropriate level of testing. Since installation depends on the location, type, and language of the user, an environment

landscape covers all relevant target environments as a basis for the installation. Each of these types of environment has to be

reset as rapidly as possible in case of defects during installation; server and client types must be covered.

Risk of Not Executing: Omitted or delayed installation testing may result in conflicts with other applications, compromised,

insecure or even broken systems. Problems with the installation will result in low user acceptance even though the software

itself has been properly tested and works as designed. On top of this, the number of manual actions and thus effort, costs,

and conflicts will increase in large software systems (e.g. 60,000 clients).

5.5. Central Component Testing

Definition: Central component testing comprises test activities that ensure the successful exchange or upgrade of central

components like run-time environments, database systems, or standard software versions. All the operation modes –

transition, standard, and crisis – are addressed.

Objective: The aim of central component testing is to obtain proof of correct functionality, sufficient performance, or

fulfilment of other quality requirements.

Page 15: White Paper Operational Acceptance Testing En

Page 15SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Parties Involved: Normally, operation teams, infrastructure teams or vendors are responsible for central components and

are following the market cycles of producers. When changes have been made, a regression test has to be performed by

application testing in projects or line organisation (application owner).

Time: There are two possible approaches for introducing central components: The first approach would be to set up central

components as productive within the development system, i.e. central components would move parallel to the application

software along the test stages towards a release date according to a common release plan. Testing would start implicitly

with developer tests. The second approach would be to test changing a central component in a production-like maintenance

landscape. In this case, a dedicated regression test would be performed parallel to production. Central components would be

released for both operation and development.

Input: This requires an impact analysis for introducing central components, and a regression test for the applications.

Test Approach:

— Deriving relevant applications from impact analysis

— Selecting regression tests on the basis of risk assessment

— Performing regression tests (including job processing)

— parallel to development

— in a dedicated maintenance environment

— Deciding on acceptance or rejection

Output: This method yields regression test results and locates possible defects.

OAT Test Environment: Depending on the approach, central component testing is performed in existing project test

environments or in a dedicated maintenance test environment.

Risk of Not Executing: System downtimes, missing fallbacks, and unresolvable data defects are all probable consequences.

This is of crucial importance for the use of external vendors or cloud computing.

5.6. End-to-End (E2E) Test Environment Operation

Definition: E2E test environment operation introduces operation teams to the operation of test environments and to

processing and monitoring the concepts of the new application. This test type addresses the standard operation mode since

E2E testing focuses on this area – other modes only become relevant in case test failures lead to problems.

Page 16: White Paper Operational Acceptance Testing En

Page 16SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Objective: The aim of this test type is to enable operation teams to process new or changed flows and monitor progress by

applying monitoring and logging functionality. In this context, especially changed or new operation control is checked for its

operability. In case errors occur during tests, the recovery functionality is either trained or implemented additionally. The

helpdesk is made familiar with the system, which reduces support times after the release of the software.

Parties Involved: The E2E test management is responsible for tests. Operation teams are involved in the definition of test

scenarios by setting control points as well as by activation or deactivation of trace levels. In addition, processing is performed

in a production-like manner by staff which later will be responsible for performing the same activities in a production

environment.

Time: E2E test environment operation is synchronous to E2E tests. Therefore, test preparation can begin as soon as the

business concepts have been described and the operation functionality has been designed.

Input: The operational activities are determined on the basis of the business concepts, the operation design, and various

handbooks.

Test Approach:

— Deriving a functional test calendar from E2E test cases

— Creating the operation calendar by supplementing the test calendar with operational activities

— Preparing and executing the test completely in a production-like manner, following the operation calendar

— Evaluating the test

— Correcting the operational procedures and job control

— Deciding on acceptance or rejection

Output: As a result of this test, operation handbooks are corrected, and the operation team is fully trained for operation.

Corrected operational procedures and job control are implemented. Moreover, activities can be derived which serve close

environment monitoring during the first few weeks after the release of the software.

OAT Test Environment: Production-like E2E test environment operation is only possible in highly integrated test

environments that employ production-like processing and system management functions. There is no need, however, for

production-like sizing of the respective environment.

Risk of Not Executing: Initially, processing will be performed by insufficiently skilled staff. Therefore, it is highly probable

that incidents may go unnoticed and data may be irreversibly corrupted.

Page 17: White Paper Operational Acceptance Testing En

Page 17SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

5.7. SLA / OLA Monitoring Test

Definition: This test type examines the implemented monitoring functionality in order to measure the service and operation

level. The test activities can be performed as part of other OAT activities mainly addressing the standard and crisis modes.

Objective: Monitoring functionality is to be characterised by completeness, correctness, and operability in order to derive the

right service and operation level.

Parties Involved: This test is aimed at operation teams and stakeholders of other test types.

Time: In principle, monitoring tests can be performed directly after the implementation if an individual application has been

developed. If monitoring is integrated into standard system management functions, tests will be possible parallel to the E2E tests.

Test Approach:

— Selecting relevant SLAs / OLAs

— Deriving monitoring scenarios to estimate service levels

— Integrating scenarios into the test scenarios of other test types

— Executing tests and calculating service levels from monitoring

Output: On the basis of the monitoring test, the service and operation level of test environments is determined.

OAT Test Environment: This test type requires a dedicated test environment.

Risk of Not Executing: The service level may be assessed incorrectly, which would result in faults in billing based on SLAs / OLAs.

5.8. Load and Performance (L&P) Test Operation

Definition: Load and performance test operation comprises the operation of test environments by the operation team and

the integration of operation into the modelling of load scenarios and monitoring concepts. These scenarios address both the

load for standard operation and stress loads to enter the crisis mode.

Objective: The aim of this test type is to enable the operation team to apply implemented performance monitoring

functionality. Moreover, operation units shall identify bottlenecks caused by hardware restrictions and solve this problem by

changing e.g. the capacity, bandwidth, or MIPs of the production environment before a release is going live. In addition, the

run-time of batch operation is determined and can be integrated into the job planning.

Page 18: White Paper Operational Acceptance Testing En

Page 18SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Parties Involved: The non-functional test management is responsible for the load and performance tests, while operation

teams are involved in the definition of test requirements in order to assess a system from the performance point of view.

Time: Load and performance testing is a discipline which comes into play very early in the software development life cycle,

starting with infrastructure evaluation and applying simple load scenarios (ping and packages) through to the testing of

prototypes and simulating realistic loads in production-like environments. Operational activities grow along this path but

already start very early on during the design phase.

Input: The basis for the operational activities is provided by the existing infrastructure landscape and by the requirements

for performance monitoring derived from system management functions which are supported by a dedicated tool set-up. The

scenarios are derived from the operation handbooks.

Test Approach:

— Collecting test requirements from an operational point of view

— Integrating requirements into the load model

— Integrating requirements into the monitoring model

— Preparing the test environment and test data

— Executing and analysing the test

— Defining mitigation scenarios for performance risks

— Deciding on acceptance or rejection

Output: As result of the test, the operation handbooks are corrected, the operation team is trained to operate, and

activities to prepare the operational environment for the new software release are defined. Moreover, activities for intensive

environment monitoring during the first few weeks after the software is released can be derived.

OAT Test Environment: The test environments depend on the different test stages and are accompanied by dedicated load

and performance tests. There is a strong demand for performance tests in production-like environments applying production

processing and monitoring.

Risk of Not Executing: Performance issues may not be recognised after going live. In case of problems, no adequate

measures will have been prepared which can be applied fast. In a worst case scenario, an environment which is not prepared

to host an application that fulfils performance requirements would negatively influence business.

Page 19: White Paper Operational Acceptance Testing En

Page 19SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

5.9. OAT Security Testing

Definition: Security testing includes all activities required to verify the operability of given security functionality and

handbooks.

Objective: This type of test is to ensure that all security issues relating to a lack of going-live maturity are identified (e.g. test

accounts, debug information).

Parties Involved: The application owners are generally responsible for ensuring on the basis of project results that the

product has reached maturity before going live. The operation teams are responsible for applying given security guidelines.

Consequently, application owners and operation teams have to be involved as active testers, but analysis may also be

performed by an independent tester or testing team. Likewise, compliance departments have to be involved to assure

fulfilment of their requirements.

Time: OAT security testing has to be performed after deployment and before going live.

Input: The system, test documentation, and configuration files as well as the live system are required for OAT security testing.

Test Approach:

— For all relevant input channels:

— Check that trash data is handled carefully (fuzzing data), i.e. ensure that the CIA concept (Confidentiality, Integrity,

Availability) is still met.

— Check that the overall system works properly when system components are switched off (e.g. firewall, sniffer, proxies).

— For all components:

— Check that all test-motivated bypasses (e.g. test users, test data) are deleted for all configuration items.

— Check that all production support members have corresponding access to all configuration items.

— Check that all sensitive data are handled according to security guidelines.

— Check that no debugging information is shown and error messages are customised (information disclosure).

— Check that standard credentials are changed to individual and secure credentials.

— Check the configuration, switch off unused components and close unused ports (firewall).

— Check used certificates for validity.

Page 20: White Paper Operational Acceptance Testing En

Page 20SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Output: A protocol records all the checked potential security problems (see Test Approach) and security issues that have

been found. It also includes suggestions for resolving these issues.

OAT Test Environment: OAT security testing has to be performed in the E2E test environment and live system.

Risk of Not Executing: There is a high risk that security vulnerabilities created during the last steps in the application

development life cycle (test data, debug functionality, misconfiguration) will affect the security of the system.

5.10. Backup and Restore Testing

Definition: In contrast to a disaster recovery scenario resulting from an event (an interruption or a serious failure), backup

and restore functionality fulfils the need of reliability under standard operation. The event of a data loss can be an accidental

deletion by the user within the normal system functionality.

Objective: Backup and restore testing focuses on the quality of the implemented backup and restore strategy. This strategy

may not only have an impact on the requirements for software development but also on SLAs that have to be fulfilled in

operation. In an expanded test execution, the test objective of a backup includes all the resources, ranging from hardware to

software and documentation, people and processes.

Parties Involved: In the event of a backup and restore request, different groups of administrators placed in operation teams

are involved: this includes the database, infrastructure, file system, and application software. These groups of people are

stakeholders who are interested in the quality of the backup and restore process but they are also key players during test

execution.

Time: Backup and restore testing can be launched when the test environment is set up and working in standard mode. The

tests have to consider the backup schedule, e.g. monthly or weekly backups.

Input: Backup and restore testing requires a working test environment and operation process.

Test Approach: Backup and restore testing can be executed in a use-case scenario based on well-defined test data and test

environments. In general, a test will comprise the following steps:

— Quantifying or setting up the initial, well-defined testing artefacts

— Backing up existing testing artefacts

— Deleting the original artefacts

— Restoring artefacts from backup

Page 21: White Paper Operational Acceptance Testing En

Page 21SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

— Comparing original artefacts with restored ones, and also analysing the backup logs

— If applicable, performing a roll-forward and checking again

Output: As a result of backup and restore testing, missing components, defects in existing components, and corrections to be

made in handbooks and manuals are identified. Also defects with respect to requirements are identified.

OAT Test Environment: If backup and restore functionality is available, testing can in principle be executed parallel to early

functional testing. However, since the tests will involve planned downtimes or phases of exclusive usage of environments,

additional test environments will be set up temporarily in order to avoid time delays in the functional testing area. Moreover,

this activity will require the following:

— Representative test data

— Established backup infrastructure

— Established restore infrastructure

Risk of Not Executing: The possibility that backups (regular and ad hoc) may not work carries the risk of losing data in a

restore situation and can impede the ability to perform a disaster recovery. Restore times may increase due to not having a

prepared functionality but trying to solve problems in an unpredictable manner in a task force mode.

5.11. Failover Testing

Definition: The real event of a serious failure shows the degree of fault tolerance of a system. The failover test systematically

triggers this failure or abnormal termination of a system to simulate the crisis mode.

Objective: A system must handle a failure event – as far as possible – with an automatic failover reaction. If human

intervention is needed, the corresponding manual process has to be tested, too. The objective of failover testing can be

subdivided into two categories:

— The degree of the quality of fault recognition (technical measures have to be implemented to detect the failure event, e.g. a

heartbeat)

— The efficiency and effectiveness of the automatic failover reaction in terms of reaction time and data loss

The use of cloud technologies can make a positive contribution to the reliability of quality model characteristics. In case you

are a cloud service customer, it can be difficult to arrange all requirements necessary for the OAT test environment and test

execution.

Page 22: White Paper Operational Acceptance Testing En

Page 22SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Parties Involved: A system designer is needed to plan and implement the possible failure events for the test execution

based on ATAM use cases or FMEA. The failure and result analysis can require additional groups of people from database

administration and infrastructure management, e.g. technical staff member checking the uninterruptible power supply (UPS).

Processes und documentation have to be in place in order to handle the event.

Time: Failover testing can be launched when the test environment is set up and working in standard mode. To prevent

interruption of normal test activities, the test schedule has to consider a period of exclusive usage.

Input: The test scenarios are derived from architecture overviews, as well as experts’ experiences and methods. Handbooks

and manuals for failure handling also need to be available.

Test Approach: The test case specification has to describe the measures taken to trigger the failure event. It is not

necessary to execute events exactly as they happen in the real world since it can be sufficient to simulate them with technical

equipment. For instance:

— Failure: Lost Network Connection

Activity: Remove Network cable

— Failure: File system or hard disk failure

Activity: Remove hot swappable hard disk within a RAID system

Output: The failover execution protocols show the time slots needed to bring the system back up and running so that they

can be compared to the SLAs.

OAT Test Environment: Even though it is just a test, it can happen that the OAT test environment cannot be used in standard

mode after the failure event. A failover test may have an impact on further test activities and schedules. Consequently, this

kind of test is executed in dedicated temporary environments or functional test environments and carries the risk of time

delay.

Risk of Not Executing: Failover may not work or take longer than expected, thus leading to service outages.

5.12. Recovery Testing

Definition: A recovery strategy for IT systems comprises a technical mechanism similar to backup and restore techniques

but also requires additional policies and procedures that define disaster recovery standards: the capability of the software

product to re-establish a specified level of performance and recover the data directly affected in case of failure.

Page 23: White Paper Operational Acceptance Testing En

Page 23SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

Objective: For OAT, this discipline focuses on the documentation, the described processes, and the resources involved. In the

phase needed to bring back the failed application, a downtime and reduced performance as well as a minimum of data and

business loss is to be expected. The degree of recoverability is defined by the achievable minimum of interrupted business

functions. Recovery testing is to ensure predictable and manageable recovery.

Parties Involved: In the event of a recovery request, different groups of administrators placed in operation teams are

involved: this includes the database, infrastructure, file system, and application software. These groups of people are

stakeholders who are interested in the quality of the recovery process but they are also key players during test execution.

Time: Since the recovery test is much more of a static test approach to the recovery plans and procedures, it can be applied

early on in the development process. Its findings can be integrated in the further system design and process development.

Dynamic test activities are executed parallel to functional testing.

Input: The recovery test can be performed with respect to processes, policies, and procedures. All documentation describing

the processes must be in place, and also recovery functionality has to be available.

Test Approach: Performing a test in a real OAT system with full interruption may be costly. Therefore, simulation testing can

be an alternative. ATAM or FMEA are static ways to determine the feasibility of the recovery process.

The following questions have to be considered during the tests:

— What are the measures to restart the system? How long is the estimated downtime?

— What are the measures to rebuild, re-install or restore?

— What are the minimum performance and data loss volumes you can accept after recovery?

Output: The downtime – i.e. counting from the moment when the service is not available any more to the moment when

the service is back up and running – is estimated. As a result of recovery testing, missing components, defects in existing

components, and corrections to be made in handbooks and manuals are identified. Also defects with respect to requirements

are identified.

OAT Test Environment: If recovery functionality is available, testing can in principle be executed parallel to early functional

testing. However, since the tests will involve planned downtimes or phases of exclusive usage of environments, additional test

environments will be set up temporarily in order to avoid time delays in the functional testing area.

Risk of Not Executing: The failover process may not work or take longer than expected, leading to service outages, and

recovery could fall into task force mode with unpredictable downtimes.

Page 24: White Paper Operational Acceptance Testing En

Page 24SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

6. Acceptance Process

The objective of OAT is to achieve the commitment of a handover of the software to the application owner and the operation

team. Acceptance is based on successful tests and known but manageable defects throughout the entire life cycle of the

software development project (see Figure 3).

Figure 3: Start and main test phases of different OAT types

A set of quality gates has to be defined which collect all the information about the various operation tests and allow decisions

to be made concerning acceptance. The testing is organised among all the stakeholders. The application owner and the

operation team

— perform a test of their own which is integrated into the overall test plan,

— support the testing teams in achieving the test results,

— or check third-party results with respect to acceptance criteria.

Consequently, operational acceptance starts early on in the project and is achieved after successfully passing all the quality

gates.

Anal

ysis

Desi

gn

Impl

emen

tatio

n

Com

pone

nt T

est

Inst

alla

tion

Inte

grat

ion

Test

Inst

alla

tion

Syst

em T

est E

2E

Inst

alla

tion

Oper

atio

n

L&P Test Operation

E2E Test Environment Operation

Operation Documentation Review

Code Analysis

Installation Testing

Security Testing

Central Component Testing

Backup and Restore TestingDress Rehearsal Transition ModeDress Rehearsal Normal Mode

Dress Rehearsal Crisis Mode

Failover Testing

Recovery Testing

SLA/OLA Monitoring Test

Quality Gates:

OAT-

QG1

OAT-

QG2

OAT-

QG3

OAT-

QG4

OAT-

QG5

High-intensity activities

Low-intensity activities

Page 25: White Paper Operational Acceptance Testing En

Page 25SQS Software Quality Systems © 2012

Whitepaper / Operational Acceptance Testing

7. Conclusion and Outlook

Operational Acceptance Testing comprises a number of different test types which are derived from quality attributes in order

to support business continuity in the transition, standard and crisis modes of operation. The relevancy and intensity of each

test type can be decided on the basis of risks involved. For each test type, there is a test scheme which is selected according

to the technology and system management functions used. The spotlight of OAT shifts between several focal points over the

course of the software development life cycle.

Following this systematic approach, any errors will be detected as early as possible – which means that OAT is well suited to

meet any current and future demands and, in particular, fulfils the operational requirements of cloud computing.

8. Bibliographical References

APM Group Limited, HM Government and TSO. ITIL – Information Technology Infrastructure Library. High Wycombe,

Buckinghamshire. [Online] 2012. http://www.itil-officialsite.com.

International Software Testing Qualifications Board. ISTQB Glossary. [Online] March 2010.

http://www.istqb.org/downloads/glossary.html.

ISO/IEC JTC 1/SC 7 Software and Systems Engineering. ISO/IEC 25000 Software Engineering – Software Product Quality

Requirements and Evaluation (SQuaRE) – Guide to SQuaRE. [Online] 17/12/2010.

http://www.iso.org/iso/iso_catalogue/catalogue_tc/catalogue_detail.htm?csnumber=35683.

Software Engineering Institute. Architecture Tradeoff Analysis Method. Carnegie Mellon University, Pittsburgh, PA. [Cited: 2012.]

http://www.sei.cmu.edu/architecture/tools/evaluate/atam.cfm.

Valentino-DeVries, J. More Predictions on the Huge Growth of ‘Cloud Computing’. The Wall Street Journal Blogs. [Online]

21/04/2011. http://blogs.wsj.com/digits/2011/04/21/more-predictions-on-the-huge-growth-of-cloud-computing/.

Wikipedia contributors. FMEA – Failure Mode and Effects Analysis. [Online] 2012. http://de.wikipedia.org/wiki/FMEA.

Page 26: White Paper Operational Acceptance Testing En